Full Judgment Text
REPORTABLE
2024 INSC 559
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE/INHERENT JURISDICTION
CIVIL APPEAL NO. 8127 OF 2024
ARISING OUT OF SLP (C) NO. 20844 OF 2022
YASH DEVELOPERS ...APPELLANT(S)
VERSUS
HARIHAR KRUPA CO-OPERATIVE HOUSING
SOCIETY LIMITED & ORS. …RESPONDENT(S)
WITH
CONTEMPT PETITION (CIVIL) NO. 217 OF 2024
IN
SLP (C) NO. 20844 OF 2022
Table of Contents
I. Introduction : ................................................................................ 2
II. Scope of Judicial Review against an order under Section 13 of
the Act: ............................................................................................... 4
III. Accountability of officers exercising power coupled with duty
under Section 13: ............................................................................. 11
IV. Submissions and Analysis: ...................................................... 13
(i) The first phase of delay is between 2003 and 2011 . ............... 14
(ii) The second phase relates to the delay in obtaining necessary
permissions, approvals and environmental clearances from 2011
to 2014. . ........................................................................................ 17
(iii) The third phase of delay relates to the alleged non-cooperation
of certain slum dwellers leading to the stalling of the project from
2014 to 2019. . ............................................................................... 18
Signature Not Verified
(iv) The next period of inaction is from 2015 to 2017. This is sought
to be justified on the ground that the Municipal Corporation
sanctioned a road that may pass through the property and
published the draft development plan (DP) on 25.02.2015 . ......... 20
Digitally signed by
Indu Marwah
Date: 2024.07.30
19:46:09 IST
Reason:
1
(v) Re: Appellant did not have the financial resources. . .............. 21
25
(vi) Re: Submission on maintainability of proceedings before AGRC.
(vii) Re: Locus or conflict of respondent no.6 . .............................. 27
V. Findings:................................................................................... 28
VI. Conclusion: ................................................................................ 32
VII. Re : Performance audit of statute: ............................................. 32
J U D G M E N T
PAMIDIGHANTAM SRI NARASIMHA, J.
1. Leave granted.
I. Introduction :
2. The present controversy is a manifestation of common
battles between competing real estate developers under the
pretext of rehabilitating slum dwellers under the Maharashtra
Slum Areas (Improvement, Clearance and Redevelopment) Act,
1
1971 . In the year 2003, the appellant was appointed as a
developer by respondent no. 1, a co-operative Housing Society
of slum dwellers having their hutments on the subject land in
Borivali, Mumbai which was declared as a ‘slum area’ under the
Act. As the development was unduly prolonged for over two
decades, the development agreement in favour of the appellant
1
Hereinafter, referred to as the “Act”.
2
2
was terminated by the Apex Grievance Redressal Committee by
its order dated 04.08.2021. The order of termination was
3
challenged by the appellant before the Bombay High Court .
3. The Bombay High Court formulated the following issues:
“(i) A developer being removed on the non-fulfillment of the
basic requirement to commence construction of a slum
rehabilitation building for a long period of 18 years, whether
is not fatal to the object and intention of a statutory intent
behind a Slum Rehabilitation Scheme.
(ii) Another question would be as to whether the right to shelter
which is part of the slum dwellers’ right to livelihood
guaranteed under Article 21 of the Constitution, can be
continued to be nullified by such actions of unconscionable
delay on the part of the developer, in not commencing
construction of the slum project even by an inch more
particularly when the nature of such work awarded to a
developer for him is purely a commercial venture, for profit.”
4. Apart from the above two issues, the High Court
highlighted the limited scope of judicial review under Article 226
of the Constitution against the decision of the statutory
authority-AGRC. The High Court, however, proceeded to
examine the facts in full detail and dismissed the writ petition
4
on facts, as well as on law . Thus, the present appeal.
5. Even before us, the appellant argued the case only on
facts, to the extent that we were under an illusion that we were
2
For short, the ‘AGRC’.
3
Writ Petition (L) No. 18022 of 2021.
4
By judgment dated 14.10.2022, reported as 2022 SCC Online Bom 3712, hereinafter referred
to as the impugned Judgment.
3
hearing suit for specific performance involving an issue of ready
and willingness. Having heard the learned counsels for the
parties at length on facts, we will certainly deal with their
submissions, but before that we must reiterate the limited scope
of inquiry under Article 226 of the Constitution.
II. Scope of Judicial Review against an order under
Section 13 of the Act:
6. In this case, as in any other public law proceedings, we are
concerned with the legality and validity of the power exercised
by the AGRC in terminating the development agreement with
the appellant by its order dated 04.08.2021. This order is in
exercise of power under Section 13 of the Act which is as under:
“ 13. Power of Competent Authority to redevelop
clearance area:
(1) Notwithstanding anything contained in sub-
section (1) of Section 12 the Competent Authority may,
at any time, after the land has been cleared of
buildings in accordance with a clearance order, but
before the work of redevelopment of that land has been
commenced by the owner, by order, determine to
redevelop the land at its own cost, if that Authority is
satisfied that it is necessary in the public interest to
do so.
(2) Where land has been cleared of the buildings
in accordance with a clearance order, the Competent
Authority, if it is satisfied that the land has been,
or is being, redeveloped by the owner thereof in
contravention of plans duly approved, or any
restrictions or conditions imposed under sub-section
(10) of Section 12, or has
not been redeveloped
within the time, if any, specified under such
conditions, may, by order, determine to redevelop
.
the land at its own cost
4
Provided that, before passing such order, the owner
shall be given a reasonable opportunity of showing
cause why the order should not be passed.”
(emphasis supplied)
7. Section 13(2) of the Act specifically empowers the
competent authority to re-determine the agreement if it is
satisfied that the re-development has not been done within the
time specified. The provision is certainly a statutory
incorporation of time integrity in the performance of the duty.
We recognise this as a statutory duty of the competent authority
to ensure that the project is completed within the prescribed
time. We have no hesitation even in holding that a writ of
mandamus would lie against the concerned authorities if they
do not perform the statutory duty of ensuring that the project is
completed within the time prescribed.
8. In Susme Builders Pvt. Ltd. v. CEO, Slum Rehabilitation
5
Authority & Ors. , this Court held that Section 13(2) of the Act
empowers the statutory authorities to take action and hand over
the project to some other agency if the development is being
delayed. The relevant portions of the judgment are as under:-
“ 49. Otherwise, there would be an anomalous
situation where the Society would have terminated its
contract with Susme but the letter of intent issued by
the SRA would continue to hold the field and it would
be entitled to develop the land. The Society
5
2018 (2) SCC 230.
5
approached the SRA, in fact, asking it to take action
against Susme. Since the SRA is the authority which
issued the letter of intent, it will definitely have the
power to cancel the letter of intent...
…
52. A bare reading of these provisions shows that in
terms of clauses (c) and (d) of sub-section (3) of Section
3-A of the Slum Act, the SRA not only has the power,
but it is duty-bound to get the slum rehabilitation
scheme implemented and to do all such other acts and
things as will be necessary for achieving the object of
rehabilitation of slums. In this case, the SRA was
faced with a situation where the slum-dwellers were
suffering for more than 25 years and, therefore the
action taken by SRA to remove Susme for the
unjustified delay was totally justified.”
9. Case after case, the Bombay High Court has been ruling
that, a) the developer is duty-bound to complete the project
within the stipulated time and that b) the Slum Rehabilitation
Authority (SRA) has not merely the power but a broader duty to
ensure that the developer completes the project within time. We
will refer to those judgments, not so much to certify that the
issue is no more res-integra, but to emphasise that the rulings
have not had the desired impact, much less compliance. The
reason is that, neither the developer nor the authority is asked
to face the consequences of their derelictions. That Section 13(2)
is a power coupled with duty is clear from the judgments of this
Court and many other judgments of the High Courts, however
experience tells us that this recognition of a statutory duty in
6
itself is not sufficient. Until and unless duty is identified with
accountability, judicial review is ineffective.
6
10. In Galaxy Enterprises v. State of Maharashtra , the Bombay
High Court observed:
“53. The record reveals that what M/s Saral could do in eight
years of its appointment, was to get the Annexure II, namely the
list of the 73 eligible occupants certified from the MHADA. It was,
thus, expected from the petitioner that the revalidation of
Annexure II, which was possibly not a complex formality be
undertaken at the earliest. However this certainly did not
happen and citing various reasons, which cannot be believed to
be not attributable to the petitioner, ultimately, the petitioner
could not get the Annexure II certified only on 23 December
2013, which is after about eight years of the petitioner's
appointment. This fact itself raises a serious doubt as to the real
intentions of the petitioner to undertake the scheme. The
petitioner could not have simply blamed the authorities for the
delay, as there is complete lack of concrete and/or any real
steps which were to be taken by the petitioner to effectively seek
different approvals, once the society had put the petitioner in the
driver's seat, in complete control of the project as rightly
commented, in the impugned orders. Thus, the case of the
petitioner, that from time to time steps were taken to implement
the slum scheme as entrusted to it be the society cannot be
accepted. These are the contentions of the petitioner, merely
pointing out some movement of the files with the authorities. This
was certainly not sufficient and what was required and
expected by the petitioner was to take real effective steps to
progress the slum redevelopment. The petitioner was expected
to expeditiously obtain an Annexure II, as certified by the
MHADA, thereafter obtain a LOI and then obtain a
Commencement Certificate to start with the constructions and
before that make a provision for temporary alternate
accommodation for the slum dwellers to reside till completion of
the scheme. There is not an iota of material to show that any
such steps much less expeditiously were taken by the petitioner
which will show the real bonafides of the petitioner to undertake
the scheme.
54. In fact the petitioner kept the slum dwellers/society in dark
on any of the steps alleged to be taken by the petitioner. There
was no transparency in the petitioner's approach with the slum-
6
2019 SCC OnLine Bom 897.
7
dwellers whose anxious, impatient and painful wait of so many
years for the slum scheme to start was continuously staring at
the petitioner's right from the word go. This was not what was
expected of a diligent developer. The slum schemes are expected
to be taken and pursued by the developers for genuine and
bonafide object and purpose to redevelop the slums as reflected
in the rules which is for the mutual benefit namely the benefit of
the slum dwellers of being provided a permanent alternate
accommodation and so far as the developer, to exploit the free
sale component, which is nothing but a business consideration
for the developer. If this be the long and short of a slum scheme
what can be the intention of a developer to sit tight on a slum
scheme and not take expeditious measures to undertake and
complete the scheme. The reasons can be innumerable, if the
reasons are attributable to the authorities, the developer has
certainly remedies in law to be immediately resorted. No forum
competent to entertain such complaints would refuse to look into
such grievances when the very right to livelihood of the slum
dwellers who are living in inhuman conditions, being a
concomitant of Article 21 of the Constitution, is involved and
which becomes a matter of urgent concern and of utmost priority.
A developer cannot shut his eyes to all these factors and
attributes, once appointed by the society. For the developer,
there has be relentless action on day to day basis as any delay
in not implementing the slum scheme is not only detrimental to
the slum dwellers, but to the society at large. Delay in effective
implementation of the slum scheme would defeat the very goal,
the ideals and the purpose of the slum redevelopment scheme.
55. A perusal of the record indicates that the society is correct in
contending that during the period from 2006 to 2016 i.e. for
about 10 years the petitioner did not take any concrete steps
towards implementation of the slum rehabilitation scheme and
the petitioner had clearly failed to obtain a LOI for such a long
period. The society, thus, was constrained to file the application
dated 15 March 2016, under Section 13(2) of the Slums Act,
praying for change of the petitioner as the developer. It is correct
that Annexure-II was originally issued by MHADA on 16 April
1998. The petitioner was appointed as developer in the month
of June 2006 and it clearly took about seven to eight years for
the petitioner to obtain revised Annexure-II which was obtained
on 23 December 2013. Before the Chief Executive Officer and
even before the appellate authority the petitioner has failed to
show any justifiable reason as to why it took these many years
for the petitioner to simply obtain a revised Annexure-II when as
per norms issued by the Slum Rehabilitation Authority
Annexure-II is required to be finalised within a period of four
months when the hutment dwellers are below 500 in number.
Further the record clearly indicates that even after obtaining the
8
revised Annexure II, on 23 December 2013, the petitioner did not
initiate immediate steps to obtain LOI for the next three years.
There is, thus, much substance in the contention of the society
that only after the society initiated proceedings under Section
13(2) of the Slums Act, the petitioner initiated steps to obtain a
LOI.
...
57. There cannot be a myopic approach to these issues of a
delay in implementation of a slum rehabilitation scheme. Things
as they stand are required to be seen in their entirety. The only
mantra for the slum schemes to be implemented is it's time
bound completion and a machinery to be evolved by the
authorities, to have effective measures in that direction to
monitor the schemes as a part of their statutory obligation to
avoid delays. Non-commencement of the slum scheme for long
years and substantial delay in completion of the slum schemes
should be a thing of the past. In the present case, looked from
any angle there is no plausible explanation forthcoming for the
delay of so many years at the hands of the petitioner to take
bare minimum steps to commence construction.
58. The authorities should weed away and reprimand persons
who are not genuine developers and who are merely agents and
dealers in slum schemes. These persons after get themselves
appointed as developers, to ultimately deal/sell the slum
schemes, as if it is a commodity. Any loopholes in the rules to
this effect, therefore, are required to be sealed.
...
64. Thus, it is quite clear that inordinate delay is a sufficient
ground for removal of a developer. There is neither any
perversity nor any illegality in the findings as recorded by both
authorities below, in observing that the petitioner had grossly
delayed the implementation of the slum scheme in question. The
findings as recorded in the impugned order passed by the Apex
Grievance Redressal Committee are also sufficiently borne out
by the files produced before this Court…"
(emphasis supplied)
11. A Full Bench of the Bombay High Court in Tulsiwadi
Navnirman Co-op Housing Society Ltd. & Anr. v. State of
7
Maharashtra & Ors. , held that the SRA has been conferred with
7
2008(1) Bom.C.R.1.
9
certain powers and each one of them is coupled with a duty. If
the slum dwellers are eligible to be rehabilitated at the site and
within a reasonable period, they cannot be left at the mercy of
developers and builders. The slum dwellers cannot be expected
to occupy a transit accommodation endlessly, without proper
maintenance, and hygiene. An independent and impartial
implementation, supervision and monitoring of the projects is
the purpose for which the authority has been set up under the
Act.
8
12. In New Janta SRA CHS Ltd. v. State of Maharashtra , the
High Court considered the dispute between two rival societies
claiming rights over a slum scheme. The Court observed as
under:-
“ 187. It thus cannot be accepted more particularly
considering the provisions of Section 13(2) of the Slums Act
that a slum society at its sole discretion and/or without any
control and regulations by SRA can change the developer. If
such a course of action is made permissible, considering the
hard realities and the hundreds of developers being
available to take over such schemes, it would create a chaos
and it is likely that a situation is created, that the slum
rehabilitation scheme never takes off and it is entangled into
fights between two factions within the society and/or two
rival developers. This is certainly not the object of the
legislation. It would be too farfetched to read such
draconian rights available to the Managing Committee or to
general body of a society without any regulation,
supervision and control of the SRA to change the developer.
The SRA has all the powers not only to regulate and control
such situations but to take a decision as to what is in the
8
2019 SCC Online Bom 3896.
10
best interest of the slum dwellers and intended to achieve
the object of the legislation.
188. Secondly it is not in dispute that the application of the
petitioner for change of respondent no.5-developer was
under Section 13(2) of the Slums Act. Having noted this
provision in the foregoing paragraphs, Section 13(2) of the
Slums Act would come into play only when the developer
fails to adhere to the provisions of the development
permissions granted by the SRA and a change of developer
can be sought only when there is an inordinate delay or the
construction carried on, is contrary to the sanctioned plans
and/or the permissions. Considering this clear position
falling under Section 13(2), in the context of this factual
controversy as raised by the petitioner in regard to the
consent of 70% of the slum dwellers being not available to
respondent no.5, 1 am of the clear opinion that the view
taken by both the authorities, in not accepting the
petitioner's contention, is required to be held to be correct
and valid. "
III. Accountability of officers exercising power coupled
with duty under Section 13:
13. Two facets of Section 13 (2) of the Act are that; a) the SRA
has the power to redevelop the project if it is satisfied that the
development is not proceeding within the time specified, and
b) that power of SRA is coupled with a duty to ensure that the
project is completed within time. We hold that the SRA is
accountable for the performance of this duty. Accountability
need not be superimposed by the text of a statute, it exists
wherever power is granted to accomplish statutory purpose. In
9
Vijay Rajmohan v. CBI , this Court held :-
9
(2023) 1 SCC 329.
11
| “34. Accountability in itself is an essential principle of | |
|---|---|
| administrative law. Judicial review of administrative action | |
| will be effective and meaningful by ensuring accountability | |
| of the officer or authority in charge. |
35. The principle of accountability is considered as a
cornerstone of the human rights framework. It is a crucial
feature that must govern the relationship between “duty
bearers” in authority and “right holders” affected by their
actions. Accountability of institutions is also one of the
10
development goals adopted by the United Nations in 2015
and is also recognised as one of the six principles of the
11
Citizens Charter Movement .
36. Accountability has three essential constituent
dimensions: (i) responsibility, (ii) answerability, and
(iii) enforceability. Responsibility requires the identification
of duties and performance obligations of individuals in
authority and with authorities. Answerability requires
reasoned decision-making so that those affected by their
decisions, including the public, are aware of the
same. Enforceability requires appropriate corrective and
remedial action against lack of responsibility and
12
accountability to be taken . Accountability has a corrective
function, making it possible to address individual or
collective grievances. It enables action against officials or
institutions for dereliction of duty. It also has a preventive
function that helps to identify the procedure or policy which
has become non-functional and to improve upon it.”
14. For effective implementation of the principle of
accountability of power under the Act, we identify the duties and
performance obligations of the CEO. It is evident from the
statutory scheme that the responsibility vests in the CEO,
defined under Section 2 (b+a) read with Section 3A(2) of the Act.
10
United Nations General Assembly Resolution 70/1 dated 25-9-2015.
11
Citizens Charter adopted by the Government in the “Conference of Chief Ministers of various
States and Union Territories” held in May 1997 in New Delhi, available from
https://goicharters.nic.in/public/website/home.
12
See
Office of United Nations High Commissioner for Human Rights, Who will be
Accountable? Human Rights and the Post-2015 Development Agenda, available from
http://www.ohchr.org/Documents/Publications/WhoWillBeAccountable.pdf
12
The CEO reports to the SRA, the duty of which is defined under
Section 3B of the Act. One of the most important duties of the
SRA is to ensure that the Slum Rehabilitation Scheme is
implemented.
14.1. The primary responsibility to implement Section 13 of
the Act and allied provisions and to monitor compliances of
schemes and agreements vests with the CEO. If the actions of
CEO are based on the directions of the SRA, then the SRA must
equally bear the responsibility. The CEO and/or the SRA must
explain the delay in implementation, failing which, the
consequences as determined by the court will follow.
PART-II
IV. Submissions and Analysis:
15. Returning to facts of the case, Mr. Kapil Sibal, learned
senior counsel, appearing on behalf of the appellant, articulated
the allegation of delay into six parts and in his inimitable style
proceeded to explain how in each part, the appellant had no role
and not at all responsible. We will deal with each phase of delay
in the same manner as Mr. Sibal has presented the case before
us.
13
16. (i) The first phase of delay is between 2003 and 2011 . The
relevant facts are as follows.
16.1. The appellant was appointed by respondent no.1 to
develop the Project under a development agreement dated
20.08.2003, following which the appellant made a proposal for
development on 11.12.2003. The Municipal Corporation of
Greater Mumbai, however, assigned the re-development to a
rival society, namely Omkareshwar Co-Operative Housing
13 14
Society and a developer, namely Siddhivinayak Developers
on 06.05.2004. Pursuant to this, on 07.09.2004, the SRA
accepted the proposal given by Omkareshwar and
Siddhivinayak for the development of the Property. After a long-
drawn litigation between the appellant and respondent no. 1 on
one side, and Omkareshwar and Siddhivinayak on the other,
the CEO, SRA finally settled the dispute by its order dated
07.06.2011 and held that the appellant had the required 70%
consent of individual slum dwellers to implement the project
and also that the proposal of Omkareshwar was not valid as it
was made after the proposal of respondent no.1. Dealing with
the period, Mr. Sibal has submitted that multiple proceedings
13
Hereinafter, referred to as “Omkareshwar”.
14
Hereinafter, referred to as “Siddhivinayak”.
14
between the appellant and respondent no. 1 on one side and
Omkareshwar and Siddhivinayak on the other consumed lot of
time. While the High Court initially disposed of a writ petition
recording a settlement that appellant and respondent no.1 are
entitled to develop the Property, Omkareshwar challenged it
leading to several rounds of litigation before the High-Powered
15
Committee and the High Court. The issue was laid to rest only
on 07.06.2011 by an order of the CEO, SRA holding that the
appellant enjoyed the consent of 70% of eligible slum dwellers and
hence was qualified to be the developer. Mr. Sibal has submitted
that the consequence of this litigation is that the LOI could be
issued in favour of the appellant only on 29.06.2011, i.e. after this
dispute was settled. The eight years’ delay in obtaining the LOI was
inevitable and was not due to any fault of the appellant.
16.2. Per contra , Mr. C A Sundaram, learned senior counsel,
appearing for the respondent no.6-Veena Developers, has
submitted that the appellant did not have the financial capacity or
the technical expertise to complete the project within the
prescribed time of 3 years. It is due to this reason that the
appellant was unable to commence construction even when all the
15
Hereinafter, referred to as the “HPC”.
15
requisite permissions and approvals had been obtained. Further,
Mr. Huzefa Ahmadi, learned senior counsel, appearing for
respondent nos.8-48, who are some of the slum dwellers, has
submitted that the delay in the construction is entirely
attributable to the appellant. He submitted that the appellant
did not take any action to obtain the LOI anytime between 2003-
2011.
16.3. While adjudicating on the delay in implementation of
the project during 2003-2011, the AGRC relied on clause 11 of
the development agreement dated 20.08.2003 requiring the
appellant to complete the development of the project within
three years from the issuance of the Commencement Certificate
dated 14.07.2014.
16.4. On the issue of delay from 2003 to 2011, the High
Court examined the facts independently and upheld the
findings of the AGRC. The High Court held that a delay cannot
be viewed as reasonable. Further, the High Court held that the
litigation with Omkareshwar did not prevent the appellant from
starting the project, especially when the appellant had the
consent of more than 70% of the slum dwellers at all material
16
times. The High Court also observed that the appellant was not
diligent in procuring the LOI.
17. (ii) The second phase relates to the delay in obtaining
necessary permissions, approvals and environmental clearances
from 2011 to 2014. The SRA issued Annexure-III, certifying the
financial capability of a developer on 21.06.2011 and this was
followed by issuance of LOI dated 29.06.2011. The appellant
16
applied for Environmental Clearance on 15.12.2011 and
obtained it only on 28.04.2014. The Commencement Certificate
for the construction of the rehabilitation building and the high-
rise clearance by the Municipal Corporation of Greater Mumbai
were issued to the appellant on 14.07.2014 and 09.10.2014,
respectively.
17.1. In the above referred background, Mr. Sibal submitted
that the EC had to be obtained before the Commencement
Certificate could be issued for the construction of the
rehabilitation building. For on-site construction of more than
20,000 square meters, EC is required and for this, he relied on
condition no. 51 of the LOI dated 29.06.2011 and condition no. 38
of the intimation of approval dated 21.04.2012. While the
16
Hereinafter, referred to as “EC”.
17
appellant made an application for EC in the year 2011, it was
granted only on 28.04.2014. He has submitted that the delay
between 2011-2014 was again unavoidable as certain mandatory
permissions were required. Per contra , Mr. Ahmadi submitted
that an EC was not required to commence construction of the
rehabilitation building as the on-site construction did not
exceed 20,000 square meters.
17.2. Upon perusing the record, the AGRC found that the
delay was indeed attributable to the appellant. The High Court
also noticed that the appellant did not commence the
construction after getting the necessary approvals but waited
for the EC. The High Court also noted that some parts of the
project like the rehabilitation building did not require an EC for
commencing construction.
18. (iii) The third phase of delay relates to the alleged non-
cooperation of certain slum dwellers leading to the stalling of the
project from 2014 to 2019. Mr. Sibal submitted that as some of
the slum dwellers were not cooperative, applications under
Sections 33 and 38 of the Act for eviction were made to the
Assistant Municipal Commissioner, MCGM. Initially, the
Deputy Collector passed orders on 05.11.2020 observing that
18
the eviction proceedings can be taken forward only after
directions from the High Court and in the meanwhile directed
the appellant to deposit 11 months rent concerning 30 non-
cooperating slum dwellers. These applications under Sections
33 and 38 of the Act came to be decided only in 2021, and that
is how, it is submitted, the project got delayed for reasons
beyond the control of the appellant.
18.1. Mr. Ahmadi submitted that the pendency of the
eviction applications does not justify the extraordinary delay of
5 years on the part of the appellant. Mr. Sundaram submitted
that the mere filing of applications under Sections 33 and 38 of
the Act is not sufficient to justify the delay. It is submitted that
the appellant has failed to take active steps in getting the
applications disposed of. This inaction suited the appellant as
it did not have the capacity or the capability to complete the
project.
18.2. Affirming the findings of the AGRC, the High Court
observed that the appellant went into deep slumber after filing
applications for eviction of non-cooperating slum dwellers
between 2014-2015.
19
18.3. The fact that the appellant had to initiate proceedings
against certain non-cooperating members and that the
proceedings were pending for a long time, whether justified or
not, should not have a bearing on the obligations of the
appellant to complete and handover the project as per the
development agreement. Under no circumstance, litigation of
this nature would justify inaction from 2014 to 2019.
19. (iv) The next period of inaction is from 2015 to 2017. This is
sought to be justified on the ground that the Municipal
Corporation sanctioned a road that may pass through the
property and published the draft development plan (DP) on
25.02.2015 .
19.1. The objections filed by the appellant on 03.04.2015
eventually came to be disposed of only on 12.11.2018 when the
said road was deleted from the development plan. This period,
Mr. Sibal submits, must be excluded as no development, much
less any construction, is permissible once the draft plan is
published.
19.2. Mr. Sundaram submitted that if the appellant had
commenced the construction after the commencement
certificate dated 14.07.2014, the draft development plan
20
published in 2015 could never have affected the re-development
at all. He further submitted that as LOI and IOA were issued in
2011 and 2012, the so-called draft DP published in 2015 cannot
be a justification. Mr. Ahmadi has submitted that except for 2
months between 25.02.2015 and 23.04.2015, there was no
proposed development plan road in any of the plans. He would
submit that the proposed DP road affected only the proposed
sale building, not the entire project. In any event, he would
submit that the sale building could not have commenced till
substantial progress in rehabilitation building was made.
19.3. The observations of AGRC also go to show that draft DP
could justify 2 years’ delay and no more. The High Court
observed that the notification dated 25.02.2015 under no
circumstances precluded the appellant from starting
construction of other parts of the Property.
20. (v) Re: Appellant did not have the financial resources.
Dealing with the findings of the AGRC and the High Court that
the appellant did not have the financial resources as evidenced
by the agreements that they have executed in favour of third
parties, Mr. Sibal submitted that this issue was never raised in
the show-cause notice dated 04.12.2020, which initiated the
21
proceedings leading to the termination of the development
agreement of the appellant. The factual background is that from
2017 onwards, the appellant executed certain financial
agreements with third parties. On 17.02.2017, an agreement
with M/s Rajesh Habitat Private Limited was executed as per
which the saleable rights under the project were transferred in
favour of Rajesh Habitat in lieu of finance of Rs. 30 crores.
Further, Rajesh Habitat mortgaged their rights in favour of M/s
Vistra ITCL by a deed dated 22.03.2017, which later came to be
cancelled on 08.02.2019 and a deed of reconveyance between
the appellant and Vistra was entered into. Later, one M/s
Sanghvi Associates provided financial assistance of Rs. 50
crores to the appellant by way of a mortgage deed. In pursuance
of these financing arrangements, Sanghvi Associates gave no
objection to the appellant entering into an agreement with
respondent no.6-Veena Developers. Following this, a joint
development agreement dated 18.10.2019 was entered into
between the appellant and respondent no. 6.
20.1. Mr. Sibal contended that the appellant has the
requisite financial capacity of technical expertise to complete
the project. He would submit that these agreements do not
22
establish that the appellant does not have the financial capacity
or the technical expertise to undertake and complete the
project. That the appellant had the capacity is evidenced by the
deposit of rents due to the slum dwellers and in fact, the SRA
has certified the appellant’s financial capacity on 21.12.2019.
20.2. Mr. Sundaram submitted that all the documents were
before the SRA and that the parties have made submissions on
all aspects of the matter. He has taken us through the various
findings of the High Court on the finances and the clauses in
the agreements entered into with the third parties. The following
findings of the High Court were referred to:
“57. In any case, the petitioner struggled to avail
finance and was facing severe financial crisis, this
itself was material for the Chief Executive Officer of the
SRA to come to a conclusion that it may not be possible
for the petitioner to execute the scheme. The Chief
Executive Officer however did not call upon the
petitioner to satisfy that it had the appropriate
finances to undertake the “entire scheme”. The Chief
Executive Officer merely asking the petitioner to
deposit the arrears of rent, can in no manner,
whatsoever, be accepted as a certificate to the
petitioner possessing a financial capacity to complete
the project.
58. It is crystal clear from the petitioner’s own
showing that the petitioner was required to take the
crutches/financial assistance initially from Rajesh
Habitat Pvt. Ltd., who in turn looked at Vistra ITCL
India Ltd. and thereafter having failed with both these
entities, with one M/s Sanghvi Associates, which is
not for a small amount but for a substantial amount of
Rs. 50 crores. Things however would not stop at this
23
and subsequently it appears that now respondent
no.6-Veena Developers was roped in, to provide
working capital for the entire project described to be
the business partners/joint developers of the
petitioner as in para 1 of the petition.”
20.3. Mr. Sundaram also brought to our notice certain
clauses in agreements with third parties and submitted that
this amounts to complete subversion of the scheme. High Court
has reflected on these clauses. The following findings of the High
Court are important:
“73. Certainly, the period of two years as
contractually agreed, under the development
agreement cannot be stretched to such a long period of
almost 17 to 18 years as in the present case, despite
these circumstances, an attempt on the part of the
petitioner to justify that such delay was not
attributable to the petitioner, at least in the facts of the
case, is wholly untenable. The AGRC examined the
case of the petitioner and of the society and the
situation persisting at the ground level. The AGRC
however not agreeing with the findings of the Chief
Executive Officer-SRA, has reached a conclusion that
the petitioner could not take the project forward for
reasons which were borne out by the record.
74. In these circumstances to upset the decision of
the AGRC would amount to rewarding the petitioner of
its defaults and the breaches committed by it, not only
of the very terms and conditions of the Development
Agreement, but also, the clear statutory mandate in
undertaking Slums Rehabilitation Schemes. In fact,
the petitioner has betrayed the trust of the
society/slum dwellers. Even otherwise, a closer
scrutiny of the petitioner’s actions clearly hint of the
petitioner’s interest not in the rehabilitation of the slum
dwellers but in its own private interest, solely in
relation to the sale component. There cannot be a
24
space for a pure commercial greed in taking up such
projects which involves the basic rights of the slum
dwellers.”
21. (vi) Re: Submission on maintainability of proceedings before
AGRC. Finally, Mr. Sibal submitted that the complaints filed by
the 12 members of the managing committee of respondent no.1 on
18.11.2019 were withdrawn by 8 members on 31.12.2019 and by
another member on 14.01.2020. Consequently, the show-cause
notice dated 04.12.2020, based on these complaints, was rightly
withdrawn on 16.03.2021. Secondly, although the managing
committee of respondent no. 1 had initially terminated the
development agreement on 02.02.2020, this termination was
revoked on 28.02.2021. The revocation of termination was because
the agreement was terminated by Mr. Rai, who did not have the
requisite authorisation. Mr. Sibal has relied on the above to submit
that respondent no.1 did not object to the withdrawal of the
termination of the development agreement of the appellant, and in
fact, wanted the appellant to continue as the developer. He would
further submit that Mr. Rai was acting without the authorisation
of the other members, and hence, he also could not have filed an
appeal before the AGRC on behalf of respondent no.1 against the
order of the respondent no. 3 – CEO, SRA dated 16.03.2021 that
25
dropped the proceedings against the appellant. Mr. Navare, learned
senior counsel, appearing for some of the slum dwellers, supported
the submissions put forth by Mr. Sibal regarding the lack of
authorisation of Mr. Rai to act on behalf of respondent no. 1.
21.1. Mr. Sundaram submitted that the appeal before the
AGRC against the order dated 16.03.2021 was maintainable even
if some of the complaints filed on 18.11.2019 were withdrawn. He
submits that Mr. Rai, who filed the appeal, had the requisite locus
because he, along with some others, had also filed complaints that
were not withdrawn. It is submitted that Mr. Rai was still a slum
dweller and a member of respondent no.1 and hence, was an
‘aggrieved person’ against the order dated 16.03.2021. There were
also, as many as 132 complaints against the appellant by other
slum dwellers who filed complaints in January and February, 2021
before the SRA under Section 13(2) of the Act alleging non-
payment of rent. Lastly, he submits that in any case, the SRA has
the power to suo moto proceed against the appellant under Section
13(2) of the Act and therefore the withdrawal of complaints is not
fatal to proceeding against the appellant and does not preclude the
AGRC from deciding the appeal. Mr. Ahmadi made a submission
along the same lines and to the same effect.
26
21.2. Answering the question regarding the maintainability
of the proceedings after the complaints dated 18.11.2019 were
withdrawn, the High Court held that even if many complaints
before the SRA were withdrawn, the complaint filed by Mr. Rai
survived to be adjudicated. Further, the High Court rejected the
contention of the appellant that Mr. Rai was not authorised by
respondent no. 1 to take any action against the appellant. In
order to reach this conclusion, the High Court observed that if
the contention of the appellant was true, then respondent no. 1
would have supported the appellant before the High Court;
however, this was not the case. The High Court also held that
in any case, the SRA and the AGRC have the requisite power
under Section 13(2) of the Act to suo moto examine the delay
caused by the appellant in implementing the project.
22. (vii) Re: Locus or conflict of respondent no.6: Mr. Sibal
concluded his submissions by arguing that respondent no.6
does not have the locus to take a stand contrary to that of the
appellant as it has been involved with the venture from the time
of the joint development agreement dated 18.10.2019. For this
reason, he would submit that the findings of AGRC and the High
Court must apply to respondent no. 6 as well.
27
22.1. Mr. Dhruv Mehta, learned senior counsel, appearing
for the administrator of respondent no.1 has argued that
Section 13(2) of the Act empowers and places an obligation upon
the SRA to take action against the developer when the project is
not being implemented. Therefore, he submits that even if some
of the complaints have been withdrawn, the termination of the
development agreement is valid.
V. Findings:
23. Having considered the findings of the AGRC and the High
Court in detail, we have found them to be correct on law and
fact. Further, having independently considered the detailed
submissions of the appellant and the respondents, on delay as
well as on lack of financial and technical capabilities and
maintainability of the appeal, we proceed to analyse and discuss
them as follows.
24. Admittedly, the delay in executing the project, by the time
of the termination order is more than 16 years. This period is
sought to be explained by fragmenting it into bits and pieces
falling between 2003 to 2011, 2011 to 2014 and 2014 to 2019.
25. What amuses us is that we are called upon to hold that the
order of termination for delaying the project for 16 years must
28
be held to be bad by examining each episode of delay as
independent and stand alone. Judicial Review Courts enquiring
into these allegations would only examine whether it would be
arbitrary and/or unreasonable to exclude the delay caused
because of the incidents that occurred from 2003 to 2019. In
other words, the inquiry must be to see whether it would be
unjust if we do not account for the long-drawn litigation with a
competing builder between 2003 to 2011, the delay in obtaining
the environmental clearances from 2011 to 2014, or the delay
caused due to non-cooperation of certain slum dwellers.
26. Having examined the matter, we are of the opinion that
the delay of 8 years in resolving disputes with a competing
builder cannot be a justification under any circumstance. The
appellant is a developer and fully understands the process of
obtaining environmental clearances while other sanctions and
permissions are pending, and it is for him to make all the
necessary arrangements. To say the least, the non-cooperation
of some of the members cannot be a ground for delaying the
project from 2014 to 2019. The findings of the AGRC and the
High Court are very clear, they have correctly held that the delay
caused due to the sanction of the draft DP for the construction
29
of the road cannot be a justification for delaying the project from
2015 to 2019.
27. In any event, execution of the project under the Slum
Rehabilitation Scheme cannot be viewed as a real estate
development project. There is a public purpose involved, and
that is inextricably connected to the right to life of some of our
brother and sister citizens who are living in pathetic conditions.
While we reject the justifications given by the appellant for
delaying the project, we are fully conscious of the dereliction of
the statutory duty of the SRA in ensuring that the project is
completed within time. We have already expressed our opinion
that the CEO and the SRA are accountable for their actions.
While we reject the justification for delay, we record our
dissatisfaction about the indifference, amounting to negligence
on the part of CEO and the SRA.
28. So far as the submissions relating to the financial
resources are concerned, we have seen the number of
agreements that the appellants have entered into. We need not
examine this aspect independently as the findings are
concurrent and thorough. The following findings of the High
Court are sufficient for disposing of this issue:
30
“59. The petitioner time and again having
approached third parties for financial requirements in
the manner as discussed above, in fact was quite fatal
and counter productive to the implementation of the
slum scheme, for the reason that if any of the financers
were to withdraw from their financial support and the
commitments as made to the petitioner, the same
would leave the petitioner with no remedy but to
wander further hunting for fresh finance. Such
financial instability of a developer certainly would
have a devastating effect on the implementation of the
slum scheme which could also result in the total
collapse of the slum scheme being implemented and in
fact a death knell for the slum scheme. It is for such
reason, the real wherewithal and financial stability of
a developer plays an extremely pivotal role, as finance
is the very lifeline for successful implementation and
completion of the slum scheme. The present case is a
classic case of how the petitioner is running helter-
skelter to secure finance, that too without taking the
society into confidence much less the authorities. This
on the basis of a solitary clause in the Development
Agreement which is being discussed hereafter.”
29. We will now deal with the submission on the maintainability
of the appeal before the AGRC and that respondent no. 6 who was
the collaborator of the appellant must face the same consequence
as that of the appellant. This submission proceeds on the
assumption that the statutory power under Section 13(2) of the
Act is to be exercised only upon an application made to the
authority. This is a complete misconception. We have already dealt
with the scope and ambit of Section 13 of the Act, and in particular
the duty followed by accountability of the SRA under the said
provision. Irrespective of whether anybody applied or not, the
31
authority is bound to ensure that the project is completed within
the time stipulated. In any event, as the dispute before us is
confined to the legality and propriety of the termination order, we
are not concerned about the relationship of the appellant with
respondent no. 6.
VI. Conclusion:
30. For the reasons stated above, there is no merit in this appeal,
and we dismiss the Civil Appeal arising out of SLP (C) No. 20844
of 2022 with costs quantified at Rs. 1,00,000/- (Rupees One Lakh)
payable to Supreme Court Mediation and Conciliation Project
Committee. In view of our decision, no further orders are
necessary in the Contempt Petition (Civil) No. 217 of 2024.
31. Pending applications, if any, stand disposed of.
VII. Re : Performance audit of statute:
32. Though we have disposed of this Civil Appeal by dismissing
it, we must record that this case has provoked us to reflect on the
working of this Act.
33. The Act came into being in 1971 and since then, for over five
decades, the High Court has been exercising judicial review
jurisdiction, disposing of Writ Petitions raising claims or
challenges to the exercise of powers or dereliction of duties by
32
Authorities under the Act. Data fetched from National Judicial
Data Grid (NJDG) reveals that a total of 1612 cases involving
disputes arising under the Act are pending before the Bombay
High Court. Of these, 135 cases are more than 10 years old. In the
last 20 years, 4488 cases have been filed and disposed of under
the said Act. Latest data from the Bombay High Court reveal that
about 923 cases on the Appellate side and 738 on the Original Side
are pending adjudication. The Act is a beneficial legislation,
intended to materialize the Constitutional assurance of dignity of
the individual by providing basic housing, so integral to human
life. However, the propensity and the proclivity of the statute to
generate litigation are worrisome. There seems to be a problem
with the statutory framework for realizing the purpose and object
of the statute. In M/s. Galaxy Enterprises v. State of Maharashtra
(supra) the Bombay High Court has remarked that:
“3. … Nonetheless, considering the volumes of disputes
still reaching the Courts, it can certainly be said that time
is ripe, if not too late, to ponder, whether things are
realistically working in the right direction, to eradicate
slums and rehabilitate the slum dwellers, with the
desired efficacy and expedition. This not only at the
hands of the authorities but also at the hands of the other
stake holders. The vital issue which has often led to
controversy and disputes, is on the rules permitting, the
selection and appointment of developers to undertake a
Slum Rehabilitation Scheme, being conferred on the slum
dwellers, who are hardly expected to know the nitty-
gritty of the slum redevelopment schemes. It is seen that
the so called leaders of the slum dwellers who are
33
themselves in need to be rehabilitated, are often lured by
developers and their agents, and once a developer is
appointed, what normally prevails is a constant fear of
incertitude and scepticism amongst the slum dwellers,
leading to disputes on variety of issues affecting their
final rehabilitation. Such issues not only frustrate the
very object of a speedy slum redevelopment but
completely derail the slum schemes. It can be seen that
scores of slum schemes have remained incomplete for
years together and are languishing on such issues, either
in litigation before Courts and/or before the authorities.
These schemes need not face such ordeal, including of
an unending litigation. To change the developer is no
answer as even this process involves dispute resolution
and ultimately lengthy litigation from one forum to
another .”
33.1. Further, referring to the statutory scheme, as per which
development is possible only when the slum dwellers feel the need
and seek development, the High Court pointed out yet another
problem about the statutory framework in the following terms;
“… It cannot be countenanced that the slums be
redeveloped only when the slum dwellers feel the need
of a redevelopment and the Government Authorities
cannot initiate redevelopment and cannot initiate a suo
motu action in that behalf. It is hence, for the Government
and the Slum Authority to give its anxious consideration
to these issues and in its wisdom to device a substantial,
nay a full proof mechanism, by undertaking a study and
identify these grey areas, so that the helping hand as
extended by the legislature in providing this beneficial
law as far back in 1971 that is almost 50 years back is
held strongly and firmly by all concerned. It is never too
late .”
34. The exasperation of the High Court about working of the Act
is understandable. The present appeal is a classic example of why
the High Court’s concern is genuine. It has been noticed that the
34
statutory scheme is problematic with respect to: i) Identification
and declaration of land as a slum. This problem involves an
examination of the role of authorities in giving such recognition,
insidious intervention of builders in the said process cast doubts
on the independence and integrity in the decision-making process;
ii) Identification of slum dwellers: This involves a complicated
process of proof of such a status, the attendant problem of
groupism, giving rise to competing claims inevitably leading to
litigation; iii) Selection of a developer: The Act leaves this decision
to the cooperative society of slum dwellers and the majority
decision is manipulated by competing and rival developers; iv)
Apportionment of the slum land between redevelopment area and
sale area: This is yet another area where court has witnessed
developers seeking to increase the proportion of the sale area,
leading to contestation; v) Obligation to provide transit
accommodation for the slum dwellers pending redevelopment:
Invariably, we see instances where the developer does not provide
transit accommodation within time or provides an inadequate
alternative in the form of a quantified amount towards rent, On
the other hand, there are instances where some slum dwellers
refuse to vacate the premises on the ground that the transit
35
accommodation is either inconvenient or the amount offered is
insufficient; vi) There are also issues of lack of independence and
objectivity in the functioning of statutory authorities: This is a
matter of serious concern. Courts have witnesses that the
authorities have no independence and, their tenure is also short.
Additionally, the functioning of these statutory authorities gives an
indication that there could be a regulatory capture; vii) Another
concern which exists is about the effectiveness of statutory
remedies: Statutory remedies are ineffective and at the same time,
lacking in accountability and vii) Judicial review proceedings
under Art. 226 cannot be a long-term solution: We have given
details of the number of writ petitions pending before the High
Court in Para 33.
35. The above-referred problems arising out of the statutory
scheme and policy framework should have come under review by
the State of Maharashtra. Assessment of the working of the statute
to realise if its purpose and objective achieved or not is the implied
duty of the executive government. Reviewing and assessing the
implementation of a statute is an integral part of Rule of Law. It is
in recognition of this obligation of the executive government that
36
the constitutional courts have directed governments to carry
performance audit of statutes.
36. Four aspects for achieving justice are well founded and
articulated as, i) distribution of advantages and disadvantages of
society, ii) curbing the abuse of power and liberty, iii) deciding
17
disputes and, iv) adapting to change . Adapting to change is
important for achieving justice, as failure to adapt produces
injustice and is, in a sense, an abuse of power. Thus, failure to use
power to adapt to change is in its own way an abuse of power. In
fact, the issue is not one of change or not to change, but of the
direction and the speed of change and such a change may come in
various ways, and most effectively through legislation. Legal
reform through legislative correction improves the legal system
and it would require assessment of the working of the law, its
accessibility, utility and abuse as well. The Executive branch has
a constitutional duty to ensure that the purpose and object of a
statute is accomplished while implementing it. It has the
additional duty to closely monitor the working of a statute and
must have a continuous and a real time assessment of the impact
that the statute is having. As stated above, reviewing and
17 th
URISPRUDENCE
See : Justice in Adapting to Change, in R.W.M. Dias , J , 305-327 (5 edn.,
2013).
37
assessing the implementation of a statute is an integral part of
Rule of Law. The purpose of such review is to ensure that a law is
working out in practice as it was intended. If not, to understand the
reason and address it quickly . It is in this perspective that this
court has, in a number of cases, directed the Executive to carry a
performance/assessment audit of a statute or has suggested
amendments to the provisions of a particular enactment so as to
18
remove perceived infirmities in its working.
37. Constitutional courts are fully justified in giving such
directions as they are in a unique position of perceiving the
working of a statute while exercising judicial review, during
which they could identify the fault-lines in the implementation
of a statute. This extraordinary capacity to assess the working
of a statute is available to the judicial institution because of its
unique position where, i) disputes, based on the statutory
provisions unfold before it, ii) claims of rights or allegations of
dereliction of duties are raised with varied, and sometimes,
contradictory interpretations of the same text of the statute, iii)
submissions of lawyers opens up a debate and as officers of the
18
State of Haryana v. Mukesh Kumar , (2011) 10 SCC 404; Pravin Electricals (P) Ltd. v. Galaxy
Infra & Engineering (P) Ltd. (2021) 5 SCC 671; Preeti Gupta v. State of Jharkhand , (2010) 7
SCC 667; Arif Azim Co. Ltd. v. Aptech Ltd. , (2024) 5 SCC 313; Public Interest Foundation v.
Union of India , (2019) 3 SCC 224.
38
Court experienced lawyers would lay bare the fault-lines in the
statutory scheme, iv) many a times court silently witnesses the
play of statutory power relegating the deserving to the backseat,
and the undeserving taking away all the benefits.
38. Laws that are made by Parliament or the legislative
assemblies create rights, entitlements, duties or liabilities.
Application of such empowerments or disabilities gives rise to
competing claims or conflicting interests. For resolution of these
19
disputes, constitutional courts provide public law remedies
where claims and contestations are decided by High Courts on
a case by case basis. Judicial review is generally episodic, and
is intended to resolve the lis on a case-to-case basis. Though
cases are decided on their own merit and the lis disposed of,
what is left behind is the institutional memory of the Court
about the working of the statute and its interpretation preserved
as precedents. Over a period of time, a critical mass of
adjudicatory determinations on the working of the statute is
19
Judicial control of administrative action in our country, the effective and the most
prolific, has evolved from its classical scrutiny of ultra vires exercise of power, to a whole
set of procedural and substantive principles, such as: legality, procedural propriety,
reasonableness, legitimate expectation, proportionality, transparency, legal certainty,
accountability, level playing field, consultation or participation etc. These principles
are now well entrenched in our judicial review processes and are part of our
administrative law. In fact, bulk of judicial review proceedings initiate before the High
Courts examine if the power exercised is with its bounds.
39
built. This critical mass, coupled with the experiences gained
by the Judges and the Court on the working of the statute, is of
immense value for auditing the working of the legislation. It
enables the court to assess whether the purpose and object of
the Act is being achieved or not.
39. The traditional perception of the constitutional role of writ
courts was confined to judicial review of executive and legislative
action. In that role, the courts were to decide the vires of the
legislative and executive actions based on constitutional
parameters. Not only have the tools of judicial review been
reinvented (the rise of the proportionality and arbitrariness
doctrines) but also the breadth of the judicial power has
substantially expanded to areas that were hitherto forbidden
(review of policy decisions, constitutional amendments and
continuing mandamus being prime examples). However, even this
expansive reading of judicial review does not capture the essence
of the judicial branch in its entirety.
40. There is yet another role which the judiciary can and ought
to perform- that of facilitator of access to justice and effective
functioning of constitutional bodies. In this role, the judiciary does
not review executive and legislative actions, but only nudges and
40
provides impetus to systemic reforms. The statute in question is
one which was intended to benefit the marginalised and the
impoverished. It is not easy for the intended beneficiaries of this
legislation to carry their voice to legislative branch for effective
reform. The exercise that this Court intends to direct presently is
aimed at facilitating their access to legislative and executive
reform, which this court believes is an essential component of
constitutional justice. That all justice is to be achieved only
through courtroom debates is too myopic an understanding of
constitutional justice. The facilitative role is not just inspired from
the institutional role that the judiciary perceives for itself, but is
also a directive of many of the fundamental rights in Part III and
the cherished preambular vision of justice- social, economic and
political.
41. A peculiar feature of how our legislative system works is that
an overwhelming majority of legislations are introduced and
carried through by the Government, with very few private member
bills being introduced and debated. In such circumstances, the
judicial role does encompass, in this court’s understanding, the
power, nay the duty to direct the executive branch to review the
working of statutes and audit the statutory impact. It is not
41
possible to exhaustively enlist the circumstances and standards
that will trigger such a judicial direction. One can only state that
this direction must be predicated on a finding that the statute has
through demonstrable judicial data or other cogent material failed
to ameliorate the conditions of the beneficiaries. The courts will
also do well, to arrive the very least, at a prima facie finding that
much statutory schemes and procedures are gridlocked in
bureaucratic or judicial quagmires that impede or delay statutory
objectives. This facilitative role the judiciary compels audit of the
legislation, promote debate and discussion but does not and
cannot compel legislative reforms.
42. In light of the foregoing, considering that the Act is a state-
legislation, implementation of which lies with the State of
Maharashtra, and till date no comprehensive statutory audit has
been undertaken, we request the Ld. Chief Justice of the Bombay
High Court to constitute a bench to initiate suo motu proceedings
for reviewing the working of the statute to identify the cause of the
problems indicated in Paragraph 34. The concerned bench will
hear the government, the statutory authorities, the necessary
stakeholders including intended beneficiaries and perhaps take
the assistance of some senior members of the bar specialising in
42
this area as amici curae . We leave it to the High Court to devise
such methods as it deems fit and appropriate. Having examined
the matter, the bench may consider directing the government to
constitute a committee for performance audit of the Act. The
court’s jurisdiction extends only to that extent, and no further. The
law-making, including amendments, is the exclusive domain of the
legislature.
………………………………....J.
[ PAMIDIGHANTAM SRI NARASIMHA ]
………………………………....J.
[ ARAVIND KUMAR ]
NEW DELHI;
JULY 30, 2024.
43