Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
CASE NO.:
Appeal (civil) 8052 of 2001
PETITIONER:
State of Rajasthan
RESPONDENT:
M/s Nav Bharat Construction Co.
DATE OF JUDGMENT: 28/03/2005
BENCH:
CJI,D.M. Dharmadhikari & P. K. Balasubramanyan
JUDGMENT:
J U D G M E N T
With
CA No.8053/2001, CA No.8054/2001, CA No.8055/2001
And
CIVIL APPEAL NO. 1400 OF 2002
M/s Nav Bharat Construction Co. Appellant
Thr. Partner
Vs.
State of Rajasthan Respondent
Dharmadhikari J.
These appeals arise out of an award dated 29.9.1997 passed by
the sole Arbitrator viz. S.S. Mathur, retired Additional Chief Engineer,
Public Works Department, on a reference of dispute concerning civil
construction work awarded to the Contractor by the State of
Rajasthan. The arbitration proceedings were regulated by provisions of
the Arbitration Act, 1940 (for short ’the Act’). The sole Arbitrator
awarded a sum of Rs.6,68,058.16 with interest @ 18% per annum
from the date of the award till date of decree or payment, whichever is
earlier.
The State of Rajasthan under Section 30(1) of the Act filed
objections to the Award. The Contractor by application under Section
17 of the Act prayed for passing a decree in terms of the Award. The
objections of the State were rejected by the Court of the District Judge
who made the Award Rule of the Court by passing a decree in terms
thereof on 5.10.1999. In the order making award Rule of the Court
and passing a decree thereon, there was omission of not mentioning
the interest payable on the amount awarded. On the application under
Section 152 of the Code of Civil Procedure (CPC) filed by the
Contractor for rectification of the decree, the court passed the order on
29.4.2000 and granted a decree of interest @ 12% p.a. on the
awarded sum of Rs. 6,68,058.16 from the date of award i.e. 29.9.1997
till the date of payment. Pursuant to the above order a modified
decree for the above-mentioned amount with 12% future interest was
passed.
We shall first dispose of the appeals preferred by the State
against the revisional and appellate orders of the High Court arising
out of orders passed by the civil court during proceedings of the
arbitration.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
Civil Appeal No. 8052 of 2001
Civil Appeal No.8052 of 2001 arises from of an order of the
High Court passed in appeal confirming the order of the civil court
dated 24.8.1992 whereby, in exercise of powers under Section 8B read
with Section 41(b) of the Act, in place of the arbitrator initially
appointed, new arbitrator was substituted on the suggestions and
proposals of the parties.
Learned counsel appearing for the State of Rajasthan invited our
attention to the contents of clause 23 of the Agreement on the basis of
which the arbitration proceedings were initiated. Clause 23 reads
thus:
"Clause 23: Except where otherwise specified in the contract the
decision of the Chief Engineer of the Government of Rajasthan
for the time being shall be final conclusive and binding on all parties
to the contract upon all questions relating to the meaning of the
specifications, decisions, drawings and instructions here-in-before
mentioned and as to the quality of workmanship or materials used on
the work or as to any other question, claim, right, matter or thing
whatsoever in any way arising out of or relating to the contract,
designs, drawings specifications, estimates, instructions, orders or
these conditions, or otherwise concerning the works, or the execution
or failure to execute the same, whether arising during the progress
of the work or after the completion or abandonment thereof, of the
contract by the contractor shall be final, conclusive and binding on
the contractor."
On behalf of the State, it is argued that the aforesaid clause,
making a provision for settlement of questions relating to specification,
design, quality and workmanship and other technical aspects by the
sitting Chief Engineer of the Government, has not been held to be an
arbitration clause in a series of the decisions of this Court. Reliance is
placed on Executive Engineer, REO vs. Suresh Chandra Panda (d)
through LRs. [1999 (9) SCC 92]; State of UP vs. Tipper Chand
[1980 (2) SCC 341]; State of Madhya Pradesh vs. KK Shukla
[2001 (10) SCC 194]; and Prabartak Commercial Corporation Ltd.
vs. Chief Administrator, Dandakaranya Project [1991 (1) SCC
498].
The submission made on behalf of the State that the above-
quoted clause 23 of the Agreement is not an arbitration clause has to
be accepted because exactly similar clause was held to be not an
arbitration clause in the case of Bharat Bhushan Bansal vs. UP
Small Industries Corporation Ltd [AIR 1999 SC 899].
Learned counsel for the State then argued that both the award
and the decree having been passed on a reference under clause 23,
which is not an arbitration clause, are liable to be set aside on that
short ground.
We have heard the Contractor appearing in person. It is not
disputed that the sitting Chief Engineer, on reference of dispute in
terms of clause 23, failed to decide the dispute, therefore, an
application under Section 8 of the Act was made to the civil court to
substitute him by an arbitrator. The record of the proceedings before
the civil court, (copies of which are before us) show that on the
application seeking substitution of the arbitrator, the Contractor and
the State through their counsel were heard. Suggestion of names for
new arbitrator were taken from the parties. The court on 14.3.1995
passed a consent order appointing Shri SS Mathur, retired Additional
Chief Engineer as the sole arbitrator to adjudicate upon the disputes
and decide the claims made by the Contractor. The relevant part of
the order of the civil court made on 14.3.1995 reads:
"The Advocates of the concerned parties have given their consent for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
appointment of Shri SS Mathur retired Additional Chief Engineer,
Udaipur as Sole Arbitrator. The advocate of the applicant has no
objection.
Hence, the application of the applicant is accepted. Shri SS Mathur
retired Additional Chief Engineer, Udaipur is appointed Arbitrator
for deciding the dispute in accordance with the agreement No.75 of
77-78 executed between the parties. The arbitrator shall pass the
award after hearing the parties in accordance with the provisions of
the Act and the terms and conditions of the agreement.
The arbitrator be informed accordingly."
The sole arbitrator, thus, substituted on consent of parties
conducted and concluded the arbitration proceedings. The State
participated in the arbitration proceedings without any demur or
protest.
We asked the learned counsel appearing for the State whether in
their objection petition filed against the award under Section 30 of the
Act, any objection on the competence of the substituted arbitrator to
make the award in terms of clause 23 was raised. The copy of the
application under Section 30 of the Arbitration Act raising objection to
the award filed by the State has been made part of record in these
appeals. We have gone through the objection petition preferred under
the said Section 30 of the Act. We find that no objection was raised on
the competence of the arbitrator or the validity of the arbitration
proceedings under Clause 23 of the agreement.
Clause 23 of the Agreement is undoubtedly not an arbitration
clause and the sitting Chief engineer, to whom earlier reference was
made, could not have acted as an arbitrator and made the award. The
sitting Chief Engineer to whom initial reference was made did not
complete the arbitration proceedings. The substituted arbitrator was a
retired Chief Engineer and parties agreed to his appointment and
submitted to his jurisdiction. By consent of parties, he was chosen
sole arbitrator and disputes were referred to him. The State, without
demur or protest, submitted to the jurisdiction of the arbitrator and
participated in the proceedings. The State is estopped on the doctrine
of acquiescence and waiver from raising objection to the competence
of the substituted arbitrator and validity of the arbitration proceedings
by taking recourse to clause 23 of the agreement on the basis of which
initial reference was made to sitting Chief Engineer. See following
observations in the case of Prasun Roy vs. Calcutta Metropolitan
Devlopment Authority [1987 (4) SCC 217]:
"The principle is that a party shall not be allowed to blow hot and cold
simultaneously. Long participation and acquiescence in the
proceedings preclude such a party from contending that the
proceedings were without jurisdiction...Basically the principle of
waiver and estoppel is not only applicable where the award had been
made but also where a party challenges the proceedings in which he
participated."
Therefore, this appeal i.e. CA No.8052 of 2001, preferred by the
State, also deserves to be dismissed.
Civil Appeal No. 1400 of 2002
CA 1400 of 2002 has been preferred by the Contractor whereby
its civil revision petition against the order granting 12% and not 18%
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
future interest on the awarded sum under his application under
Section 152 CPC, was dismissed. This court issued notice on the SLP
and subsequently granted leave to appeal on a limited question as to
why the decree drawn up in conformity with the order making award
rule of the court should not direct payment of interest pendente lite
and future at the rate of 18% per annum. During pendency of this
appeal, IA No.4 of 2002 has been made by the Contractor seeking
permission to argue the appeal on the additional ground that interest
awarded by the arbitrator on pre reference period, pendente lite, and
post award should in aggregate be deemed as principal amount
awarded for the purpose of awarding future interest on the composite
sum at the rate of 18% per annum.
The civil court on the application of the Contractor under Section
152 CPC had modified the decree by directing payment of interest @
12% on the awarded principal amount specified to be Rs. 6,68,058.16.
The period for which interest has been awarded is from the date of the
award 29.9.1997 till the date of payment.
The Contractor who appeared in person submitted that for
carrying out the work awarded under the contract he had to raise loan
and borrow money from banks and financial institutions at the rate of
interest ranging between 18% per annum to 21% per annum
The arbitrator has awarded interest at the rate of 18% p.a. from the
date of award till the date of decree or payment. When the
award was made rule of the court, the civil court could not, without
assigning any reason, reduce the rate of future interest from 18% to
12% on the awarded amount of Rs.6,68,058.16 by treating it to be
the total principal sum. Reliance is placed on the five Judges Bench
decision of this Court in the case of Central Bank of India vs.
Ravinndra [2002 (1) SCC 367].
The submission of the contractor is that on the aggregate
amount that is principal sum plus pendente lite and future interest
from date of award to the date of decree or payment whichever is
earlier, he was entitled to grant of decree by civil court of future
interest @ 21% as claimed by him and in any case @ 18% as awarded
by the arbitrator.
On behalf of the State, the award of interest on the aggregate
sum, that is, the principal sum plus all interests payable, upto the date
of decree or payment has been questioned on the ground that it would
amount to directing payment of interest on amount of interest which is
not permissible under section 29 of the Act. It empowers the court to
award future interest only on the ’principal sum’ excluding the interest
amount.
On the question of rate of future interest from the date of decree
to the date of payment, Section 29 of the Act empowers the Court to
order payment of interest at such rate as the court deems reasonable
to be paid on the principal sum as adjudged by the award and
confirmed by the decree. The decision in the case of Central Bank of
India vs. Ravindra (supra) was based on Section 34 of the Code of
Civil Procedure as it stood prior to and after its amendment by Act
No.66 of 1956 and has no direct application to the rate of future
interest payable on the principal sum awarded by the arbitrator in the
proceedings under the Arbitration Act. The interest @ 12% awarded
on the principal sum by the court cannot be held to be so low as to
treat it as unreasonable. We decline to interfere under Article 136 of
the Constitution in the rate of interest awarded by the civil court
treating it to be a reasonable rate. The appeal, preferred by the
Contractor claiming future interest at higher rate, is dismissed.
Civil Appeal No. 8053 of 2001
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
Civil Revision Petition filed by the State of Rajasthan against the
order rejecting objection under Section 30 of the Act was dismissed by
the High Court by impugned order dated 21.12.2000 on the ground
that Revision was barred by limitation and there was no sufficient
cause to condone the delay under Section 5 of the Limitation Act.
We have perused the impugned order whereby application
seeking condonation of delay was rejected and the Revision Petition
was dismissed as barred. The cause for the delay stated was long
strike of government employees. In the application seeking
condonation of delay there was no mention as to when the strike
commenced and terminated. The application was completely vague
and the High Court committed no error in rejecting it. We find no
ground to interfere in the said order. Civil Appeal No.8053 of 2001 is,
therefore, dismissed.
Civil Appeal No. 8055 of 2001:
Against the order of the Civil Court rejecting objection under
Section 30 of the Act and making award rule of the Court, an appeal
was also filed by the State. The said appeal was also barred by time
and the cause shown for seeking condonation of delay was same that
there was strike of government employees. For the same reason on
which the connected civil revision was dismissed by the High Court,
the appeal against rejection of objection under Section 30 of the Act
and passing decree in terms thereof was also dismissed as barred by
time. Since we have found no error in the order of the High Court
dismissing the revision petition as barred by time, the dismissal of
appeal as barred by limitation on the same ground also deserves to be
maintained. This appeal stands dismissed.
Civil Appeal No. 8054 of 2001
Civil Appeal 8054 of 2001 has been preferred by the State of
Rajasthan against the order whereby the High Court has upheld the
modification of the decree passed by the civil court in terms of the
award which directs payment of future interest on the awarded
amount from the date of award till the date of payment. The High
Court in dismissing the appeal against the said order has stated that
merely an accidental error or an omission in the initial decree passed,
was corrected and that too with the consent of the parties. This
appeal preferred against the order of the High Court passed on
consent of parties cannot be interfered with. It is also, accordingly,
dismissed.
In the conclusion, all the appeals preferred by the State and the
appeal and the interlocutory application preferred by the Contractor
are dismissed. We direct the parties to bear their own costs in these
appeals.