Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 15
CASE NO.:
Appeal (civil) 1979 of 2008
PETITIONER:
M/s. Girias Investment Pvt.Ltd. & Anr
RESPONDENT:
State of Karnataka & Ors
DATE OF JUDGMENT: 13/03/2008
BENCH:
TARUN CHATTERJEE & HARJIT SINGH BEDI
JUDGMENT:
J U D G M E N T
CIVIL APPEAL NO 1979 / 2008
(arising out of SLP) No. 21826/2007)
HARJIT SINGH BEDI,J.
1. Leave granted.
2. This appeal arises out of the following facts.
3. The 3rd respondent, the Karnataka Industrial Area
Development Board (hereinafter called the ’Board’) issued a
Notification dated 6th April 2004 under Section 28(1) of the
Karnataka Industrial Area Development Board Act, 1966 (for
short the ’Act’) proposing acquisition of land bearing serial
Nos. 114,115 and 116 in village Kannamangala for the
purpose of constructing a trumpet interchange and access
road from National Highway No. 7 to the Bangalore Airport.
This land was notified for acquisition on the basis of a
comprehensive feasibility report submitted by the Technical
Consultant for the project, Sikon Private Ltd. The Karnataka
State Industrial Investment and Development Corporation (for
short "KSIIDC") in the meantime proposed a change in the
location of the trumpet interchange and the access road on the
ground that only 53 Acres of land needed for these two
projects whereas the Notification was dated 6th April 2004
pertaining to 80 acres and 27 gunthas was far in excess of the
requirement and therefore suggested reconsideration of the
matter. Vide letter dated 24th August 2004 the Bangalore
Airport Ltd. informed the KSIIDC that the proposed location of
the trumpet interchange and the access road was final and
that there was no reason to make a change in their alignment.
Notwithstanding the aforesaid communication the Board
issued a fresh Notification under section 28(1) of the Act on
5th December 2005 releasing the land proposed to be acquired
by the earlier Notification dated 6th April, 2004, and proposing
acquisition of the land bearing serial Nos.118-119. The
appellants who had in the meanwhile purchased the aforesaid
land vide two Registered Sale Deeds dated 23rd and 26th
November 2005 appeared in the enquiry under Section 28(3) of
the Act before the second respondent i.e. the Special Land
Acquisition Officer and submitted their objections, inter-alia,
pointing out that the land now notified for acquisition had
been converted to non-agricultural use by orders of the
Revenue Authorities and that they proposed to put up a
commercial complex at that place. They also pointed out that
that there were other alternative Government lands available
for construction of the trumpet interchange and access road
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 15
which could be utilized thus sparing the lands of the
appellants from acquisition. The second respondent,
however, overruled the objections on various grounds
particularly highlighting that the change had been
necessitated as the earlier proposal had not been found to be
technically sound. The Board also issued a notification dated
3rd June 2006 under section 28(4) of the Act acquiring the
land belonging to the appellants. The appellants thereupon
filed a writ petition challenging the acquisition primarily on
the ground that a large chunk of Government land was
available which could be utilized and that the acquisition of
private land was therefore not justified. It was also pleaded
that the second respondent had not given a personal hearing
to the appellants as envisaged under section 28(3) of the Act
and that the reports submitted by the said respondent to the
State Government did not adequately meet the issue raised
before him. It was also submitted that the acquisition was
motivated by malafides as there were no sound and technical
reasons for the sudden change in the alignment that was now
proposed. The learned Single Judge in his judgment and
order of 9th August 2007 found that the allegations of
malafide had not been made out and the contention that the
personal hearing envisaged under section 28(3) of the Act had
not been given also deserved to be rejected. The learned Judge
also opined that the change had been necessitated on account
of technical reasons and having held as above, dismissed the
writ petition. The matter was then taken in appeal before the
Division Bench. Similar arguments were raised before the
Bench which in its judgment dated 20th September 2007 held
as under:
"On a thorough consideration of the
documentary material and the
submission made at the Bar, we are of
the view that the proposed change of
locating T.I & A.R by the 1st respondent
is well-founded based on sound technical
reasons. It may be that because of
change of location, the appellants might
lose lucrative and prime property but
nonetheless the individual interests have
to yield to the public demands and public
needs. If the lands are converted to non-
agricultural purpose, the appellants do
get the market value for their property.
Therefore, we do not find any reason to
hold that the proposed change of location
of the T.I & A.R is actuated with any
malafides.
The appellant makes only a vague
statement of alternate availability of the
Government lands without precisely
pointing out the particulars of the
Government lands which can suitably
satisfy the needs. The contention that
there are alternate Government lands
available for construction of T.I & A.R
without need of acquisition of other
private lands, is not substantiated by any
credible material.
The proceedings of the enquiry
dated 16.1.2006 of the 2nd respondent
discloses that the appellants were present
in the enquiry, submitted written
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 15
objections with documentary materials.
The acquisition is resisted on the ground
that the lands are converted for non-
agricultural purpose and that they have
borrowed loan from Andhra Bank for
putting up a shopping complex. The
appellants have not requested the 2nd
respondent for an opportunity of further
hearing in the matter. It appears from
the proceedings that the appellants had
nothing more to say than what is stated
in their objection statement. There is no
request for further personal hearing.
Therefore, it cannot be said that the 2nd
respondent did not provide necessary
opportunity of personal hearing as
required under Section 28(3) of the Act
and the finding of the learned Single
Judge in this regard is sound and proper.
We find no merit in the appeal. Hence,
dismissed.
4. It is in this situation that the present appeal is before us
by way of special leave.
5. Mr. Dushyant Dave, the learned senior counsel for the
appellants has reiterated the arguments that had been raised
earlier. He has pointed out that the action of the respondents
in changing the location of the interchange and the access
road which had led to the acquisition of the appellants land
was actuated by malafides and the explanation offered by the
respondents that this had been necessitated on account of
technical reasons was an after thought and not based on the
record. He has pointedly stressed that in its letter of 24th
August 2004, the Airport Authority had emphatically denied
the need for a change and it was in explicable as to what had
prompted a reversal of the decision a few days later. Mr. Dave
has accordingly placed reliance on Smt. S.R. Venkataraman
vs. Union of India & Anr. (1979) 2 SCC 491, State of
Punjab vs. Gurdial Singh (1980) 2 SCC 471, Collector
(D.M.) vs. Raja Ram Jaiswal (1985) 3 SCC 1, S.N.Patil vs.
Dr. M.M. Gosavi & Ors. (1987) 1 SCC 227 and
B.E.M.L.Employees House Bldg Coop. Society Ltd. vs.
State of Karnataka (2005) 9 SCC 248 to argue that even in
cases of land acquisition the bonafides of the acquiring
authority had to be shown and that it was open to an
aggrieved party to plead malice in fact or law so as to avoid an
acquisition. It has also been submitted that the personal
hearing envisaged under section 28(3) of the Act was akin to a
hearing under section 5-A of the Land Acquisition Act, 1894
and that in the absence of any such effective hearing the
acquisition was liable to fail. It has been highlighted that the
appellants had requested for a personal hearing and it was
thus obligatory on the Collector to give one but he had bye-
passed the provisions of section 28 (3) and directly made an
order under section 28(4) of the Act. It has accordingly been
pleaded that in the light of the judgments reported in
Shri Farid Ahmed Abdul Samad & Anr. Vs. The Municipal
Corporation of City of Ahmedabad and Anr. (1976) 3 SCC
719, Rambhai Lakhabai Bhakt vs. State of Gujarat & Ors.
(1995) 3 SCC 752, State of Rajasthan vs. Prakash Chand
& Ors. (1998) 6 SCC 1, Union of India & Ors. vs. Mukesh
Hans (2004) 8 SCC 14, Union of India & Ors. vs. Krishan
Lal & Ors. (2004) 8 SCC 453 and Hindustan Petroleum
Cor.Ltd. Vs. Darius Shapur Chennai & Ors. (2005) 7 SCC
627 an acquisition made without giving an effective and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 15
meaningful personal hearing was liable to be quashed.
6. The arguments raised by Mr. Dave have been strongly
controverted by the learned counsel for the respondents. It
has been pointed out at the very outset that the allegations of
malafide were on the face of it unacceptable for the simple
reason that the proposal to change the alignment of the
trumpet interchange and access road had been initiated after
a complete technical re-survey and long before the date of the
sales in favour of the appellants and that in any case,
allegations of malafides had to be leveled against some
identified individual(s) who had to be impleaded as a party to
the litigation failing with the court was precluded from
examining this plea. Reliance for this submission has been
placed on Keshab Rao vs. State of West Bengal (1973) 3
SCC 216, First Land Acquisition Collector & Ors. vs.
Nirodhi Prakash Gangoli & Anr. (2002) 4 SCC 160, Ajit
Kumar Nag vs . G.M. (PJ) Indian Oil Corporation Ltd.,
Haldi & Ors. (2005) 7 SCC 764 and Prakash Singh Badal &
Anr. Vs. State of Punjab & Ors. (2007) 1 SCC 1. It has also
been pointed out that the personal hearing envisaged under
Section 28(3) had indeed been given and as a token of this
hearing the appellants had signed the relevant proceedings.
7. It would be seen that the primary issue raised by
Mr. Dave pertains to the malafides in the acquisition of the
appellants land. These allegations are sought to be proved by
inference on the premise (Mr. Dave’s second argument) that
the change had been made suddenly and without necessity
which showed the malafides of the respondents. We,
therefore, deem it appropriate to take up the first two
arguments together. It is Mr. Dave’s contention that on the
24th August 2004 the Airport Authority had itself ruled out any
change and as such, a complete volte face a week later showed
the malafides on the part of the respondents. We are unable
to accept this argument as the facts depict quite a different
picture. From the statement of objections filed on behalf of
the respondent No.1, the State of Karnataka before the
Karnataka High Court, we notice that the lands covered by the
Notification dated 6th April 2004 were proposed to be acquired
based on the tentative requirements indicated by the Airport
Authority in its letter dated 2nd December 2002. After
issuance of the aforesaid Notification a letter was addressed to
the Airport Authority to reappraise the matter keeping in view
the technical needs and requirements on which a team of the
Chief Executive Officer and Head Technical of the Airport
Authority, a representative of the KSIIDC and other local
revenue officials visited the site on 1st September 2004 and
noticed that there were some adverse ground conditions and
difficulties such as the existence of a large pond which
necessitated the change. It also appears that there was a
great deal of correspondence between all concerned and the
final decision was taken to change the location of the trumpet
interchange and access road after due deliberation, as has
been revealed from the letters dated 22nd April 2005, 14th July
2005 and 19th July 2005. Our pointed attention has been
brought to the letter of 19th July 2005 and we reproduce the
relevant contents hereinbelow:
"Trumpet Interchange (TI) & Access Road:
The earlier proposal envisaged acquisition
of 80 acres 27 guntas of land for TI and
Access Road from the National Highway
upto the airport boundary based on the
detailed study conducted by Bangalore
International Airport Ltd. (BIAL) in
consultation with the National Highway
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 15
Authority of India (NHAI). However, at the
time of physical survey of the land, certain
adverse ground conditions and difficulties
such as existence of large pond in the
alignment of the access road were
encountered. This necessitated change in
the alignment of the access road and in
turn, the location of the TI. In the
meanwhile, the issue of construction TI
through NHAI was discussed in the meeting
at the Prime Minister’s Office on 29.11.2004
and also in the meeting convened at NHAI
on 8.12.2004. Based on the decisions taken
in these meetings, NHAI appointed
International Consultants and Technocrats
Pvt. Ltd. (ICT) to carry out the General
Alignment Drawing (GAD) as well as DP for
the TI. Accordingly, GAD and a draft DPR
have been prepared by CT and submitted to
NHAI. Based on these NHAI has confirmed
the details of coordinates of proposed right
of way (PROW) for land acquisition purpose
and set out data for accommodating two
future railway tracks. A copy of the letter
dated 06.7.2005 received from NHAI in this
regard, is enclosed for ready reference
(Enclosure-I) .
Based on these details, BIAL with
the assistance of M/s. Secon Surveys has
finalized the revised extent of land / Sy. No.
to be acquired and has confirmed vide their
letter dated 14.7.2005. A copy of this letter
is also enclosed (Enclosure-II).
The details of villages, Sy. No. and extent
in respect of modified requirement of lands
to be acquired for TI and Access Road as
confirmed by BIAL are enclosed for your
needful action (Enclosure-III).
8. Mr. Dave’s peripheral argument that the change had
been made on account of the objections raised by the
prospective land losers of the first acquisition is also
unacceptable as this objection had been made only with
respect to the land proposed for the special runway, a fact
which had also figured in the letter dated 19th July 2005. It
is the admitted position that the land had been purchased
by the appellants vide sale deeds dated 23rd November 2005
and 26th November 2005 i.e. long after the final decision
had been taken to acquire the land in the light of the
revised proposal. It is also significant that in the objections
filed before the Land Acquisition Collector, no malafide
against any person has been alleged. We also find that
malafides have been alleged in paragraph 4.9 of the
pleadings filed before the Karnataka High Court. Paragraph
4.9 is reproduced hereunder.
"4.9 It is important to note that lands
covered under Annexure-J and the lands
now sought to be acquired are adjacent to
each other. However, apparently to help
the owners of the said lands sought to be
denotified as per Annexure-K and with
ulterior motives, there appears to be a
change of plan, for no ostensible reason
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 15
at all, whereby instead of locating the
trumpet on the said Survey No.115, 116,
117, 121 (P) and 90 belonging to some
influential persons and Sy. No.73 vast
stretch of Government Gomal land, a
plan is hatched up to denotify all the said
survey numbers including the
Government land in Sy. No. 73 and
acquire Schedule A and B lands
belonging to the 1st petitioner company.
This apparently has been done by certain
interested quarters in the respondents’
offices with ulterior motives with a view to
help and to the advantage of the owners
of the said lands and others, to the
detriment of the interest of the
petitioners. A proposal, therefore,
appears to have been mooted for a
Trumpet interchange. The proposal
interchange has been sought to be
followed up by proposal as could be seen
in Annexure-K, the revised details for
acquisition of lands, a true copy of which
is produced herewith as Annexure-K."
9. These allegations have been replied to in
paragraphs 11 to 14 of the objections filed on behalf of the
State Government, respondent No.1. These too are
reproduced:
"11. It is submitted that, the extent and
location of land required for TI was
finalized after due consultation with
BIOAL, NHAI and also the Railway
Authorities after holding series of
meetings with the concerned authorities
in this behalf. The process of acquisition
of lands required is completed. It is
submitted that, there is only a national
interest involved in this project by all
concerned and the Project is certainly not
aimed at helping any specific parties or to
affect someone as alleged by the
petitioners in the Writ Petition at Paras
4.6, 4.9, 4.11, 4.12, 4.13 and 4.14 and
other parts of the Writ Petition. It is
submitted that the allegations of
malafide, arbitrariness, highhandedness
etc., on the part of this respondent in
notifying Schedule. A and B properties
for acquisition in the above case are
hereby emphatically denied as baseless
and without any foundation. It is further
submitted that the said averments are
made by the petitioners to mislead this
Hon’ble Court. The documents marked
as Annexure \026J and H in the Writ Petition
do not disclose the full facts of the case.
In this context, it is relevant to make a
mention about the correspondence
between BIAL and KSIIDC dated
24.8.2004, 30.3.2005, 22.4.2005,
14.7.2005 and 19.7.2005 and marked at
Annexures \026 R 1 to R.5 respectively with
enclosures therein. These five documents
bring out the development, subsequent to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 15
the Notification of 7.4.2004, relied upon
by the petitioners. As explained in
subsequent paragraphs of this petition,
these five documents explain the reason
for relocation of the TI.
12. With regard to the averments made
in para 4.9 of the Writ Petition, it is not
correct to say that the lands covered
under Annexure-J to the Notification
dated 7.4.2004 and the lands now being
acquired are adjacent to each other. The
lands being acquired now are at a
distance of about 350 meters away from
the lands notified earlier. The lands
covered in the Preliminary Notification
mentioned in Annexure-J were proposed
to be acquired based on the tentative
requirements indicated by BIAL in its
letter dated 2nd December 2002 and a
copy of the same is herewith produced
and marked as Annexure R6. After
issuance of Preliminary Notification, a
letter was addressed to BIAL requesting
to review thoroughly the scheme and
reconfirm the access road alignment, TI
position and the corresponding
actual/exact extent of land required
therefore to initiate final action towards
acquisition of the required additional
lands. Subsequently a team comprising
of the Chief Executive Officer and the
Head Technical of Bangalore
International Airport Limited, a
representative of KSIIDC and the local
revenue officials visited the site on 1st
September 2004 and during the said
visi, it was noticed that there were certain
adverse ground conditions and difficulties
such as existence of a large pond in the
alignment of the access road, regarding
existence of pond and the map are
produced herewith and marked as
Annexures R1 & R8 respectively. Thus,
this aspect has necessitated marginal
change in alignment of the access road
and in turn the location of the TI.
13. It is submitted that the petitioner
refers to the 1st Survey Report of Secon
dated 27.11.2002 (Annexure H) to the
Writ Petition but makes no reference to
the 2nd Revised Report of Secon dated
30.3.2005 (Annexure R-2 to this
Statement of Objections). In the
Preliminary Notification dated 7.4.2004, a
total extent of 242 acres 27.5. guntas of
land covering 7 villages viz. Begur,
Hikkanahlli, Mylanahalli, and
Gangamuthanahalli were published. In
letter dated 23.8.2004 of KSIIDC the BIAL
was requested to reconfirm the alignment
of access road/Trumpet Interchange. As
already stated at para \026 12, at the request
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 15
of KSIIDC a joint inspection by a team
comprising of the Chief Executive Officer
and the Head Technical of BIAL,
representative of KSIIDC and the local
revenue officials was done. During the
visit it was observed that there were
certain adverse ground condition and
difficulties such as existence of a large
pond in the alignment of the access road
(Annexure R-3). Accordingly, the Secon
furnished the revised Survey Report on
30.3.2005 (Annexure R-2). BIAL in its
letter dated 14.7.2005 confirmed the final
coordinates, Survey Nos. extent of land
etc. It was on the basis of this final plan
for the TI that the KIADB issued
impugned Notification dated 5.12.2005.
Strangely, the writ petitioner has chosen
not to bring these facts to the notice of
the Hon’ble Court. These facts clearly
indicate that the petitioner is stating the
facts to mislead this Hon’ble Court.
14. With regard to the averments made
in para 4.12 of the writ petition, it is
submitted that Sy. No.133 belongs to
Sanjeevappa, son of K.Chowdappa
Anjanamma, wife of later Munlyappa
Venkatashamappa who are ordinary
citizens and not influential persons.
Lands of Survey Nos. 115, 116 and 117 of
Kannamangala Village which are
standing in the name of one Gullamma,
wife of late R. Annaiah is also an ordinary
citizen and not influential person as
alleged by the petitioners. Thus the
contention of the petitioners that there is
conspiracy either to help a few persons
owning certain pieces of land or to
deprive the petitioners of their valuable
lands with ulterior motives etc. is
untenable in law and also on facts. It will
accordingly be seen that issuance of
Notification dated 2.6.2006 by this
respondent is in accordance with law and
came to be passed after observing and
following all the necessary formalities as
contemplated in the provisions of the
Karnataka Industrial Areas Development
Board Act, 1966. It is submitted that as
regards the permission/clarification by
the Tahsildr, Devanahali Taluk from the
Assistant Commissioner, Doddaballapur
Sub-Division to auction portion of land in
Sy. No.73 of Kannamangala Village, the
matter is under consideration between
Revenue Department and KIADB. No
final decision has yet been taken to
auction land in Sy. No. 73 is not required
as per modified alignment, the proposal
for auction was motted but no final
decision is yet taken. In fact Sy. No.73
measures nearly 94 and odd acres. It is
further submitted that the notice under
Section 28 (2) of the KIADB Act, 1966
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 15
(hereinafter called the ’Act’) was issued in
the name of Sri N.R. Prakash. This is so
because his name was shown as owner of
the said lands in the relevant land
records i.e. RTC obtained as on the date
of publication of Preliminary Notification
under Section 28(1) of the Act."
10. The reply comprehensively dispels any indication of
malafides on the part of the respondents and categorically
bears out the circumstances and justification for the revised
proposal, and that no individual or party was responsible for
the alleged malafide change.
11. It is obvious from a reading of the pleadings quoted
above that only vague allegations of malafides have been
leveled and that too without any basis. There can be two ways
by which a case of malafides can be made out; one that the
action which is impugned has been taken with the specific
object of damaging the interest of the party and, secondly,
such action is aimed at helping some party which results in
damage to the party alleging malafides. It would be seen that
there is no allegation whatsoever in the pleadings that the case
falls within the first category but an inference of malafide has
been sought to be drawn in the course of a vague pleading
that the change had been made to help certain important
persons who would have lost their land under the original
acquisition. These allegations have been replied to in the
paragraph quoted above and reveal that the land which had
been denotified belonged to those who had absolutely no
position or power. In this view of the matter, the judgments
cited by Mr. Dave have absolutely no bearing of the facts of the
case. S.R.Venkataraman’s case (supra) was a case where a
Central Government officer challenged her premature
retirement in the High Court, making allegations of malafides
against one of her superior officers. She then approached this
Court where the respondent Union of India conceded that
there was no material which could justify an order of
premature retirement, resulting in an order by this Court in
her favour. In Gurdial Singh’s case (supra) it was found
that the acquisition of the land belonging to the petitioner was
on account of the malafides on the part of the Chief Minister of
the State as the land owner was a political rival. In paragraph
10 it was observed as under:
"By these canons it is easy to hold that
where one of the requisites of sections 4
or 6, viz., that the particular land is
needed for the public purpose in view, is
shown to be not the goal pursued but the
private satisfaction of wreaking
vengeance, if the moving consideration in
the selection of the land is an extraneous
one, the law is derailed and the exercise
is bad. Not that this land is needed for
the mandi, in the judgment of
government, but that the mandi need is
hijacked to reach the private destination
of depriving an enemy of his land through
back-seat driving of the statutory engine!
To reach this conclusion, there is a big ’if’
to be proved \026 if the real object is the
illegitimate one of taking away the lands
of respondents 1 to 21 to vent the
hostility of respondent 22, under the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 15
mask of acquisition for the mandi."
12. In Raja Ram Jaiswal’s case (supra) several
questions including one of malafides were raised before the
Supreme Court. The facts of the case are however tell-tale. It
appears that the Hindu Sahitya Sammelan Parishad had
obtained a large piece of land from the Municipal Board in
1953 for constructing a Hindi Sangrahalaya but the land
remained unutilized for a long time. The land belonging to
the respondent Raja Ram Jaiswal, who was apparently a well
connected individual, was in the immediate vicinity on which
he proposed to construct an air-conditioned cinema hall. The
Parishad opposed the proposal on the ground that, that it
would be destructive of its cultural and academic
environment. This objection was overruled by the District
Magistrate who granted the requisite certificate for the
construction of the cinema. The Parishad thereafter made an
application to the Government for acquiring the respondent’s
land as it was needed for the purpose for the extension of the
Hindi Sangrahalaya although it later deviated from its stand
and suggested that the additional portion was needed for a
Natyashala and Rangmanch. The Collector who was to initiate
the proceedings was apparently reluctant to do so on the plea
that the Parishad had sought the acquisition not because it
required the land but because it wished to stall the
construction of a cinema next door. Notwithstanding the
aforesaid facts, a Notification under Section 4(1) of the Land
Acquisition Act was issued. This Notification was challenged
and the matter ultimately came to the Supreme Court and this
is what the Court had to say:
"It is well-settled that where power
is conferred to achieve a certain purpose,
the power can be exercised only for
achieving that purpose. Section 4(1)
confers power on the Government and the
Collector to acquire land needed for a
public purpose. The power to acquire land
is to be exercised for carrying out public
purpose. If the authorities of the
Sammelan cannot tolerate the existence of
a cinema theatre in its vicinity, can it be
said that such a purpose would be a public
purpose? May be the authority of the
Sammelan may honestly believe that the
existence of a cinema theatre may have the
pernicious tendency to vitiate the
educational and cultural environment of
the institution and therefore, it would like
to wish away a cinema theatre in its
vicinity. That hardly constitutes public
purpose. We have already said about its
proclaimed need of land for putting up
Sangrahalaya. It is an easy escape route
whenever Sammelan wants to take over
some piece of land. Therefore, it can be
fairly concluded that the Sammelan was
actuated by extraneous and irrelevant
considerations in seeking acquisition of the
land and the statutory authority having
known this fact yet proceeded to exercise
statutory power and initiated the process
of acquisition. Does this constitute legal
mala fides ?
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 15
Where power is conferred to achieve
a purpose it has been repeatedly reiterated
that the power must be exercised
reasonably and in good faith to effectuate
the purpose. And in this context ’in good
faith’ means ’for legitimate reasons’.
Where power is exercised for extraneous or
irrelevant considerations or reasons, it is
unquestionably a colourable exercise of
power or fraud on power and the exercise
of power is vitiated. If the power to acquire
land is to be exercised, it must be
exercised bona fide for the statutory
purpose and for none other. If it is
exercised for an extraneous, irrelevant or
non-germane consideration, the acquiring
authority can be charged with legal mala
fides."
13. For arriving to its conclusion, the Court relied,
amongst others, on the judgments of this Court in Gurdial
Singh’s case aforesaid and on S.N.Patil’s case (supra) where
again specific allegations were made and proved against the
Chief Minister. In BEML Employees House Building Co-
operative Society Ltd.’s case (supra) the acquisition was
quashed on the ground that the land belonging to some
persons who were similarly situated as the appellant, had
been released and that the State Government had been unable
to show any rational discrimination between the case of the
appellant and that of the other landowners and that this act
amounted to "hostile discrimination".
14. It is no doubt open to the court to go into the question
of malafides raised by a litigant but in order to succeed, much
more than a mere allegation is required. Mr. Dave’s inference
of malafide based on the ground that the change in the
location of the trumpet interchange and the access road had
been suddenly made without proper application of mind to
help certain unidentified individuals resulting in the
acquisition of the land belonging to the appellants is, thus,
without any factual basis.
15. Mr. Hulla, the learned counsel appearing for some
of the respondents has also placed reliance on Keshab Rao vs.
State of West Bengal (1973) 3 SCC 216, First Land
Acquisition Collector & Ors. vs. Nirdohi Prakash Ganguli &
Anr. (2002) 4 SCC 160, Ajit Kumar Nag vs. G.M.(PJ)
I.O.C.Ltd., Haldi & Ors. (2005) 7 SCC 764 and Prakash
Singh Badal & Anr. Vs. State of Punjab and & Ors. (2007) 1
SCC 1 to submit that a mere allegation of malafide is not
enough and cogent evidence thereof must be given. We
respectfully endorse the opinion expressed in these judgments
and reiterate that no material or details of malafides have
come on record in the present case. We nevertheless quote
paragraphs 56 and 57 from Ajit Kumar Nag’s case (supra) to
support our discussion:
56. In our view, neither the learned Single
Judge nor the Division Bench has committed
any error of law and/or of jurisdiction which
deserves interference in exercise of
discretionary jurisdiction under Article 136 of
the Constitution. As is clear, the situation has
been created by the appellant. It was very
grave and serious and called for immediate
stern action by the General Manager. Exercise
of extraordinary power in exceptional
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 15
circumstances under Standing Order 20(vi) in
the circumstances, cannot be said to be
arbitrary, unreasonable or mala fide. It is well
settled that the burden of proving mala fide is
on the person making the allegations and the
burden is "very heavy". (vide E.P. Royappa v.
State of T.N. ( 1974) 4 SCC 3) There is every
presumption in favour of the administration
that the power has been exercised bona fide
and in good faith. It is to be remembered that
the allegations of mala fide are often more
easily made than made out and the very
seriousness of such allegations demands proof
of a high degree of credibility. As Krishna Iyer,
J. stated in Gulam Mustafa v. State of
Maharashtra ((1976) 1 SCC 800 p.802, para 2)
: "It (mala fide) is the last refuge of a losing
litigant."
57. We hold clause (vi) of Standing Order 20
of the Certified Standing Orders of the
respondent Corporation valid, constitutional
and intra vires Article 14 of the Constitution.
We also hold the action taken by the General
Manager of the respondent Corporation
dismissing the appellant-petitioner from
service as legal and lawful. We thus see no
substance either in the appeal or in the writ
petition and both are, therefore, dismissed. In
the facts and circumstances of the case,
however, there shall be no order as to costs.
In the light of the above, no further discussion on this
aspect is called for.
16. The learned counsel for the respondents has also
taken pains to point out that in the absence of specified
individuals, who are to be made parties in a litigation alleging
malafides, an enquiry into such an allegation was
impermissible. The learned counsel has placed reliance on
State of Bihar and another vs. P.P.Sharma, IAS & Anr.
(1992) 1 Suppl. SCC 222 and All India State Bank Officers’
Federation & Ors. vs. Union of India & Ors. (1997) 9 SCC
151. In P.P.Sharma’s case (supra) it was observed that :
"It is a settled law that the person
against whom malafides or bias was
imputated should be impleaded eo nomine
as a party respondent to the proceedings
and given an opportunity to meet those
allegations. In his/her absence no enquiry
into those allegations would be made.
Otherwise it itself is violative of the principle
of natural justice as it amounts to
condemning a person without an
opportunity."
17. A similar opinion was expressed in All India State
Bank Officers Federation & Ors. (supra) in the following
words:
"In view of the aforesaid explanation
of the respondent-Bank, which we see no
reason to disbelieve, it is clear that the
petitioners have made baseless and
reckless allegations of mala fide.
Respondents 4 and 5 obviously had no
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 15
direct or indirect role to play either in the
formulation of the policy or in the
memorandum being placed as a table
item to be taken up for consideration in
the meeting held on 7.3.1999. The
modification was approved by the
Chairman and all the Directors who were
present in the meeting of the Board. For
an allegation of mala fide to succeed it
must be conclusively shown that
respondents 4 and 5 wielded influence
over all the members of the Board, who
were present in the said meeting. No
such allegation has been made. The
decision to modify the promotion policy
was taken by a competent authority,
namely, the Central Board in a duly
constituted meeting held on 7.3.1989 and
we are unable to accept that this change
in the policy was brought about solely
with a view to help Respondents 4 and 5.
There is yet another reason why
this contention of the petitioners must
fail. It is now well settled law that the
person against whom mala fides are
alleged must be made a party to the
proceeding. The allegation that the policy
was amended with a view to benefit
Respondents 4 and 5 would amount to
the petitioners contending that the Board
of Directors of the Bank sought to favour
Respondents 4 and 5 and, therefore,
agreed to the proposal put before it.
Neither the Chairman nor the Directors,
who were present in the said meeting,
have been impleaded as respondents.
This being so the petitioners cannot be
allowed to raise the allegations of mala
fides, which allegations, in fact, are
without merit."
18. As observed above, the appellants have not identified
any person who had been instrumental in harming their
cause. We would, therefore, even be precluded from going into
the question of malafides although we have nevertheless
examined the matter in extenso.
19. Mr. Dave has argued with emphasis, that the
personal hearing envisaged to an interested person under
section 28(3) of the Act had in fact not been given to the
appellants and that the proceedings held by the Collector
pursuant to the notice dated 12th December 2005 were a mere
eye wash. He has pointed out that as per the written
objections filed by the petitioner on 16th January 2006, a
specific request had been made for a personal hearing, but
notwithstanding the request the Collector gave his decision on
the objections on 2nd February 2006 and the final Notification
was issued on 2nd June 2006. To supplement his argument
that in the absence of a personal hearing under section 5(A) of
the Land Acquisition Act, or section 28(3) of the Act stand
vitiated, Mr. Dave has placed reliance on Shri Farid Ahmad
Abdul Samad & Anr. Vs. The Municipal Corporation of City
of Ahmedabad & Anr. (1976) 3 SCC 719, Rambhai Lakhabai
Bhakt vs. State of Gujarat & Anr. (1995) 3 SCC 752, Om
Prakash & Anr. Vs. State of U.P. & Ors. (1998) 6 SCC 1,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 15
Union of India & Ors. vs. Mukesh Hans (2004) 8 SCC 14,
Union of India & Ors. vs. Krishan Lal & Ors. (2004) 8 SCC
453, Hindustan Petroleum Cor. Ltd. vs. Darius Shapur
Chennai & Ors. (2005) 7 SCC 627 and P.Naranayyapa &
Anr. Vs. State of Karnataka (2006) 7 SCC 578. Concededly,
Section 28 (3) of the Act gives a right of personal hearing to the
owner of the land or any other interested person and the
judgments cited by the learned counsel therefore eminently
support the appellant’s case. The question as to whether an
effective personal hearing was given or not, however is a
question of fact and we notice from a perusal of the record
that such hearing was indeed given and that the appellant had
exercised his rights thereunder and it was only after the
procedure under section 28(3) had been followed, that the final
Notification had been issued. We find that the learned Single
Judge and the Division Bench of the High Court have given
categorical findings against the appellant on this score and we
have no reason to differ therefrom. We have nevertheless
examined the record to re-assure ourselves as to the
correctness of the High Court’s decision. After the
objections/documents had been filed, the file was taken up by
the Collector on 16th January, 2006 on which date Shri N.R.
Prakash representing the land owners was not present. The
Collector, after examining the facts of the case, adjourned the
case to 24th January 2006 for ’orders’ in accordance with
Section 28(3) of the Act and the final orders on the
proceedings under section 28(3) of the Act were, in fact, made
on the 2nd February 2006. Mr. Dave has emphasized that as
the matter had been adjourned on 16th January 2006 for
’orders’ there was absolutely no justification in finalizing the
proceedings on 2nd February 2006 without giving a hearing to
the appellants. We observe, however, that merely because the
word ’orders’ has been recorded in the proceedings of
16th January 2006, it does not imply that the matter remained
incohate or that it envisaged a further hearing. The record
shows that comprehensive objections alongwith documents
had been filed by the appellants on 16th January 2006 wherein
after stating the history as to how they had become owners of
the land they had given their objections to its acquisition and
in paragraphs 19 and 21 stated as under:
"In the event of your requiring any
clarification, we also request you to offer us
a personal hearing in the above matter for
us to place the above facts for your kind
consideration.
We do hope that justice would be done
and valuable investment in the land would
be protected and we are permitted to carry
on the construction of the Shopping
Complex as planned towards which the
necessary finance have been made available
to us by Andhra Bank.
We have to request you to provide us with
a personal hearing in the matter, as also
permit us to file any other documents or
additional statements as may be required".
20. The aforesaid paragraphs clearly reveal that the
request for a personal hearing was conditional in that if a
clarification or additional documents were required, time for
that purpose be given. It is also significant that the objections
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 15
filed by the appellants form (almost exclusively) the basis for
the present writ petition inasmuch the fact that there was no
need for the change of the alignment of the trumpet
interchange and the access road or that alternative land was
available for that purpose, had been spelt out therein. The
Collector in dealing with the objections had observed that
several objections/documents had been filed by the appellants
but were liable to rejection as the acquisition was necessary
for the Bangalore Airport. We are also not mindful of the fact
that though the rights of an individual whose property is
sought to be acquired must be scrupulously respected, an
acquisition for the benefit of the public at large is not to be
lightly quashed and extraordinary reasons must exist for doing
so. This is the ratio of the judgment of this Court in
Ramniklal N.Bhutta & Anr. Vs. State of Maharashtra &
Ors. (1997) 1 SCC 134 wherein it has been held as under:
"Whatever may have been the
practices in the past, a time has come
where the courts should keep the larger
public interest in mind while exercising
their power of granting stay/injunction.
The power under Article 226 is
discretionary. It will be exercised only in
furtherance of interests of justice and not
merely on the making out of a legal point.
And in the matter of land acquisition for
public purposes, the interests of justice
and the public interest coalesce. They
are very often one and the same. Even in
a civil suit, granting of injunction or other
similar orders, more particularly of an
interlocutory nature, is equally
discretionary. The courts have to weigh
the public interest vis-‘-vis the private
interest while exercising the power under
Article 226 \026 indeed any of their
discretionary powers. It may even be
open to the High Court to direct, in case
it finds finally that the acquisition was
vitiated on account of non-compliance
with some legal requirement that the
person interested shall also be entitled to
a particular amount of damages to be
awarded as a lump sum or calculated at
a certain percentage of compensation
payable. There are many ways of
affording appropriate relief and
redressing a wrong; quashing the
acquisition proceedings is not the only
mode of redress. To wit, it is ultimately a
matter of balancing the competing
interests. Beyond this, it is neither
possible nor advisable to say. We hope
and trust that these considerations will
be duly borne in mind by the courts while
dealing with challenges to acquisition
proceedings."
21. We thus find no merit in the appeal. Dismissed. There
will be no order as to costs.