THE STATE OF GUJARAT STATE OF GUJARAT vs. JAYANTIBHAI ISHWARBHAI PATEL

Case Type: Civil Appeal

Date of Judgment: 17-03-2023

Preview image for THE STATE OF GUJARAT STATE OF GUJARAT vs. JAYANTIBHAI ISHWARBHAI PATEL

Full Judgment Text

//  1  // REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION     CIVIL APPEAL NOS.                      /2023 (@SLP (C) NOS.34752­53 OF 2016) STATE OF GUJARAT & ORS.          ..APPELLANT(S)      VERSUS JAYANTIBHAI ISHWARBHAI PATEL         .. RESPONDENT(S) J U D G M E N T M. R. Shah, J. 1. Feeling aggrieved and dissatisfied with the impugned judgment and order dated 31.08.2015 passed by the High Court of Gujarat at Ahmedabad in Special Civil Application   No.9740/2012   by   which   the   Division Bench of the High Court of Gujarat has allowed the Signature Not Verified Digitally signed by R Natarajan Date: 2023.03.17 14:30:32 IST Reason: said writ petition and has declared that the acquisition with respect to the land in question is deemed to have //  2  // lapsed   under   Section   24(2)   of   the   Right   to   Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (hereinafter referred to as “Act, 2013”) as also the judgment and order dated 01.04.2016 passed by the High Court of Gujarat in Misc. Civil Application (For Review) No.3036 of 2015 in Special Civil Application No.9740/2012, the State of Gujarat and others have preferred the present appeals.  2. The facts leading to the present appeals in nut­shell are as under: 2.1 That, the respondent herein – original writ petitioner was   the   owner   of   the   land   bearing   Survey   No.287 admeasuring 2 Hectare 37 Are 75 Sq. Mtrs. of village Tarsava,   Taluka   Vaghodia,   District   Vadodara (hereinafter   referred   to   as   “land   in   question”).   A notification under Section 4 of the Land Acquisition Act, 1894 (hereinafter referred to as “Act, 1894”) came to   be   issued   on   11.04.1991   to   acquire   the   land   in question alongwith adjacent agricultural lands for the //  3  // purpose of re­settlement of Narmada Project oustees. That,   thereafter,   notification  under   Section  6   of   the Act, 1894 was issued on 06.02.1992. The respondent herein – original land owner – original writ petitioner entered into an agreement and a consent award was passed on 11.06.1993. As per the agreement and the consent   award,   initially   90%   of   the   amount   of compensation   was   required   to   be   paid   to   the   land owners   and   10%   amount   was   required   to   be   paid thereafter. However, it appears that the respondent – land owner had second thought about the consent and on   13.02.1995,   he   wrote   to   the   Assistant Commissioner, Sardar Sarovar Rehabilitation Agency that the compensation may not be paid and the land in question   be   released   from   acquisition.   On   such application,   the   Assistant   Commissioner   passed   an order dated 07.03.1995, in which, he recorded that the order   was   passed   for   payment   of   90%   of   the compensation, however, the land owner did not accept such   compensation.   Thereafter,   even   the   order   of payment of remaining 10% of compensation was also //  4  // passed however, the land owner – respondent herein did not accept such compensation and that he has now applied for cancellation of acquisition itself on the ground  that due to family disagreements, he  is not prepared to sell the land. Thereafter, nothing further happened   till   2009   and   it   appears   that   the   land owner/s continued to be in possession and continued to cultivate the agricultural lands. 2.2 That,   on   21.01.2009,   the   Assistant   Commissioner, Sardar   Sarovar   Rehabilitation   Agency   cancelled   the order   dated   07.03.1995   by   observing   that   the acquisition of the land in question has been completed and   the   land   has   been   vested   in   Sardar   Sarovar Rehabilitation   Agency   and   on   basis   of   that   affected persons were allotted also and therefore, as per the legal   provision,   once   an   order   is   passed,   it   is mandatory   to   make   the   payment   of   compensation. Therefore, the Assistant Commissioner, Sardar Sarovar Rehabilitation Agency cancelled the earlier order dated 07.03.1995 and restored the order for 90% and 10% //  5  // amount   of   compensation   as   per   the   earlier   orders dated 05.05.1993 and 09.02.1994 (for payment of 90% and 10% of the amount of compensation respectively). Pursuant to the aforesaid order dated 21.01.2009 of the   Assistant   Commissioner,   the   Special   Land Acquisition Officer vide communication / letter dated 05.04.2010   conveyed   to   the   respondent   herein   – original   land   owner   that   his   case   for   payment   of compensation is fixed on 16.04.2010 in the office of Talati­cum­Mantri,   Tarsava   and   therefore,   he   shall remain   present   and   receive   compensation.   That, thereafter the respondent No.1 – original writ petitioner filed   the   writ   petition   for   setting   aside   the   consent award dated 11.06.1993 passed under Section 11 of the Act, 1894. 2.3 Before the High Court, it was the case on behalf of respondent No.1 – original writ petitioner – land owner that   his   request   for   withdrawal   of   the   consent   was accepted by the Special Land Acquisition Officer and thereafter,   no   compensation   was   received   and   the //  6  // possession of the land in question was also not taken over   and   therefore,   many   years   later   the   authority cannot implement the award by insisting on payment of compensation. 2.4 In the meantime, Act, 2013 came into force with effect from 01.01.2014 and therefore, Section 24(2) of the Act,   2013   was   pressed   into   service   and   it   was submitted on behalf of the land owner that as, neither the compensation has been paid nor the possession of the land in question is taken and that the land owner continued to be in possession of the land in question, the acquisition proceedings are deemed to have lapsed under Section 24(2) of the Act, 2013. 2.5 It was the case on behalf of the Acquiring Body and the State   Government   that   the   land   owner   cannot withdraw such consent once the award was passed. It was also submitted on behalf of the Acquiring Body and   the   State   Government   that  merely   because   the land owner did not accept the compensation would not //  7  // make   any   difference.   It   is   submitted   that   once   the award was passed and a further order was passed to pay the amount of compensation as per the consent award, the same has to be implemented and therefore, the Assistant Commissioner was justified in passing the order dated 21.01.2009 which was communicated by Land Acquisition Officer on 05.04.2010 asking the land owner to receive the compensation, as originally fixed. 2.6 By the impugned judgment and order, the High Court has set aside the order dated 05.04.2010 by observing that such an order could not have been passed after a period of 15 years having once accepted the request on behalf   of   the   land   owner   to   cancel   the   acquisition. Thereafter, the Division Bench of the High Court has further   passed   an   order   that   as,   neither   the compensation   is   paid   nor   the   possession   is   taken and/or   the   original   land   owner   continued   to   be   in possession and cultivating the land in question, the acquisition is deemed to have lapsed under Section //  8  // 24(2)   of   the   Act,   2013.   Consequently,   the   Division Bench  of  the   High Court  has  allowed  the   said  writ petition by setting  aside  the land  acquisition  award dated 11.06.1993  qua  the land in question. 2.7 That,   thereafter   the   Assistant   Commissioner   and others filed the review petition before the High Court against the observations made by the Division Bench that   possession   has   not   been   taken   over.   It   was pointed out that as such the possession was already taken   over   by   the   Sardar   Sarovar   Rehabilitation Agency at the time of passing of the award. However, the High Court has dismissed the review application. 2.8 The impugned judgment and order passed by the High Court   in   Special   Civil   Application   as   well   as   the impugned order passed in Review Application are the subject matter of present appeals.   3. Ms. Deepanwita Priyanka, learned counsel appearing for the State of Gujarat has vehemently submitted that as such the issue involved in the present appeals viz. //  9  // Whether in the facts and circumstances of the case, there   shall   be   deemed   lapse   of   acquisition   under Section 24(2) of the Act, 2013 is now not  res integra  in view of the decision of the Constitution Bench of this Court in the case of   Indore Development Authority Vs. Manoharlal and Ors.   reported in   (2020) 8 SCC 129.  3.1 It is submitted that in the present case there was a consent award passed on 11.06.1993 and thereafter the   orders   were   passed   to   pay   90%   and   10% compensation   vide   orders   dated   05.05.1993   and 09.02.1994. However, the original land owner did not accept   the   compensation   though   offered   and   he insisted   for   withdrawal   of   the   acquisition.   It   is submitted that therefore, thereafter vide order dated 07.03.1995,   the   order   of   compensation   under   the award came to be cancelled.  3.2 It is submitted that however as Award under Section 11   of   the   Act,   1894   continued   and   amount   of //  10  // compensation   was   to   be   paid   under   the   consent award   /   award,   the   Assistant   Commissioner   was justified in passing the order dated 21.01.2009, which was communicated to the original writ petitioner by the   Special   Land   Acquisition   Officer   vide communication dated 05.04.2010.  3.3 It is submitted that once the award under Section 11 of the Act, 1894 was a consent award, the same could not   have   been   set   aside   by   the   High   Court subsequently   on   the   ground   that   the   compensation under the Act, 1894 has not been paid for number of years   and   that   the   land   owner   continued   to   be   in possession of the land in question. It is submitted that as   such   it   was   the   specific   case   on   behalf   of   the appellants   before   the   High   Court   that   it   was   the original   land   owner   who   did   not   accept   the compensation offered and despite consent award, he continued to cultivate the land forcibly. It is submitted that   even   it  was   the   specific   case   on   behalf   of   the appellants before the High Court that possession of the //  11  // land   in   question   was   taken   over   by   drawing panchnama   at   the   time   of   passing   of   the   consent award. It is submitted that however the High Court has   not   believed   taking   over   the   possession considering   the   affidavit   filed   by   the   Assistant Commissioner   in  which  the  Assistant   Commissioner stated that the land owner continued to cultivate the land. It is submitted that however the High Court has not considered the entire affidavit on possession in its true   perspective.   It   is   submitted   that   as   per   the decision   of   this   Court   in   the   case   of   Indore   taking   over   the Development   Authority   (Supra) possession   of   land   /   open   land   by   drawing   the panchnama   is   one   of   the   mode   which   is   legally permissible.   It   is   submitted   that   therefore   the   High Court has materially erred in setting aside the award dated 11.06.1993 under Section 11 of the Act, 1894 and also declaring that the acquisition with respect to the land in question is deemed to have lapsed under Section 24(2) of the Act, 2013.  //  12  // 3.4 Ms. Deepanwita Priyanka, learned counsel appearing for the appellants – State of Gujarat and Others has further submitted that even otherwise in the facts and circumstances   of   the   case,   there   shall   not   be   any deemed lapse of acquisition under Section 24(2) of the Act, 2013.  It is submitted that in the present case admittedly pursuant to the consent award passed under Section 11 of the Act, 1894, the orders were passed to pay the compensation to the land owner and the land owner was called upon to come to the office of Talati­cum­ Mantri, Tarsava to accept the compensation.  However, the land owner refused to accept the compensation as offered. It is submitted that once there was a refusal on   the   part   of   the   land   owner   to   accept   the compensation though offered, there shall not be any deemed lapse under Section 24(2) of the Act, 2013.  3.5 It is further submitted that as observed and held by this   Court   in   the   case   of   Indore   Development //  13  // Authority (Supra) , only  in a case where there is a lapse   on   the   part   of   the   Acquiring   Body   in   not tendering / paying the compensation, and not taking over the possession, there shall be deemed lapse under Section 24(2) of the Act, 2013. It is submitted that in the present case there was no lapse at all on the part of the Acquiring Body and/or State Government in not taking the possession and in not tendering / paying the  compensation. It is submitted that as such the original   land   owner   refused   to   accept   the compensation which has been recorded in the order dated 07.03.1995.  Making   above   submissions   and   relying   upon decision of the Constitution Bench of this Court in the case of   , it is Indore Development Authority (Supra) prayed to allow the present appeals.  4. Present appeals are vehemently opposed by Shri Nakul Diwan, learned senior counsel appearing on behalf of the contesting respondent – original writ petitioner – original land owner.  //  14  // 4.1 It   is   prayed   by   Shri   Diwan,   learned   senior   counsel appearing on behalf of the original land owner that before the High Court there was a challenge to the subsequent communication dated 21.01.2009 by the Assistant   Commissioner   communicated   vide   letter dated   05.04.2010   by   the   learned   Special   Land Acquisition Officer  cancelling the earlier order suo moto  dated 07.03.1995. It is submitted that the said issue has not been decided by the High Court and therefore, the   matter   may   be   remanded   to   the   High   Court  to consider the legality and validity of the order dated 21.01.2009 passed by the Assistant Commissioner and the communication dated 05.04.2010 by the Special Land Acquisition Officer calling upon the land owner to remain   present   in   the   office   of   Talati­cum­Mantri, Tarsava to receive / accept the compensation.  4.2 It is further submitted by Shri Diwan, learned senior counsel appearing on behalf of the original land owner that   in   the   present   case   the   original   land   owner withdrew his consent and therefore, refused to accept //  15  // the compensation awarded under the consent award and   requested   to   withdraw   the   acquisition,   which came to be accepted by the Assistant Commissioner vide   order   dated   07.03.1995   and   the   award   was cancelled.   It   is   submitted   that   in   that   view   of   the matter, thereafter, after a period of 15 years, it was not open   for   the   Assistant   Commissioner   to   cancel   the order   dated   07.03.1995   that   too   in   exercise   of   suo moto   powers   and   without   giving   any   opportunity   of hearing to the original land owner.  4.3 It is further submitted by Shri Diwan, learned senior counsel  that   even   otherwise   when   the   original   land owner continued to remain in physical possession and cultivating the land in question even for a period of 15 years after the consent award passed in the year 1993 and   the   compensation   was   not   paid   for   number   of years, in view of Section 24(2) of the Act, 2013, there shall be deemed lapse of acquisition proceedings. It is submitted   that   therefore   the   Division   Bench   of   the High   Court   has   not   committed   any   error   in   setting //  16  // aside the consent award on the ground that the same has not been implemented for number of years and that the land in question is not used by the Acquiring Body for the purpose for which it was acquired and the High Court has rightly declared that the acquisition with respect to the land in question is deemed to have lapsed under Section 24(2) of the Act, 2013.  Making   above   submissions,   it   is   prayed   to dismiss the present appeals.  5. We   have   heard   learned   counsel   appearing   for respective parties at length.  5.1 At the outset it is required to be noted that the original award dated 11.06.1993 passed under Section 11 of the Act, 1894 was a consent award with respect to the land owned by the present respondent – original land owner as well as other lands acquired for re­settlement of Narmada Project oustees. It is also to be noted that thereafter   and   pursuant   to   the   consent   award,   the amount   of   compensation   (90%   +   10%)   was   in   fact //  17  // offered to the land owner and he was called upon to accept the compensation offered, but the respondent – original   land   owner   refused   to   accept   the compensation   offered   and   insisted   to   withdraw   the acquisition. It was the case on behalf of the appellants before the High Court that the possession of the land in question was taken by drawing spot panchnama at the time of passing of the consent award. However, the High Court has disbelieved the same by observing that even   as   per   the   affidavit   of   the   Assistant Commissioner,   the   land   owner   continued   to   be   in possession of the land in question and continued to cultivate   the   same.   However,   the   affidavit   which   is reproduced in the  impugned judgment and order is required to be considered in its true perspective and in its entirety. In the affidavit dated 22.03.2013 filed by one Shri Bhagora Kamlasingh Jokhanbhai on behalf of the Assistant Commissioner, it was stated as under:  “6. I   state   that   however   the   Petitioner refused   to   handover   the   land   and   to   take compensation   along   with   other   similarly situated   farmers   whose   land   were   also //  18  // acquired as per the Award dated 11.06.1993. The Petitioner along with other persons made an   application   dated   27.07.1993   for cancellation of the Award. 7. I   state   that   by   the   order   dated 07.03.1995, pursuant to the reluctance of the Petitioner to hand over the possession and to take the compensation on so called grounds of family   disputes,   the   order   of   payment   of compensation was cancelled, but at the same time,   the   order   of   acquisition   was   not cancelled. It appears that the Petitioner has successfully   avoided   to   handover   the possession   of   the   land   acquired   under   the provisions of Act though the land is vested in the Respondent No.3” 14. With regard to the averments made in para No.3.2 of the petition, I deny the same inasmuch   as   Petitioner   refused   to   take   the compensation and therefore, last notice was given to the Petitioner on 05.04.2010 and the Petitioner refused to accept the compensation, the   same   is   now,   deposited   with   the Government Treasury as stated hereinabove. The   Petitioner   is,   therefore,   require   to handover   the   possession   of   land   to   the Respondent   No.3   so   that   the   same   can   be allotted   for   rehabilitation   of   the   affected persons of Narmada Project.” 5.2 Thus, from the aforesaid it can be seen that it was the specific   case   on   behalf   of   the   appellants   and   the Assistant Commissioner that the land owner refused to hand   over   the   land   and   refused   to   accept   the //  19  // compensation   alongwith   other   similarly   situated farmers  whose  lands  were also  acquired  as  per  the consent award dated 11.06.1993. It can also be seen that it was the case on behalf of the appellants that by order dated 07.03.1995, pursuant to the reluctance of the land owner to hand over the possession (physical possession) and to take the compensation on so­called ground   of   family   disputes,   the   order   of   payment   of compensation was cancelled.   But at the same time, the order of acquisition was not cancelled and that the land   owner   successfully   avoided   to   hand   over   the possession of the land acquired under the provisions of the Act, 1894 though the land vested in the Sardar Sarovar Rehabilitation Agency.  5.3 Considering the aforesaid factual aspects it is required to be considered whether there shall be deemed lapse of acquisition under Section 24(2) of the Act, 2013 as observed and held by the High Court ? In  the  case  of   Indore  Development Authority , it is observed and held as under:  (Supra) //  20  // “366.  In view of the aforesaid discussion, we answer the questions as under: 366.1.   Under the provisions of Section 24(1) (a) in case the award is not made as on 1­1­2014, the date of commencement of the 2013 Act, there is no lapse of proceedings. Compensation has to be determined under the provisions of the 2013 Act. 366.2.   In  case  the  award  has  been  passed within the window period of five years excluding the period  covered  by  an  interim   order  of  the  court, then proceedings shall continue as provided under Section 24(1)(b) of the 2013 Act under the 1894 Act as if it has not been repealed. 366.3.   The word “or” used in Section 24(2) between   possession   and   compensation   has   to   be read as “nor” or as “and”. The deemed lapse of land acquisition proceedings under Section 24(2) of the 2013   Act   takes   place   where   due   to   inaction   of authorities   for   five   years   or   more   prior   to commencement of the said Act, the possession of land   has   not   been   taken   nor   compensation   has been paid. In other words, in case possession has been taken, compensation has not been paid then there is no lapse. Similarly,  if compensation has been   paid,   possession   has   not   been   taken   then there is no lapse.  The expression “paid” in the main part 366.4. of Section 24(2) of the 2013 Act does not include a deposit of compensation in court. The consequence of non­deposit is provided in the proviso to Section 24(2) in case it has not been deposited with respect to   majority   of   landholdings   then   all   beneficiaries (landowners) as on the date of notification for land acquisition under Section 4 of the 1894 Act shall be entitled   to   compensation   in   accordance   with   the provisions of the 2013 Act. In case the obligation under Section 31 of the Land Acquisition Act, 1894 has not been fulfilled, interest under Section 34 of the   said   Act   can   be   granted.   Non­deposit   of //  21  // compensation (in court) does not result in the lapse of   land   acquisition   proceedings.   In   case   of   non­ deposit with respect to the majority of holdings for five years or more, compensation under the 2013 Act has to be paid to the “landowners” as on the date   of   notification   for   land   acquisition   under Section 4 of the 1894 Act. 366.5.  In case a person has been tendered the compensation as provided under Section 31(1) of the 1894 Act, it is not open to him to claim that acquisition has lapsed under Section 24(2) due to non­payment   or   non­deposit   of   compensation   in court.   The   obligation   to   pay   is   complete   by tendering   the   amount   under   Section   31(1).   The landowners   who   had   refused   to   accept compensation or who sought reference for higher compensation,   cannot   claim   that   the   acquisition proceedings had lapsed under Section 24(2) of the 2013 Act.   The   proviso   to   Section   24(2)   of   the 366.6. 2013 Act is to be treated as part of Section 24(2), not part of Section 24(1)(b).   The mode of taking possession under 366.7. the 1894 Act and as contemplated under Section 24(2) is by drawing of inquest report/memorandum. Once award has been passed on taking possession under Section 16 of the 1894 Act, the land vests in State there is no divesting provided under Section 24(2) of the 2013 Act, as once possession has been taken there is no lapse under Section 24(2).   The   provisions   of   Section   24(2) 366.8. providing   for   a   deemed   lapse   of   proceedings   are applicable   in   case   authorities   have   failed   due   to their   inaction   to   take   possession   and   pay compensation for five years or more before the 2013 Act   came   into   force,   in   a   proceeding   for   land acquisition pending with the authority concerned as on 1­1­2014. The period of subsistence of interim orders passed by court has to be excluded in the computation of five years. //  22  // 366.9.  Section 24(2) of the 2013 Act does not give  rise  to   new  cause   of   action  to   question   the legality   of   concluded   proceedings   of   land acquisition.   Section   24   applies   to   a   proceeding pending on the date of enforcement of the 2013 Act i.e.   1­1­2014.   It   does   not   revive   stale   and   time­ barred   claims   and   does   not   reopen   concluded proceedings nor allow landowners to question the legality   of   mode   of   taking   possession   to   reopen proceedings or mode of deposit of compensation in the   treasury   instead   of   court   to   invalidate acquisition.” 5.4 Therefore, as per the law laid down by this Court in the case of   , Indore Development Authority (Supra) taking   over   the   possession   of   the   land   by   drawing panchnama is held to be legally permissible and can be said to be taking over the possession legally. In the present case, there was a consent award under Section 11   of   the   Act,   1894.   The   possession   was   taken   by drawing the panchnama at the time of passing of the consent award dated 11.06.1993. However, thereafter, because   of   the   reluctance   on   the   part   of   the   land owner, he did not actually and physically hand over the   possession   and   he   continued   to   cultivate   the acquired   land   which   actually   vested   in   the   State //  23  // Government   /   Acquiring   Body   /   Sardar   Sarovar Rehabilitation Agency.  6. Even otherwise, in the facts and circumstances of the case,   there   shall   not   be   any   deemed   lapse   under Section 24(2) of the Act, 2013 on the ground that the amount   of   compensation   was   not   paid.   It   is   an admitted position that after the consent award, under Section   11   of   the   Act,   1894,   was   passed   on 11.06.1993, the amount of compensation was in fact offered to the land owner alongwith other land owners and the respondent – original land owner was called upon to remain present in the  office  of Talati­cum­ Mantri to receive / accept the compensation. However, the   land   owner   refused   to  accept  the  compensation though offered. In that view of the matter, once the compensation was offered, which as such was offered pursuant to the consent award under Section 11 of the Act, 1894, but the land owner refused to accept the same,   how   there   can   be   any   deemed   lapse   of acquisition under Section 24(2) of the Act, 2013?  //  24  // 6.1 As per the law laid down by this Court in the case of Indore   Development   Authority   (Supra)   and   even otherwise   considering   the   object   of   providing   the deemed lapse of acquisition under Section 24(2) of the Act, 2013 seems to be that if there is any lapse on the part of the Acquiring Body / agency in not taking the possession   and   not   paying   the   compensation   there shall be deemed lapse of acquisition. Therefore, for a deemed lapse under Section 24(2) of the Act, 2013, there shall be a lapse on the part of the Acquiring Body /   beneficiary   in   not   taking   the   possession   and   not paying the compensation. In the present case, both the conditions   are   not   satisfied.   In   fact,   the   amount   of compensation under the consent award under Section 11 of the Act, 1894 was offered and the land owner was called upon to accept the compensation however, the land owner refused to accept the same. Even the possession was taken by drawing the panchnama at the  time of  declaration of  the  consent award under Section   11   of   the   Act,   1894.   However,   thereafter, //  25  // because of the reluctance on the part of the original land owner, the physical and actual possession of the land could not be taken by the Acquiring Body. From the aforesaid it can be seen that there was no lapse at all on the part of the Authority neither in offering / paying   the   compensation   nor   in   not   taking   the possession. Therefore, the Division Bench of the High Court   has   materially   erred   in   declaring   that   the acquisition   with   respect   to   the   land   in   question   is deemed to have lapsed under Section 24(2) of the Act, 2013.  7. Now,   so   far   as   the   impugned   judgment   and   order passed by the High Court in setting aside the award dated 11.06.1993 on the ground that the award has not been implemented for number of years and the amount of compensation has not been paid for number of years and the land is not utilized / used for number of years is concerned, at the outset it is required to be noted that it was the original owner who refused to accept   the   compensation   offered   in   the   year   1993. //  26  // Therefore,   an   order   dated   07.05.1993   was   passed cancelling   the   order   of   offering   the   compensation. However, the acquisition and the consent award, both continued.   However,   thereafter,   the   land   owner continued to make representations to release the land from acquisition.  Therefore, it was the  original land owner who did not accept the compensation offered and continued to make representations to release the land   from   acquisition.   In   these   circumstances,   the Division Bench of High Court has committed a very serious error in setting aside the consent award on the aforesaid ground. The consent award under Section 11 of the Act, 1894 ought not to have been set aside in the manner in which it is set aside. The High Court has not at all properly appreciated and considered the conduct on the part of the land owner. At this stage it is required to be noted that at many places the High Court   has   observed   in   paragraph   11   that   “the petitioner, alongwith other land owners of the area, agreed to acquisition of his  land  on a fixed  rate  of compensation”. Even the High Court has also taken //  27  // note of the fact that the amount of compensation was offered but the original land owner refused to accept the same. Once the land owner refuses to accept the amount   of   compensation   offered   by   the   Acquiring Body, thereafter it will not be open for the original land owner to pray for lapse of acquisition on the ground that the compensation has not been paid. As observed hereinabove, there shall be deemed lapse of acquisition under Section 24(2) of the Act, 2013 if there is a lapse on the part of the Acquiring Body / beneficiary in not taking   the   possession   and   the   compensation   is   not paid.   Even   otherwise   as   observed   and   held   by   this Court in the case of   Indore Development Authority (Supra) , for the deemed lapse under Section 24(2) of the   Act,   2013,   twin   conditions   of   not   taking   the possession and not paying the compensation, both are required   to   be   satisfied.   Therefore,   if   one   of   the conditions   is   not   satisfied,   there   shall   not   be   any deemed lapse. 8. Now, so far as the prayer on behalf of the land owner //  28  // to remand the matter to the High Court to consider the legality   and   validity   of   the   subsequent   order   dated 21.01.2009   cancelling   the   earlier   order   dated 07.03.1995 is concerned, at the outset it is required to be noted that the order dated 21.01.2009 was as such not the subject matter of the writ petition before the High Court. No prayer was made to set aside the order dated   21.01.2009   passed   by   the   Assistant Commissioner, Sardar Sarovar Rehabilitation Agency. What was challenged before the High Court was award under Section 11 of the Act, 1894 and the subsequent communication   dated   05.04.2010   issued   by   the Special Land Acquisition Officer calling upon the land owner to remain present in the office of Talati cum Mantri to accept the compensation and to release the land. Be that as it may, assuming that the order dated 21.01.2009 was bad in law and the earlier order dated 07.03.1995 is restored, in that case also, it would not have a bearing on the aspect of deemed lapse under Section 24(2) of the Act, 2013. The fact remains that though the amount of compensation was offered and //  29  // the original land owner was called upon to accept the compensation as per the consent award, he refused to accept the same.  9. In view of the above and for the reasons stated above, present   appeals   succeed.   Impugned   judgment   and order dated 31.08.2015 passed by the High Court of Gujarat in Special Civil Application No.9740/2012 and the   order   dated   01.04.2016   passed   in   review application being Misc. Civil Application   (For Review) No.3036   of   2015   in   Special   Civil   Application No.9740/2012 are hereby quashed and set aside. In the facts and circumstances of the case, there shall be no order as to costs.  …………………………………J.             (M. R. SHAH) …………………………………J.     (MANOJ MISRA) New Delhi,  March 17, 2023