Full Judgment Text
$~
* IN THE HIGH COURT OF DELHI AT NEW DELHI
nd
% Judgment reserved on : 22 February, 2019
Judgment pronounced on : 14 November, 2019
+ FAO(OS) (COMM) 195/2017
GLENCORE INTERNATIONAL AG ..... Appellant
Through Mr. Rajiv Nayyar, Sr. Advocate with
Mr. Sumeet Lall, Mr. Sidhant Kapoor
and Mr. Nikhil Lal, Advocates
versus
M/S SHREE GANESH METALS & ANR ..... Respondents
Through Mr. V.K. Garg, Sr. Advocate with
Karunesh Tandon and Mr. Awanya
Madhusudan, Advocates
CORAM:
HON'BLE MR. JUSTICE G.S. SISTANI
HON'BLE MS. JUSTICE SANGITA DHINGRA SEHGAL
G.S. SISTANI, J.
1. The present appeal has been filed by the appellant under Section 13(1)
of the Commercial Courts, Commercial Division and Commercial
Appellate Division of High Courts Act, 2015 read with Section 50(1)(a)
of the Arbitration and Conciliation Act, 1996 (hereafter “the Act”) for
setting aside the impugned order dated 02.11.2017 passed by a learned
Single Judge of this Court in an application being I.A. 4550/2017 filed
under Section 45 of the Act seeking mandatory reference of respondent
no.1 to arbitration.
FAO (OS)(COMM)195/2017 Page 1 of 15
2. The necessary facts required to be noticed for disposal of this appeal,
are as under: -
3. The appellant herein is a company incorporated under the laws of
Switzerland and is engaged in the business of commodity trading and
mining whereas respondent No.1 is one of the highest producers of zinc
alloys in India with its office at Kalaamb, Himachal Pradesh.
4. Respondent No.1 purchased zinc metal from the appellant for the first
time in 2011. In relation to this transaction, the parties executed an
agreement dated 20.04.2011 being contract no.061-11-13375-S (first
contract), pursuant to which, respondent no.1 agreed to purchase 400
metric tons of zinc metal from the appellant to be supplied in four lots
of 100 metric tons each by June, 2011. The first contract was governed
by the laws of England and Wales and contained an arbitration clause
28.2, which provided for resolution of disputes through arbitration
under the London Court of International Arbitration (LCIA) rules. The
seat of arbitration was at London.
5. The parties executed the second contract being no.061-11-15016-S
(second contract) on 01.07.2011 whereunder the appellant was to
supply 400 metric tons of zinc metal to respondent No.1 in two lots of
200 each. On 26.09.2011, an amendment was carried out to the second
contract for replacing certain clauses on quantity, quality, shipment,
price, quotational period and payment. The appellant further agreed to
supply 600 metric tons with one lot of 200 metric tons by July 2011,
another lot of 200 metric tons during July 2011/August 2011 and two
lots of 100 metric tons each in October, 2011 as per the similar laws as
that of the first contract, the seat being at London.
FAO (OS)(COMM)195/2017 Page 2 of 15
6. Being satisfied with the performance of the appellant, the parties
entered into a third contract executed on 23.11.2011 bearing contract
no.061-11-17714-S (third contract) for supply of 600 metric tons of
zinc metal to respondent No.1 from December, 2011 to April, 2012.
The contract containing arbitration Clause 29.2 was also governed by
English laws and the seat was at London.
7. On 11.01.2012, the parties executed the fourth contract for supply of
200 metric tons of zinc metal during January, 2012 to February, 2012
on the similar terms of the third contract.
8. Subsequently, the parties wished to enter into a fifth contract for the
sale-purchase of 6000 metric tons of zinc metal from March, 2016 to
February, 2017 (Clause 5 of the contract). The business modalities were
reduced into writing in an email dated 10.03.2016 for deciding the
commercial terms. The respondent through an email dated 11.03.2016
expressly agreed to and accepted ‘all’ terms of the previous emails
except the terms relating to provisional prices. Pursuant to the approval
given by respondent No.1, the parties entered into a fifth contract,
arbitration being governed under Clause 32.2 of the contract, which was
also based on the English laws and provided for a three-member
Tribunal, the seat of arbitration was again based at London.
9. With respect to the fifth contract, respondent no.1 was required to open
an irrevocable letter of credit at a bank nominated by the appellant
which would cover the provisional value of materials. The contract
stipulated that respondent No.1 is to open a standby letter of credit
(SBLC) of USD 50,000 available by payment at sight against
FAO (OS)(COMM)195/2017 Page 3 of 15
presentation of either a demand for payment or against the appellant’s
stand that respondent no.1 has failed to perform its obligation.
10. Subsequently, differences and the disputes arose between the parties
with regard to the terms and conditions of the fifth contract as
respondent No.1 did not pay the outstanding amount in sum of USD
867,411.23 to the appellant. Resultantly, the appellant encashed the
SBLC of USD 1,003,000 towards such outstanding amount.
11. In response to the encashment of SBLC by the appellant, respondent
No.1 filed a suit being CS (Comm) 154/2017 for declaration, permanent
injunction and recovery of Rs.8 crores (approx.) whereunder the
application being I.A. No.4550/2017 of the appellant under Section 45
of the Act was dismissed by the learned Single Judge as being without
merits. Hence, the present appeal.
12. Mr. Rajiv Nayyar, learned senior counsel appearing for the appellant
submits that the intention of the parties to refer their dispute to
arbitration under the rules of LCIA in London is consistently evident
from the past contractual relationship between the parties since the year
2011 when the first agreement was entered into between the parties.
13. Mr. Nayyar contends that there exists an arbitration agreement between
the parties in terms of Clause 32.2 of the 2016 contract or Clause 29.2
of the 2012 contract, which is squarely covered within the meaning of
section 44 read with section 2(f) of the Act. Thus, the arbitration
agreement between the parties is a valid agreement. Counsel for the
appellant submits that respondent No. 1, while challenging the validity
of 2016 contract, has failed to challenge the validity of arbitration
agreement on the narrow grounds under Section 45 of the Act. Contrary
FAO (OS)(COMM)195/2017 Page 4 of 15
to the said challenge, respondent no.1 has contradicted itself by relying
upon the terms and conditions of the business confirmation email, as the
arbitration agreement, incorporated by reference and mutually agreed
between the parties cannot be unilaterally denied by respondent no.1 to
avoid the arbitration clause. Counsel has further argued that the learned
Single judge failed to interpret the legislative intention of Section 45 of
the Act because mere signing or not signing of a contract is not a
sufficient measure to determine the validity of the contract. In support
of the contention that the arbitration clause can be validly incorporated
by mutual consent by reference, learned counsel places reliance on para
17 of the judgement given in the case of Inox Wind Limited v. Thermo
Cables Ltd. reported at 2018 (2) SCC 519, as reproduced under:
“17 . This Court in M.R. Engineers case [ M.R. Engineers &
Contractors (P) Ltd. v. Som Datt Builders Ltd. , (2009) 7
SCC 696 : (2009) 3 SCC (Civ) 271] , which is discussed in
detail supra, held the rule to be that an arbitration clause in
an earlier contract cannot be incorporated by a general
reference. The exception to the rule is a reference to a
standard form of contract by a trade association or a
professional institution in which case a general reference
would be sufficient for incorporation of an arbitration
clause. Reliance was placed by this Court on Russell on
Arbitration , 23rd Edn. (2007). The development of law
regarding incorporation after the judgment in M.R.
Engineers [ M.R. Engineers & Contractors (P) Ltd. v. Som
Datt Builders Ltd. , (2009) 7 SCC 696 : (2009) 3 SCC (Civ)
271] requires careful consideration. It has been held
in Habas Sinai Ve Tibbi Gazlar Isthisal Endustri
AS v. Sometal SAL [ Habas Sinai Ve Tibbi Gazlar Isthisal
Endustri AS v. Sometal SAL , 2010 Bus LR 880 : 2010
FAO (OS)(COMM)195/2017 Page 5 of 15
EWHC 29 (Comm)] that a standard form of one party is also
recognised as a “single contract” case. In the said case, it
was also held that in single-contract cases general reference
is enough for incorporation of an arbitration clause from a
standard form of contract. There is no distinction that is
drawn between standard forms by recognised trade
associations or professional institutions on one hand and
standard terms of one party on the other. Russell on
Arbitration , 24th Edn. (2015) also takes note of Habas
case [ Habas Sinai Ve Tibbi Gazlar Isthisal Endustri
AS v. Sometal SAL , 2010 Bus LR 880: 2010 EWHC 29
(Comm)].”
14. Mr. Nayyar further contends that the conduct of respondent No.1 in
accepting invoices containing specific reference to 2016 contract,
issuing standby letters of credit and furnishing letters of credits
specifically referring to 2016 contract and addressing correspondence
specific to contract 2016 makes it evident that the respondent has
accepted the basic and essential conditions of the 2016 contract,
including the arbitration agreement contained therein.
15. Counsel for the appellant submits that 2016 contract and business
confirmation email contained a valid, enforceable and operative
arbitration agreement with the seat being in London and accordingly,
the present disputes among the parties ought to be referred to arbitration
in accordance with the legislative mandate under Section 45 of the Act.
16. Mr. Nayyar further contends that Section 45 of the Act casts an
obligation on the judicial authority before whom the matter is pending
to refer the dispute to arbitration thereby protecting the sanctity of the
contract, which was entered into between the parties by mutual consent.
FAO (OS)(COMM)195/2017 Page 6 of 15
He further argues that it is a settled position of the law that provisions
of Section 45 of the Act prevails over the provisions of CPC and as
such the jurisdiction of the civil court can be excluded when there exists
an arbitration agreement which is valid and binding.
17. Mr. Nayyar has laboured hard to submit that 2016 contract expressly
contained the acceptance of the terms and conditions as per the last
contract i.e. 2012 contract. The contract of 2012 specifically provided
for an arbitration clause whereby the disputes arising between the
parties were to be referred to arbitration. It is the stand of the appellant
that at no stage during the present dispute, the respondent objected to
the arbitration clause. On the contrary, various invoices were raised
incorporating the contract number relating to the 2016 contract and
these were never objected to by the respondent. Further, respondent
no.1’s entire claim of alleged outstanding payments is solely premised
on the terms and conditions of 2016 contract. Thus, respondent no.1
cannot refuse to acknowledge the 2016 contract, particularly, when it
seeks to rely upon the terms and conditions for recovery of such
payment. Further, the issue regarding encashment of letter of credit and
bank guarantee, which was occasioned on account of respondent no.1’s
repeated breach is consequential to the main dispute between the
parties.
18. Mr. V.K. Garg, learned senior counsel appearing for the respondents
has contradicted the stand of the appellant. Mr. Garg has strongly urged
before this Court that there was no arbitration agreement between the
parties as mandated by Section 7 of the Act. He further submits that
terms and conditions referred under the 2016 contract were neither
FAO (OS)(COMM)195/2017 Page 7 of 15
accepted nor concluded as the said agreement was never signed by the
appellant. Since the said contract remained unsigned, there arises no
question of acceptance of the arbitration clause for adjudication of any
dispute. Mr. Garg has further that email dated 10.03.2016 is of no
consequence as it was written by Glencore India and not by the
appellant. It is the stand of the respondent that appellant is pleading a
new case in appeal by averring that the arbitration clause was
incorporated by reference since these are standard form contracts.
However, this aspect was never specifically pleaded before the learned
Single Judge nor argued.
19. It is further submitted that business modalities were initially reduced
into writing vide email dated 10.03.2016. The issue of referring the
dispute to arbitration was neither discussed nor approved by the
respondent at any stage. The principle of noscitur a sociis will apply
while construing the phrase ‘all other terms and conditions.’ The phrase
referred to the other commercial terms and not the arbitration clause,
which implies that the parties did not have any intention to resolve their
disputes through arbitration. Thus, no valid arbitration agreement came
into existence between the parties.
20. We have heard the learned counsel for the parties and carefully
examined the impugned order dated 02.11.2017, terms of the first
contract (2012) and the contract of the year 2016 and the rival
contentions of the learned counsel appearing in the matter.
21. The short question which arises for our consideration is as to whether or
not the arbitration agreement between the parties in terms of Clause
29.2 of the 2012 contract would apply to the disputes which have arisen
FAO (OS)(COMM)195/2017 Page 8 of 15
between the parties with regard to the supply of the year 2016 whereby
the supplies were to be made between March 2016 to February 2017.
22. Learned Senior Counsel for the appellant has strongly urged before us
that the contract of 2016, comprising of the arbitration Clause 32.2, was
validly entered into between the parties. It is contended that the email
dated 10.03.2016 sent by the appellant, along with the commercial
business modalities, also reduced in writing other terms and conditions
as per the 2012 contract and the said terms and conditions included the
arbitration clause as well. It is also contended that the respondent vide
email dated 11.03.2016 accepted all the terms as per the 2012 contract
except one, which did not pertain to the arbitration clause, thereby
making the arbitration clause of the 2012 contract acceptable on the part
of the respondent.
23. We find no infirmity in the impugned order dated 2.11.2017 of the
learned Single Judge in observing that the agreement entered into by the
parties was not valid due to absence of parties being ad idem.
Paragraphs 11 to 14 of the aforementioned order of the learned Single
Judge passed in CS(COMM) 154/2017 read as under:
“11. When the parties entered into negotiation for sale
purchase of 6000 metric tons of zinc in 2016, no concluding
contract wherein signatures o the plaintiff came into
existence. Contract No. 061-16-12115-S (Annexure D)
dated 11.03.2016 incorporating comprehensive terms and
conditions of the transaction bears signatures only on behalf
of the defendant No.1. The terms and conditions contained
therein apparently were not accepted, signed or stamped by
the plaintiff or its duly authorized person. Business
confirmation E-mail dated 10.03.2016 incorporating
detailed terms and conditions of the agreement begins with:
Dear Mr. Aggarwal,
FAO (OS)(COMM)195/2017 Page 9 of 15
Further to discussions and your below mail , please
following are the final terms at which GIAG can offer zn
metal to Ganesh metals: XXXX
12. Apparently, it was an offer made to the plaintiff for its
acceptance. The plaintiff vide email dated 11.03.2016 did
not accept the offer in its entirety and respondent as “We
confirm the same terms as said just one thing that
provisional price of both, either the LC or invoice will be
average of last 5 LME days.
13.Nothing is on record if this change in the offer expressly
accepted by the defendant no.1. It responded by another
email, “thanks for business confirmation. Reverting with
contract and performa ”. Nothing is on record to show if the
contract containing detailed terms and conditions was
exchanged thereafter and it was accepted by the plaintiff.
The defendant No. 1 did not insist to get plaintiffs
signatures on the contract accepting all the terms and
conditions. Seemingly the defendant no.1 started acting
upon the said unsigned contract.
14.From the exchange of emails reproduced above, it cannot
be inferred that the plaintiff had expressly or impliedly
agreed to all the terms and conditions incorporated in 2012
contract. The emails sent by the applicant to the plaintiff did
not specifically record the terms and conditions as contained
in 2012 contract. In fact, there was no reference of 2012
contract in the various exchanges that took place between
the parties.”
24. As far as the submission of the petitioner with respect to the
incorporation of the arbitration agreement of 2016 contract in terms of
2012 contract is concerned, the perusal of the relevant Clauses 32.2
(2016 contract) and 29.2 (2012 contract) display variations in the terms.
The arbitration Clause 29.2 interalia included a part stating that the
FAO (OS)(COMM)195/2017 Page 10 of 15
parties waive irrevocably their right to any form of appeal, review or
recourse to any state court or other judicial authority, whereas the
arbitration Clause 32.2 of 2016 contract was devoid of such a part.
Moreover, the Clause 32.2 contained an additional part which stated
that the number of arbitrators shall be three (one arbitrator to be
appointed by each party and the third to be chosen by the two party
appointed arbitrators). Thus, learned Single Judge has rightly observed
that if the petitioner had the intention to retain all the terms and
conditions of the 2012 contract in 2016 contract there was no reason to
change the terms of the arbitration clause and therefore there was no
acceptance, whether implied or express, on the part of the respondent.
25. Learned counsel for the petitioner, while relying on the judgement in
the case of Inox Wind Limited (supra), has strongly urged before us
that the contract of 2012, containing the arbitration clause, is a standard
form of a contract and therefore the said clause can be incorporated in
the 2016 contract by general reference. Law pertaining to the
incorporation of the arbitration clause by reference has been discussed
by the Apex Court in a catena of judgements. In the case of M. R.
Engineers and Contractors (P) Ltd. v. Som Datt Builders Ltd. reported
at (2009) 7 SCC 696 the Apex Court held that an arbitration clause in a
previous contract cannot be incorporated by reference in a subsequent
contract. However, as an exception to this rule, an arbitration clause of
an earlier standard form contract by trade association or professional
institutions can be incorporated by reference in a subsequent contract.
26. In the case Habas Sinai Ve Tibbi Gazlar Isthisal Endustri AS v.
Sometal SAL reported at 2010 Bus LR 880 before the Queen’s Bench
FAO (OS)(COMM)195/2017 Page 11 of 15
Division, the Court categorised the contracts and held that in single-
contract cases (category 1 and 2) a general reference to the arbitration
clause from a standard form contract would be sufficient whereas in
two-contract cases(category 3 and 4) a specific reference to the
arbitration clause from an earlier contract is required. The said
categories are reproduced as under:
| “(1) A and B make a contract in which they incorporate | ||
|---|---|---|
| standard terms. These may be the standard terms of one | ||
| party set out on the back of an offer letter or an order, or | ||
| contained in another document to which reference is made; | ||
| or terms embodied in the rules of an organisation of | ||
| which A or B or both are members; or they may be terms | ||
| standard in a particular trade or industry. | ||
| (2) A and B make a contract incorporating terms | ||
| previously agreed between A and B in another contract or | ||
| contracts to which they were both parties. | ||
| (3) A and B make a contract incorporating terms agreed | ||
| between A (or B) and C. Common examples are a bill of | ||
| lading incorporating the terms of a charter to which A is a | ||
| party; reinsurance contracts incorporating the terms of an | ||
| underlying insurance; excess insurance contracts | ||
| incorporating the terms of the primary layer of insurance; | ||
| and building or engineering sub-contracts incorporating the | ||
| terms of a main contract or sub-sub-contracts incorporating | ||
| the terms of a sub-contract. | ||
| (4) A and B make a contract incorporating terms agreed | ||
| between C and D. Bills of lading, reinsurance and insurance | ||
| contracts and building contracts may fall into this category.” | ||
relying on Habas (supra), held that a general reference to a consensual
standard form contract between parties is sufficient for incorporation of
an arbitration clause. The Court, while modifying the law laid down in
FAO (OS)(COMM)195/2017 Page 12 of 15
M.R. Engineers (supra), also observed that a general reference to a
standard form of contract of one party along with those of trade
associations and professional bodies will be sufficient to incorporate the
arbitration clause. It was also observed that a conscious acceptance of
the arbitration clause of the other document is necessary for the purpose
of incorporating it into the contract. Para 18 is reproduced as under:
“18. We are of the opinion that though general reference to
an earlier contract is not sufficient for incorporation of an
arbitration clause in the later contract, a general reference to
a standard form would be enough for incorporation of the
arbitration clause. In M.R. Engineers [ M.R. Engineers &
Contractors (P) Ltd. v. Som Datt Builders Ltd. , (2009) 7
SCC 696 : (2009) 3 SCC (Civ) 271] this Court restricted the
exceptions to standard form of contract of trade associations
and professional institutions. In view of the development of
law after the judgment in M.R. Engineers [ M.R. Engineers
& Contractors (P) Ltd. v. Som Datt Builders Ltd. , (2009) 7
SCC 696 : (2009) 3 SCC (Civ) 271] case, we are of the
opinion that a general reference to a consensual standard
form is sufficient for incorporation of an arbitration clause.
In other words, general reference to a standard form of
contract of one party will be enough for incorporation of
arbitration clause. A perusal of the passage from Russell on
Arbitration , 24th Edn. (2015) would demonstrate the change
in position of law pertaining to incorporation when read in
conjunction with the earlier edition relied upon by this
FAO (OS)(COMM)195/2017 Page 13 of 15
Court in M.R. Engineers case [ M.R. Engineers &
Contractors (P) Ltd. v. Som Datt Builders Ltd. , (2009) 7
SCC 696 : (2009) 3 SCC (Civ) 271] . We are in agreement
with the judgment in M.R. Engineers case [ M.R. Engineers
& Contractors (P) Ltd. v. Som Datt Builders Ltd. , (2009) 7
SCC 696 : (2009) 3 SCC (Civ) 271] with a modification that
a general reference to a standard form of contract of one
party along with those of trade associations and professional
bodies will be sufficient to incorporate the arbitration
clause.”
28. The facts in the case of Inox Wind Limited (supra) do not apply to the
present case as the Supreme Court therein allowed the appeal for the
reason that in the purchase order it was categorically stated that the
supply would be as per the terms mentioned therein and in the attached
standard terms and conditions, which contained the arbitration clause,
and the supplier being in the know of the said standard terms and
conditions, accepted the same. Therefore, the purchase order being a
single contract, a general reference to the standard terms and conditions
was found to be sufficient. However, in the present case, in the contract
of 2016, there was no categorical mention of purchase or supply to be
based on the standard terms and conditions, including the arbitration
clause, contained in the contract of the year 2012. Moreover, there is
nothing on record which clearly shows that the respondent gave its
acceptance to enter into a contract of 2016 for the supply to be made
between March 2016 to February 2017 as per the standard terms and
conditions of the contract of 2012.
FAO (OS)(COMM)195/2017 Page 14 of 15
29. Additionally, a standard form of contract is a ‘take it or leave it’
contract which does not leave scope for any negotiation with respect to
its terms and conditions. However, in the present case the parties
negotiated on the one of the terms of the contract that is the provisional
price of LC or invoice. Also, the contract of 2016 contained an
arbitration Clause 32.2, but the same was at variance with the
arbitration Clause 29.2 of the contract of 2012. Therefore, we find no
force in the contention of the Mr. Nayyar that the contract of 2016 was
a standard from contract.
30. In view of the above discussion, we find no infirmity in the decision of
the learned Single Judge.
31. Accordingly, the appeal stands dismissed.
CM APPL 40960/2017
32. In view of the order passed in the appeal, the application also stands
dismissed.
G.S.SISTANI, J
SANGITA DHINGRA SEHGAL, J
NOVEMBER 14, 2019//
FAO (OS)(COMM)195/2017 Page 15 of 15