Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 15
PETITIONER:
EXECUTIVE ENGINEER IRRIGATION GALIMALA & ORS. A
Vs.
RESPONDENT:
ABAADUTA JENA
DATE OF JUDGMENT22/09/1987
BENCH:
REDDY, O. CHINNAPPA (J)
BENCH:
REDDY, O. CHINNAPPA (J)
KANIA, M.H.
SHETTY, K.J. (J)
CITATION:
1988 AIR 1520 1988 SCR (1) 253
1988 SCC (1) 418 JT 1987 (4) 8
1987 SCALE (2)675
CITATOR INFO :
F 1988 SC1530 (4)
F 1988 SC1791 (13)
RF 1989 SC 777 (16)
R 1989 SC 973 (12,14)
F 1989 SC1987 (2)
F 1989 SC2125 (4)
D 1989 SC2257 (3,8)
R 1990 SC 685 (11,12)
RF 1990 SC 864 (5)
R 1990 SC1340 (13 TO 17)
O 1992 SC 732 (2,9,10,11,22,33,43,46,47)
RF 1992 SC2090 (2)
ACT:
Arbitration Act, 1940: Sections 14, 15, 30 and 33-
Arbitrator-Competency of-To award interest on reference made
without intervention of Court-Court whether entitled to go
behind the award and decide whether award of interest
justifiable. C
InterestAct 1839/lnterestAct 1978.
Civil Procedure Code 1908, Section 34. Award of
pendente lite interest by arbitrator. D
HEADNOTE:
In the appeals by Special Leave to this Court the
question for consideration was: whether an arbitrator to
whom a reference was made without the intervention of the
Court could award interest during the period prior to the
reference and during the pendency of the arbitration:
^
HELD: 1. The general statutory provisions in regard to
the award of interest by the Court are contained in the
Interest Act and the Civil Procedure Code. [258F]
2. The Interest Act of 1839 was repealed and a new
Interest Act incorporated in 1978. Both these Acts provide
for the award of interest upto the date of the institution
of the proceedings. Neither the Interest Act of 1839 nor the
Interest Act of 1978 provides for the award of pendente lite
interest. [260D]
3. The award of pendente lite interest is provided for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 15
in Section 34 of the Civil Procedure Code. Section 34
however, applies to arbitrations in suits for the simple
reason that where a matter is referred to arbitration in a
suit, the arbitrator will have all the powers of the Court
in deciding the dispute. Section 34 does not otherwise apply
to arbitrations as arbitrators are not courts within the
meaning of s. 34 Civil Procedure Code. [260E]
254
4. While under the Interest Act of 1978 the expression
’court’ was defined to exclude an arbitrator, under the
Interest Act of 1839 it was not so defined. The result is
that while in cases arising after the commencement of the
Interest Act of 1978 an arbitrator has the same power to
award interest upto the date of institution of proceedings,
in cases which arose prior to commencement of the 1978 Act
the arbitrator has no such power under the Interest Act of
1839. [260G]
5. Since the arbitrator is required to conduct himself
and make the award in accordance with law, the substantive
law has to be looked into for the power of the arbitrator to
award interest before the commencement of the proceedings.
[260H-261A]
6. If the agreement between the parties entitles the
arbitrator to award interest no further question arises and
the arbitrator may award interest. Similarly, if there is a
usage of trade having the force of law the arbitrator must
award interest. [261B]
7. Again, there are other provisions of the substantive
law enabling the award of interest by the arbitrator.
Section 80 of the Negotiable Instruments Act under which the
court may award interest even in a case where no rate of
interest is specified in the promissory note or bill of
exchange, and Section 61(2) of the Sale of Goods Act which
provides for the award of interest to the seller or the
buyer under certain circumstances in suits filed by them.
[261C]
8. There is also the instance of non-performance of a
contract of which equity could give specific performance and
to award interest. [261C]
9. Where one of the parties is forced to pay interest
to a third party say on an overdraft, consequent on the
failure of the other party to the contract not fulfilling
the obligation of paying the amount due to them, equity may
compel the payment of interest. [261C]
10. Loss of interest in the place of the right to
remain in possession may be rightfully claimed in equity by
the owner of a property who has been dispossessed from it.
[261D]
11. In the instant appeals, in those cases in which the
references to arbitration were made prior to the
commencement of the new Act which was on August 19, 1981 and
the amount claimed was a certain sum payable at a certain
time by virtue of a written instrument, interest is payable
under the Interest Act for the period before the
commencement of the proceeding. [269H-270A]
255
12. In regard to pendente lite interest, that is,
interest from the date of reference to the date of the
award, the claimants would not be entitled to the same for
the simple reason that the arbitrator is not a court within
the meaning of s. 34 of the CPC, nor were the references to
arbitration made in the course of suits.[1270C]
13. In the remaining cases which arose before the
commencement of the Interest Act, 1978, the respondents are
not entitled to claim interest either before the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 15
commencement of the proceedings or during the pendency of
the arbitration. They are not entitled to claim interest for
the period prior to the commencement of the arbitration
proceedings for the reason that the Interest Act, 1839 does
not apply to their cases and there is no agreement to pay
interest or any usage of trade having the force of law or
any other provision of law under which the claimants were
entitled to recover interest. They are not entitled to claim
pendente lite interest as the arbitrator is not a court nor
were the references to arbitration made in suits. [270D-E]
14. The arbitrator is bound to make his award in
accordance with law. If the arbitrator could not possibly
have awarded interest on any permissible ground because such
ground did not exist, it would be open to the court to set
aside the award relating to the award of interest on the
ground of an error apparition the record. On the other hand,
if there was the slightest possibility of the entitlement of
the claimant to interest on one or other of the legally
permissible grounds, it may not be open to the court to go
behind the award and decide whether the award of interest
was justifiable. [270F-G]
Bengal Nagpur Railway Company Limited v. Ruttanji Ramji
6S Indian Appeals 66; Thawardas Pherumal v. The Union of
India, [1955] 2 SCR 48; Union of India v. Prem Chand Satnam
Das, AIR 1951 Patna 20l; Nachiappa Chettiar v. Subramaniam
Chettiar, [1960] 2 SCR 209; Satinder Singh v. Amrao Singh,
[1961] 3 SCR 676; Firm Madanlal Roshanlal Mahajan v.
Hukumchand Mills Ltd., [1967] 1 SCR lO5; Union of India v.
Bungo Steel Furniture Pvt. Ltd., [1967] 1 SCR 324 and State
of Madhya Pradesh v. M/s. Saith & Skelton Pvt. Ltd., [1972]
3 SCR 233, referred to.
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 6245-46
of 1983.
From the Judgment and order dated 9.1.1981 of the
orissa High
256
Court in Miscellaneous Appeal Nos. 285 and 286 of 1980.
G.L. Sanghi, D.P. Mohanty, R.K. Mehta, Inderjit Roy,
P.N. Misra and R.N. Poddar for the Petitioners.
Probir Patil, Y.S. Chitale, Sankar Ghosh, Jitender
Sharma, Vinoo Bhagat, Arun Madan, P.N. Misra, D.N.
Mukherjee, M.M. Kashtriya P.K. Banerjee, P.K. Mukherjee, Ms.
Lily Thomes, Bagga Mrs. S.K. Bagga, B.P. Meheshwari, J.R.
Das, Parijat Sinha, and M.A. Firoz for the Respondents. .
The Judgment of the Court was delivered by
CHINNAPPA REDDY, J. This group of appeals raises the
question of award of interest by an arbitrator to whom a
reference is made without the intervention of the court.
Special leave to appeal was granted under Art. 136 of the
Constitution limited to the question of award of interest
during the period prior to the reference and during 1:) the
pendency of the arbitration proceedings. Special leave was
not granted in regard to the award of interest subsequent to
the date of the arbitrator’s award. This question,
therefore, does not concern us in these appeals.
The various references to arbitration in these cases
were in regard to work done by different contractors in
excess of what was stipulated under the several contracts.
The contracts generally contained a clause to the following
effect:
"Clause 11-The Engineer-in-charge shall have power
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 15
to make any alterations in or additions to the
original specifications, drawings, designs, and
instructions that may appear to him to be
necessary or advisable during the progress of the
work, and the contractor shall be bound to carry
but the work in accordance with any instructions
which may be given to him in writing signed by the
Engineer-in charge, and such alteration shall not
invalidate the contract; and any additional work
which the contractor may be directed to do in the
manner above specified as part of the work shall
be carried out by the contractor on the same
conditions in all respects on which he agreed to
do the main work, and at the same rates as are
specified in the tender for the main work. The
time for the completion of the work shall be
extended in the proportion that the addi-
257
tional work bears to the original work bears to
the original contract work and the certificate of
the Engineer-in-charge shall be conclusive as to
such proportion. And if the additional work
includes any class of work, for which no rate is
specified in this contract, then such class of
work shall be carried out at the rates entered in
the sanctioned schedule of rates of the locality
during the period when the work is being carried
on and if such last mentioned class of work is not
entered in the schedule of rates of the district
then the contractor shall within seven days of the
date of his receipt of the order to carry out the
work inform the Engineer-in-charge of the rate
which it is his intention to charge for such class
of work, and if the Engineer-in-charge does not
agree to this rate he shall by notice in writing
be at liberty to cancel his order to carry out
such class of work and arrange to carry it out in
such manner as he may consider advisable, provided
always that if the contractor shall commence work
order of any expenditure in regard thereof before
the rates shall have been determined as lastly
herinbefore mentioned, then and in such case he
shall only be entitled to be paid in respect of
the work carried out or expenditure incurred by
him prior to the date of the determination of the
rate as aforesaid according to such rate or rates
as shall be fixed by the Engineer-in-charge. In
the event of a dispute, the decision of the
Superintending Engineer of the circle will be
final:
Provided always that the contractor shall not be
entitled to any payment or any additional work
done unless he has received an order in writing
from the Engineer-in-charge for the additional
work that the contractor shall be bound to submit
his claim for any additional work done during any
month on or before the 15th day of the following
month accompanied by a copy of the order in
writing of the Engineer-in-charge for the
additional work, and that the contractor shall not
be entitled to any payment in respect of such
additional work if he fails to submit his claim
within the aforesaid period."
All the contracts also contained a provision for a reference
to arbitration in case of disputes. The clause of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 15
contract enabling the reference was as follows:-
258
"Clause 23-Except where otherwise provided in the
contract all questions and disputes relating to
the meaning of the specifications, designs,
drawings, and instructions herinbefore mentioned
and as to the quality of workmanship, or materials
used on the work, or as to any other question,
claim, right matter, or thing whatsoever, in any
way arising out of, or relating to the contract,
designs, drawings, specifications, estimates
instructions, orders, or these conditions, or
otherwise concerning the work or the execution, or
failure to execute the same, where arising during
the progress of the work, or after the completion
or abandonment thereof shall be referred to the
sole arbitration of a Superintending Engineer of
the State Public Works Department unconnected with
the work at any stage nominated by the concerned
Chief Engineer. If there be no such Superintending
Engineer it should be referred to the sole
arbitration of the Chief Engineer concerned. If
will be no objection to any such appointment that
the arbitrator so appointed is a Government
servant. The award of the arbitrator so appointed
shall be final, conclusive and binding on all
parties to these contracts."
Pursuant to the clause in the contracts enabling the Chief
Engineer to refer disputes to an arbitrator, references were
made. For the purposes of our decision, we are proceeding on
the basis that in the notices of demand made by the
contractors before the disputes were referred to arbitration
interest on the amounts said to be payable was claimed.
The general statutory provisions in regard to the award
of interest by a court are contained in the Interest Act and
the Civil Procedure Code. The Interest Act of 1839 contained
only one section and it was as follows:-
" 1. It is, therefore, hereby enacted that, upon
all debts or sums certain payable at a certain
time or otherwise, the Court before which such
debts or sums may be recovered may, if it shall
think fit, allow interest to the creditor at a
rate not exceeding the current rate of interest
from the time when such debts or sums certain were
payable, if such debts or sums be payable by
virtue of some written instrument at a certain
time; or if payable otherwise, then from the time
when demand of payment shall have been made in
writing so as such demand shall give notice pay
the debtor that
259
interest will be claimed from the date of such
demand until the term of payment; provided that
interest shall be payable in all cases in which it
is now payable by law. "
In 1978, the Interest Act of 1839 was repealed and a new
Interest Act was enacted. The Statement of objects and
Reasons of the new Act recited,
"The Law Commission of India in its sixty-third
report had recommended the revision of the
existing Interest Act, 1839. This Act is a very
short one; besides a preamble, it contains only
one section and a proviso. However, it is a
statute of importance, since it prescribes the
general law of interest which becomes applicable
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 15
in the absence of any contractual or statutory
provisions specifically dealing with the subject.
According to the Commission, almost every phrase
used in the Act has given rise to problems of
interpretation and judicial decisions have
disclosed divergence of views in respect of the
same. The Commission has revised the Act
comprehensively so as to make its provisions more
precise, specific, unambiguous and juristically
satisfactory. It is proposed to replace the
existing Act by a new Act based on the
recommendations of the Law Commission." The new
Act has made some important changes. One of the
important changes is that the expression ’court’
is defined to include a tribunal and an
arbitrator. Debt is defined as meaning any
liability for an ascertained sum of money,
including a debt payable in kind, but not
including a judgment debt. Section 3(1) enables
the court, if it so thinks fit, to award interest,
in any proceeding for the recovery of any debt or
damages or in any proceeding in which a claim for
interest in respect of any debt or damages already
paid is made, to the person entitled to the debt
or damages or to the person making such claim, for
the whole or part of the following period; (a) if
the proceeding relates to a debt payable by virtue
of a written instrument at a certain time, then,
from the date when the debt is payable to the date
of institution of the proceedings; (b) if the
proceeding does not relate to any such debt, then
from the date mentioned in this regard in a
written notice given by the person entitled or the
person making the claim to the person liable that
interest will be claimed, to the date of
institution of the proceeding. Section 3(3)
provides that
260
nothing in the section shall apply in relation to
(i) any debt or damages upon which interest is
payable as of right, by virtue of any agreement;
or (ii) any debt or damages upon which payment of
interest is barred by virtue of an express
agreement. Section 3(3)(c) provides that nothing
in the section shall empower the court to award
interest upon interest. Section 4(1) provides,
"notwithstanding anything contained in section 3,
interest shall be payable in all cases in which it
is payable by virtue of any enactment or other
rule of law or usage having the force of law."
Section 4(2) further provides notwithstanding
anything as s. 4, the court shall allow interest
in the class of cases specified in s. 4(2) from
the dates stipulated to the dates stipulated in
the provision. Section 5 provides that nothing in
the Act shall affect the provisions of s. 34 of
the Code of Civil Procedure, 1908.
It is important to notice at this stage that both the
Interest Act of 1839 and the Interest Act of 1978 provide
for the award of interest upto the date of the institution
of the proceedings Neither the Interest Act of 1839 nor the
Interest Act of 1978 provides for the award of pendente lite
interest. We must look elsewhere for the law relating to the
award of interest pendente lite. This, we find, provided for
in s. 34 of the Civil Procedure Code in the case of courts.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 15
Section 34, however, applies to arbitrations in suits for
the simple reason that where a matter is referred to
arbitration in a suit, the arbitrator will have all the
powers of the court in deciding the dispute, Section 34 does
not otherwise apply to arbitrations as arbitrators are not
courts within the meaning of s. 34 Civil Procedure Code.
Again, we must look elsewhere to discover the right of the
arbitrator to award interest before the institution of the
proceedings, in cases where the proceedings had concluded
before the commencement of the Interest Act of 1978. While
under the Interest Act of 1978 the expression ’court’ was
defined to include an arbitrator, under the Interest Act of
1839 it was not so defined. The result is that while in
cases arising after the commencement of the Interest Act of
1978 an arbitrator has the same power as the court to award
interest upto the date of institution of the proceedings, in
cases which arose prior to the commencement of the 1978 Act
the arbitrator has no such power under the Interest Act of
1839. It is, therefore necessary, as we said, to look
elsewhere for the power of the arbitrator to award interest
upto the date of institution of the proceedings. Since the
arbitrator is required to conduct himself and make the award
in accordance with law we must look to the substan
261
tive law for the power of the arbitrator to award interest
before the commencement of the proceedings. If the agreement
between the parties entitles the arbitrator to award
interest no further question arises and the arbitrator may
award interest. Similarly if there is a usage of trade
having the force of law the arbitrator may award interest.
Again if there are any other provisions of the substantive
law enabling the award of interest the arbitrator may award
interest. By way of an illustration, we may mention s. 80 of
the Negotiable Instruments Act as a provision of the
substantive law under which the court may award interest
even in a case where no rate of interest is specified in the
promissory note or bill of exchange. We may also refer s.
61(2) of the Sale of Goods Act which provided for the award
of interest to the seller or the buyer as the case may be
under certain circumstances in suits filed by them. We may
further cite the instance of the nonperformance of a
contract of which equity could give specific performance and
to award interest. We may also cite a case where one of the
parties is forced to pay interest to a third party, say on
an overdraft, consequent on the failure of the other party
to the contract not fulfilling the obligation of paying the
amount due to them. In such a case also equity may compel
the payment of interest. Loss of interest in the place of
the right to remain in possession may be rightfully claimed
in equity by the owner of a property who has been
dispossessed from it.
We may now refer to the case law. We may start the
discussion of the topic with the case of Bengal Nagpur
Raiiway Company Limited v. Ruttanji Ramji (65 Indian Appeals
66). There certain rates of payment under an agreement for
the construction of a railway line were abandoned by mutual
consent of the parties and the contractor was required to be
paid at rates which were fair and reasonable for the work
done. The question arose whether the contractor was entitled
to be paid interest on the amount which the Railway Company
was liable to pay. The Privy Council found that the railway
was liable to pay to the plaintiff an amount of Rs.66,980-
10-6 on July 26, 1925. The suit for recovery of the amount
was filed on November 29, 1927. The Privy Council held that
award of interest from the date of the institution of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 15
suit was governed by s. 34 of the Code of Civil Procedure
and went on to observe that the crucial question was whether
the court had authority to allow interest for the period
prior to the institution of the suit. They observed that the
solution of the question depended not upon the Code of Civil
Procedure out upon substantive law. Interest for the period
prior to the date of suit may be awarded if there was an
agreement for the payment of interest at a fixed rate or it
was payable by the usage of trade having the force of law or
under the provision of H
262
any substantive law entitling the plaintiff to recover
interest. Section 80 of the Negotiable Instruments Act was
cited as a provision of the substantive law under which the
court may award interest when no rate of interest is
specified in the promissory note or bill of exchange. In the
case before them however, they observed there was neither
usage nor any contract, express or implied, to justify the
award of interest. Interest was not payable by virtue of any
provision of the law governing the case. Under the interest
Act of 1839, the court may allow interest to the plaintiff
if the amount claimed is a sum certain which is payable at a
certain time by virtue of a written instrument. But it was
conceded that the amount claimed in the case was not a sum
certain. Referring to the provisions of s. 1 of the Interest
Act which stated that interest shall be payable in all cases
in which interest was then payable by law, the Privy Council
observed that the proviso applied to cases in which the
court of equity exercised the jurisdiction to allow
interest. But then they said that the case before them did
not attract the jurisdiction of the court. An example of
cases which attract the equitable jurisdiction of the court
to award interest was given as the nonperformance of a
contract of which equity could give specific performance.
Considering next the question whether interest could be
awarded by way of damages, it was held that it could not be
so done. It was categorically stated that interest could not
be allowed by way of damages. It was also pointed out that
in England, the law had been amended by the Law Reform
Miscellaneous Provisions Act which empowered a court of
record to-award interest on whole or any part of damages.
But there was no such amendment of the law in India (at that
time).
Seth Thawardas Pherumal v. The Union of India, [1985] 2
SCR 48 was a case which arose out of a decision of the Patna
High Court, which is reported in Union of India v. Prem
Chand Satnam Das, AIR 1951 Patna 201. Some. Of the facts
have been taken by us from the judgment of the Patna High
Court as those facts were not evident from the judgment of
this court. Pursuant to clause 14 of the contract between
the Dominion of India and the contractor which provided that
all disputes arising out of or relating to the contract
should be referred to the Superintending Engineer, a
reference was made on January 21, 1949 and an award followed
on May 8, 1949. Before the arbitrator the contractor
submitted a claim under 17 heads. Item No. 17 as mentioned
in the Statement of claim before the arbitrator was
"interest on the amount of money involved in this claim at
the rate of six per cent-Rs.27,665. This work was finished
in May 1946 and it was proper for the Department to have
decided all our claims at least by
263
31st December, 1947 .. But this was not done. Due to this, a
heavy amount remained blocked and we were compelled to take
money from our bankers on interest. We pray, therefore, for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 15
interest for 15 months from January 1, 1948 to March 31,
1949." The arbitrator held: "The contract’s contention that
his claims should have been settled by January 1948 is, in
my opinion, reasonable. I, therefore, award interest at six
per cent for sixteen months on the total amount of the
awards given, that is, Rs.17,363". The question arose
whether the arbitrator could award the interest? The Patna
High Court noticed that the contractor did not include any
claim for interest for the period March 3 1, 1947 to April
20, 1949 in the bill originally submitted by him to the
Chief Engineer and that the claim was made for the first
time before the arbitrator during the progress of the
arbitration proceedings. The High Court also noticed that
the Executive Engineer who appeared on behalf of the Union
of India before the arbitrator did not seem to have
submitted to the jurisdiction of the arbitrator to decide
the question of interest. In those circumstances, the High
Court held that it could not be said that the claim for
interest was one of the matters referred to arbitration. The
arbitrator, it was, therefore, held, had no jurisdiction to
entertain the claim and award interest. In the appeal by the
contractor, the Supreme Court noticed that the claim under
each head on which interest was awarded was for an
unliquidated sum and observed that in that kind of case,
interest was not payable by law otherwise than by the
application of the Interest Act. Reference was made to the
Bengal Nagpur Rly. Co. v. Ruttanji Ramji, 65 I.A. 66 as an
authority for that proposition. The Court then proceeded to
say that even if an arbitrator could be assumed to be a
court within the meaning of the Act, which he did not appear
to be, none of the four conditions, which required to be
fulfilled, was present in the case before them. It was then
said that the arbitrator erred in thinking he had the power
to allow interest simply because he thought the demand was
reasonable. A further argument that interest could be
awarded at least from the date of the suit on the analogy of
sec. 34 of the Civil Procedure Code was repelled with the
following observations: "It was suggested that at least
interest from the date of suit could be awarded on the
analogy of sec. 34 of the Civil Procedure Code, 1908. But
sec. 34 does not apply because an arbitrator is not a court
within the meaning of the Code nor does the Code apply to
arbitrator, and, but for sec. 34 even a court would not have
the power to give interest after the suit. This was,
therefore, also rightly struck out from the award." These
observations of Bose, J. gave rise to considerable
difficulty in later cases, but in the series of cases,
Nachiappa Chettier v. Subramaniam Chettier, [1960] 2 SCR
209; Setinder Singh v. Amrao Singh, [1961] 3
264
SCR 676; Firm Madanlal Roshanlal Mahajan v. Hukumchand Mills
Ltd., [1967] 1 SCR lO5; Union of India v. Bungo Steel
Furniture Pvt. Ltd., [ 1967] 1 SCR 324 and State of Madhya
Pradesh v. M/s. Saith & Skelton Pvt. Ltd., [1972] 3 SCR 233,
these observations have been explained and it was held that
the observations never intended to lay down the broad and
unqualified proposition that they appeared to lay down on a
first impression. We will presently refer to these cases. At
this juncture, it is necessary to note that in Seth
Thawardas Pherumal’s case the question of payment of
interest was not the subject matter of reference to the
arbitrator and that the interest claimed before the
arbitrator and awarded by the arbitrator related to the
period prior to the reference to arbitration and the period
during the pendency of the arbitration. It is also to be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 15
noted that the reference was not in the course of a suit.
Nachiappa Chettier v. Subramaniam Chettier, (supra) was
a case of arbitration in a suit. The arbitrator made an
interim award on August 1, 1944 and December 6, 1944. He
awarded interest pendente lite as well as future interest
until the date of payment. Relying on the observations in
Seth Thawardas Pherumal v. Union of India, the award of
interest was questioned. The court doubted whether the
observations in Seth Thawardas Pherumal’s case were intended
to lay down such a broad and unqualified proposition, but
did not pursue the matter further as that contention was not
urged before the High Court. E
Satinder Singh v. Amrao Singh (supra) was a case which
arose under the East Punjab Acquisition and Requisition of
Immovable Property (Temporary) Powers Act, 1948. The Act
containd no provision for payment of interest. It was argued
that in the absence of a provision providing for interest
could be awarded. The court approved the observation of the
Privy Council in 1928 A.C. 429 that where the owner is
deprived of his property "the right to receive the interest
takes the place of the right to retain possession and is
within the rules." The court then observed, "it would thus
be noticed that the claim for interest proceeds on the
assumption that when the owner of immovable property loses
possession of it he is entitled to claim interest in place
of right to retain possession." and held that this general
rule was not excluded by the 1948 Act. Referring then to the
observations in Seth Thawardas Pherumal v. Union of India,
(supra) what was said in Nachiappa Chettier v. Subramaniam
Chether, (supra) was reitereated that no broad and
unqualified proposition was intended to be laid down in Seth
Thawards Pherumal v. The Union of India. Referring to the
Interest Act and the power of the Court to allow
265
interest, it was expressly noticed that the proviso to sec.
1 of the Interest Act, 1939 made it clear that interest
shall be payable in all cases in which it was now payable by
law. The power to award interest on equitable grounds or
under any provisions of the law was held to be expressly
saved by the proviso. The award of interest by the
arbitrator was upheld on the ground that the right to
receive interest in lieu of possession of immovable property
taken away either by private treaty or by compulsory
acquisition was generally regarded by judicial decisions as
an equitable right.
In Union of India v. Watkins & Co. (AIR 1966 SC 275,
the question arose when interest could be awarded for the
period prior to the date of the institution of the suit. The
suit there was for compensation for storage of over 600
tonnes of iron sheets for a period of about five years. It
was held that interest could not be awarded for the period
prior to the suit as there was no agreement for the payment
of interest nor was their any usage of trade having the
force of law or any provision of the substantive law which
entitle the plaintiff to recover interest. Under the
Interest Act, 1839, the court could allow interest if the
amount claimed was a sum certain, payable at a certain time,
by virtue of a written instrument. The compensation for an
unliquidated amount was not a sum certain. Interest prior to
the institution of the suit was not awardable.
In Union of India v. West Punjab Factories, [ 1961] 1
SCR 580, it was held, that in a suit, interest by way of
damages could not be awarded in the absence of any usage or
contract, express or implied, or of any provision of law.
Bengal Nagpur Railway Co. v. Ruttanji Ramji, (supra) and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 15
Seth Thawardas Pherumal v. Union of India, (supra) were
relied on
Firm Madanlal Roshanlal Mahajan v. Hukumchand Mills
Ltd. (supra) was a case where the arbitration was in a suit.
Before the arbitrator, no claim was made for interest prior
to the institution of the suit, but interest was claimed
from the date of institution of the suit till recovery of
the amount. The arbitrator awarded interest on the sum
determined by him from the date of the award till the date
of payment. The award was then filed in the court. One of
the objections was to the grant of interest during the
pendency of the suit relying on the observations of Seth
Thawardas Pherumal v. Union of India, (supra) that sec. 34
CPC did not apply to arbitration proceedings. The court
observed that the observations lent colour to the argument
that the arbitrator had no power to award pendente lite
interest, but the obser-
266
vations were not intended to lay down such a broad and
unqualified proposition. A reference was made to Nachiappa
Chettier v. Subramaniam Chettier, (supra) and Satinder Singh
v. Amrao Singh, (supra). It was further observed "In the
present case, all the disputes in the suit were referred to
the arbitrator for his decision. One of the disputes in the
suit was whether the respondent was entitled to pendente
lite interest. The arbitrator could decide the dispute and
we could award pendente lite interest just as a court could
do so under sec. 34 of the Civil Procedure Code. Though, in
terms, s. 34 of the Code of Civil Procedure does not apply
to arbitrations, it was an implied term of the reference in
the suit that the arbitrator would decide the dispute
according to law and would give such relief with regard to
pendente lite interest as the court could give if it decided
the dispute. This power of the arbitrator was not fettered
either by the arbitration agreement or by the Arbitration
Act, 1940. The condention that in an arbitration in a suit
the arbitrator had no power to award pendente lite interest
must be rejected." Thus while the court did not dispute the
proposition that the arbitrator was not a court, it held
that in a case where the reference was made to arbitration
in a suit, the arbitrator would have the same power as the
court to award interest.
In Union of India v. Bungo Steel Furniture Private
Limited, [1957] 1 SCR 324, certain disputes between the
Union of India and a contractor in respect of certain
contracts for the supply of bedsteads were referred to
arbitration. The question arose whether the arbitrator had
jurisdiction to award interest on the amount found due by
the arbitrator from the date of the award till the date of
the decree. This of course is not the question before us.
But even so we must say that the observations made therein
appear prima facie to justify the view that interest may be
awarded by the arbitrator pendente lite. Ramaswamy, J. who
spoke for the court, observed that the observations of Bose,
B. in Seth Thawardas Pherumal’s case (supra) were not
intended to lay down any broad and unqualified proposition
and that though sec. 34 of the Code of Civil Procedure did
not apply in terms to arbitration proceedings, the principle
of that section would be applied by the arbitrator for
awarding interest in the classes of cases where the court
having jurisdiction in a suit over the subject matter or the
proceeding would be competent to award interest. It was said
"In the present case, all the disputes in the suit,
including the question of interest were referred to the
arbitrator for his decision. In our opinion, the arbitrator
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 15
had jurisdiction, in the present case, to grant interest on
the amount of the award from the date of the award till the
date of the decree." The words emphasised by us clearly show
that in this case
267
too, the arbitration was in a suit and it was therefore,
held that the arbitrator had the same power to award
interest as the court would h ave .
In M/s. Ashok Construction Company v. Union of India,
[1971] 3 SCC 66, there was an arbitration on the
intervention of the Court (Deputy Commissioner). Before the
arbitrator, a total claim for Rs.4,41,440.20p was made
consisting of a claim of Rs.64,006.71 for works done, a
claim for Rs. l,83,393.77p for damages at 13 per cent per
annum and a claim for Rs.1,91,097.88p for depreciation of
the value of money. The arbitrator made an award for a sum
of Rs.1,79,843,80p. He gave no reasons for his award. The
last item of the claim was wholly unjustified, but there was
nothing to show that the arbitrator had taken that claim of
account in making the award. Considering the question of
award of interest by way of damages, the court referred to
the arbitration agreement and on its interpretation held
that the terms of the arbitration agreement did not exclude
the jurisdiction of the arbitrator, to entertain a claim for
interest, award amount due under the contract
In State of Madhya Pradesh v. M/s. Saith & Skelton P.
Limited, [1972] 3 SCR 233, with the consent of the parties,
the Court appointed an arbitrator and referred all the
disputes to him. The arbitrator awarded interest from the
date when the amount became payable till the date of the
decree. The question arose whether the arbitrator had the
power to do so. It was held that, in the case before them,
interest prior to the suit could be awarded under sec. 61(2)
of the Sale of Goods Act, 1930 which expressly provides for
the award of interest to the seller in any suit by him for
the amount of the price-from the date of the tender of the
goods or from the date on which the price was payable and to
the buyer in a suit by him for the refund of the price in a
case of the breach of contract on the part of the seller-
from the date on which the payment was made. In view of the
provision of substantive law which enabled the award of
interest it was held that interest prior to the suit could
be awarded by the arbitrator. In regard to pendente lite
interest, it was held that since all the disputes were
referred to arbitration by the court, the arbitrator had the
same power as the court to award the pendente lite interest.
As a result of the discussion of the various cases, we
see that Bengal Nagpur Railway Company Ltd. v. Ruttanji
Ramji, (supra), Union of India v. West Punjab Factories,
(supra) and Union of India v. Watkins & Co. (supra) were
cases of award of interest not by an
268
arbitrator, but by the court. It was laid down in these
three cases that interest could not.be awarded for the
period prior to the suit in the absence of an agreement for
the payment of interest or any usage of trade having the
force of law or any provision of the substantive law
entitling the plaintiff to recover interest. Interest could
also be awarded by the court under the Interest Act if the
amount claimed was a sum certain payable at a certain time
by virtue of a written instrument. In regard to pendente
lite interest, the-provisions of the Civil Procedure Code
governed the same.
The question of award of interest by an arbitrator was
considered in the remaining cases to which we have referred
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 15
earlier. Nachiappa Chettier v. Subramanian Chettier, (supra)
Sattinder Singh v. Amrao Singh (supra), Firm Madanlal
Roshanlal Mahajan v. Hukum Chand Mills Ltd. (supra) Union of
India v. Bungo Steel Furniture Private Limited (supra),
Ashok Construction Company v. Union of India, (supra) and
State of Madhya Pradesh v. M/s. Saith & Skelton Private
Limited were all cases in which the reference to arbitration
was made by the court, of all the disputes in the suit. It
was held that the arbitrator must be assumed in these
circumstances to have the same power to award interest as
the court. It was on that basis that the award of pendente
lite interest was made on the principle of s. 34 Civil
Procedure Code in Nachiappa Chettier v. Subramaniam Chettier
(supra), Firm Madanlal Roshanlal Mahanan v. Hukamchand Mills
Limited, (supra), Union of India v. Bungo Furniture Private
Limited, (supra) and State of Madhya Pradesh v. M/s. Saith &
Skelton Private Limited, (supra). In regard to interest
prior to the suit, it was held in these cases that since the
Interest Act, 1839 was not applicable, interest could be
awarded if there was an agreement to pay interest or a usage
of trade having the force of law or any other provision of
substantive law entitling the claimant to recover interest.
Illustrations of the provisions of substantive law under
which the arbitrator could award interest were also given in
some of the cases. It was said, for instance, where an owner
was deprived of his property, the right to receive interest
took the place of the right to retain possession, and the
owner of immovable property who lost possession of it was,
therefore, entitled to claim interest in the place of right
to retain possession. It was further said that it would be
so whether possession of immovable property was taken away
by private treaty or by compulsory acquisition. Another
instance where interest could be awarded was under s. 61(2)
of the Sale of Goods Act which provided for the award of
interest to the seller or the buyer, as the case may be,
under the circumstances specified in that section.
269
Sec. 80 of the Negotiable Instruments Act was mentioned
as an instance of a provision of the substantive law under
which interest prior to the institution of the proceedings
could be awarded. Interest could also be awarded in cases of
non-performance of a contract of which equity could give
specific performance. Seth Thawardas Pherumal was a case of
direct reference to arbitration without the intervention of
a court. Neither the Interest Act, 1839 nor the Civil
Procedure Code applied as an arbitrator was not a court.
Interest could, therefore, be awarded only if there was an
agreement to pay interest or a usage of trade having the
force of law or some other provision of the substantive law
which entitled to plaintiff to receive interest. In that
case, interest had been awarded on the ground that it was
reasonable to award interest and the court, therefore, held
that the arbitrator was wrong in awarding the interest.
While this is the position in cases which arose prior
to the coming into force of the Interest Act, 1978, in cases
arising after the coming into force of the Act, the position
now is that though the award of pendente lite interest is
still governed by the same principles, the award of interest
prior to the suit is now governed by the Interest Act, 1978.
Under the Interest Act, 1978, an arbitrator is, by
definition, a court and may now award interest in all the
cases to which the Interest Act applies.
We were referred to certain English cases: London
Chatham and Dover Rly. Co. v. South Eastern Ply. Co., [1893
AC 429], Chandris v. Isbrandtsen Mollar Co., [1951] 1 KB
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 15
240, Timber Shipping Co. v. London & overseas Freighters
Ltd., [1972] AC 1 and President of lndia v. La Pintada Cia
Navegacion, [1984] 2 All Eng. Law Reports. Passages from
Halsbury’s Laws of England and Russell’s Arbitration were
also read out. We have read them out we refrain from
referring to those cases and passages because of the
abundance of authoritative pronouncements of the Supreme
Court of India.
Coming to the cases before us, we find that in Civil
Appeal Nos. 120 and 12 1 of 1981 before the arbitrator,
there was no answer to the claim for interest and we see no
justification for us at this stage to go into the question
whether interest was rightly awarded or not. Out of the
remaining cases we find that in all cases except two (Civil
Appeal Nos. 6019-22 of 1983 and Civil Appeal No. 2257 of
1984, the references to arbitration were made prior to the
commencement of the new Act which was on August 19, 1981. In
the cases to which the Interest Act, 1978 applied, it was
argued by Dr. Chitale, learned counsel for H
270
the respondents, that the amount claimed was a sum certain
payable at a certain time by virtue of a written instrument
and, therefore, interest was payable under the Interest Act
for the period before the commencement of the proceedings.
In support of his contention that the amount claimed was a
sum certain payable at a certain time by virtue of a written
instrument, the learned counsel relied upon the decision of
this court in State of Rajasthan v. Raghubir Singh, [ 19791
3 SCR 6. The case certainly supports him and in the cases to
which the 1978. Interest Act applies the award of interest
prior to the proceeding is not open to question. In regard
to pendente lite interest, that is, interest from the date
of reference to the date of the award, the claimants would
not be entitled to the same for the simple reason that the
arbitrator is not a court within the meaning of sec. 34 of
the CPC, nor were the references to arbitration made in the
course of suits. In the remaining cases which arose before
the commencement of the Interest Act, 1978, the respondents
are not entitled to claim interest either before the
commencement of the proceedings or during the pendency of
the arbitration. They are not entitled to claim interest for
the period prior to the commencement of the arbitration
proceedings for the reason that the Interest Act, 1839 does
not apply to their cases and there is no agreement to pay
interest or any usage of trade having the force of law or
any other provision of law under which the claimants were
entitled to recover interest. They are not entitled to claim
pendente lite interest as the arbitrator is not a court nor
were the references to arbitration made in suits. One of the
submissions made on behalf of the respondents was that in
every case, all disputes were referred to arbitration and
the jurisdiction of the arbitrator to award interest under
certain circumstances was undeniable. The award not being a
speaking award, it was not permissible to speculate on the
reasons for the award of interest and the court was not
entitled to go behind the award and disallow the interest.
It is difficult to agree with this submission. The
arbitrator is bound to make his award in accordance with
law. If the arbitrator could not possibly have awarded
interest on any permissible ground because such ground did
not exist, it would be open to the court to set aside the
award relating to the award of interest on the ground of an
error apparent on the record. On the other hand, if there
was the slightest possibility of the entitlement of the
claimant to interest on one or other of the legally
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 15
permissible grounds, it may not be open to the court to go
behind the award and decide whether the award of interest
was justifiable. We do not want to enter into a discussion
on the legality or properiety of a non-speaking award as we
understand the question is now awaiting the decision of a
Seven Judge Bench. In the light of what we have said above,
Civil Appeal Nos. 120
271
and 121 of 1981 are dismissed, Civil Appeal Nos. 6019-22 of
1983 and A Civil Appeal No. 2257 of 1984 are allowed to this
extent that interest during the pendency of the arbitration
proceedings is disallowed and the rest of the civil appeals
are allowed to the extent that both interest prior to the
proceedings and interest during the pendency of the
proceedings are disallowed. There will be no order as to
costs. S.L.P.8640/81 is disposed of on the same lines.
N.V.K.
272