Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
PETITIONER:
HUDA & ANR.
Vs.
RESPONDENT:
RANJAN DHAMINA & ANR.
DATE OF JUDGMENT: 17/12/1996
BENCH:
K. RAMASWAMY, G.B. PATTANAIK
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
PATTANAIK, J.
Leave granted
This appeal by special leave is directed against the
judgment dated 25.3.1996 of a learned Single Judge of the
Punjab and Haryana High Court in R.S.A. No. 288 of 1996
dismissing the defendants’ second Appeal and confirming the
judgment and decree of the learned trial Judge as affirmed
by the learned Additional district judge.
The plaintiffs filed the suit for a declaration that
the notice issued by Defendant No 1 on 5.4.1990 demanding
the additional sum of Rs. 4,66,847/- is illegal, invalid and
inoperative and as such defendants are not entitled to
claim the said amount. The short facts as pleaded in the
plaint are that industrial plot No. 42 in Sector 10 in
industrial estate, Gurgaon was provisionally allotted to the
plaintiffs in the name of M/s. Exotica International
Enterprises under letter dated 7.10.1984 (Ex. P.1). The
price fixed for the plot was Rs.1,54.870/ - at the rate of
Rs 154.87 per square metre. A part of the amount was
required to be paid immediately and accordingly the
plaintiffs deposited the demanded amount of Rs. 48,396.90
under Exhibit P.2 dated 9.10.1985. The possession of the
plot was delivered to the plaintiffs on 14.11.1985 and the
delivery of possession is indicated under Ex. P.3. The
plaintiffs thereafter started construction on the plot as
per approved plan and ultimately requested the defendants by
his letters dated 9.5.1989 and 2.6.1989 to finalise the
matter on receipt of the entire remaining price. At that
point of lime the defendants demanded that unless the
plaintiff pays at the rate of Rs. 269.92 pr square metre the
matter cannot be finalised 87 that time plaintiff had
already spent a huge sum in making construction had already
agent a huge sum in making construction over the land and
therefore, had no other option than to agrey to any the
enhanced price . consequently the defendants issued the
letter of allotment dated 24.11.1983 (Ex.P.11) fixing the
price of the plot at Rs.3,78,250/- and pursuant to the
aforesaid letter the plaintiff paid the balance amount which
was acknowledged by the defendants under receipt No.13126
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
dated 24.11.1989 (Ex.P.7) and receipt No. 13169 dated
24.11.1989 (Ex.P.8). When the plaintiff then requested to
get the conveyance need executed the defendant No. 2 issued
the impugned letter No. 2108 dated 5.4.1990 (Ex.P.12)
intimating the plaintiff that the extent of Rs. 560.60 per
square mere and therefore plaintiffs are required to pay a
further sum of Rs. 4,66. 847/- The plaintiffs, therefore,
filed the suit for the validity of the aforesaid demand of
the defendants. The defendants in their written statement
challenged the main inability of the suit and also took the
stand that the plaintiffs had not approached the court with
clean hands. The defendants admitted of having issued the
letter of allotment (Ex.P.11) dated 24.11.1989 under which
the price of the plot of land been fixed at Rs.3,79,250/-
but contended that defendants were entitled to a higher sum
in accordance of the parties the learned sub-judge, Gurgaon
framed as many as issues and parties laid evidence on the
suit on discussion of the entire evidence on the suit on
discussion of issue Nos. 1 and 2 came to the finding that
increase in the rate was taken by the defendants due to
default of the plaintiffs . On Issue No.3 which is most
crucial issue the learned trial judge came to hold that
under condition No 9 of Ex P.11 enhancement can be claimed
only when the cost of land date enhanced on account of
Acquisition of the competent authority under the land
Acquisition Act and the absence of any material to indicate
that the cost of the land was increased on account of award
of compensation by the competent court under the Land
Acquisition Act the defendants were not entitled to raise
the additional amount of Rs. 4,66,841/- under their letter
dated 5.4.l990, Ex. P.12 and as such the said demand is
illegal, void and ultravires. On issue No. 4 the learned
Judge came, so hold that the area of plot was 1250 square
metre. On the question of jurisdiction of the Court under
Issue No. 5 it was held that the Civil Courts have the
jurisdiction to entertain and decide the controversy. Issue
Nos. 6, 7 and 8 were not pressed by the counsel appearing
for the defendants and as such they are held against the
defendants. On these findings the suit was decreed and it
was held that the defendants are not entitled to claim the
additional amount as per their letter dated 5.4.l990 ( Ex .
P .12 ). Against the judgment and decree of the learned
trial Judge the defendants carried the matter in appeal. The
additional District Judge, Gurgaon disposed of the Civil
Appeal No. 41 of 1994 by his judgment dated 26th of April,
l995 and on reconsideration of the material on record
confirmed the findings of the trial Judge and dismissed the
appeal. While dismissing the appeal the learned Additional
Judge observed that the counsel for the appellant failed to
indicate on what account the rates of the land were further
enhanced from Rs. 269.92 per square metre to Rs. 560.60 per
square metre. The Appellate court also came to the
conclusion that defendants are not entitled to go beyond the
condition laid down in clause (9) of the letter of allotment
(Ex.P.11) and since there was no enhancement of the
compensation by any court in the land acquisition
proceedings the additional demand letter dated 5.4.1990
(Ex.P.12) is without any basis and thus liable to be set
aside. Against the dismissal of the appeal by be set aside.
Against the dismissal of the appeal by the learned
Additional District judge, Gurgaon, defendants preferred the
second appeal which was registered as R.S.A. No.288 of 1996
the learned counsel appearing for the defendants -
appellants himself stated before the high court that in
spite of making efforts the appellants have not been able to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
satisfy as to how defendants are entitled to claim to
enhance price the learned counsel could not indicate any
error in the judgment and decree of the courts below and,
therefore, the second appeal was dismissed by the impugned
judgment dated 25.3.1996 . Hence this appeal by special
leave.
The learned counsel for the appellants contended with
emphasis that the price indicated in the letter of allotment
(Ex.P.11) was tentative as is apparent from clause (9) of
the letter of allotment and therefore, when clause (9) of
the letter of allotment itself postulates enhancement of the
cost of the land the authorities were justified in raising
the additional demand. We do not find any force in the
contentions of the learned counsel for the appellants since
clause (9) enable the competent authority to ask for
additional amount only when there has been enhancement in
the cost of land on account of any award by the competent
authority determining compensation under the land
Acquisition Act. clause (9) is extracted hereinbelow in
extenso:
"The above price is tentative to
the extent that any enhancement in
the cost of land awarded by the
competent Authority under the Land
Acquisition Act shall also be
payable proportionately as
determined by the authority. The
additional price determined shall
be paid within thirty days of its
demand"
The aforesaid clause unequivocally indicates that if
there has been any enhancement in the cost of the land on
account award by the competent authority under the land
Acquisition Act then the said enhancement would be payable
proportionately as determined by the authorities. The
aforesaid clause does not authorise the alloting authority
to raise addition. It is well settled that the competent
authority is entitled to demand the price as on the date of
final letter of allotment, Ex.P.11 has been found to be the
letter of allotment which has not been assailed before us.
Even though the appeal arises out of a civil suit and
parties had appeal arises out of a civil suit and parties
had laid evidence in the forums below and no evidence was
laid indicating the enhancement of cost of land on account
of any development of cost of land on account of any
developmental work yet the appellant being a public
authority, this court had directed by order dated 23.9.1996
to place materials to indicate any development effected to
the plaintiffs plot from the date of possession given to the
plaintiffs and the resultant enhancement of the price. It
was also indicated that the defendants - appellants should
also indicate how many more cases of this type are pending
pursuant to the aforesaid order a letter dated 16.1.1990
from the chief Administrator Haryana Development Authority
to the Estate officer HUDA, Gurgaon has been filed
whereunder the chief Administrator had directed the estate
officer to charge at the current rate of Rs. 560.60 per
square metre while issuing the final allotment letter. The
appellants have also produced a copy of the land to Rs.
560.60 per square metre But these documents are of no
assistance to the appellants inasmuch as the final letter of
allotment (Ex.P.11) was dated 24.11.1989 much prior to the
issuance of letter officer dated 16.1.1990. That apart by
order of this court to dated 23.9.1996 the appellants were
called upon to place materials to indicate if any further
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
development to the plaintiffs land has been made from the
date of possession given to them but no such materials have
been placed before us. The so called resolution alleged to
have been passed by the authority enhancing the price of the
land will not be applicable to the plaintiffs plot in whose
case the final letter of allotment had been issued on
24.11.1989 as per Ex.P.11. In the aforesaid circumstances
with the impugned judgment of the High Court affirming the
decision of the learned Additional district judge. This
appeal is accordingly dismissed but in the circumstances
there will be no order as to costs.