Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
PETITIONER:
ARMY WELFARE HOUSING ORGANISATION
Vs.
RESPONDENT:
M/S. GAUTAM CONSTRUCTION & FISHERIES LTD.
DATE OF JUDGMENT: 17/09/1998
BENCH:
A.S. ANAND, D.P. WADHWA
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
D.P.Wadhwa. J.
IAs 17 to 20 of 1998 are objections filed by
M/s Gautam Construction and Fisheries Ltd., (GC&FL)
under Section 15,17 and 33 of the Arbitration Act,
1940 (for short, the ’Act’) to the award dated
September 9, 1997 of the sole Arbitrator, Justice V.
Khalid, a retired Judge of this Court. IAs 21 to 24
are the objections similarly filed by the Army
Welfare Housing Organisation (AWHO) against the same
award.
GC&FL in their objections seek directions
for modification of the award to correct an error
with regard to wrong deduction of Rs.30,000,00/-
twice by the Arbitrator from their claims 1 and 13
in their statement of claim. They have also claimed
interest @ 18% per annum on the amount of the award
in their favour till payment. AWHO in their
objections also seek modification of the award
stating that their claim for anticipated liability
towards completion of the contract was wrongly
rejected by the Arbitrator when some of the amounts
claimed were towards "firm liability". Both parties
disputed the objections of each other to the award
as aforesaid.
Little background will be necessary to
understand the objections raised by the parties.
There was a contract entered into between them for
construction of certain number of dwelling units by
GC&FL for AWHO on the land belonging to GC&FL.
Contract contained an arbitration clause. Disputes
arose between the parties resulting in cancellation
of contract by the WHO and issuance of publication
of notice for re-tendering of the contract for the
balance of the work. Instead of the contract, GC&FL
filed an application under Section 20 of the Act and
also filed an application under Section 41 of the
Act seeking interim directions. These proceedings
were filed in the Madras High Court. These learned
single Judge by order dated September 18, 1995
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
appointed a retired Judge of the Madras High Court
as sole arbitrator and at the same time restrained
WHO from re-tendering the work pending disposal of
arbitration proceedings. Arbitration agreement
under the contract prescribed a different mode for
appointment of arbitrator but that is nor relevant
now and unnecessary for us to examine that aspect.
Aggrieved by the judgement of the High Court, WHO
sought leave to appeal to this court which was
granted by order dated December 4, 1995 and the
appeal itself was also heard and disposed of on the
same day. With the consent of the parties, this
Court, as the Arbitrator and also authorised him to
take any help from any technically qualified person.
Liberty was given to the parties to approach the
Arbitrator for any interim relief including vacation
of the injection order granted by the High Court
regarding re-tendering of the work. It was also
directed that the Arbitrator would file the award in
this court only and other courts were interdicted
from interfering in the arbitration proceedings.
After entering in to the reference, the
Arbitrator gave an interim award on May 8, 1996
whereby he vacated the order of injunction granted
by the High Court in its judgement dated September
18, 1995. This interim award when filed in this
court was made rule of the Court as no party filed
any objection to the same. Thereafter, the
Arbitrator gave his final award on September 9, 1997
and on notice of filing the same given to the
parties, they filed their objections now under
consideration.
The award is quite elaborate. It take into
account numerous details. Arbitrator framed as many
as 10 issues and then went on to examine each of the
claims put forward by the parties with reference to
the record before him. In the objections filed by
AWHO it seeks remission of the award. The
objections are though under Section 15, 17 and 33 of
the Act. In the course of arguments, it was
submitted by Mr. Tiwari, learned counsel for the
AWHO that the award be remitted back to the
Arbitrator which would be under Section 16 of the
Act, though in the prayer modification of the award
under Section 15 is sought. AWHO submitted that
though if claimed certain amounts as ’firm
liability’ after the contract was cancelled and
there were certain ’anticipated expenses’ required
to complete the contract. It was submitted that the
Arbitrator treated even the firm liability as in the
nature of elements of anticipated expenses and
disallowed, the Arbitrator committed a mathematical
error. It is not the case of the AWHO that the
Arbitrator did not examine or did not take into
account the claim put forward by the AWHO. It is
not possible for us to re-appreciate the evidence
produced before the Arbitrator and then ourselves
coming to the conclusion whether a certain amount
claimed was towards firm liability’ or in the
’nature of anticipated expenses. Once the
Arbitrator had held that the claim would be in the
’nature of anticipated expenses. It is difficult
for us to hold the same otherwise. It cannot be
said that the award is not good on the face of it on
that account. The objections of AWHO have no force
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
and IAs 21 to 24 are rejected.
Under the terms of the contract GC&FL would
be entitled to a total amount of Rs.54,95,271.72 as
retention money from the total contract amount. The
Arbitrator found that under the Contract, GC&FL
executed work of the value of Rs.4,52,10,002/- and
as such GC&FL would be entitled to retention money
to the extent of 63.47%. Thus from the retention
money of Rs.54,95,271/- which GC&FL would be
entitled to on compaction of the contract, a sum of
Rs.34,87,848.90 is now due to them being 63.47% of
Rs. 54,95,271.72. On completion of 50% if the
work, GC&FL had already received Rs. 30,00,000/- as
retention money in three installments. Thus, GCC&FL
would be entitled to the balance amount of
Rs.4,87,848.90 towards the retention money. The
Arbitrator found that under claims 1 and 13 of GC&FL
an amount of Rs.7,08,893.60 would be due to GC&FL
from AWHO. This is how the Arbitrator arrived on
this figure :
"The ultimate position is as follows:
RAR BILL 23 DEMAND:Rs.
1.Value of work exeuted 450,44,002.35
2.Value of extra work 1,66,000.00
3.Total 4,52,10,002.35
4.Val.of materials lying site 29,57,657.00
5.Grand total 4,81,67,659.70
6.Percentage of work done 63.47%
DEDUCTION
a) Retention Money 2,00,000
b) Cost of Schedule "B"
materials supplied by
AWHO 1,69,37,615
c) Income Tax 11,52,990
d) Interest on Rs.18 lakhs
advance’ 6,26,117
e) Payment for RAR bills
upto Bill No.22 2,47,55,521
f) Advance of retertion
money after 50%
work done 30,00,000
g) Advance made at site 12,74,372 4,79,46,615.00
Balance Receivable 2,21,044.70
h) Proportionate retention money
payable at 63.47%ofRs.54,95,271.72
less Rs.30,00,000/-already paid 4,87,848.90
Total Balance Receivable 7,08,893.60
Thus, a sum of Rs.7,08,893.50 is allowed
under Claim No.1 and 13."
The objection of GC&FL is that amount of
Rs.30,00,000/- has been deducted twice by the Arbitrator
which was a mistake apparent on the face of it and as such
this Court should modify the award and grant a further
amount of Rs.30,00,000/- to that already awarded by the
Arbitrator under claims 1 and 13. We do not think that Mr.
Thakur is right in his approach. GC&FL is entitled to
Rs.4,87,848.90 towards balance of retention amount as an
amount of Rs.30,00,000/- GC&FL, it should have deducted
Rs.30,00,000/- which it had already received. As a matter
of fact, the Arbitrator observed as under :-
"Claim No. 1 suffers from a serious flaw
and the same can be rejected outright. On
a perusal of the claim and the various
items shown therein. it is seen that the
petitioners have either inadvertently or
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
deliberately omitted to deduct Rs. 30
lakhs towards retention money obtained by
them on three occasions for 50% of the
work done. If this Rs.30 lakhs is
deducted from the claim minus figure.
This error, however, is seen corrected in
the petitioners’ reply to the Respondents’
claim No.1"
In fact, in the calculations aforesaid, under Item
(h), the Arbitrator could have said : "Balance of the
retention money payable - Rs.4,87,848.90" Retention money
due to GC&FL is from the whole of the value of the contract.
Total of retention money as arrived at by the Arbitrators is
Rs.54,95,271.72 which is payable on completion of the
contract by the AWHO. Since GC&FL, executed only 63.47% of
the value of the contract they became entitled to
Rs.34,87,848.90 being 63.47% of Rs.54,95,271.72. Having
already received Rs.30,00,000/- GC&FL became entitled to
balance amount of Rs.4,87,848.90 which the Arbitrator
allowed them under the award.
As far as the claim of interest is concerned, the
award has already allowed the same and no objection thereto
has been filed by AWHO or even by GC&FL on the claim due to
AWHO under the award. IAs 17 to 20 of the GC&FL are
rejected.
IAs 13 to 16 filed by GC&FL seeking directions for
modification of the Award and for grant of interest also
stand dismissed.
Accordingly the award dated September 9, 1997 is
made rule of the court and decree in terms thereof will be
passed. Since both the parties have failed in their
objections to the award, they shall bear their own costs.