Full Judgment Text
1
Reportable
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO.1368 OF 2007
M/s. Jayasawals Neco Ltd. Appellant
Versus
Chhattisgarh State Electricity Respondents
Regulatory Commission and Another
J U D G M E N T
Dipak Misra, J.
The respondent No.2, Chhattisgarh State Electricity
Board (CSEB), filed Petition No.5/2005 under Sections 45,
JUDGMENT
46 and 64 of the Electricity Act, 2003 (for brevity, 'the Act')
for determination of Retail Supply Tariff for the financial
year 2005-2006. The Chhattisgarh State Electricity
Regulatory Commission (for short, 'the Commission'), while
dealing with the power intensive industries adverted to the
tariff that is to be determined qua the present appellant.
Paragraph 3 of the HV-5 Power Intensive Industries that
Page 1
2
deals with tariff reads thus:-
| Category of Demand Charges Energy<br>consumers [Rs./KVA/month] Charges<br>[Rs./KWh]<br>HV-5 Power Intensive<br>Industries<br>5.1. 220/132 KV 260 2.55<br>Supply<br>5.2. At 33 KV Supply 275 2.65<br>2. Paragraph 4(a) adverts to minimum monthly payment<br>of charges. It reads as follows:-<br>“4. Minimum Charge [a] For 220/132 KV<br>Supply<br>The consumer will guarantee a minimum<br>monthly payment of charges of the unit [Kwh]<br>equivalent to 30% load factor on the contract | Category<br>consumers | of Demand Charges<br>[Rs./KVA/month] | Energy<br>Charges<br>[Rs./KWh] | |
|---|---|---|---|---|
| HV-5 | Power Intens<br>Industries | ive | ||
| 5.1. | 220/132<br>Supply | KV 260 | 2.55 | |
| 5.2. | At 33 KV Supply | 275 | 2.65 |
JUDGMENT
3. In the present appeal, we are only concerned with
minimum charges as nothing else is in dispute. The
Commission, while dealing with minimum charges, fixed
30% of the load factor taking into consideration the pattern
of consumption as minimum charges. Be it noted, the said
tariff determination was applicable for the said financial
Page 2
3
year in respect of all the power intensive industries.
4. After the said order was passed, the appellant filed
Petition No.19 of 2005 (M) under Section 94 of the Act. The
th
Commission vide order dated 5 October, 2005, taking note
of the consumption in the said year, reduced the minimum
monthly payment of charges to 10% of the load factor. The
analysis of the Commission is reproduced below:-
“11. Based on last eight months consumption
(January 2005 to August 2005), the average load
factor is found to be as 11.4%. If the load factor
is decided to be maintained at 10% then the TMG
unit comes to 12,31,200 as against the average
consumption of 11,27,525 units which would
appear to be reasonable though marginally more
for which the petitioner has to pay the charges
irrespective of his consumption. In that case the
petitioner will still be required to pay the demand
charges of Rs.41.26 lakh per month which he was
not required to pay earlier, and Rs.31.39 lakh
towards energy charges totalling to Rs.72.65 lakh
per month, as against Rs.60.50 lakh at the
pre-revised tariff rate. According to this the
average unit rate comes to Rs.6.44 as against
Rs.5.37 earlier, i.e. rise by about 20%. The
request of the petitioner for reducing the demand
charge to 33% on the ground that he draws power
only for 8 hours and exports power to CSEB for
16 hours has no logic as the concept of demand
charge has been introduced to recover the fixed
charges. In this case, the CSEB has to remain
prepared to supply power to the petitioner for 8
hours and the power not drawn or less drawn by
the petitioner from CSEB can not be allotted to
other consumers.
JUDGMENT
Page 3
4
12. In view of the petitioner's peculiar pattern of
power consumption, the Commission feels that
the minimum guaranteed consumption of the
petitioner should be different from the other
industries in his tariff category and should be
fixed at a much lower level. The Commission
accordingly directs that the petitioner be required
to guarantee a minimum monthly payment of
charges of units equivalent to 10% load factor on
the contract demand plus demand charges on the
billing demand per month irrespective of whether
any energy is consumed during the month or not.
This will not adversely affect the income of the
CSEB, as it will be earning Rs.10 lakh extra per
month as compared to the pre-revised tariff. This
will be further increased due to increased rate of
low P.F. penalty.”
5. The aforesaid order was assailed before the Appellate
Tribunal for Electricity (for short, ‘the tribunal’) in Appeal
No.186 of 2005.
6. During the pendency of the appeal, the appellant along
JUDGMENT
with others approached the Commission in Petition No.17 of
2005, making manifold prayers. The Commission
enumerated the following aspects for consideration:-
“(i) Set off on contract demand (CD) of the
CPP-holder, captive consumer and
non-captive consumers availing power from
the CPP through open access.
(ii) Parallel operation charges.
Page 4
5
(iii) Separate tariff for start up power.
(iv) Tariff for supply to CSEB/licensee and
definition for firm and infirm power.
(v) Issue of sale of electricity to third parties.
(vi) Wheeling charges.
(vii) Introduction of ABT for CPP-holders.”
7. While dealing with the minimum charges, which was
the part of issue No.1, the Commission came to hold that:-
“In view of the above, the Commission decides
that for the present no set off on CD may be
permitted. The Commission will review the
position when the intra-State ABT regime is fully
operational and the Balancing and Settlement
Code is fully implemented. The Commission,
however, decides that both the captive as also the
non-captive consumers of the CPPs, while paying
demand charges including tariff minimum
charge, will not be required to pay monthly
minimum charges on consumption considering
the fact that their requirement of power is to be
met from the CPP only and they may take very
little power from the licensee/CSEB. Thus such
consumers, whether EHV or HT, shall be required
to pay tariff minimum charges on the contract
demand or the recorded maximum demand,
whichever is higher only. This dispensation will,
however, be available to these
captive/non-captive consumers who avail power
both from a CPP and the licensee, on the
condition that the supply from the CPP is more
than 50% of their requirement in terms of unit
consumption. Every captive and non-captive
consumer will have to declare that they will be
JUDGMENT
Page 5
6
drawing more than 50% of their monthly
consumption from the CPP failing which it will be
presumed that their power requirement from the
CSEB/licensee is more than 50% and they will
not get the benefit of waiver of monthly minimum
charge on consumption.”
8. We may note here that the said order passed by the
Commission was challenged in appeal before the appellate
authority and the appeal has been disposed of affirming the
same. It is also apt to note here that the appellant is not a
party to the same and in the instant case, the only issue is
levy of minimum charges at 10% for the financial year
2005-2006.
9. We have heard Mr. Devashish Bharuka, learned
counsel for the appellant and Ms. Swapna Seshadri, learned
counsel for the respondent No.1.
JUDGMENT
10. Mr. Bharuka, learned counsel for the appellant
submits that the minimum charge has been abolished as a
concept in the case of likes of the appellant and, therefore,
there is no justification whatsoever to levy the same for the
year 2005-2006. It is urged by him that though the order
passed in Petition No.17 of 2005 was brought to the notice
of the tribunal, the same has neither been appropriately
Page 6
7
dealt with or addressed to inasmuch as the tribunal has
concurred with the order passed in review by ascribing no
reason.
11. Ms. Swapna Seshadri, learned counsel for the
respondent-Commission, in support of the order contends
that the appellant is enjoying the benefit of the order of the
Commission that has been affirmed by the tribunal after the
concept of levy of minimum charges has been abolished in
respect of subsequent years, but the said principle cannot
be made applicable to the year 2005-2006, for the “load
factor”, that is, 11.4% was specifically taken into
consideration by the Commission in respect of the said year.
12. From the rivalized submissions canvassed at the Bar,
JUDGMENT
we find that both sides lay emphasis on the “consumption
pattern of the load factor” for the calculation of monthly
minimum charges. It is the admitted position that the
Commission while dealing with Petition No.17 of 2005 has
returned a categorical finding that the likes of the appellant
are not liable to pay the minimum charges. However, as we
find, it is not a determination in absoluteness. It depends
Page 7
8
upon the scrutiny and analysis of the factual score. To
elucidate, abolition of minimum charges is not stated as a
principle of law but has been so adjudicated on the basis of
certain conditions precedent being satisfied. Therefore, the
factual score, delineation thereof and the ultimate analysis
thereon constitute the structural pillar of the discussion.
13. Our duty would have been easier had the tribunal
adverted to the said aspect. As we find from paragraph 18
of the order passed by the tribunal, it has really not taken
th
note of the order passed on 6 February, 2006, wherein as
a concept which is founded on factual analysis, the
minimum charges stood abolished. Needless to say, as the
conclusion is based on appreciation of relevant facts and
other enquiry, it was incumbent on the Commission to dwell
JUDGMENT
upon the same and then only such analysis could be
scrutinised in appeal by the appellate authority in its proper
perspective. It is a statutory obligation. At this juncture, it
is fairly stated by the learned counsel for the Commission
that the factual analysis can be made in an apposite
manner by the Commission but not by the tribunal at the
first instance. Learned counsel for the appellant does not
Page 8
9
dispute the said position.
14. As the factual analysis is necessary and certain
conditions precedent are required to be gone into for the
purpose of determination as regards the aspect whether
there should be abolition of the minimum charges for the
financial year 2005-2006 or not, the competent authority,
we are disposed to think, should be the Commission.
Therefore, we are inclined to remit the matter to the
Commission for fresh determination.
15. In view of the aforesaid premises, the appeal is
allowed, the order passed by the tribunal as well as by the
Commission is set aside and the matter is remitted to the
Commission for determination on the basis of the factual
JUDGMENT
score keeping its own analysis that has been made while
dealing with the grievance put forth in Petition No.17 of
2005. We may repeat at the cost of repetition that levy or
non-levy being determinable on the factual base, every
aspect relatable to the same has to be considered.
Accordingly, we direct that the said determination shall be
done within a period of four months from the date of receipt
Page 9
10
of the order. We will be failing in our duty if we do not note
that the tribunal has dealt with other aspects. As the
learned counsels have restricted the argument pertaining to
contract demand, we have only delved into the same. There
shall be no order as to costs.
.........................................J.
(Dipak Misra)
.........................................J.
(A.M. Khanwilkar)
.........................................J.
(Mohan M. Shantanagoudar)
New Delhi;
February 22, 2017.
JUDGMENT
Page 10