Full Judgment Text
1
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 5887 OF 2012
@ SPECIAL LEAVE PETITION (CIVIL) NO. 8734 OF 2009
Punjab Urban Planning & Dev. Authority & Ors. … Appellants
Versus
Raghu Nath Gupta & Ors. … Respondents
WITH
CIVIL APPEAL NO. 5888 OF 2012
@ SPECIAL LEAVE PETITION (CIVIL) NO. 22823 OF 2009
J U D G M E N T
JUDGMENT
K.S. Radhakrishnan, J .
1. Leave granted.
2. The questions raised in both these appeals are the same, hence,
we are disposing of both the appeals by a common judgment.
-
Page 1
2
3. The question that has come up for consideration in these appeals
is whether the respondents are legally obliged to pay the interest,
penal interest and penalty on account of the delayed payment of
| gh Court | has take |
|---|
was delay on the part of the Punjab Urban Planning and Development
Authority (for short “PUDA”) in providing the basic amenities like
parking, lights, road, water, sewerage etc. in time, PUDA cannot legally
claim the interest, penal interest as well as penalty on account of the
delayed payment of installments. The High Court placed reliance on
the judgment of this Court in Municipal Corporation, Chandigarh
and Ors. v. Shantikunj Investment (P) Ltd. (2006) 4 SCC 109 to
reach that conclusion.
4. We heard Mrs. Rachna Joshi, learned counsel appearing on behalf
JUDGMENT
of PUDA as well as Shri P.S. Patwalia, learned senior counsel assisted
by Mr. Tushar Bakshi, appearing for the respondents.
5. For the disposal of these appeals, we may refer to the facts of
Civil Appeal No. …… of 2012 [arising out of SLP (Civil) No. 8732 of
2009], as follows:
-
Page 2
3
PUDA, on 16.3.2001, conducted a public auction for sale of the
commercial plots. Raghu Nath Gupta, the respondent was the
successful bidder of a single storey shop no. 134 in Phase III BIT, for a
| respond | ent on 2 |
|---|
Rs.7,93,750/- being 25% of the total cost of site. Installment facility
was extended to the respondent for paying the balance 75% of the
amount, that was Rs.23,81,250/- The relevant clauses of the
Allotment Letter dated 16.3.2011 are extracted below for easy
reference:
“4. The sum of Rs.7,93,750/- being 25% of the total cost
of the site deposited by you after the ….. been
adjusted as 25% of the sale.
5. The balance amount i.e. Rs.23,81,250/- being 75% of
above piece of the writ, can be paid in lump sum
without interest within 60 days from the date of
auction or in 4 equated yearly installments along with
interest @ 15 % per annum.
JUDGMENT
6. The annual quoted installment with interest @ 15%
per annum will be payable as per the following
schedule:
Installment Due date Amount of
Installment
Interest Total amount
payable
st
1 16.3.2002 5,95,313/- 3,57,188/- 9,52,501/-
nd
2 16.3.2003 5,95,313/- 2,67,891/- 8,52,501/-
rd
3 16.3.2004 5,95,312/- 1,78,594/- 7,73,906/-
th
4 16.3.2005 5,95,312/- 89,297/- 6,84,609/-
Page 3
4
23,81,250/- 8,92,970/- 32,74,220/-
th
In case the installment is not paid on the 10 of the month following
| due, PUD | A can im |
|---|
Clause 9 reads as follows:
th
“9. In case the installment is not paid by the 10 of the
month following the month, in which it falls due, the
Estate Officer shall proceed to take action for
imposition of penalty charged @ 2% per month of the
amount i.e. from the due date in addition to normal
simple interest. In case of non-payment of the
installment along with interest due thereon for a
continuous period of 3 months, the whole or any part
of the money paid in respect of the site shall be
forfeited and the Estate Officer shall cancel the
allotment and resume the site, after giving you
appropriate notice and an opportunity of being heard
shall continue to be charged in the whole due amount
till the date of payment of amount due.”
JUDGMENT
6. Above mentioned conditions were accepted and the plot was
allotted. On getting possession after payment of 25% of the total
cost, respondent raised construction on the allotted site in the year
2002. PUDA completed the development work by 20.12.2002 and
provided all the facilities for the enjoyment of the various commercial
plots allotted.
Page 4
5
7. Respondent filed CWP No. 6156 of 2002 before the High Court
seeking a direction to PUDA not to charge interest on the balance
installments till the basic amenities were provided on the site. The writ
-
Estate Officer, PUDA, Mohali to pass a speaking order. Consequently,
the Estate Officer passed the order on 5.9.2002 rejecting the demand
made in the notice, which was challenged by the respondents by filing
CWP No. 18753 of 2002, which was disposed of vide order dated
13.7.2006 directing the respondents to file detailed representations
before the Additional Chief Administrator. Consequently, a detailed
representation was filed by the respondents on 29.8.2006 before the
Additional Chief Administrator stating that since PUDA had failed to
provide the basic amenities like drinking water, drainage and public
JUDGMENT
toilets, respondents were not legally obliged to pay interest, penal
interest, penalty etc. on the delayed installments. PUDA took up the
stand before the Additional Chief Administrator that the basic
amenities like parking, lights, roads, water, sewerage etc. were not
provided at the site when they were allotted, but the toilet was shown
near SCF No. 124-125. PUDA submitted that the electrical works had
been completed by 24.12.2002, public health works had been
Page 5
6
completed by 22.11.2002 and the development of the commercial
pocket had been completed by 20.12.2002.
8. After having examined the contentions raised by both,
| e Additio | nal Chief |
|---|
-
representation vide his order dated 31.3.2007, which was challenged
by the respondents before the High Court by filing CWP No. 6929 of
2007. The High Court allowed that CWP vide its judgment dated
5.11.2008 placing reliance on the judgment of this Court in
Shantikunj Investment (supra), which is impugned before this
Court.
9. Mrs. Rachana Joshi took us through the terms and conditions of
Auction Notice and also to the various terms and conditions of the
JUDGMENT
allotment, as well as the judgment of this Court in Shantikunj
Investment (supra).
10. Shri P.S. Patwalia submitted that the High Court was justified in
allowing the writ petition, since there was a failure on the part of PUDA
in providing the necessary facilities for enjoyment of the plots allotted
to the respondents. Further, it was also contended by the learned
Page 6
7
senior counsel that the High Court had rightly applied the principle laid
down by this Court in Shantikunj Investment (supra).
11. We are of the view that the terms and conditions stipulated in the
| lotment | of comm |
|---|
the parties. We, therefore, called for the auction notification -
published by PUDA and the same was made available to us. There
was no dispute that the plots were auctioned on 16.3.2001 on the
basis of the terms and conditions stipulated therein. Clause 25 is the
most important clause, which binds both the parties, reads as follows:
“25. The site is offered on “as is where is” basis and the
Authority will not be responsible for leveling the site or
removing the structures, if any, thereon.”
In other words, the plot in question was auctioned on “as is where is”
JUDGMENT
basis and the same was accepted by the respondent on “as is where
is” basis. Plot was allotted to the respondent by PUDA vide Memo No.
A-5/2001/3192 dated 25.5.2001. The relevant terms and conditions
of the allotment have already been referred to by us in the earlier part
of the judgment. Respondents could have paid the entire amount in
lump sum, however, they availed off the installment facility offered. It
was made clear in the allotment letter that, in case, there was a failure
Page 7
8
th
to pay the installment by the 10 of the month following the month in
which the payment fell due, the Estate Officer should proceed to take
action for imposition of penalty charged @ 2% per month of the
| in the a | llotment |
|---|
payment of installment along with interest due thereon for a -
continuous period of three months, the whole or any parts of the
money paid in respect of the site, should be forfeited and the Estate
Officer could even cancel the allotment.
12. We notice that the respondents had accepted the commercial
plots with the open eyes, subject to the above mentioned conditions.
Evidently, the commercial plots were allotted on “as is where is” basis.
The allottees would have ascertained the facilities available at the time
of auction and after having accepted the commercial plots on “as is
JUDGMENT
where is” basis, they cannot be heard to contend that PUDA had not
provided the basic amenities like parking, lights, roads, water,
sewerage etc. If the allottees were not interested in taking the
commercial plots on “as is where is” basis, they should not have
accepted the allotment and after having accepted the allotment on “as
is where is” basis, they are estopped from contending that the basic
amenities like parking, lights, roads, water, sewerage etc. were not
Page 8
9
provided by PUDA when the plots were allotted. Over and above,
the facts would clearly indicate that there was not much delay on the
part of PUDA to provide those facilities as well. As noted, the
| nd all the | facilities |
|---|
water, sewerage etc. were also provided.
-
13. On facts, we find that this is not a case where PUDA was callous
or indifferent or had caused an inordinate delay in providing the basic
facilities to allottees. In our view, the High Court has not properly
comprehended the scope of the judgment of this Court in Shantikunj
Investment (supra) and the terms and conditions of the auction.
This Court, in that case, has specifically held as follows:
JUDGMENT
“26…….It is the common experience that for full
development of an area it takes years. It is not possible in
every case that the whole area is developed first and
allotment is served on a platter. Allotment of the plot was
made on an as is where is basis and the Administration
promised that the basic amenities will be provided in due
course of time. It cannot be made a condition
precedent………….
28. It is true that once allotment of the land has
been made in favour of the allottee, he can take possession
of the property and use the same in accordance with the
Rules. That does not mean that all the facilities should be
Page 9
10
provided first for so called enjoyment of the property as this
was not the condition of auction. The party knew the
location & condition prevailing thereon. The interpretation
given by the Division Bench of the High Court of Punjab &
Haryana and contended before us cannot be accepted as a
settled proposition of law………….
(emphasis supplied)”
We may also refer to another judgment of this Court in UT
Chandigarh Administration and Anr. v. Amerjeet Singh and Ors.
-
(2009) 4 SCC 660, in which, after having referred to the judgment of
this Court in Shantikunj Investment case, this Court held as follows:
“19. …………In a public auction of sites, the position is
completely different. A person interested can inspect the
sites offered and choose the site which he wants to acquire
and participate in the auction only in regard to such site.
Before bidding in the auction, he knows or is in a position to
ascertain, the condition and situation of the site. He knows
about the existence or lack of amenities. The auction is on
`as is where is basis'. With such knowledge, he participates
in the auction and offers a particular bid. There is no
compulsion that he should offer a particular price.
JUDGMENT
20. Where there is a public auction without assuring
any specific or particular amenities, and the prospective
purchaser/lessee participates in the auction after having an
opportunity of examining the site, the bid in the auction is
made keeping in view the existing situation, position and
condition of the site. If all amenities are available, he would
offer a higher amount. If there are no amenities, or if the
site suffers from any disadvantages, he would offer a lesser
amount, or may not participate in the auction. Once with
open eyes, a person participates in an auction, he cannot
Page 10
11
thereafter be heard to say that he would not pay the
balance of the price/premium or the stipulated interest on
the delayed payment, or the ground rent, on the ground
that the site suffers from certain disadvantages or on the
ground that amenities are not provided.”
| w that th | e judgm |
|---|
respondents. We may reiterate that after having accepted the offer of
the commercial plots in a public auction with a super imposed
condition i.e. on “as is where is” basis and after having accepted the -
terms and conditions of the allotment letter, including installment
facility for payment, respondents cannot say that they are not bound
by the terms and conditions of the auction notice, as well as that of
the allotment letter. On facts also, we have found that there was no
inordinate delay on the part of PUDA in providing those facilities.
15. We are of the view that the High Court was not justified in
JUDGMENT
holding that the respondents are not liable to pay the interest, penal
interest and penalty for the period commencing from 1.6.2001 to
31.12.2002 for the belated payment of installments. Consequently,
the judgments of the High Court are set aside and the writ petitions
would stand dismissed and the appeals would stand allowed as above.
There will be no order as to costs.
Page 11
12
……………………………J.
(K.S. Radhakrishnan)
……………………………J.
(Madan B. Lokur)
New Delhi;
August 16, 2012
JUDGMENT
Page 12