Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 16
PETITIONER:
MURARI & ORS.
Vs.
RESPONDENT:
UNION OF INDIA & ORS.
DATE OF JUDGMENT: 01/11/1996
BENCH:
KULDIP SINGH, FAIZAN UDDIN
ACT:
HEADNOTE:
JUDGMENT:
With transferred cases No. 21, 22, 23, 24, 25, 26, 27,
28, 29, 30, 31/1995
Nos.13961-14029/96
With Civil Appeals/arising out of SLP (C) Nos. 2395, 2397,
2399, 2400, 2401, 2421, 394, 484, 305, 430-432, 1026, 1084,
2403, 740, 744, 2439, 2440, 1212, 802, 2608, 2669, 2601,
2815, 3434, 3611-3613, 3964, 5563, 5344, 4463, 4465, 4243,
5398, 4161, 4181. 1264, 1270, 2523, 2527, 2528, 3968, 3969,
4344, 5738, 5749, 5781, 5911, 5914, 5916, 5771, 6060, 6061,
6064, 6066, 5567, 7908, 6362, 7700, 8012, 8018, 8019, 8026,
8027, 8036, 7889 & 7875/1996. SLP(C) No.21671/96 (CC
1607/96)
J U D G M E N T
Faizan Uddin, J.
Leave granted,
1 .The appellants in the appeals enumerateted herein
above had challenged the acquisition proceedings in respect
of their respective lands acquired under he Land Acquisition
Act, 1894 for purposes of planed development of Delhi by
filing various writ phitions before the High Court of Delhi.
The said write petition were dismissed by a Full Bench of
the Delhi High Court by judgment dated December 14, 1995
against which these appeals have been preferred by special
leave. Various notifications were issued from time to time
under Section 4 of the Land Acquisition Act, 1894 for
acquisition of land for the public purpose of
planneddevelopment of Delhi. The said notification covered
the land belonging to the transfer petitioners, appellants
and some other persons. The transfer petitioners like others
had also filed writ petitions in the High Court of Delhi
being writ petitions No. 2179, 2178, 2140, 2139, 2197, 2083,
2138, 2144, 2199/1983 and civil writ petitions No. 810-
812/1984 challening the acquisition of their respective
lands on various grounds. These writ petitions were pending
in the High Court. However, during the course of hearing of
writ petition (C) No. 4677/1985 pending before this Court it
was felt necessary to transter all the aforesaid writ
petitions from Delhi High Court to this Court. Consequently
on the basis of Interlocutory Applications No. 20 and 21 of
1995 in W.P. (C) No. 4677/1985 this court by order dated
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 16
December 14, 1994 directed that all the aforementioned writ
petitions be transferred to this court. This is how those
writ petitions stand transferred to this court which have
been registered as transfer cases Nos. 21, 22, 23, 24, 25,
26, 27, 28, 29, 30 and 31 of 1995. As said earlier besides
the aforementioned transfer cases large number of writ
petitions filled by various persons were already pending
before the High Court of Delhi challenging the acquisition
of their respective lands for the public purpose of planned
development of Delhi which were dismissed by a full Bench of
the High Court of Delhi by the impugned common judgment
dated December 14, 1995 against which the appeals referred
to above have been filed by special leave. Since the common
question of law and facts arise in all these transfer cases
and appeals and, therefore, they were clubbed together and
are being disposed of by this common judgment.
2. The facts in brief leading to the transfer cases and
the appeals may he narrated thus:-
Various notifications under Section 4 of the Land
Acquisition Act (hereinafter referred to as the Act) were
issued from time to time between 1959 and 1965 for the
acquisition of several thousand acres of land for the
common, public project, namely, planned development of
Delhi. Declarations under Section under Section 6 of the Act
were also made between the years 1966 and 1969, while the
making of the awards was deferred till the year 1979-80. The
master plan of Delhi was brought into force in September
1962 giving the details of the facts and circumstances under
which it became imperative to have a development plan of the
city of Delhi. It is common knowledge that after the
partition of the country there was enormous and huge
migration of population into India mainly at Delhi which
resulted into a phenomenal growth of population of the
settlers in Delhi besides considerable growth of industrial
and commercial activities, which gave rise to various
residential and occupational problems as a result of which
various sub standard structures, complexes and colonies came
into being without proper layouts and other essentials of
life. No lands was available at reasonable price and within
the reach of common man. It was in these circumstances and
with a view to give a proper shape to the city of Delhi, the
capital of India, the Central Government had set up a Delhi
Development Authority in 1950 and later in December 1955 a
Town Planning Organisation was set up under the
administrative control of Delhi Improvement Trust to monitor
the planning development in the National Capital Territory
of Delhi. It was in this background that planned development
of Delhi was conceived of and to achieve that objective
various notifications under Section 4 of the Act were issued
from time to time between the period from 13.11.1959 and
21.11965 whereby large chunks of land were sought to be
acquired. after issuance of notices under Section 9 and 10
of the Act a spate of writ petitions were filed challenging
the acquisition proceedings on various grounds whose lands
were sought to be acquired, most of which were dismissed
including the Letters Patent Appeal by the High Court by an
earlier judgment dated April 29,1972 vide I.L.R. (1971)
3. The said judgment was challenged in appeal before this
Court which was also dismissed by judgment dated August 23,
1974 by a Constitution Bench of this Court which is reported
in 1975 (1) SCR 8O2 = AIR 1974 SC 2077 Aflatoon & Ors. Vs.
Ltd. Governor of Delhi, in which amongst others the
contentions before this Court were raised that (1) the
public purpose specified in the notification under Section 4
of the Act was vague as neither master plan nor zonal plan
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 16
was in existence on the date of notification; (2) that there
was inordinate delay in finalising the acquisition
proceedings by reason of which the land owners were deprived
of the benefits of the appreciation of price between the
date of notification under Section 4 and the date of taking
possession of the property; (3) that provisions of Section
23 of the Act laying down that the compensation should be
determined with reference to the market value of the land as
on the date of notification under Section 4 of the Act was
unreasonable restriction and affecting the fundamental
rights of the land owners. but this Court repelled all the
contentions and dismissed the appeals and the writ petitions
by maintaining the validity of notices issued under Section
4 of the Act laying down that in the case of an acquisition
of large areas of land belonging to different persons, the
specification of public purpose can only be with reference
to the acquisition of the whole area for it may be difficult
to specify the particular purpose for which each and every
item of land comprised in the area is needed but unlike the
case of an acquisition of a small area. The said
Constitution Bench of this Court dispelled the challenge of
the acquisition proceedings on the ground of delay by
holding that the appellants of that case did not move the
Court in the matter even after the declaration under section
6 was published in the year 1966 but they preferred to
approach the Court with their writ petitions only in 1970
when notices under Section 9 were issued. This Court further
took the view that the appellants of that case allowed the
Government to complete the acquisition proceedings on the
basis of the notifications under Section 4 and declaration
under Section 6 of the Act which were available to them at
the time when the notifications were published and if their
objection is allowed to stand it would amount to putting a
premium on dilatory tactics adopted by them. On the question
of delay in completing the acquisition proceedings the
Constitution Bench in the aforementioned case observed that
about 600 objections were filed under Section 5-A of the Act
and civil writ petitions were also filed challenging the
validity of the acquisition proceedings. Consequently the
Government unnecessarily had to wait for disposal of those
objections and petitions before proceeding further in the
matter and, therefore, it was bound to result in delay. It
was further held that the Land Acquisition Act being a pre
constitution Act its provisions are not liable to be
challenged on the ground that they are not in conformity
with the requirement of Article 31(2) of the Constitution.
The land owners, therefore, could not complain about the
payment of compensation computing with reference to the
market value of the land as on the date of notification
under section 5 and Section 23 of the Act could not be held
to be bad, as such a challenge is precluded in view of
Article 31(5) of the Constitution. This Court further held
that it is true that there could be no planned development
of Delhi except in accordance with the provisions of Delhi
Development Act after that Act came into force but there was
no inhibition in the acquisition of land for planned
development of Delhi under the Act before the master plan
was ready.
4. Before the High Court a number of controversies and
objections were raised and the acquisition proceedings were
sought to be challenged on various grounds including
challenge to the validity of the declarations made from time
to time under Section 6 of the Act using the notification
issued under Section 4 of the Act as the reservoir and that
more than one declarations under Section 6 of the Act were
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 16
issued which according to the transfer petitioners and the
appellants were not permissible. A plea was raised that
after the lapse of a long period and inordinate delay in
completing the proceedings, the proceedings must result in
the abandonment of the acquisition proceedings and no award
on the basis of such proceedings can validly be made. It was
also contended that more there one award is not contemplated
by law in respect of the land, which was the subject matter
of one declaration issued under Section 6 of the Act. A
further contention raised before the High Court was with
regard to the interpretation of Section 55 of Delhi
Development Act, 1957 (hereinafter referred to as the Delhi
Act). It was contended that some of the land owners had
issued notice to the Central Government under sub-section
(1) of Section 55 of the Delhi Act with regard to the
requirement of the designated land under the master plan or
sta zonal development plan but the Central Government failed
to acquire the land within a period of 6 months from the
date of receipt of the said notice as required by sub-
section (2) of Section 55 and, therefore, the said omission
on the part of the authorities to complete the acquisition
proceedings within the stipulated time would result in
abandonment of the acquisition proceedings completely in
respect of such land to which Section 25 of the Delhi Act
was applicable. It was also contended before the High Court
by some of the transfer petitioners and appellants that
according to Article 31-A of the Constitution the
appropriate value of the land forming part of an estate
which is sought to be acquired would be the market value
prevailing at the time of award and not the value prevailing
on the date of notification under Section 4 of the Act as
contemplated in Section 23 thereof. The appellants of the
civil writ petition No. 325/1982 (Ram Phal Vs Union of
India) before the High Court took the plea that the Central
Government had issued an order under Section 48 of the Land
Acquisition Act withdrawing the acquisition proceedings in
respect of their land and, therefore, the acquisition
proceedings in respect of the said land be quashed. The High
Court repelled all the aforementioned contentions as well as
some other grounds on the basis of which the acquisition
proceedings were sought to be quashed and dismissed the writ
petitions by the common judgment as said earlier against
which these appeals have been preferred. To some extent same
grounds are advanced by the learned counsel appearing for
the land owners in the transfer cases.
5. The main attack by learned counsel appearing for all
the appellants and those representing the transfer
petitioners was advanced for quashing the acquisition
proceedings on the ground of delay in completing the
acquisition proceedings. M/s. Soli Sorabjee, Venugopal, P.N.
Lekhi, Kapil Sibal, Rajiv Dhavan, H.N. Salve, G.L. Sanghi
learned senior counsel and host of other advocates appearing
for the appellants made a concerted effort to show that
there was unreasonable delay of about 15 to 20 years in
completing the acquisition proceedings by the respondents by
reason of which the land owners were deprived of the
reasonable and real price of their properties who have been
offered only a pittance of compensation after a long lapse
of time while the prices have gone up many times high in
between the period from the date of notification under
Section 4 to the date of making the award and taking
possession of the properties. It was submitted that the main
purpose in issuing the notifications under Section 4 of the
Act during the period from 1959 - 1965 was to freeze the
price of the land causing great loss to the land owners. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 16
decision rendered in the case of Ram Chand Vs. Union of
India 1994 (1) SCC 44 was sought to be distinguished by
contending that the same cannot stand as a bar in cases for
the reason that though the award had been made in the year
1980 but no possession was taken from the land owners and,
therefore, Ram Chand’s case has no application to the facts
of the present case. Shri Soli Sorabjee further added that
there is internal inconsistency in the decision of Ram
Chand’s case and the same cannot be taken to be an authority
on the proposition in all situations but different
principles have to be applied on circumstances of each case
when the fact situation is different. It was vehemently
urged by all the learned advocates that the award of
interest at the rate of 12 percent after the expiry of two
years from August 1974 in respect of the awards made prior
to the amendment of Section 23 of the Act would not mitigate
the loss suffered by the land owners. The 18th report of the
Public Accounts Committee of the 7th Lok Sabha on the
working of the Delhi Development Authority was also sought
to be pressed in service to support the aforementioned
submissions in addition to various decisions of this, Court.
It was stated that the Public Accounts Committee in its
report dated 26.4.1981 at page 101 stated in para 5.29 that
it is well known fact that the D.D.A. acquires land from the
land owners at a very low rate and after development sells
it at exorbitant rates thereby earning huge profits. It was
stated that even where land is acquired for a public
purpose, a reasonable compensation has to be paid but in
cases where land is acquired and later sold by auction or
for commercial purposes, as has happened in most cases, the
ommittee feels the land owners/farmers should not be
compelled to part with their holdings at throw away price,
the committee therefore recommended that the Land
Acquisition Act may be suitably amended so that the interest
of the farmers are properly safeguarded.
6. After giving our thoughtful consideration to the
submissions made above, it may be stated that the report of
the Public Accounts Committee referred to above and on which
great emphasis was laid is nothing but recommendations for
the necessary amendment in the Act. The recommendations of
any authority howsoever high it may be cannot be enforced
unless the same take the shape of law. The provisions of the
Land Acquisition Act as they stand today have to be
interpreted and applied in accordance with existing position
of law and in its true sense of perspective in respect of
which this Court has made authorotative pronouncements on
the points raised and contended by the learned counsel. In
the present case as stated earlier after issuance of the
notifications and notices under Section 9 and 10 of the Act
not only large number of objections were filed by the land
owners whose land was sought to be acquired but a number of
writ petitions were filed in the Delhi High Court
challenging the validity of the notification under Section
4 as well as the declaration under Section 6 in which
interim orders of stay were passed by the High Court which
resulted in the considerable delay. Thus the authorities
alone were not responsible for the delay but the land owners
were equally responsible for the same . In such
circumstances and on consideration of several decisions of
this Court including those rendered in the case of Bihar
State Housing Board Vs. Ram Behari Mahato AIR 1988 SC 2134;
and Ujjain Vikas Pradhikaran Vs. Raj Kumar Johri 1992 (1)
SCC 329 this Court in the case of Ram Chand Vs. Union of
India 1994 (1) SCC 44 took the view that in any case
there. was no justification for the authorities to make the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 16
award in 1980/1981/1983 when the declaration under Section 6
was made in 1966-69, but at the same time, in view of the
facts of delay caused by land owners themselves in
approaching the Courts and the developments already made on
the lands for public use, quashing of acquisition
proceedings would not be appropriate. But at the same time
in the said decision this Court also took the view that the
land owners alone were not responsible for the entire delay
that was caused in completing the acquisition proceedings.
This Court in the said decision pointed out that all those
writ petitions were dismissed by this Court on August 23,
1974 in the case of Aflatoon Vs. Ltd. Governor of Delhi yet
no effective steps were taken by the respondents till 1980-
81 and in some cases even till 1983 for which the
respondents could give no justification for that delay on
their part in completing the acquisition proceedings even
after the judgment of this Court in Aflatoon’s case. This
Court having regard to the fact that the Delhi
Administration and Delhi Development Authority after taking
possession of the lands various developments have been made
and third party interest have also been created and,
therefore, having regard to the larger public interest
declined to quash the acquisition proceedings on the ground
of delay but at the same time having regard to the interest
of the land owners who were likely to suffer loss in rating
the price of the land with reference to the date of
notification under Section 4, directed payment of an
additional amount of compensation to be calculated at the
rate of 12 percent per annum after expiry of two years from
August 23, 1974, the date of judgment of this Court in
Aflatoon’s case (supra) till the date of the making of the
awards by the Collector to be calculated with reference to
the market value of the lands in question on the date of
notification under Section 4(1) of the Act. We do not find
any inconsistency in the said decision (Ram Chand’s case)
and find ourselves in respectful agreement to the view taken
by this Court in the case of Ram Chand (supra). The same
principle has to be applied in those cases in which the
possession is not taken and there is no reason to
distinguish such cases from the application of the
principles laid down in Ram Chand’s case merely on the
ground that possession is not taken from some of the land
owners. In this connection the fact could not be lost sight
of that the land owners have enjoyed possession all these
years and have taken the benefit of the usfruct and other
advantages out of the said land and, therefore, they stand
even in an advantageous position than those land owners from
whom the possession was taken earlier.
7. It was then contended that it was not open to the
Government to issue more than one declaration under Section
6 of the Act with regard to the land comprised within one
notification under Section 4 of the Act. In other words it
was submitted that the notification under Section 4 cannot
be treated as a reservior from which land could be taken
from time to time and declaration one after the other may be
made under Section 6 of the Act which is not permissible
under the Act and, therefore, the acquisition proceedings
were liable to be, quashed on this ground. In this
connection we feel it necessary to mention some of the facts
and circumstances which are relevant to the submissions made
above and to see whether the submissions have any merit or
not to the facts and circumstances of the present case. It
may be stated that similar question was raised before this
Court in the case of State of M.P. Vs. Vishnu Prasad Sharma
AIR 1966 SC 1593 decided by a Bench comprised of three
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 16
learned Judges of this Court. The majority view taken was
that the provisions in Section 17(4) of the Act do not lead
to the conclusion that Section 6 of the Act contemplates
successive notification following the notification made
under Section 4 of the Act. It was held that the intention
of Section 4, 5-A and 6 of the Act was not to have
successive declarations under Section 6. It was observed
that even in a case of emergency there can at the most be
only two notifications under Section 6 following one
notification under Section 4(1), one relating to the land
which is covered by S.17 (1) and the other relating to the
land which is not covered by Section 17(1), provided both
kinds of land are notified by one notiication under Section
4(1) of the Act. In order to meet the situation created by
the judgment in the case of Vishnu Prasad Sharma (supra) the
President of India promulgated the Land Acquisition
(Amendment Validation) Act No. 13 of 1967, Section 2 of
which purported to amend Section 5-A of the Principal Act
permitting more than one award in respect of the land which
had been notified under Section 4 of the Act; Section 3 of
the said amendment Act purported to amend Section 6 of the
Principal Act by empowering different declaration to be made
from time to time in respect of different parcels of land
covered by the same notification made under Section 4(1)
irrespective of whether one report or the different reports
had been made under sub-Section 2 of Section 5-A of the
Principal Act. Further Section 4 of the Amendment Act, 1967
purported to validate all acquisitions of land made or
purported to have been made under the Principal Act before
the commencement of the ordinance dated January 20, 1967,
notwithstanding that more than one declaration under Section
6 had been made in pursuance of the same notification under
Section 4(1) and notwithstanding the judgment decree or
order of any Court to the contrary. The validity of the
aforesaid Amending Act has been upheld by this Court in the
case of Uday Ram Sharma Vs. Union of India 1968 (3) SCR 41 =
AIR 1968 SC 1138 which has been further reaffirmed by this
Court in the case of Aflatoon (supra). Some of the learned
counsel appearing for the appellants contended that the
aforementioned Amending Act was promulgated with a view to
over reach the decision of this Court rendered in the case
of Vishnu Prasad Sharma but such a submission could not be
accepted in view of the decision of this Court referred to
above upholding the validity of the said Amending Act.
8. Dr. Siddhu learned counsel appearing for the appellants
in the civil appeal arising out of SLP (C) No. 2669/1978 as
well as some other counsel contended that the land in
village Masodpur sought to be acquired is in personal
cultivation of the land owner which is a small area and by
virtue of the second proviso of Article 31-A of the
Constitution it will not be lawful for the State to acquire
any portion of such land as is within the ceiling limit
applicable to the land owner under any law for the time
being in force. It was also asserted that the market price
of the land prevailing on the date of taking over the
possession of the land should be ascertained and paid to the
land owner and not the price prevailing on the date of
notification under Section 4 of the Act. Reliance was placed
on the decision rendered by this Court in the case of D.G.
Mahajan Vs. State of Maharashtra AIR 1977 SC 915 wherein it
has been observed that the second proviso of Article 31-A
confers a right and this right is higher than the one under
clause (2) of Article 31 on a person in respect of such
portion of land under his personal cultivation as is within
the ceiling limit applicable to him and if the Act by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 16
creating an artificial concept of a family unit and fixing
ceiling on holding of agricultural land by such family unit,
enables land within the ceiling limit to be acquired without
payment of full market values it would be taking away or
abridging the right conferred by the second proviso. Thus
even according to this decision the land within the ceiling
limit may be acquired but on payment of the full market
value. The question, therefore, arises whether the market
value prevailing on the date of the award or taking of
possession of the land or the one with reference to the date
of notification made under Section 4(1) of the Act is
payable as the just and proper compensation.
9. In the present case it may be noted that the provisions
of sub-Section (1) of Section 23 of the Act provide the
payment of the compensation of such land, building or
structure prevailing on the date of publication of the
notification under sub-Section (1) of Section 4, the
validity of which was upheld by this Court in the case of
Aflatoon (supra) wherein it was observed at page 809-F.G. of
the report as under:
"The Land Acquisition Act is a pre-
Constitution Act. Its provisions
are not, therefore, liable to be
challenged on the ground that they
are not in conformity with the
requirement of article 31(2). What
the appellants and writ petitioners
complain is that their properties
were acquired by paying them
compensation computed with
reference to the market value of
the land as on the date of the
notification under S. 4 and that S.
23 is, therefore, bad. This, in
substance, is nothing but a
challenge to the adequacy of
compensation. Such a challenge is
precluded by reason of Article
31(5). In other words, the
appellants and the writ petitioners
cannot challege the validity of
S.23 on the ground that
compensation payable under its
provisions is in any way
inadequate, because, such a
challenge would fly in the face of
Article 31(5)."
That being to, the argument advanced by the learned
counsel could not be accepted. Here a reference may also be
made to the decision in the case of P.V. Mudaliar Vs. Deputy
Collector 1965 (1) SCR 614 (621-H) in which it has been
observed as under:
"Under Article 31(2) and (2A) of
the Constitution a State is
prohibited from making a law for
acquiring land unless it is for a
public purpose and unless it fixes
the amount of compensation of
specifies the principles for
determining the amount of
compensation. But Article 31-A
lifts the ban to enable the State
to implement the pressing agrarian
reforms. The said object of the
Constitution is implicit in Article
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 16
31-A. If the argument of the
respondents be accepted, it would
enable the State to acquire the
lands of citizens without reference
to any agrarian reform in
derogation of their fundamental
rights without payment of
compensation and thus deprive
Article 31(2) practically of its
content. If the intention of the
parliament was to make Article
31(2) a dead letter it would have
clearly expressed its intention.
This Court cannot by interpretation
enlarge the scope of Article 31-A.
On the other hand the Article , as
pointed out by us earlier, by
necessary implication, is confined
only to aqrarian reforms. Therefore
, we held that Article 31-A would
apply only to a law made for
acquisition by the State of any
"estate" or any rights therein or
for extinguishment or modification
of such rights if such acquisition,
extinguishment or modification is
connected with agrarian reform."
(emphasis supplied)
In the same report it has been further observed at page
631-D as under:
One of the elements that should
properly be taken into account in
fixing the compensation is omitted:
it results in the inadequacy or the
compensation but that in itself
does not constitute fraud on power,
as we have explained earlier. We,
therefore , hold that the Amending
Act does not offend Article 31(2)
of the Constitution."
A reference may also be made to the decision in the
case of Nagpur Improvement Trust Vs. Vithal Rao 1973 (1) SCC
page 500 para 35 which reads as under:
"The learned counsel was not able
to satisfy us that the above case
was distinguishable. We are of the
opinion that the case was rightly
decided and must govern this case.
In this view of the matter, it is
not necessary to refer to all the
cases referred to us at the Bar. We
may mention that Mr. Tarkunde also
placed reliance on Article 31(A)
(l)(a) of the Constitution. It is
now well settled that Article 31(A)
(1)(a) has relevance to agrarian
reforms and development. It has
nothing to do with acquisition of
land for building of a capital of a
State.
10. further, a Constitution Bench of this Court in the case
of Vajravalu Vs. Sp. Dy. Collector - AIR 1965 SC 1017
observed in para 14 page 1083 Col. IT as under:-
" A scrutiny of the amended Article
discloses that it accepted the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 16
meaning of the expressions
"Compensation" and "principles" as
defined by this Court in Mrs Bela
Banerjee’s case, 1954 SCR 558 (AIR
1954 SC 170). It may be recalled
that this Court in the said
expressions and then stated whether
the principles laid down take into
account all the elements which make
up the true value of the properly
appropriated and exclude matters
which are to be neglected, is a
justiciable issue to be adjudicated
by the Court. Under the amended
Article, the law fixinq the amount
of compensation or laying down the
principles governing the said
fixation cannot be questioned in
any court on the ground that the
compensation provided by that law
was inadequate."
10. It is thus clear from these decisions that Article 31A
has got nothing to do with acquisition of land for building
of a capital of a State. In the present case before us also
the land is not said to be acquired for purposes of any
agrarian reforms and development but for the planned
development of Delhi and that being so the argument advanced
by the learned counsel in this behalf that the land
belonging to a small agriculturist within celling limit
cannot be acquired or the value of the land of the
agriculturists sought to be acquired should be determined on
the price/value prevailing on the date of award or taking of
possession and not on the value prevailing on the date of
notification under Section 4(1) cannot be accepted. In the
case of Ram Chand (supra) also in para 4 of the report this
Court while dealing with Article 31-A took the view that the
Constitution ensures under the second proviso to Article 31-
A that where any law makes provision for the acquisition by
the State, of land held by a person, under his personal
cultivation, within the ceiling limit, it shall not be
lawful for the state to acquire any portion of such land
"unless the law relating to the acquisition of such land,
building or structure provides for payment of compensation
at a rate which shall not be less than the market value
thereof". It has been further observed in the same para
that by Constitution (Forty Fourth Amendment) Act, 1978,
clause (f) of Article 19 and Article 31 have been deleted
and, as such, to hold property is no more a fundamental
right. But still the mandate under second proviso to Article
31-A continues regarding payment of market value in respect
of the land, the subject matter of acquisition, and that the
Act provides for payment of compensation in respect of the
acquisition made, at the market value of the land, as such
it is consistent with the second proviso to Article 31-A.
But in view of sub-section (1) of Section 11 and sub-section
(1) of Section 23 the market value of such land is to be
fixed with reference to the date of the publication of
notification under section 4, sub-section (1), irrespective
of the dates on which declaration under Section 6 or award
under Section 11 are made or possession is taken under
Section 16 of the Act. In this view of the matter the
contentions raised with regard to Article 31-A could not be
accepted and are accordingly rejected. The acquisition
procedings, therefore, could not be quashed on that account
also.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 16
11. Dr. Sidhu learned counsel appearing for the appellants
in appeal arising out of SLP (C) No. 2669/1996 further
submitted that Khasra No. 364/21 was not notified under
Section 6 of the Act as the land to be acquired yet an award
has been made in respect thereto also which deserves to be
quashed to the extent of the land of the said khasra No. He
submitted that forgery was committed by changing the khasra
No. 264/21 into khasra No.364/21 as in the gazette
notification the land notified was khasra No.264/21 and not
khasra No. 364/21. This contention of the learned counsel
may be disposed of without going into the merits of the
submissions in view of the fact that the learned counsel
himself admitted that a review against the said mistake is
pending in the High Court itself.
12. Learned counsel for the appellants as well as the
counsel appearing for the transfer petitioners also
strenuously urged with great force that the land was sought
to be acquired for the planned development of Delhi and,
therefore the provisions of Delhi Development, Act, 1957
became applicable to such acquisition of land and the
acquisition or land can be made only in accordance with
master plan and zonal plans to be framed under the Delhi
Development Act. It was contended that on the issuance of
the notification under Section 4 of the Act for acquisition
of the land for planned development of Delhi it has to be
inferred that the land which was notified under Section 4 of
the Act for planned development of Delhi is the land
designated for compulsory acquisition within the meaning of
Sub-Section (1) of Section 55 of the Delhi Act but as the
land sought to be acquired was not so acquired within the
period of six months from the date of service of notice
under sub-section (2) of section 55 of the said Act by the
land owners, therefore after the expiry of the period of 10
years of the coming into force of the master plan, the land
sought to be acquired went out of the compulsory acquisition
and the same would be deemed to have been released from
acquisition. It was submitted that sub-section (2) of
Section 55 provides that the owner of the land may serve on
the Central Government a notice requiring his interest in
the land to be acquired and if the Central Government fails
to acquire the land within the period of six months the same
shall have the effect as if the land were not required to be
kept as an open space or unbuilt or were not designated as
subject to compulsory acquisition. It was asserted that
since some of the land owners whose land was sought to be
acquired had given such notice to the Central Government but
the Central Government did not acquire the land within the
specified period and, therefore, the acquisition proceedings
must be quashed on that account. After a careful
consideration of the submissions made above, we are of the
view that there is absolutely no merit in this contention.
It must be shown that the particular land is designated in
the master plan of zonal development plan which is the
subject matter of acquisition.
13. It may be pointed out that in the present case before
us no zonal development plans were prepared with regard to
the said land. In the master plan there is no
particularisation of any land which can be said to be
required for compulsory acquisition under the Delhi Act.
Neither Section 55 nor any other provisions of the Delhi Act
contain any inhibition for acquisition of the land for the
public purposes of planned development of Delhi under the
provisions of the Land Acquisition Act. As said earlier, the
notifications under section 4 of the Act were already issued
between the period from 1959 to 1965 as a result of which
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 16
the application of Section 55 of the Delhi Act was locked up
by virtue of acquisition process under the Land Acquisition
Act. This apart the land cannot be acquired within the
period of six months as contemplated in Section 55 of the
Delhi Act unless an agreement under Section 11(2) of the Act
has reached because if the objections are filed under
Section 5-A or in response to notice under Section 9 and 10
the proceedings are bound to consume considerable time
beyond the prescribed limit of six months contained in
Section 55 of the Delhi Act. It is for these reasons that
Section 15(1) was enacted in the Delhi Act which provides
interalia that if in the opinion of the Central Government
any land is required for the purpose of development , or for
any other purpose, under the said Act, (Delhi Act) so the
Central Government may acquire such land under the
provisions of the Land Acquisition Act 1894. It is thus
distinctly clear that despite the enforcement of the Delhi
Development Act, 1957 Section 15 (1) thereof lays down that
the land for the purposes of development may be acquired
under the provisions of the Land Acquisition Act. This
contention was also advanced before the High Court, The Full
Bench of the High Court after considering the arguments at
length and taking all the facts and circumstances of the
case into consideration recorded the following conclusion:-
Assuming that the argument advanced
by Mr. Lekhi is correct that once
the land is notified for compulsory
acquisition in Section 4 and 6 of
the Land Acquisition Act, it would
be deemed to have been so
designated in the master plan, even
then the provisions of Section 55
would not come into force till the
zonal development plan is also
prepared and thereafter 10 years
period had elapsed and the land so
designated is not acquired within
the stipulated period after service
of notice, only in that situation,
it may be possible to say that the
land has gone out of the expression
of compulsory acquisition used in
Section 55 of the Act. It is not
possible to agree with the
contentions that the land is deemed
to be designated for the purpose of
master plans it would not be deemed
to be designated by same inference
for the purpose of zonal
development plan."
We find ourselves in agreement with the view taken by
the High Court referred to above. Thus the argument based on
the provision of Section 55 (1) and (2) of the Delhi Act
have no merit and, therefore, the same cannot be sustained.
14. A half hearted argument was also advanced to the
effect that the life span of the master plan was 20 years
but the acquisition proceedings are not yet complete and
therefore, the notifications issued for acquisition of the
land for planned development of Delhi have lost their value
and the acquisition proceedings should be quashed. These
argument is also without any merit for the simple reason
that Delhi is the capital of the largest democratic country
of the world. There is inflow of more than a lacs of people
every year to this city. It is ever expanding cosmopolitan
commercial and industrial city with multifarious national
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 16
and international activities. The city of Delhi is
confronted with serious housing problems due to enormous
growth and ever expanding population. Consequently Delhi
Development is a continuous unending process for which no
terminal point for the completion of such process can be
visualised. In these facts and circumstances simply because
there is a delay which in the facts and circumstances of the
present case was bound to occur, it cannot justifiably
contended that the notifications issued were rendered
ineffective. As pointed out by the High Court and in our
opinion rightly so that large tracks of land was sought to
be acquired for purpose of constructing huge residential
colonies and commercial areas and, therefore, the delay was
bound to occur in completing the acquisition proceedings.
However, the Legislature appears to have taken notice of
such delays and it was for these reasons that it came to the
rescue of land owners by amending the Land Acquisition Act
by introducing Section 11-A in the Act providing the
completion of the acquisition proceedings within the time
frame stipulated therein in order to save the land owners
from undue loss with regard to the price of land sought to
be acquired compulsorily.
15. Shri P.N. Lekhi, Shri Rajiv Dhavan and various other
counsel appearing for the appellants contented that the
Government by its order dated August 4, 1995 had withdrawn
its notification issued under Section 4 of the Act involving
certain areas of land sought to be acquired in exercise of
its power under Section 48 of the Act and, therefore, it was
submitted that if one part of the land is released for the
public purpose the whole land covered under the notification
will stand released as the Government cannot give a
differential treatment which will be get by the principles
enunciated in Article 14 of the Constitution. As against
this the learned counsel for the respondents refuted the
allegation with regard to the withdrawal of certain land
from the acquisition for the planned development of the city
of Delhi. Alternatively it was submitted that the withdrawal
of certain land included in the notification under Section 4
could be effected only by denotifying the release and since
there is no such notification denotifying the release it
could not be regarded as a release within the meaning of
Section 48 of the Act. In other words Section 48 of the Act
may be applied only when the release is published in the
official gazette in the same manner as the notification
under Section 4 and declaration under Section 6 of the Act
are published in view of the provisions contained in Section
21 of the General Clauses Act and since no such notification
was published in the official gazette mere information give
with regard to the withdrawal from acquisition will be of no
consequence. Various decisions were cited for and against by
the parties at the Bar but we do not propose to burden this
judgment by citing them all except those which are most
relevant on the point in controversy.
16. It may be noticed that Sub-Section (1> of Section 48 of
the Act contemplates that except in the case provided for in
Section 36, the Government shall be at liberty to withdraw
from the acquisition of any land of which possession has not
been taken. This Section thus confers power on the
Government to withdraw any land from the acquisition but
such power can be exercised only before taking the
possession of the land sought to be acquired. In this
connection before we proceed to examine the relevant
decisions it would be appropriate to refer to the
observations made by the Full Bench of the High Court in the
impugned judgment with regard to this controversy. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 16
original record in which the Minister concerned is said to
have passed the order for withdrawal was produced before the
High Court which was perused by the Full Bench. The
photostat copies of the notings were also placed on record
of the High Court and after the perusal of the original
record the Full Bench found that in fact no order has been
made by the Minister concerned which may be said to be an
order for withdrawal of acquisition. The High Court observed
that mere communication of the misconstrued orders by the
officials would not have the effect of an order of the
Government withdrawing from acquisition. The High Court on a
careful perusal of the original file and the noting
contained therein and approved by the Minister came to the
definite conclusion that the Minister had directed that the
matter be taken up with the N.C.T Delhi for denotifying and
for release of the land immediately which was indicative of
the fact that the Minister had not himself passed the order
for releasing the land from acquisition and the release from
acquisition was left to the decision of N.C.T, Delhi and
since N.C.T Delhi did not give its consent the release of
the said land was not denotified. The High Court, therefore,
took the view that the communication sent to the appellants
concerned purporting to be an order under Section 48 of the
Acat is invalid and the land acquisition proceedings cannot
be quashed on the basis of such invalid communication. In
our opinion the view taken by the High Court cannot be said
to be erroneous calling for any interference by this Court.
17. Here it would be relevant to refer to some of the
decisions of this Court on the question of release of the
land under Section 48 and its validity under the law. In the
case of Chandra Bansi Singh & Ors. Vs. State of Bihar & Ors.
1984 (4) SCC page 316 this Court observed that perhaps the
appellants wanted to persuade this Court to strike down the
entire notification so that when a fresh notification is
issued they may be able to get a higher compensation in
view of sudden spurt and rise in the price of land and other
commodities in between the period when the acquisition was
made and when the actual possession was taken. This Court
took the view that it was not acceptable to uphold the
aforesaid process of reasoning. The release was declared to
be bad as a result of which the entire notification issued
under Section 4 would be deemed to be valid and the land
specially belonging to the land owner would form part of the
acquisition. It has been further held that the release being
a separate and subsequent act of the Collector, could not
invalidate the entire notification but would only invalidate
the portion released, with the result that the original
notification would be restored to its position as it stood
on the date of its notification. Assuming therefore, that
there was release of certain areas of land belonging to
certain land owners, the entire notification could not be
rendered invalid. Further this Court in a recent decision
rendered in State of Maharashtra Vs. Uma Shankar Rajabhau &
JT 1995 (8) SC 508 took the view in para 3 of the report as
follows:-
"It is brought to our notice that
after the notification was quashed
by the High Court, no further steps
were taken by the Government. It is
not necessary since it is being
challenged in the appeal in respect
of these three plots. A submission
was made that the Corporation does
not need these three plots of lands
for the employees. So long as there
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 16
is no notification published under
Section 48(1) of the Act
withdrawing from the acquisition,
the Court cannot take notice of any
subsequent disinclination on the
part of the beneficiary."
18. The same view was expressed by this Court in yet
another decision in the case of U.P. Jal Nigam Vs. M/s Kalra
Properties (P) Ltd. In this view of the matter even if we
assume that there was an order for release of certain land
from the acquisition the same could not be given effect to
in the absence of a notification denotifying the acquisiton
of land.
19. Some of the learned counsel for the appellants also
submitted that even the land shown in the green colour in
the master plan which has been sought to be acquired but it
is not understood as to for what purpose the said land is
being acquired. It was also submitted that there are large
number of structures and complexes raised on the land sought
to be acquired in which schools, sports and other
recreational activities are going on Shri G.L. Sanghi,
learned counsel appearing for the appellants in Civil Appeal
arising out of SLP (c) No.5771/1996 and Civil Appeal arising
out of SLP (c) No.740/1996 as well as other advocates
appearing for some other appellants submitted that there
exist factories, workshops, godowns and MCD school besides
residential houses and quarters over the land belonging to
the appellant Partap Singh situated at Roshanara Road, Sabzi
Mandi, Delhi which has been acquired and that there exist
modern and well developed farm house with modern facilities
in the land belonging to the appellant Roshanara Begum,
where there are a good number of other structures and fruit
bearing trees. Consequently these areas do not require
further development as they are already developed and,
therefore, the said land should be released from
acquisition. Mr. Sanghi , learned counsel appearing for some
of the appellants urged that the concerned appellant had
developed a sports complex providing modern amenities
therein and if the same is demolished there would be great
national waste. It was, therefore, urged that such Complexes
and built up areas should be deleted from the acquisition.
It may be pointed out that in the master plan the land
indicated in green colour is reserved for recreational
facilities. The recreational facilities are also part of the
planned development of Delhi and it cannot be disputed that
recreational amenities are also part of the life of the
people and an important feature of a developed society.
Therefore, no legitimate objection can be made in the
acquisition of such land which are shown in green colour. So
far as the structures and constructions made on the land are
concerned there is no material to show that they were made
before the issuance of notification under Section 4 of the
Act. It is also not clear whether such constructions were
raised with or without necessary sanction/approval of the
competent authority. No grievance therefore can legitimately
be raised in that behalf as the same would be regarded as
unauthorised and made at the risk of the land owners. Here a
reference of a decision of this Court in the case of State
of U.P. Vs. Pista Devi - AIR 1986 SC 2025 may be made with
advantage, para 7 of which reads as under:
"It was next contended that in the
large extent of land acquired which
was about 412 acres there were some
buildings here and there and so the
acquisition of these parts of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 16
land on which buildings were
situated was unjustified since
these portions were not either
waste to or arable lands which
could be dealt with under S. 17(1)
of the Act. This contention has not
been considered by the High Court.
We do not, however, find any
substance in it. The Government was
not acquiring any property which
was substantially covered by
buildings. It acquired about 412
acres of land on the outskirts of
Meerut city which was described as
arable land by the Collector. It
may be true that here and there
were a few superstructures. In a
case of this nature where a large
extent of land is being acquired
for planned development of the
urban area it would not be proper
to leave the small portions over
which some superstructures have
been constructed out of the
development scheme. In such a
situation where there is real
urgency it would be difficult to
apply S. 5-A of the Act in the case
of few bits of land on which some
structures are standing and to
exempt the rest of the property
from its application."
In the present case also a large extent of land
measuring thousands of acres has been acquired and,
therefore, it would not be proper to leave out some small
portions here and there over which some structures are said
to be constructed out of the planned development of Delhi.
We may, however, add here that during the course of the
arguments Shri Goswami learned counsel appearing for the
respondents-State made a statement that the Government will
consider each of the structures and take a decision in that
respect. We, therefore, leave this issue to the discretion
of the respondent.
20. After overall consideration of the issues involved in
these transfer cases and the appeals we find no ground to
take a different view than the one taken by the High Court
in the impugned judgment. Consequently, the acquisition
proceedings could not be quashed on any grounds. We also
find ourselves in respectful agreement with the view taken
by this Court in the case of Ram Chand (supra).
Consequently. the appeals fail and are hereby dismissed. The
transfer cases are allowed in terms of the order made in the
case of Ram Chand (supra) directing that the tranfer
petitioners and the appellants shall be paid an additional
amount of compensation to be calculated at the rate of 12
per cent per annum, after the expiry of two years from the
date of decision of Aflatoon’s case i.e. August 23, 1974
till the date of making of the awards by the Collector, to
be calculated with reference to the market value of the land
in question on the date of notification under Section 4(1)
of the Act. In the facts and circumstances of the case we
make no order as to costs.