Full Judgment Text
$~43
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ W.P.(C) 5840/2019 & CM APPLN. No.25477/2019
M/S APANA LOGISTICS PVT. LTD. ..... Petitioner
Through Mr. Rakesh Tiku, Sr. Adv. with
Ms. Meenu Pandey and Mr.
Gaurav Kohli, Advs.
versus
CONTAINER CORPORATION OF INDIA LTD. AND ANR.
..... Respondents
Through Mr. Rajinder Dhawan and Mr.
B. S. Rana, Advs.
CORAM:
HON'BLE MR. JUSTICE VIBHU BAKHRU
O R D E R
% 24.05.2019
VIBHU BAKHRU, J
1. The petitioner has filed the present petition, inter alia , impugning
a communication dated 08.04.2019 issued by the respondents (hereafter
referred to as “CONCOR”), terminating the contract for handling of
containers awarded to the petitioner. It is the petitioner’s case that the
termination is illegal and arbitrary.
2. On 25.11.2016, CONCOR had issued a notice inviting e-tender
for Handling Containers at CFS, Dronagiri by reverse auction. The
petitioner had participated in the said tender process and was declared
successful. On 03.03.2017, a Letter of Intent was issued to the
petitioner. Subsequently, on 01.04.2017, the petitioner had entered into
an agreement (hereafter ‘the Contract’) to act as a terminal handling
contractor for the respondents at Dronagiri.
W.P. (C) 5840 of 2019 Page 1 of 7
3. It is the petitioner’s case that pursuant to the said tender, it had
purchased the necessary equipment to execute the contract and had
incurred an expenditure of ₹10,17,000/-.
4. Subsequently however, on 28.01.2019, the petitioner had
received a letter from CONCOR informing the petitioner that it would
be deploying Reach Various Stacker (RST) machines owned by it at
various terminals and therefore, such activities would be taken over by
it. Thereafter, the petitioner received a letter dated 13.02.2019 eliciting
the petitioner’s response whether it was willing to operate a part of the
Contract relating to ‘Internal Transportation of Containers at CSF-
DRT” which, according to CONCOR, was part of the scope of the
Contract.
5. The petitioner responded to the said letter, inter alia , lodging its
protest against the said decision and further requesting that they be
permitted to deploy 50% of the RSTs. The petitioner also claimed that
the said notices were in violation of the Contract entered into between
the parties. It is apparent from the said letter that the petitioner was not
interested in taking up the work of Internal Transportation of Containers
at CFS-DRT.
6. There is some controversy as to whether this procedure was
included within the scope of work under the Contract. Whereas the
petitioner contends that it was not part of the contract awarded to the
petitioner, CONCOR disputes the same and asserts that the said
procedure was also included in the scope of the work awarded to the
petitioner under the Contract. Be that as it may, there is no dispute that
the petitioner was not willing to undertake the said work at that time,
W.P. (C) 5840 of 2019 Page 2 of 7
nor is it currently interested in doing so.
7. Thereafter on 08.04.2019, CONCOR issued a letter informing the
petitioner that in terms of Clause 19 of the Contract, CONCOR was
terminating the contract and the said letter be treated as a notice of
termination under Clause 19 of the Contract. The said notice of
termination has been impugned in the present petition.
8. Before proceeding further, it would be relevant to refer to Clause
19 of the said Contract which reads as under:
“ 19. EXIT CLAUSE
CONCOR will have the liberty to terminate the
contract by giving an advance notice of (60) sixty
days in case there are strong business reasons for it
to do so as determined by its management,”
9. It is clear from the above that the said Clause enables CONCOR
to terminate the Contract by giving a prior notice of 60 days in case
there are strong business reasons for it do so as determined by its
management . According to CONCOR, there are strong business
reasons for terminating the Contract and its management has exercised
its option under the said Exit Clause. The petitioner contests the same
and asserts that there are no strong business reasons for doing so.
10. It is apparent from the above that the controversy involved in the
present petition relates to the scope and interpretation of the Contract
between the parties. Such a dispute is in the realm of private law and
this Court is unable to accept that there is any element of public law
involved. This Court is, prima facie , of the view that the question
whether there are strong business reasons would be as perceived by the
W.P. (C) 5840 of 2019 Page 3 of 7
management of CONCOR and it is not open to judicial review in these
proceedings.
11. It is also relevant to note that the Contract between the parties
includes an Arbitration Clause and the learned counsel appearing for
CONCOR submits that the dispute raised by the petitioner squarely falls
within the scope of the said Clause.
12. Mr. Tiku, the learned Senior Counsel appearing for the petitioner
referred to the decision of the Supreme Court in Harbanslal Sahnia
and Anr. v. Indian Oil Coporation. Ltd. And Ors.: AIR (2003) SC
2120 , and on the strength of the same, contended that an Arbitration
Clause would not preclude this Court from exercising its jurisdiction
under Article 226 of the Constitution of India. The said proposition
cannot be faulted with. Plainly, existence of an arbitration agreement
does not denude this Court of its jurisdiction under Article 226 of the
Constitution of India. However, the courts must be circumspect in
exercising such jurisdiction and do so only where an element of public
law is involved and where the actions of the state fall foul of the
Wednesbury principle, that is, no reasonable person could possibly take
such a decision.
13. In Joshi Technologies International Inc. v. Union of India:
(2015) 7 SCC 728 , the Supreme Court summarised the scope of judicial
review in contractual matters and held as under:
“ 69. The position thus summarised in the aforesaid
principles has to be understood in the context of
discussion that preceded which we have pointed out
above. As per this, no doubt, there is no absolute bar to
the maintainability of the writ petition even in contractual
W.P. (C) 5840 of 2019 Page 4 of 7
matters or where there are disputed questions of fact or
even when monetary claim is raised. At the same time,
discretion lies with the High Court which under certain
circumstances, it can refuse to exercise. It also follows
that under the following circumstances, “normally”, the
Court would not exercise such a discretion:
69.1. The Court may not examine the issue unless the
action has some public law character attached to it.
69.2. Whenever a particular mode of settlement of
dispute is provided in the contract, the High Court would
refuse to exercise its discretion under Article 226 of the
Constitution and relegate the party to the said mode of
settlement, particularly when settlement of disputes is to
be resorted to through the means of arbitration.
69.3. If there are very serious disputed questions of fact
which are of complex nature and require oral evidence
for their determination.
XXXX
70. Further, the legal position which emerges from
various judgments of this Court dealing with different
situations/aspects relating to contracts entered into by the
State/public authority with private parties, can be
summarised as under:
XXXX
70.3. Even in cases where question is of choice or
consideration of competing claims before entering into
the field of contract, facts have to be investigated and
found before the question of a violation of Article 14 of
the Constitution could arise. If those facts are disputed
and require assessment of evidence the correctness of
which can only be tested satisfactorily by taking detailed
evidence, involving examination and cross-examination
of witnesses, the case could not be conveniently or
satisfactorily decided in proceedings under Article 226 of
the Constitution. In such cases the Court can direct the
aggrieved party to resort to alternate remedy of civil suit,
etc.
70.4. Writ jurisdiction of the High Court under Article
W.P. (C) 5840 of 2019 Page 5 of 7
| 226 of the Constitution was not intended to facilitate | ||
|---|---|---|
| avoidance of obligation voluntarily incurred. | ||
| XXXX | ||
| 70.8. If the contract between private party and the | ||
| State/instrumentality and/or agency of the State is under | ||
| the realm of a private law and there is no element of | ||
| public law, the normal course for the aggrieved party, is | ||
| to invoke the remedies provided under ordinary civil law | ||
| rather than approaching the High Court under Article 226 | ||
| of the Constitution of India and invoking its | ||
| extraordinary jurisdiction.” | ||
14. In the present case, CONCOR has found no fault with the
petitioner’s performance of its obligations under the Contract and there
is no allegation of any shortcoming in this regard. However, CONCOR
has a contractual right to terminate the Contract in terms of Clause 19
of the Contract, even in cases whether there is no fault on the part of the
petitioner. Although the petitioner disputes that the conditions for
exercise of such rights exist, this Court is of the view that it would
not be apposite for this Court to entertain such disputes in these
proceedings.
15. Mr. Tiku also contended that the real cause of terminating the
Contract was the reluctance of the petitioner for accepting the work of
internal transportation. The said contention is unmerited. It is apparent
from the communications placed on record that CONCOR has
exercised its right to terminate the Contract under Clause 19 of the
Contract for the reason that CONCOR had decided to deploy their own
RSTs and not on account of petitioner declining to take other works.
16. The petition is accordingly dismissed leaving it open for the
petitioner to avail all remedies available in law. The pending
W.P. (C) 5840 of 2019 Page 6 of 7
application also stands disposed of.
VIBHU BAKHRU, J
MAY 24, 2019
DR
W.P. (C) 5840 of 2019 Page 7 of 7