Full Judgment Text
NEUTRAL CITATION NO. 2023/DHC/001847
* IN THE HIGH COURT OF DELHI AT NEW DELHI
rd
% Date of Order: 3 March, 2023
+ O.M.P. (COMM) 96/2023 & I.A. 4264/2023 & I.A. 4265/2023 &
I.A. 4266/2023 & I.A. 4267/2023 & I.A. 4268/2023 & I.A.
4269/2023 & I.A. 4270/2023
UNION OF INDIA ..... Petitioner
Through: Mr. Ruchir Mishra, Mr. Sanjiv Kr.
Saxena, Mr. Mukesh Kr. Tiwari,
Ms. Reba Jena Mishra and Ms.
Poonam Mishra, Advocates
versus
M/S SATISH BUILDERS ..... Respondent
Through: None
CORAM:
HON'BLE MR. JUSTICE CHANDRA DHARI SINGH
O R D E R
CHANDRA DHARI SINGH, J (Oral)
1. The instant objection petition under Section 34 of the Arbitration
and Conciliation (Amendment) Act, 2015 has been filed on behalf of the
petitioner seeking the following reliefs:
“a) Set aside the award passed by the Ld Arbitrator dated
22.10.2022 passed by the learned Sole Arbitrator Sh J .S.
Sharma in Agreement No. 01/EE/MPD-I/2018-19 titled as
M/s Satish Builders Vs Union of India in Arbitration Case
No. JSS/ARB/4, received by Petitioner on 22.10.2022, to the
extent it awards claims to the respondent contractor and
rejects counter claims of the petitioner;
b) Direct cost of the proceedings in favour of the
petitioners/objectors and against the respondent;
O.M.P. (COMM) 96/2023 Page 1 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
c) Pass any other or further order as this Hon'ble tribunal
deem fit and proper in the fact and circumstances of the
case.”
FACTUAL MATRIX
2. In January 2018, the Contractor/respondent was awarded a
Contract for work by the Central Public Works Department (CPWD)
(hereinafter referred to as “CPWD/petitioner”). The first Contract was
awarded vide Agreement No. 06/EE/CUHPD/2017-18 for the tendered
value of INR 21,44,15,236 which was shut as the funds allocated by the
client for the same were exhausted.
3. In between the execution of the work under the first Contract,
th
another Contract for work vide letter dated 18 May 2018 was awarded to
the respondent, and Agreement no. 01/EE/MPD-1/2018-19 was executed
for the tendered value of INR 2,84,94,777. The stipulated time of
completion was 6 months.
th th
4. On or about 16 November 2018, the 6 RA bill was released
whereby the Central University of Haryana (CUH) Mahendergarh
(hereinafter referred to as "Client") was requested to provide funds as
there was a temporary unavailability of funds in the month of December
2018 and January 2019.
5. The issue of funds was known to the respondent in view of which a
th
letter dated 20 December 2018 was sent by the respondent requesting
the CPWD/petitioner to grant extension and release the amount withheld
th
from 6 RA bill. In the aforesaid letter the respondent undertook that no
extra claims would be made.
O.M.P. (COMM) 96/2023 Page 2 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
6. The respondent‟s request was approved by the then Assistant
st
Engineer, CPWD vide letter dated 21 December 2018, and extension of
st
time till 31 March 2019 and the release of the withheld amount of INR
th
7,12,444 was granted on 27 December 2018.
7. On the very next date of extension, the respondent vide letter dated
nd th
22 December 2018 submitted the 7 RA bill claiming INR 92,11,697
th
which was later revealed to be a design to repudiate the Contract. The 7
RA bill was passed for INR 43,90,947 after adjustment of amount
advanced earlier as per the Clause 10B of the Agreement, INR 1 was
th
released on 7 March 2020.
8. While the funds were awaited from the Client, the respondent,
th
repudiated the said Contract vide letter dated 18 January 2019.
9. In the month of January 2019, when the funds were made
available, a meeting between the CPWD/petitioner and the Agencies
th
including the respondent was held on 11 February 2019 and the minutes
th
of meeting thereto were issued vide letter dated 12 February 2019, inter
alia , to the effect that the respondent shall complete the work. By
agreeing to complete the work, the repudiation letter by the respondent
stood withdrawn casting an obligation to complete the work.
10. From April 2019 to October 2019 various letters were issued
granting extension of Contract so as to enable the respondent to complete
th
the balance work. On 30 October 2019, the respondent vide letter inter
alia stated that the work is not closed.
O.M.P. (COMM) 96/2023 Page 3 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
11. On account of respondent not resuming work, several
letters/reminders were issued by the CPWD/petitioner requesting the
respondent to start the work.
th
12. On 30 December 2012 the CPWD/petitioner issued a final notice
to the respondent demanding that the work may be resumed immediately,
failing which it would determine the Contract as per Clause 3(a) and 3(b),
and in consequent to the final notice, the Contract was determined by the
th
CPWD/petitioner vide letter dated 7 January 2021.
th
13. A Dispute Resolution Committee was set-up on 25 February 2021
on account of the respondent raising disputes/claims. The DRC had
rejected all the claims of the respondent.
14. Statement of Claims was filed by the respondent before the learned
Arbitral Tribunal raising 18 claims and a few amendments were made to
the Statement of Claims at a later date followed by a Statement of
Defence filed by the CPWD/petitioner .
nd
15. The Learned Arbitrator passed the impugned Award dated 22
October 2022 which was communicated to the CPWD/petitioner through
email
16. Aggrieved with the findings recorded in the impugned Arbitral
Award, the CPWD/petitioner has approached this Court under Section 34
of the Arbitration Act.
O.M.P. (COMM) 96/2023 Page 4 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
SUBMISSIONS
(On behalf of the CPWD/petitioner)
17. Learned counsel for the petitioner submits that Impugned Award is
liable to be set aside as the findings of the Learned Arbitrator to the effect
of repudiating Contract are justified whereas the determination of
Contract is unjustified.
18. Learned counsel for the CPWD/petitioner submits that findings in
Para 28 of the Impugned Award are erroneous as the said paragraph does
nd
not take into consideration and even refers to the letter dated 22
February 2019 which prove that funds were available with department but
the work was not resumed.
19. Learned counsel for the petitioner further submits that the works
such as Earthwork, which were already paid, are allowed based on
CPWD specification. It is further submitted that Earthwork as inspected
by the independent engineer was not visible as it was beneath the earth.
20. The learned counsel for the petitioner submits that the award of
amount of INR 42,052 is without any evidence as that quantum of work
done by the respondent was duly measured and paid for by the
CPWD/petitioner.
21. The learned counsel for the petitioner further submits that as per
the Agreement, the amount cannot be paid for the items not provided.
However, the item no. 2.3 claimed under sub claim 1.1 has been allowed
by the impugned Award awarding INR 73,270.
O.M.P. (COMM) 96/2023 Page 5 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
22. The learned counsel for the petitioner further submits that items
claimed under statement 1.3 were substituted items and the
CPWD/petitioner already paid the respondent at market rates. However,
the substituted items were alleged to be extra items, which the arbitrator
nd
accepted vide award dated 22 October 2022 and awarded INR
32,97,769, treating substituting items as extra items.
23. The learned counsel for the petitioner submits that that the learned
Arbitrator failed to appreciate that under Clause 29, CPWD is entitled to
recover due amounts from the respondent under another Contract.
24. The learned counsel for the CPWD/petitioner submits that award
of amount of INR 51,321 against statement 1.9 is contrary to agreement
provision 10B(iv) and award of INR 84,162 against claim under
statement 1.14 is contrary to Agreement provisions.
25. The learned counsel for the CPWD/petitioner submits that the
award of INR 6,61,430 against Claim 3 is against Agreement Clause 1A
and that the Learned Arbitrator has committed illegality in releasing the
security amounts deducted by CPWD from RA bills prematurely as
defect liability period is yet to get over and on the other hand that learned
Arbitrator erred in not appreciating that the said security amounts were
rightly forfeited by CPWD on determination of the Contract as per Clause
3 of the Agreement.
26. The learned counsel for the CPWD/petitioner submits that
Performance Bank Guarantee (hereinafter “PBG”) submitted by the
respondent for INR 12,60,000 as per Clause 1 has been directed to be
O.M.P. (COMM) 96/2023 Page 6 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
released by the learned Arbitrator contrary to Agreement provisions and
Claim 4 has been allowed and Counter-Claim 1 has been rejected. It is
submitted that the facts of the present case are indicative of the fact that
respondent voluntarily did not execute the work.
27. The learned counsel for the CPWD/petitioner submits that the
findings in the award in support of release of PBG that release of PBG by
the CPWD on earlier occasion confirms that the respondent performed
the Contract, is perverse finding as a part of PBG was released by the
th
CPWD in accordance with OM dated 13 May 2020.
28. The learned counsel for the CPWD/petitioner submits that findings
in the award are self-contradictory as the award rejects the claim no. 5
and 6 for want of proof/documentary/evidence/necessary details by the
respondent. However, some claims which were not supported were also
allowed by the learned Arbitrator.
29. The learned counsel for the CPWD/petitioner further submits that
award of INR 2,55,390 against Claim 7 is perverse as the respondent had
himself requested to shift milestone specifically agreeing that he would
not claim anything extra, therefore, no award could be awarded under
Claim 7.
30. The learned counsel for the CPWD/petitioner further submits that
st
respondent issued notice dated 31 December 2018 conveying its
intention to repudiate the Contract. Therefore, even if the respondent is
th
entitled to overhead expenses, the Award cannot be awarded till 18
O.M.P. (COMM) 96/2023 Page 7 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
January 2019 as the respondent had already made up his mind to
repudiate the Contract.
31. The learned counsel for the CPWD/petitioner submits that the
learned Arbitrator passed the Award on the premise that the repudiation is
justified, is bad, perverse and contrary to the agreement provisions.
32. The learned counsel for the CPWD/petitioner submits that Counter
Claim 3 has been erroneously rejected by the Learned Arbitrator on the
ground that compensation under Clause 2 is not payable to CPWD as the
balance work has not been executed. It is submitted that balance work
was not available due to reasons attributable to the respondent.
FINDINGS AND ANALYSIS
33. Heard learned counsel for the petitioner and perused the record. I
have also perused the impugned arbitral award as well as the entire
arbitral record brought on record. I have also given thoughtful
considerations to the submissions advanced by the parties.
34. The challenge to the impugned arbitral award inter alia has been
made on the ground that the learned Arbitrator has failed to consider
relevant evidence on record to award the claims made by the respondent.
35. Another ground which has been relied upon by the learned counsel
for the petitioner is that the learned Arbitrator‟s finding that the
repudiation is justified, is bad perverse and contrary to agreement
provisions.
O.M.P. (COMM) 96/2023 Page 8 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
36. The arbitral judgment stands at the centre of the current dispute and
is being contested on the grounds of patent illegality, perversity, and at
odds with India's fundamental policy before delving into the judicial
decisions, it is pertinent to reproduce the relevant portion of Section 34 of
the Act, 1996:-
"34. Application for setting aside arbitral award .—(1)
Recourse to a Court against an arbitral award may be made
only by an application for setting aside such award in
accordance with sub-section (2) and subsection (3).
(2) An arbitral award may be set aside by the Court only if—
(a) the party making the application [establishes on
the basis of the record of the arbitral tribunal that]—
(i) a party was under some incapacity; or
(ii) the arbitration agreement is not valid under
the law to which the parties have subjected it
or, failing any indication thereon, under the law
for the time being in force;or
(iii) the party making the application was not
given proper notice of the appointment of an
arbitrator or of the arbitral proceedings or was
otherwise unable to present his case; or
(iv) the arbitral award deals with a dispute not
contemplated by or not falling within the terms
of the submission to arbitration, or it contains
decisions on matters beyond the scope of the
submission to arbitration: Provided that, if the
decisions on matters submitted to arbitration
can be separated from those not so submitted,
only that part of the arbitral award which
contains decisions on matters not submitted to
arbitration may be set aside; or
O.M.P. (COMM) 96/2023 Page 9 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
(v) the composition of the arbitral tribunal or
the arbitral procedure was not in accordance
with the agreement of the parties, unless such
agreement was in conflict with a provision of
this Part from which the parties cannot
derogate, or, failing such agreement, was not in
accordance with this Part; or
(b) the Court finds that—
(i) the subject-matter of the dispute is not
capable of settlement by arbitration under the
law for the time being in force, or
(ii) the arbitral award is in conflict with the
public policy of India. [Explanation 1.—For
the avoidance of any doubt, it is clarified that
an award is in conflict with the public policy of
India, only if,— (i) the making of the award was
induced or affected by fraud or corruption or
was in violation of Section 75 or Section 81; or
(ii) it is in contravention with the fundamental
policy of Indian law; or
(iii) it is in conflict with the most basic notions
of morality or justice.
Explanation 2.—For the avoidance of doubt, the test as to
whether there is a contravention with the fundamental policy
of Indian law shall not entail a review on the merits of the
dispute.
(2-A) An arbitral award arising out of arbitrations other
than international commercial arbitrations, may also be set
aside by the court, if the court finds that the award is
vitiated by patent illegality appearing on the face of the
award: Provided that an award shall not be set aside merely
on the ground of an erroneous application of the law or by
reappreciation of evidence.]"
O.M.P. (COMM) 96/2023 Page 10 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
37. A bare reading of the Section 34 of the Act makes it abundantly
clear that in order to set aside an Arbitral Award, it should be found to be
patently illegal and contrary to the fundamental policy of Indian Law.
38. The law regarding patent illegality and public policy of India is no
more res integra and has been authoritatively clarified by the Hon‟ble
Supreme Court in a number of judicial pronouncements.
39. In Ssangyong Engineering & Construction Co. Ltd. (Supra) , the
Hon‟ble Supreme Court while explaining the scope of the expression
„public policy of India‟ made the following pertinent observations:
"23. What is clear, therefore, is that the expression ”public
policy of India”, whether contained in Section 34 or in
Section 48, would now mean the “fundamental policy of
Indian law” as explained in paragraphs 18 and 27 of
Associate Builders (supra), i.e., the fundamental policy of
Indian law would be relegated to the “Renusagar”
understanding of this expression. This would necessarily
mean that the Western Geco (supra) expansion has been
done away with. In short, Western Geco (supra), as
explained in paragraphs 28 and 29 of Associate Builders
(supra), would no longer obtain, as under the guise of
interfering with an award on the ground that the arbitrator
has not adopted a judicial approach, the Court„s
intervention would be on the merits of the award, which
cannot be permitted post amendment. However, insofar as
principles of natural justice are concerned, as contained in
Sections 18 and 34(2)(a)(iii) of the 1996 Act, these continue
to be grounds of challenge of an award, as is contained in
paragraph 30 of Associate Builders (supra).
xxxxxx
25. Thus, it is clear that public policy of India is now
constricted to mean firstly, that a domestic award is contrary
O.M.P. (COMM) 96/2023 Page 11 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
to the fundamental policy of Indian law, as understood in
paragraphs 18 and 27 of Associate Builders (supra), or
secondly, that such award is against basic notions of justice
or morality as understood in paragraphs 36 to 39 of
Associate Builders (supra). Explanation 2 to Section
34(2)(b)(ii) and Explanation 2 to Section 48(2)(b)(ii) was
added by the Amendment Act only so that Western Geco
(supra), as understood in Associate Builders (supra), and
paragraphs 28 and 29 in particular, is now done away with.
26. Insofar as domestic awards made in India are
concerned, an additional ground is now available under sub-
section (2A), added by the Amendment Act, 2015, to Section
34. Here, there must be patent illegality appearing on the
face of the award, which refers to such illegality as goes to
the root of the matter but which does not amount to mere
erroneous application of the law. In short, what is not
subsumed within “the fundamental policy of Indian law”,
namely, the contravention of a statute not linked to public
policy or public interest, cannot be brought in by the
backdoor when it comes to setting aside an award on the
ground of patent illegality.
27. Secondly, it is also made clear that re-appreciation of
evidence, which is what an appellate court is permitted to
do, cannot be permitted under the ground of patent illegality
appearing on the face of the award.
28. To elucidate, paragraph 42.1 of Associate Builders
(supra), namely, a mere contravention of the substantive law
of India, by itself, is no longer a ground available to set
aside an arbitral award. Paragraph 42.2 of Associate
Builders (supra), however, would remain, for if an arbitrator
gives no reasons for an award and contravenes Section
31(3) of the 1996 Act, that would certainly amount to a
patent illegality on the face of the award.
xxxxxx
30. What is important to note is that a decision which is
perverse, as understood in paragraphs 31 and 32 of
O.M.P. (COMM) 96/2023 Page 12 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
Associate Builders (supra), while no longer being a ground
for challenge under “public policy of India”, would
certainly amount to a patent illegality appearing on the face
of the award. Thus, a finding based on no evidence at all or
an award which ignores vital evidence in arriving at its
decision would be perverse and liable to be set aside on the
ground of patent illegality. Additionally, a finding based on
documents taken behind the back of the parties by the
arbitrator would also qualify as a decision based on no
evidence inasmuch as such decision is not based on evidence
led by the parties, and therefore, would also have to be
characterised as perverse."
40. In the case of Associate Builders vs. Delhi Development
Authority, (2015) 3 SCC 49, the Hon‟ble Supreme Court clarified the
meaning and scope of “Fundamental Policy of Indian Law” in the
context of Section 34 of the Arbitration Act in the following manner:
“28. In a recent judgment, ONGC Ltd. v. Western Geco
International Ltd., 2014 (9) SCC 263, this Court added
three other distinct and fundamental juristic principles
which must be understood as a part and parcel of the
fundamental policy of Indian law. The Court held-
35. What then would constitute the “fundamental
policy of Indian law” is the question. The decision in
ONGC [ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC
705] does not elaborate that aspect. Even so, the
expression must, in our opinion, include all such
fundamental principles as providing a basis for
administration of justice and enforcement of law in
this country. Without meaning to exhaustively
enumerate the purport of the expression “fundamental
policy of Indian law”, we may refer to three distinct
and fundamental juristic principles that must
necessarily be understood as a part and parcel of the
fundamental policy of Indian law. The first and
foremost is the principle that in every determination
whether by a court or other authority that affects the
O.M.P. (COMM) 96/2023 Page 13 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
rights of a citizen or leads to any civil consequences,
the court or authority concerned is bound to adopt
what is in legal parlance called a “judicial approach”
in the matter. The duty to adopt a judicial approach
arises from the very nature of the power exercised by
the court or the authority does not have to be
separately or additionally enjoined upon the for a
concerned. What must be remembered is that the
importance of a judicial approach in judicial and
quasi-judicial determination lies in the fact that so
long as the court, tribunal or the authority exercising
powers that affect the rights or obligations of the
parties before them shows fidelity to judicial
approach, they cannot act in an arbitrary, capricious
or whimsical manner. Judicial approach ensures that
the authority acts bona fide and deals with the subject
in a fair, reasonable and objective manner and that its
decision is not actuated by any extraneous
consideration. Judicial approach in that sense acts as
a check against flaws and faults that can render the
decision of a court, tribunal or authority vulnerable to
challenge.
xxxxxx
38. Equally important and indeed fundamental to the
policy of Indian law is the principle that a court and
so also a quasi judicial authority must, while
determining the rights and obligations of parties
before it, do so in accordance with the principles of
natural justice. Besides the celebrated audi alteram
partem rule one of the facets of the principles of
natural justice is that the court/authority deciding the
matter must apply its mind to the attendant facts and
circumstances while taking a view one way or the
other. Non-application of mind is a defect that is fatal
to any adjudication. Application of mind is best
demonstrated by disclosure of the mind and disclosure
of mind is best done by recording reasons in support
of the decision which the court or authority is taking.
O.M.P. (COMM) 96/2023 Page 14 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
The requirement that an adjudicatory authority must
apply its mind is, in that view, so deeply embedded in
our jurisprudence that it can be described as a
fundamental policy of Indian law.
39. No less important is the principle now recognised
as a salutary juristic fundamental in administrative
law that a decision which is perverse or so irrational
that no reasonable person would have arrived at the
same will not be sustained in a court of law.
Perversity or irrationality of decisions is tested on the
touchstone of Wednesbury principle of
reasonableness. Decisions that fall short of the
standards of reasonableness are open to challenge in
a court of law often in writ jurisdiction of the superior
courts but no less in statutory processes wherever the
same are available. 40. It is neither necessary nor
proper for us to attempt an exhaustive enumeration of
what would constitute the fundamental policy of
Indian law nor is it possible to place the expression in
the straitjacket of a definition. What is important in
the context of the case at hand is that if on facts
proved before them the arbitrators fail to draw an
inference which ought to have been drawn or if they
have drawn an inference which is on the face of it,
untenable resulting in miscarriage of justice, the
adjudication even when made by an Arbitral Tribunal
that enjoys considerable latitude and play at the joints
in making awards will be open to challenge and may
be cast away or modified depending upon whether the
offending part is or is not severable from the rest.”
xxxxxx
31. The third juristic principle is that a decision which is
perverse or so irrational that no reasonable person would
have arrived at the same is important and requires some
degree of explanation. It is settled law that where:
1. a finding is based on no evidence, or
2. an arbitral tribunal takes into account something
irrelevant to the decision which it arrives at; or
O.M.P. (COMM) 96/2023 Page 15 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
3. ignores vital evidence in arriving at its decision,
such decision would necessarily be perverse.
xxxxxx
33. It must clearly be understood that when a court is
applying the “public policy” test to an arbitration award, it
does not act as a court of appeal and consequently errors of
fact cannot be corrected. A possible view by the arbitrator
on facts has necessarily to pass muster as the arbitrator is
the ultimate master of the quantity and quality of evidence to
be relied upon when he delivers his arbitral award. Thus an
award based on little evidence or on evidence which does
not measure up in quality to a trained legal mind would not
be held to be invalid on this score . Once it is found that the
arbitrators approach is not arbitrary or capricious, then he
is the last word on facts......”
41. It is, therefore clear, that the decisive test is that first , the learned
arbitrator had to adopt a judicial approach; second , the principles of
natural justice had to be upheld; third, the decision must not have been
egregious, or rather, perverse.
42. In R vs. Northumberland Compensation Appeal Tribunal. Ex
Parte Shaw, 1952 1 All ER 122 , Lord Denning made the following
pertinent observations:
"Leaving now the statutory tribunals, I turn to the awards of
the arbitrators. The Court of King's Bench never interfered
by certiorari with the award of an arbitrator, because it was
a private tribunal and not subject to the prerogative writs. If
the award was not made a rule of court, the only course
available to an aggrieved party was to resist an action on
the award or to file a bill in equity. If the award was made a
rule of court, a motion could be made to the court to set it
aside for misconduct of the arbitrator on the ground that it
was procured by corruption or other undue means: see the
statute 9 and 10 Will. III, c. 15. At one time an award could
O.M.P. (COMM) 96/2023 Page 16 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
not be upset on the ground of error of law by the arbitrator
because that could not be said to be misconduct or undue
means, but ultimately it was held in Kent v. Elstob, (1802) 3
East 18, that an award could be set aside for error of law on
the face of it. This was regretted by Williams, J., in
Hodgkinson v. Fernie, (1857) 3 C.B.N.S. 189, but is now
well established.”
43. The Privy Council in Champsey Bhara Company vs. The Jivraj
Balloo Spinning and Weaving Company Ltd., AIR 1923 PC 66 , held as
follows:
“The law on the subject has never been more clearly stated
than by Williams, J. in the case of Hodgkinson v. Fernie
(1857) 3 C.B.N.S. 189 :-
“The law has for many years been settled, and
remains so at this day, that, where a cause or matters
in difference are referred to an arbitrator a lawyer or
a layman, he is constituted the sole and final judge of
all questions both of law and of fact …… The only
exceptions to that rule are cases where the award is
the result of corruption or fraud, and one other, which
though it is to be regretted, is now, I think firmly
established viz., where the question of law necessarily
arises on the face of the award or upon some paper
accompanying and forming part of the award. Though
the propriety of this latter may very well be doubted, I
think it may be considered as established.”
xxxxxx
Now the regret expressed by Williams, J. in Hodgkinson v.
Fernie has been repeated by more than one learned Judge,
and it is certainly not to be desired that the exception should
be in any way extended. An error in law on the face of the
award means, in their Lordships„ view, that you can find in
the award or a document actually incorporated thereto, as
for instance, a note appended by the arbitrator stating the
O.M.P. (COMM) 96/2023 Page 17 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
reasons for his judgment, some legal proposition which is
the basis of the award and which you can then say is
erroneous. It does not mean that if in a narrative a reference
is made to a contention of one party that opens the door to
seeing first what that contention is, and then going to the
contract on which the parties„ rights depend to see if that
contention is sound. Here it is impossible to say, from what
is shown on the face of the award, what mistake the
arbitrators made. The only way that the learned judges have
arrived at finding what the mistake was is by saying:
“Inasmuch as the Arbitrators awarded so and so, and
inasmuch as the letter shows that then buyer rejected the
cotton, the arbitrators can only have arrived at that result by
totally misinterpreting Cl.52.” But they were entitled to give
their own interpretation to Cl. 52 or any other article, and
the award will stand unless, on the face of it they have tied
themselves down to some special legal proposition which
then, when examined, appears to be unsound. Upon this
point, therefore, their Lordships think that the judgment of
Pratt, J was right and the conclusion of the learned Judges
of the Court of Appeal erroneous.”
44. The Hon‟ble Supreme Court in Associate Builders (supra) , while
explaining the meaning and scope of patent illegality, held as follows:
“42. In the 1996 Act, this principle is substituted by the
“patent illegality” principle which, in turn, contains three
subheads
42.1 (a) A contravention of the substantive law of
India would result in the death knell of an arbitral
award. This must be understood in the sense that such
illegality must go to the root of the matter and cannot
be of a trivial nature. This again is a really a
contravention of Section 28(1)(a) of the Act, which
reads as under:
“28. Rules applicable to substance of dispute.—
(1) Where the place of arbitration is situated in
O.M.P. (COMM) 96/2023 Page 18 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
India,— (a) in an arbitration other than an
international commercial arbitration, the
arbitral tribunal shall decide the dispute
submitted to arbitration in accordance with the
substantive law for the time being in force in
India;”
42.2 (b) a contravention of the Arbitration Act itself
would be regarded as a patent illegality- for example
if an arbitrator gives no reasons for an award in
contravention of section 31(3) of the Act, such award
will be liable to be set aside.
42.3 (c) Equally, the third sub-head of patent illegality
is really a contravention of Section 28 (3) of the
Arbitration Act, which reads as under:
“28. Rules applicable to substance of dispute.—
(3) In all cases, the arbitral tribunal shall
decide in accordance with the terms of the
contract and shall take into account the usages
of the trade applicable to the transaction.”
This last contravention must be understood with a
caveat. An arbitral tribunal must decide in
accordance with the terms of the contract, but if an
arbitrator construes a term of the contract in a
reasonable manner, it will not mean that the award
can be set aside on this ground. Construction of the
terms of a contract is primarily for an arbitrator to
decide unless the arbitrator construes the contract in
such a way that it could be said to be something that
no fair minded or reasonable person could do.
45. A relevant portion of the Impugned Arbitral Award has been
reproduced below, to apply the test as to whether the Learned Arbitrator
had indeed wrongly appreciated, or ignored relevant evidence.
“CLAIM N0.5:
O.M.P. (COMM) 96/2023 Page 19 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
CONTRACTOR CLAIMS ON ACCOUNT OF COST OF
TOOLS & PLANTS, MACHINERY, SCAFFOLDING,
CENTERING AND SHUTTERING MATERIAL ETC.
WRONGLY, ILLEGALLY AND UNILATERALLY
RECOVERED MOBILISATION ADVANCE BEFORE
80% WORKDONE IN 7TH RA BILL AND
CONFISCATED BY RESPONDENT.
Under this claim, the Claimant I Contractor had sought the
value of the Tools, Plant and Machinery that was brought on
to the site by the Claimant itself and for which the advances
were also given by the Respondent Department.
It is submitted on behalf of the Claimant that despite
recovering the advances vide various EA Bills, the said tools,
plant and machinery were illegally retained at the site by the
Respondent Department.
In support of the above contention, the Claimant has placed
reliance upon the 2nd RA Bill to show that the Respondent
Department had issued advance for various tools, plant and
machinery tools, plant and machinery advance after
assessing in date market value of the same. However, the
Department had recovered the said advances through
various RA Bills and had also illegally confiscated the said
tools, plant and machinery.
It is further contended on behalf of the Claimant that after
repudiation of the contract by the Claimant, the said tools,
plant and machinery were not allowed to be removed from
the site by the Respondent Department. It is submitted further
that for taking the same out of the possession /site of the
Department, a gate pass was required from Engineer in
Charge or from the office of the University itself.
The Claimant further contends that admittedly the entire
campus and the project site was guarded by the security
guards who were deployed by the University/Respondent
Department. No material or tool, plant or machinery was
O.M.P. (COMM) 96/2023 Page 20 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
allowed to be taken out of the campus without the issuance of
appropriate gate-pass for the same.
The Claimant also contends that even today it can be verified
from a simple visit to the project site, that guards don't allow
anything out of the site without the issuance of a proper gate-
pass for the same.
Per contra, the Respondent Department has negated the
version of the Claimant and has argued that tools, plant and
machinery advance was given under hypothecation deed
signed between the Claimant and the Respondent. The tools,
plant and machinery brought under these advances belong to
the Claimant only. As per the terms of the agreement, the
watch and ward of the entire tools, plant and machinery and
material was to be of the Claimant itself.
It has further been contended on behalf of the Respondent
Department that there is no requirement for issuance of any
gate pass for the Claimant to remove and tools, plant and
machinery from the site and therefore the Respondent
Department is not responsible for the reimbursement if any
such loss.
Decision of Tribunal:
It is seen from the record that the tools, plant and machinery
were to remain under custody of Claimant, as is also
recorded in the hypothecation deed execution against tools,
plant and machinery advance. Security of all tools, plants
and machinery is the responsibility of the Claimants.
Claimants could ·not prove that any point of time tools, plant
and machinery was handed over to Respondents. If
Respondents have taken any illegal and unlawful action to
remove the machines under custody of Claimants without
their permission, immediate action under law should have
been taken by them. There is no record of any action taken
against Respondents. Therefore, Respondents are not
responsible for any missing tools, plants and machinery.
O.M.P. (COMM) 96/2023 Page 21 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
Accordingly, I award the Claimant an amount of Rs. NIL
against Claim No.5 .
CLAIM N0.6:
CONTRACTOR CLAIMS ON ACCOUNT OF BANK
CHARGES, INSURANCE CHARGES, TESTING
CHARGES & OTHER CHARGES IN VARIOUS SUB
HEADS PAID BY US ALONG WITH 12% INTEREST
PER ANNUM ON ALL OUR PAYMENTS DUE FROM
THE DATE OF PAYMENT DUE TO TILL DATE OF
PAYMENT DUE TO PROLONGATION OF CONTRACT
UNILATERALLY BY THE RESPONDENT, NON-
AVAILABILITY OF FUNDS WITH THE RESONDENT,
BREACH OF CONTRACT ON THE PART OF
RESPONDENT, HINDRANCE ON THE PART OF
RESPONDENT.
Claim No. 6 of the claimant is divided in two parts. First,
Part 1 deals with the charges incurred on maintaining the
bank guarantees for amount in excess of the actual work
executed at the site. In this regard, the claimant has stated
that the work of tendered amount could not be executed at the
site since the respondent department created an atmosphere
which left the claimant with no other option but to repudiate
the contract. It is the case of the claimant that the claimant
had submitted the bank guarantees with respect to the total
tender amount. However, on account of default on part of the
department, the claimant was prevented from executing the
work of the complete amount. As such, the claimant claims
that the claimant ought not to have been burdened for
maintaining bank guarantee in respect of complete tender
amount. Accordingly, the claimant seeks payment of bank
charges incurred towards the excess value of bank guarantee
that were being maintained by the claimant in terms of
calculations filed as 6.1 in ANNEXURE C-66.
O.M.P. (COMM) 96/2023 Page 22 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
In response to the aforesaid, the Respondent has contended
that it was the default on part of the claimant as a result' of
which the claimant did not execute the complete work under
the agreement. The balance work was very much required by
the department; however, the Claimant abandoned the work
thereby causing loss to the department. Thus, it has been
claimed that there is no question of the Respondents
reimbursing any such bank charges.
Decision of Tribunal:
After going through above arguments tribunal is of the view
that Claimants have submitted Bank Guarantees at the time
of start of work as per tendered value. In claim no 2 it is seen
that Claimants have executed work around tendered value.
After expiry of initial bank guarantee, Claimants never got
them renewed. Due to breaches on the part of Respondents,
Claimants themselves decided to repudiate the agreement of
their own sweet will. So, in entire process Claimants have not
incurred any extra amount on bank guarantees. Therefore,
contention of Claimants in this regard is not acceptable.
Further the second part of this claim pertains to reimburse
the charges incurred in testing of materials by the claimant.
The claimant contends that the testing of materials was the
duty of the department, and the claimant was only meant to
provide the sample for testing. However, on several
occasions, the claimant has claimed that although the testing
charges were paid by the claimant, amounting to Rs. 48,756/-
, the department only reimbursed only Rs. 29.500/- and thus
the claimant has sought reimbursement of the balance
amount. On the contrary, the department has sought to rely
upon additional conditions, point number 52.7, which makes
it clear that the cost for testing with respect to steel was to be
borne by the contractor and has thus contended that it is only
the testing charges with respect to material of steel, that was
not paid by the department and rest amount has already been
paid to the claimant.
O.M.P. (COMM) 96/2023 Page 23 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
That the tribunal finds force in the above contentions of the
respondent that the contractor is not entitled for
reimbursement for testing charges with respect to steel.
However, it is an admitted fact by the department that for
other materials, reimbursement needs to be done to the
contractor. A perusal of the present claim shows that the
claimant has failed to provide the necessary details for
bifurcation with respect to the testing charges claimed
herein. Accordingly, this tribunal is of the opinion that in
case the claimant is not able to provide the necessary proof
regarding non-payment of any testing charges incurred for
materials other than steel, nothing is payable to them. No
proof provided by Claimants, so nothing is payable to them
in this regard.
The above claim is decided accordingly.
Therefore, I award the Claimant an amount of Rs. NIL
against Claim No. 6."
46. A clear reading of the precedents cited proves that under the
limited scope of Section 34, the present case does not warrant the
interference of this Court, as the grounds stated by the Petitioner in the
instant petition do not meet the scope of this section. The petitioner
claimed that the learned Arbitrator failed to consider the Agreement but a
careful reading of the Award proves that the Arbitrator has rightly relied
on relevant evidence and the Agreement to adjudicate.
47. A relevant portion of the Impugned Arbitral Award has been
reproduced below, to adjudicate whether the learned Arbitrator has
accurately considered the provisions in the Agreement.
CLAIM N0.7:
WE CLAIM 7.5% OVERHEAD ON ACCOUNT OF T&P,
STAFF, ESTABLISHMENT, HEAD OFFICE EXPENSES
O.M.P. (COMM) 96/2023 Page 24 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
SHUTTERING MATERIAL LYING IDLE AT SITE IN
EXTENDED PEROID AS WELL AS UNDERUTILISED
WITHIN STIPULATED DATE OF COMPLETION DUE TO
PROLONGATION OF CONTRACT UNILATERALLY BY THE
RESPONDENT, ON-AVAILABILITY OF FUNDS WITH THE
RESONDENT, BREACH OF CONTRACT ON THE PART OF
RESPONDENT, HINDRANCE ON THE PART OF
RESPONDENT.
The said claim pertains to the loss incurred by the claimant
on account of overheads like T&P, staff, establishment, etc.
incurred during the extended period of the contract on
account of delays on part of the department. It is the
contentions of the claimant that the claimant was to execute
agreement · work of Rs. 2, 84, 97,777/- within a period of
180 days. As per the calculations submitted by the claimant,
per day work executed was to the tune of Rs.t, 58,320/-
wherein the accepted cost of overheads per day, as per
Schedule-F @ 7.5% came out to be Rs.11,874.07/-.
The claimant contends that at the time of entering into the
agreement with the department, the tender amount was
determined by the claimant keeping in view the stipulated
period and overhead costs. However, once the contract got
extended, for reasons not attributable to the claimant, the
overhead costs of the claimant ought to be reimbursed by the
department. Accordingly, the claimant has stated that due to
various breaches and defaults solely attributable to the
respondent, the claimant had to repudiate the work vide its
notice dated 18.01.2019. The said notice was kept in
abeyance in view of the decisions taken in the meeting dated
12.02.2019. On the specific assurance that the department
th
shall process the 7 RA Bill and make the payment against
th
the same. It is a matter of record that the 7 RA Bill was not
processed in a timely manner and was only finalized
unilaterally by the department on 22.10.2019 that too for Rs.
1/-, which was also not paid to the claimant till further 5-6
months. Aggrieved by the aforesaid breaches, the claimant
O.M.P. (COMM) 96/2023 Page 25 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
removed all its labour, machinery etc., from the site w.e.f.
16.11.2019. Since this extended period i.e., from 08.12.2018
till 16.11.2019 was not to be accounted for in the overhead
costs of the claimant, the claimant has thus sought payment
on account of the overhead costs for this period of 343 days
which comes to Rs. 40,72,807/-. The respondent has
contended that the claimant had abandoned the work after
issuance of its repudiation notice dated 18.01.2019 and
thereafter no work was executed by the claimant at the
project site.
It is further contended that the claimant had in fact not
deputed any staff or maintained any establishment or TNP at
the site after its repudiation notice issued on 18.01.2019 and
thus the claimant has neither incurred any overhead loss nor
is it entitled for any such overhead costs during the alleged
extended period.
Decision of Tribunal:
The tribunal, after going through above facts, is of the view
that Claimants have given a legal notice of repudiation on
18.01.19 after coming to conclusion that work cannot
proceed further due to breaches by Respondents. There was
no point in maintaining over heads after issue of notice.
Various developments after considered decision of issue of
notice. by Claimants have no effect on withdrawal of
overheads. During arguments Claimants have accepted
repudiation date as 18. 01. 19. Therefore, it can be safely
presumed that the overheads were being maintained by the
claimant during the extended period from 09. 12.18 to 18.0
1. 19 i.e. 41 days.
It is clear from various submissions by Claimants that work
has slowed down due to breaches on part of Respondents.
So, it was the duty of Claimants to mitigate losses due to
overheads. End of justice will be met if 4% overheads are
allowed during extended period. Calculation is as below:
28497777 X .04 X 41 /183 = Rs. 255390/-
O.M.P. (COMM) 96/2023 Page 26 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
Therefore, I award the Claimant an amount of Rs. 2,
55,390/- against Claim No. 7.
48. Reiterating as previously observed, “patent illegality” is an
illegality that goes to the root of the matter but excludes the erroneous
application of the law by an arbitral tribunal or re-appreciation of
evidence by an appellate court. In this instant case, the Arbitral Award
was a well-reasoned award, with the findings being clearly arrived at
based on all the documents/evidence on record.
49. Further in Ssangyong Engineering & Construction Co. Ltd.
(Supra), the Hon‟ble Supreme Court went on to say that reappreciation of
evidence cannot be permitted under the ground of patent illegality in a
Section 34 petition under Act, 1996. The relevant portion has been
reiterated below:-
38. “Secondly, it is also made clear that reappreciation of
evidence, which is what an appellate court is permitted to
do, cannot be permitted under the ground of patent illegality
on the face of award.”
50. This is so because the decision of the Arbitral Tribunal is final and
this Court is not required to carry out an exercise of re-adjudicating the
disputes. An arbitral award may be impeached on the ground of patent
illegality but as explained by the Hon‟ble Supreme Court in Delhi
Airport Metro Express Pvt Ltd vs. Delhi Metro Rail Corporation (2022)
1 SCC 131 :-
"28. The limited grounds available to Courts for annulment
of arbitral awards are well known to legally trained minds.
O.M.P. (COMM) 96/2023 Page 27 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
However, the difficulty arises in applying the well-
established principles for interference to the facts of each
case that come up before the courts. There is a disturbing
tendency of Courts of setting aside arbitral awards, after
dissecting and reassessing factual aspects of the cases to
come to a conclusion that the award needs intervention and
thereafter, dubbing the award to be vitiated by either
perversity or patent illegality, apart from the other grounds
available for annulment of the award.
29. Patent illegality should be illegality which goes to the
root of the matter. In other words, every error of law
committed by the Arbitral Tribunal would not fall within the
expression “patent illegality”. Likewise, erroneous
application of law cannot be categorised as patent illegality.
In addition, contravention of law not linked to public policy
or public interest is beyond the scope of the expression
“patent illegality”. What is prohibited is for Courts to
reappreciate evidence to conclude that the award suffers
from patent illegality appearing on the face of the award, as
Courts do not sit in appeal against the arbitral award. The
permissible grounds for interference with a domestic award
under Section 34(2-A) on the ground of patent illegality is
when the arbitrator takes a view which is not even a possible
one, or interprets a clause in the contract in such a manner
which no fair-minded or reasonable person would, or if the
arbitrator commits an error of jurisdiction by wandering
outside the contract and dealing with matters not allotted to
them. An arbitral award stating no reasons for its findings
would make itself susceptible to challenge on this account.
The conclusions of the arbitrator which are based on no
evidence or have been arrived at by ignoring vital evidence
are perverse and can be set aside on the ground of patent
illegality. Also, consideration of documents which are not
supplied to the other party is a facet of perversity falling
within the expression “patent illegality”."
O.M.P. (COMM) 96/2023 Page 28 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
51. This was earlier enunciated in State of Jharkhand v. HSS
Integrated SDN , (2019) 9 SCC 798 . The relevant paragraph of the
judgment is reiterated below:
"6.2. This Court has observed and held that the Arbitral
Tribunal is the master of evidence and the findings of fact
which are arrived at by the arbitrators on the basis of the
evidence on record are not to be scrutinised as if the Court
was sitting in appeal."
52. The Petitioner had raised a ground that the learned Arbitrator‟s
interpretation of the Agreement was wrongful. The petitioner claims that
the learned Arbitrator in complete derogation of the contemporaneous
conduct of the parties to the Contract has arrived at perverse findings.
The Court relies on Foo Jong Peng and others v Phua Kiah Mai and
another [2012] 4 SLR 1267, where the Hon‟ble Supreme Court of
Singapore delved into the interpretation of contracts by the Learned
Arbitrator during the Arbitral process. The relevant portion of the
judgment is reiterated below:-
"36. In summary, although the process of the implication of
terms does involve the concept of interpretation, it entails
a specific form or conception of interpretation which
is separate and distinct from the more general process of
interpretation (in particular, interpretation of
the express terms of a particular document). Indeed, the
process of the implication of terms necessarily involves a
situation where it is precisely because the express term(s)
are missing that the court is compelled to ascertain the
presumed intention of the parties via the “business efficacy”
and the “officious bystander” tests (both of which are
premised on the concept of necessity). In this context, terms
will not be implied easily or lightly. Neither does the court
O.M.P. (COMM) 96/2023 Page 29 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
imply terms based on its idea of what it thinks ought to be
the contractual relationship between the contracting parties.
The court is concerned only with the presumed intention of
the contracting parties because it can ascertain
the subjective intention of the contracting
parties only through the objective evidence which is
available before it in the case concerned. In our view,
therefore, although the Belize test is helpful in reminding us
of the importance of the general concept of interpretation
(and its accompanying emphasis on the need for objective
evidence), we would respectfully reject that test in so far as
it suggests that the traditional “business efficacy” and
“officious bystander” tests are not central to the implication
of terms. On the contrary, both these tests (premised as they
are on the concept of necessity) are an integral as well as
indispensable part of the law relating to implied terms in
Singapore."
53. Further, in the case of Ssangyong Engineering & Construction
Co. Ltd. (Supra) , the Hon‟ble Supreme Court made the following
pertinent observations:
"40. The change made in Section 28(3) by the Amendment
Act really follows what is stated in paras 42.3 to 45 in
Associate Builders, namely, that the construction of the
terms of a contract is primarily for an arbitrator to decide,
unless the arbitrator construes the contract in a manner that
no fair-minded or reasonable person would; in short, that
the arbitrator's view is not even a possible view to take. Also,
if the arbitrator wanders outside the contract and deals with
matters not allotted to him, he commits an error of
jurisdiction. This ground of challenge will now fall within
the new ground added under Section 34(2-A).
xxxxxx
76. However, when it comes to the public policy of India,
argument based upon “most basic notions of justice”, it is
clear that this ground can be attracted only in very
O.M.P. (COMM) 96/2023 Page 30 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
exceptional circumstances when the conscience of the Court
is shocked by infraction of fundamental notions or principles
of justice. It can be seen that the formula that was applied by
the agreement continued to be applied till February 2013 —
in short, it is not correct to say that the formula under the
agreement could not be applied in view of the Ministry's
change in the base indices from 1993-1994 to 2004-2005.
Further, in order to apply a linking factor, a Circular,
unilaterally issued by one party, cannot possibly bind the
other party to the agreement without that other party's
consent. Indeed, the Circular itself expressly stipulates that
it cannot apply unless the contractors furnish an
undertaking/affidavit that the price adjustment under the
Circular is acceptable to them. We have seen how the
appellant gave such undertaking only conditionally and
without prejudice to its argument that the Circular does not
and cannot apply. This being the case, it is clear that the
majority award has created a new contract for the parties by
applying the said unilateral Circular and by substituting a
workable formula under the agreement by another formula
dehors the agreement. This being the case, a fundamental
principle of justice has been breached, namely, that a
unilateral addition or alteration of a contract can never be
foisted upon an unwilling party, nor can a party to the
agreement be liable to perform a bargain not entered into
with the other party. Clearly, such a course of conduct
would be contrary to fundamental principles of justice as
followed in this country, and shocks the conscience of this
Court. However, we repeat that this ground is available only
in very exceptional circumstances, such as the fact situation
in the present case. Under no circumstance can any court
interfere with an arbitral award on the ground that justice
has not been done in the opinion of the Court. That would be
an entry into the merits of the dispute which, as we have
seen, is contrary to the ethos of Section 34 of the 1996 Act,
as has been noted earlier in this judgment.”
O.M.P. (COMM) 96/2023 Page 31 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
54. The principle is that if arbitrators use the contract itself to
determine a dispute, clauses should, in principle, be construed contra
proferentem , meaning that they should be interpreted against the party
that drafted it.
55. The rule of contra proferentem can be regarded as a „general
canon‟ of interpretation that exists independently of national legal
systems. In ICC Case No. 7110 , (1999) 10 ICC Bulletin 39, 44 , the
Arbitral Tribunal made it clear that it is a „general principle of
interpretation‟ widely accepted by national legal systems and by the
practice of International Arbitral Tribunals, including ICC Arbitral
Tribunals, that in case of doubt or ambiguity, contractual provisions,
terms or clauses should be interpreted against the drafting party.
56. In the instant case, the petitioner had drafted the Agreements in
which the respondent was a signatory. The Learned Arbitrator having
observed various interpretations of the contract, chose to endorse the
interpretation that is favorable to the respondent. The application of the
rule of contra proferentem validates the learned Arbitrator‟s findings and
observations regarding the interpretation of the contract so as to decide
the question of breach of the contract.
57. It is, thus, clear that a reading of the Impugned Arbitral Award
proves that where a multiplicity of views regarding the interpretation of
the Contract exists, the Learned Arbitrator chose one view that falls
within the principles of jurisprudence and gave ample reasoning for the
same.
O.M.P. (COMM) 96/2023 Page 32 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
58. Therefore, as discussed in the foregoing paragraphs, in the present
petition, the Learned Arbitrator had clearly referred to the evidence on
record, as reproduced above, and made his observations within the ambit
of the contract.
CONCLUSION
59. In light of the facts, submissions and contentions in the pleadings,
this Court finds that the Petitioner has failed to corroborate with evidence
how the Learned Arbitrator‟s findings are contrary to the Public Policy of
India. Even if the submissions of the Petitioner qua patent illegality in the
Impugned Arbitral Award is accepted, then also no ground has been made
out to set aside the Award inasmuch as the threshold to interfere and set
aside an Arbitral Award has not been met.
60. It is settled law that the ground of patent illegality gives way to
setting aside an Arbitral Award with a very minimal scope of
intervention. A party cannot simply raise an objection on the ground of
patent illegality if the Award is simply against them. Patent illegality
requires a distinct transgression of law, the clear lack of which thereof
makes the petition simply a pointless effort of objection towards an
Award made by a competent Arbitral Tribunal.
61. The Court is unable to subscribe to the submissions made by the
learned counsel for the Petitioner. The Petitioner has failed to show that
the arbitral award has been passed by the Learned Arbitrator without
considering the evidence on record. Further, the petitioner has not been
able to prove that the impugned Arbitral Award is patently illegal, and
O.M.P. (COMM) 96/2023 Page 33 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25
NEUTRAL CITATION NO. 2023/DHC/001847
contrary to the fundamental policy of Indian Law, and hence, is liable to
be set aside.
62. The Court is of the view that on the application of the rule of
contra proferentem , the Agreements were fittingly interpreted by the
Learned Arbitrator, leaving no scope for the interference of this Court on
the Award.
63. In view of the above discussion of facts and law, this Court finds
that the petitioner has failed to establish a prima facie case for setting
aside the Impugned Arbitral Award and has failed to make out a case
warranting interference from this Court.
64. The petition is, accordingly, dismissed.
65. Pending applications, if any, also stand dismissed.
66. The order be uploaded on the website forthwith.
CHANDRA DHARI SINGH, J
MARCH 3, 2023
gs/as
Click here to check corrigendum, if any
O.M.P. (COMM) 96/2023 Page 34 of 34
Signature Not Verified
Digitally Signed
By:DAMINI YADAV
Signing Date:14.03.2023
18:24:25