Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 9
PETITIONER:
JAWAHARLAL WADHWA AND ANOTHER
Vs.
RESPONDENT:
HARIPADA CHAKROBERTY
DATE OF JUDGMENT14/10/1988
BENCH:
KANIA, M.H.
BENCH:
KANIA, M.H.
MUKHARJI, SABYASACHI (J)
RANGNATHAN, S.
CITATION:
1989 AIR 606 1988 SCR Supl. (3) 513
1989 SCC (1) 76 JT 1988 (4) 138
1988 SCALE (2)1033
ACT:
Arbitration Act, 1940--Sections 30,33 and 34--Award--
Setting aside--Only an error of law and not mistake of fact
committed by Arbitrator justiciable before Court.
%
Transfer of Property Act, 1882-- Section 53--
Anticipatory breach of contract--Option to claim damages--
Otherwise keep contract alive by performing us its part of
contract and show readiness and willingness in order to
claim specific performance--Transferee in possession of
premises --Stopped paying monthly instalments--Could not
claim protection under section 53A.
HEADNOTE:
The respondent had taken a loan of Rs.15,000 from the
Ministry of Defence for construction of a house on a plot
allotted to him. As the amount of loan was insufficient to
complete the construction, he took a loan of Rs.5,000 from
Appellant No. 1 and on 6th September, 1973 he entered into
an agreement to sell the house and the plot to Appellant No.
1. The aforesaid amount of Rs.5,000 was shown as advance of
sale price. Clause 2(b) of the Agreement provided that the
appellant purchaser shall pay to the seller!respondent a sum
of Rs.105 every month against the sanctioned loan of Rs.
15,000 till the full amount is recovered from the
respondent. I he payment of Rs. 105 per month was made by
the appellant only up to .January 1976 and this payment
covered upto 23 instalments, and more than l00 instalments
remained unpaid.
On January 29, 1974 another agreement, for construction.
was entered into between Appellant No. 1 and the respondent.
Under this agreement, Appellant No. 1 was to complete
construction of the house and alter the completion of the
house the respondent was to return the cost of construction
amounting to Ks.1,15,000 including appellant’s profit of
Rs.20,000 and security amount of Rs. 15,000 deposited by the
Appellant No. 1 with the respondent, within three years in a
lump sum and on payment the Appellant No. I was to hand over
the possession of the building and the plot to the
respondent. Till that amount was paid. Appellant No 1 was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 9
entitled to possess and occupy and enjoy the building
PG NO 513
PG NO 514
The house was not completed but the appellants who are
husband and wife were occupying the same.
According to the respondent this transaction was sham
and bogus and he repudiated the same. Disputes arose
between the parties.
The respondent filed a suit claiming for the return of
possession of the said plot of land and house. The
application ot’ the appellant under s. 34 of the Arbitration
Act was dismissed.
In the appeals preferred by the appellant the Additional
District Judge, appointed a sole arbitrator with the consent
of the parties. The arbitrator made and published his award
which went against the appellants. The High Court dismissed
the appeal filed by the appellants against the order of the
District Judge dismissing their application challenging The
Award.
This Court. in appeal, set aside the award of the
Arbitrator and also the judgment of the High Court and
appointed Shri A.C. Gupta, a former Judge of this Court as
the sole arbitrator.
It was contended before the said Arbitrator that the
agreement for sale was not registered and might not convey
any interest to appellant No. 1 in the property, but the
appellants, who had been put in possession of the said land
and construction. were entitled to retain possession under
th4’ protection affOrded by S. 53A of the Transfer of
Property Act. The arbitrator made and published his award
which went against the appellants. The arbitrator held from
the receipts filed, that the respondent paid only rent up to
than 100 instalments remained to be paid, and that there was
no valid reason why the respondent should have failed to
carry out his obligation under The contract. The arbitrator
further held that the respondent could not, therefore, claim
that his possession was protected, under s. 53A of the
Transfer of Property Act and was, therefore. not entitled to
retain possession of the disputed property beyond January
1976.
In the objection filed by the appellants challenging the
award before this Court it was contended that the award is
bad in law and liable to be set aside as there is an error
of law disclosed on the face of the award as the statements
contained in the award ran counter to the settled position
in law that wrongful repudiation by the respondent of the
contract by his letter dated 16 January, 1976, before mutual
obligation under the contract were carried out, amounted to
PG NO 515
an anticipatory breach of contract by him and therefore the
Appellant No. 1 is absolved from carrying out his remaining
obligation under the contract, and could claim specific
performance of the same even though he failed to carry out
his remaining obligations under the contract.
Dismissing the objections and upholding the award, the
Court,
HELD: l. It is settled in law that where a party to a
contract commits an anticipatory breach of the contract, the
other party to the contract may treat the breach as putting
an end to the contract and sue for damages, but in that
event he cannot ask for specific performance. The other
option open to the other party, namely, the aggrieved party,
is that he may choose to keep the contract alive till the
time for performance and claim specific performance but, in
that event, he cannot claim specific performance of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 9
contract unless he shows his readiness and willingness to
perform the contract. [521B-C]
International Contractors Ltd. v. Prasanta Kumar Sur,
[1961]3 SCR 579, distinguished.
2. It is an error of law and not a mistake of fact
committed by the Arbitrator which is justiciable in the
application before the Court. [521A]
If there is no legal proposition either in the award or
in any document annexed to the award which is erroneous and
constitutes the basis of the award and the alleged mistakes
or alleged errors are only mistakes of fact the award is
not amenable to correction by the Court. [522A-B]
Coimbatore District Podu Thozillar Sangam v.
Balasubramania Faundary and Others, [1987] 3 SCC 723;
Champsey Bhara and Co. v. Jivraj Balloo Spinning Weaving Co.
Ltd., [1922-23] LR 50 IA 324, 1923 AC 480; Kanpur Nagar
Mahapalika v. M/s Narain Das Haribansh, [1970] 2 SCR 28,1969
2 SCC 620 and State of Orissa & Ors.v.M/s Lall Brothers,
[1988] Judgment Today S.C. 552, referred to.
In this case, what the arbitrator has done is to set out
in his award the relevant portion of s. 53A of the Transfer
of Property Act, in terms of the said section. There can be
no dispute that these provisions have been correctly set
out. There is thus no error in the proposition of law set
out by the learned Arbitrator in the award. It may be that
there is an error, although that is by no means certain, in
PG NO 516
the application of these principles in coming to the
conclusion that, notwithstanding the repudiation of the said
contract by the respondent, Appellant No. 1 was not absolved
in the facts and circumstances of the case from his
obligation to pay the remaining instalments of Rs.105 per
month as provided under the contract. [521F-G]
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2678 of
1985.
From the Judgment and order dated 30.4.1985 of the Delhi
High Court in F.A.O. No. 270 of 1982.
M.C. Bhandare, Sandeep Narain and Shri Narain for the
Appellants.
Dr. Shankar Ghosh and N.R. Choudhary for the Respondent.
The Judgment of the Court was delivered by
KANIA,J. The hearing before us now relates to certain
objections filed to the Award made by Shri A.C. Gupta a
former Judge of this Court who was appointed the sole
arbitrator to adjudicate upon the dispute between the
parties pursuant to the Order of this Court dated 18th
November, 1987 in the circumstances as set out hereinafter.
In order to appreciate the objections, it is necessary to
refer to certain facts.
The Settlement Commissioner, Government of India
allotted Plot No. 631 at Chitranjan Park, New Delhi
measuring 160 sq. yds to the Respondent under the
Settlement Scheme for the refugees from Pakistan for a total
price of Rs.4,800. This allotment was made by the Settlement
Commissioner on behalf of the Rehabilitation Department of
the Government of India. The Respondent applied for a loan
from the Ministry of Defence for construction of the house
on the said plot and a loan of Rs.15,000 was sanctioned in
his favour. Under the House Construction Rules of the
Government, the plans and estimates had to be submitted
along with the application and a sanctioned amount was paid
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 9
in four instalments at different stages of construction. The
Respondent started the construction of a building on the
said land. By the end of 1973, the Respondent had
constructed a house on the said plot upto the roof level. By
that time he had obtained and used up a sum of Rs.12,000 out
of the loan sanctioned to him and only a balance of Rs.3,000
PG NO 517
remained to be paid to him under the said loan. According to
the Respondent, this amount was not sufficient for the final
completion of the house and he, therefore, sought the help
of Appellant No. I who advanced a sum of Rs.5,000 to him. In
September, 1973 the Respondent entered into an agreement
dated September 6, 1973 to sell the house and the said plot
to the Appellant No. 1. The aforesaid amount of Rs.5,000
given by way of loan was shown in that agreement as an
advance paid towards the sale price. The Respondent also
executed a General Power of Attorney in favour of Appellant
No. 1 inter alia enabling him to carry on construction work
on the said land on behalf of the Respondent. According to
the Respondent, the house was not complete but the
Appellants who are husband and wife were occupying the same.
Under circumstances, we need not discuss here, on January
29, 1974 another agreement was entered into between
Appellant No. 1 and the Respondent which has been described
as an agreement for construction. Under that agreement,
Rs.80,000 was to be paid by the Respondent as the price of
the construction to be put up by Appellant No. I on the said
plot and he was to charge Rs.20,000 as the profits and
labour charges. He was to deposit Rs.15,000 with the
Respondent, this transaction was sham and bogus. Disputes
arose Respondent was to return the amount of Rs.1,15,000
within three years in a lump sum and on such payment,
Appellant No. I was to hand over the possession of the
building and the plot to the Respondent. Till that amount
was paid, Appellant No. 1 was entitled to possess and occupy
and enjoy the same and to receive rents thereof. According
to the Respondent, this transaction was sham and bogus.
Disputes arose between the parties and the Respondent filed
a suit in August 1977 claiming for the return of the
possession of the said plot and the house. A notice of
motion under section 34 of the Arbitration Act 1940 for stay
taken out by the Appellants was dismissed. An appeal was
preferred against the said decision. In the appeal, which
came up for hearing before the Additional District Judge,
Delhi. with the consent of the parties, Shri Bakshi Man
Singh was appointed as the sole arbitrator to adjudicate
upon the disputes in the suit. The said Shri Bakshi Man
Singh died in July 1979 without making any award. On an
application by the Respondent, the learned Additional
District Judge filled up the vacancy by appointing Shri Hari
Shanker, Advocate, as the sole rbitrator. Shri Hari Shanker
made and published his award which went against the
Appellants. According to the Appellants, the said award was
made ex parte. The appellants challenged the award by filing
objections under sections 30 and 33 of the Arbitration Act
before the learned Additional District Judge and applied for
setting aside the said award. This application was dismissed
by the learned Additional District Judge. The Appellants
PG NO 518
filed an appeal against this decision on October 14,1982
before the Delhi High Court but the said appeal was
dismissed by the learned Single Judge of that High Court on
April 30, 1985. This decision of the learned Single Judge
was challenged before this Court by way of Special Leave
Petition under Article 136 of the Constitution. Leave was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 9
granted and the present Appeal came to be numbered as
aforesaid. This Appeal came up for hearing before a
Division Bench of this Court on November 18,1987. After
hearing Counsel for the parties. in order to ensure
fairplay in the action, this Court set aside the award of
the Arbitrator and also the judgment of the Delhi High Court
and appointed Shri A.C. Gupta, a former Judge of this Court,
as the sole arbitrator to adjudicate upon the disputes
between the parties. The arbitrator was directed to make his
award with short reasons within four months from the receipt
of the the order. Certain other conditions like payment of
compensation and additional expense were imposed on the
Appellants. Pursuant to the said order of this Court, the
said Shri A.C. Gupta entered upon the reference and made and
made and published his award on March 18,1988. Under the
said award, it was held that the Respondent was entitled to
a sum of Rs.58,498.60p and interest on this amount at the
rate of 18 per annum from the date of the reference to the
date of the award which worked out to a sum of Rs.3,510.
Taking into account the amount paid by the Respondent
initially towards the arbitrator’s remuneration and others
costs and after setting off the dues of Appellants against
the Respondent, it was held that the Respondent-claimant was
entitled to recover possession of the disputed building from
the Appellants and that a sum of Rs.57,753 was payable by
the Appellants to the Respondent. It is this award which is
challenged before us now.
The sole submission made by Mr. Bhandare, learned
Counsel for the Appellants is that the award is bad in law
and liable to be set aside as there is an error of law
disclosed on the face of the award. In this connection, Mr.
Bhandare drew our attention to clause 2(b) of the agreement
to sell dated September 6, 1973 referred to earlier. Ten
earlier part of the agreement set out that the purchaser
(Appellant No. 1) had paid to the seller (Respondent) a sum
of Rs.5,000, the receipt of which was acknowledged by the
Respondent and the balance amount payable was to be paid in
the manner set out in the said clause 2(b) which runs as
follows:
"The purchaser shall pay to the seller Rs.105 each month
against the .sanctioned loan of Rs.15,000 by the fifth day
of every English Calendar month till such time the full
PG NO 519
amount of loan is recovered from the seller by the
Government of lndia. The first instalment shall commence
with effect from 5th October, 1973 The purchaser, if he
desires, can also deposit the actual remaining amount
towards this loan at any time in lump sum to the Government
of India on behalf of the seller."
It is a common ground that the sum of Rs. 105 per month
referred to clause 2(b) of the said agreement was paid by
the Respondent only upto January 1976 and that this payment
covered upto 23 instalments more than 100 instalments were
remaining unpaid. Mr. Bhandare pointed out that it was
contended by the Appellants before the arbitrator that,
although the agreement for sale between the parties was not
registered and might not convey and interest to Appellant
No. 1 in the property, the Appellants had been put in
possession of the said land and construction pursuant to the
said agreement since September 1973, as appears from the
agreement of sale. and, in view of this, Appellants were
entitled to retain possession under the protection afforded
by Section 53A of the Transfer of Act. 1882. He drew our
attention to the following statements contained in the award
of the learned Arbitrator:
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 9
"The Respondent who has been in possession of the
property since September 1973 as would appear from the
agreement for sale, claimed that his possession was
protected Under Section 53A of the Transfer of Property
Act ......
Section 53A affords protection to a transferee on
certain condition, One of which is that ‘the transferee has
performed or is willing to perform his part of contract’.
Under the agreement for sale, the respondent was required to
pay the claimant a monthly sum of Rs. 105 to enable the
latter to pay the instalments in discharge of the house
building loan. From the receipts filed it appears that the
respondent paid only upto January 1976 which covered 23
instalments only and more than 100 instalments remained to
be paid. There is no valid reason why he should have failed
t to carry out his obligation under the contract. Thus it
cannot be said that the respondent had performed or was
willing to perform his part of the contract. Therefore, the
respondent was not entitled to retain possession of the
disputed property beyond January 1976."
PG NO 520
It was submitted by Mr. Bhandare that these statements
clearly disclose close an error apparent on the face of the
award. It is pointed out by him that, prior to February
1976, the Respondent by his Advocate’s notice dated
16.1.1976 had repudiated the said agreement for sale by
contending in his notice that it had been procured by fraud,
undue influence and coercion practised by Appellant No. I
and it was submitted that the said repudiation was wrongful
and in view thereof Appellant No. 1 was absolved from his
obligation to make any further payment of Rs.105 per month
or to continue to be ready and willing to perform the
agreement. It was submitted by him that the aforestated
statements contained in the award ran counter to the settled
position in law and disclosed a clear error of law on the
face of the award. He drew our attention to the decision of
this Court in International Contractors Ltd. v. Prasanta
Kumar Sur, [1961] 3 S.C.R. 579. In that case the appellant
had purchased the property in dispute from the respondent
but soon thereafter there was an agreement for reconveyance
of the property to the respondent within a period of two
years for almost the same value for which it was sold.
Before the expiry of the stipulated period, the respondent
entered into correspondence with the appellant, asking for
the completion of the agreed reconveyance and intimating
that the purchase money was ready to be paid, but after some
further correspondence, the appellant’s solicitors, on his
behalf, repudiated the agreement for reconveyance. The
respondent then did not tender the price agreed to be paid
and filed a suit for specific performance. The suit was
dismissed by the trial court on the ground that the
respondent had not paid the money. The High Court reversed
the decision and decreed the suit. On an appeal to this
Court, it was held that as the appellant had totally
repudiated the contract for reconveyance and had tailed lo
perform his part of the contract, it was open to the
respondent to sue for its enforcement and the High Court was
right in holding that respondent was entitled to a decree
for specific performance. In our view, Mr. Bhandare may be
right in contending that this decision does show that it has
been held by this Court that in certain circumstances once a
party to a contract has repudiated a contract, it is not
necessary for the other party to tender the amount payable
under the contract in the manner provided in the contract in
order to successfully claim the specific performance of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 9
contract. The decision, however, nowhere lays down that
where one party to a contract repudiates the contract, the
other party to the contract who claims specific performance
of the contract is absolved from his obligation to show
that he was ready and willing to perform the contract. Mr.
Bhandare’s argument really is to the effect that the
Respondent wrongly repudiated the contract by his said
letter dated 16th January, 1976, before all the mutual
PG NO 521
obligations under the contract had been carried out, that is
to say, he committed an anticipatory breach of the contract
and in view of this, Appellant No. 1 was absolved from
carrying out his remaining obligations under the contract
and could claim specific performance of the same even though
he failed to carry out his remaining obligations under the
contract and might have failed to show his readiness and
willingness to perform the contract. In our view, this
argument cannot be accepted. It is settled in law that where
a party to a contract commits an anticipatory breach of the
contract, the other party to the contract may treat the
breach as putting an end to the contract and sue for
damages, but in that event he cannot ask for specific
performance. The other option open to the other party,
namely, the aggrieved party, is that he may choose to keep
the contract alive till the time for performance and claim
specific performance but, in that event. he cannot claim
specific performance of the contract unless he shows his
readiness and willingness to perform the contract. The
decision of this Court in International Contractors Limited
v. Prasanta Kumar Sur, (supra), properly analysed, only lays
down that in certain circumstances it is not necessary for
the party complaining of an anticipatory breach of contract
by the other party to offer to perform his remaining
obligations under the contract in order to show his
readiness and willingness to perform the contract and claim
specific performance of the said contract. Mr. Bhandare also
referred to the decision of the Andhra Pradesh High Court in
Makineni Nagayya and Others v Makineni Bapamma., AIR (45)
1958 A.P. 504. We do not consider it necessary to refer this
decision as it does not carry the case of the Appellants any
further. The ratio of the said decision in no way runs
counter to the said position in law set out above.
In the case before us, what the arbitrator has done is
to set out in his award the relevant portion of Section 53A
of the Transfer of Property Act in terms of the said
section. There can be no dispute that these provisions have
been correctly set out. There is thus no error in the
proposition of law set out by the learned Arbitrator in the
award. It may be that there is an error, although that is by
no means certain. in the application of these principles in
coming to the conclusion that, notwithstanding the
repudiation of the said contract by the respondent,
Appellant No. I was not absolved from his obligation to pay
the remaining instalments of Rs.105 per month as provided
under the contract.
In Coimbatore District Podu Thozillar Samgam v.
Balasubramania Foundary and others, [1987] 3 S.C.C. 723 it
has been held by this Court that it is an error of law and
PG NO 522
not a mistake of fact committed by the Arbitrator which is
justiciable in the application before the Court. If there is
no legal proposition either in the award or in any document
annexed to the award which is erroneous and constitutes the
basis of the award and the alleged mistakes or alleged
errors, are only mistakes of fact the award is not amenable
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 9
to corrections by the Court. In its judgment, the Court
referred to the decision of this Court in Union of India v.
A. L. Rallia Ram, [1964] 3 S.C.R. 164; AIR 1963 SC 1685 and,
after referring to certain factors pertaining to awards in
arbitration proceedings and the machinery devised by the
Arbitration Act 1940, pointed out that the award was the
decision of a domestic tribunal chosen by the parties and
the civil courts which were entrusted with the power to
facilitate arbitration and to effectuate the awards, could
not exercise appellate powers over the decisions. This Court
reiterated that it was now firmly established that an award
was bad on the ground of error of law on the face of it only
when in the award itself or in a document actually
incorporated in it, there was found some legal proposition
which was the basis of the award and which was erroneous.
This view was enunciated by the Judicial Committee in
Champsey Bhara and Co. v. Jivraj Balloo Spinning and Weaving
Co. Ltd., [1922-23] LR 5O IA 324; 1923 AC 480. This view was
again reiterated and emphasised by this Court in Kanpur
Nagar Mahapalika v M/s Narain Das Haribansh, 11970] 2 S.C.R.
28; (1969) 2 SCC 620 where Ray, J., as the learned Chief
Justice then was, observed at page 30 of the Report relying
on Champsey Bhara case:
"An error of law on the face of the award meant that one
could find in the award, or in a document actually
incorporated thereto, as, for instance. a note appended by
the arbitrator stating the reasons for his judgment, some
legal proposition which was the basis of the award and which
one can say is erroneous."
In State of Orissa & Ors v M/s Lall Brothers, [1988]
Judgment Today S.C. 552 it was held by a Bench of this
Court that it is not open to the Court to speculate, where
no reasons are given by the arbitrator, as to what impelled
him to arrive at his conclusions. Reference was made in
this connection (see paragraph 8) to the observations of the
Judicial Committee in Champsey Bhara & Co. v. Jivraj Balloo
Spinning & Weaving Co. ltd. and of this Court in Jivarajbhai
Ujamshi Sheth & Ors. v. Chintamanrao Balaji and Ors, [1964]
5 S.C.R. 480.
PG NO 523
It was next contended by Mr. Bhandare that the award
disclosed an error in law as certain important documents
relied on by the Appellants were not referred to or
discussed in the award at all. In support of this contention
Mr. Bhandare referred to the decision in K.P. Poulose v.
State of Kerala and Another, [1975] 2 S.c.c. 236. In that
case the arbitrator failed to take into account material
documents, which were necessary to arrive at for a just and
fair decision to resolve the controversy between the parties
and it was held that this amounted to legal misconduct on
the part of the arbitrator and his award liable to be set
aside. This decision is not of much assistance in the case
before us as it is not the contention of Mr. Bhandare that
the award is bad on the ground of any misconduct of the
arbitrator but on the ground that it discloses an error of
law on the face of the record. Moreover, our attention has
not been drawn to any particular document which was
essential to resolve the controversy between the parties nor
has it been demonstrated that any such document was not
taken into account by the arbitrator. In view of this, there
is no basis to support the contention of Mr. Bhandare which
must be rejected. It cannot be even said in this case that
the arbitrator was guilty of any legal misconduct or
otherwise .
The objections to the Award of Shri A.C. Gupta,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 9
therefore, fail and are dismissed. There will be a judgment
in terms of the Award. Let the decree be drawn up
accordingly. In the facts and circumstances of the case,
there will be no order as to costs to the hearing before us.
N.V.K.