Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
CASE NO.:
Appeal (civil) 3032 of 2004
PETITIONER:
Jespar I. Slong
RESPONDENT:
State of Meghalaya & Ors.
DATE OF JUDGMENT: 07/05/2004
BENCH:
N Santosh Hegde & B P Singh.
JUDGMENT:
J U D G M E N T
(Arising out of SLP ) No.5185 of 2003)
SANTOSH HEGDE, J.
Heard learned counsel for the parties.
Leave granted.
In this appeal the appellant questions the correctness and
legality of the judgment of the High Court of Gauhati dated
28.1.2003 made in Writ Appeal No.710/2002 confirming the
judgment dated 7.11.2002 made by the learned Single Judge of
the same High Court at Shillong Bench in W.P. )
No.355(SH)/2002. The facts necessary for the disposal of this
appeal are as follows :
The State of Meghalaya owns a weigh bridge at
Morkjniange which it had decided to lease out to contractors who
were willing to take it on lease on yearly basis. For the said
purpose it issued a Notice Inviting Tender (NIT) from interested
persons for operating the said weigh bridge. Pursuant to the said
notification number of tenderers offered their bids. On 11.2.2002,
the respondent-State accepted the bid of one Smt. Nila Niangti,
respondent No.5 herein, which was for a sum of Rs.1.21 crores
and the contract was settled in her favour. One of the bidders who
participated in the said tender challenged the said acceptance of
the bid before the High Court in W.P. No.34(SH) of 2002, inter
alia, on the ground that the said acceptance was contrary to the
prescribed guidelines and the bid amount accepted was
speculatory and predatory in nature. The learned Single Judge
who heard the said writ petition accepted the contention of the
writ petitioner that the bid offered by the 5th respondent herein
was speculatory and predatory in nature. According to the learned
Judge the approximate value of the contract would have been
only Rs.40,29,600/-which figure the learned Judge arrived at by
taking into consideration a report submitted by the enforcement
staff of the Department of Transport. On the said basis while
setting aside the acceptance of the bid of 5th respondent herein the
court directed the respondent to call for fresh tenders and re-
examine and re-assess the value of tender keeping in view the
observations made in the said judgment. A further direction was
given that a fresh tender should be called for and the exercise of
acceptance of that tender should be made within a period of 45
days from the date of the said judgment.
In compliance of the directions issued by the High Court in
the above said judgment, the Tender Approval Committee made a
fresh assessment of the approximate value of the tender. While
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
doing so it took into consideration the above-mentioned report of
the enforcement staff of the Department of Transport as also
Traffic Census Data provided by the Public Works Department
and came to the conclusion that the annual collection from the
weigh bridge fees would be to the tune of Rs.2.11 crores and the
said Committee evaluated the value of the tender at Rs.2 crores.
This assessment was made by the said Tender Committee after
considering the above two reports. In the meantime, it is to be
noted that a fresh tender was called for and in the said tender 27
bids were received. The highest bid was for Rs.3,03,33,333 and
the next highest bid was for Rs.2,53,60,333/-. These two bids
were rejected by the Tender Committee because the said bid
forms were not affixed with the necessary court fees stamp. The
3rd highest bid was of Mr.C.Yonbon for Rs.1,75,00,567/-. The 4th
and 5th bids were for Rs.1,63,00,987/- and 1,35,00,867 which
were withdrawn by the concerned tenderers. The 6th highest bid
was for Rs.97,77,777 but the said tenderer has not pursued the
matter any further for whatever reason. The 7th bidder who is the
appellant now before us offered a bid for Rs.62,70,797/- the 8th,
9th and 10th bidders are respondents 5, 6 and 4 respectively in this
appeal who offered identical bids of Rs.40,29,600/- each which
was actually the figure identified by the learned Single Judge in
his order dated 15.3.2002. It is not necessary for us to go into the
particulars of the other bids for the purposes of disposal of this
appeal, hence, we will not refer to those particulars.
The Tender Acceptance Committee recommended to the
Minister of Transport for approval of the acceptance of tender of
Mr.C.Yonbon whose bid was 1,75,00,567/- and who was
otherwise qualified in all respects as per the tender regulation.
However, the Minister disagreed with the recommendations made
by the Tender Committee solely on the ground that the High
Court as per its order dated 15.3.2002 had directed the
respondent-State to take into consideration the report submitted
by the Enforcement Inspector of the Department of Motor
Vehicles as regards the average number of trucks loaded and
unloaded plying from Jaintia Hills to Guwahati and vice-versa
per day while making the re-tender, hence, any deviation from the
above direction would amount to contempt of court and it would
be contrary to the mandate of the said judgment to rely on any
other source of information like the data supplied by the Public
Works Department while making an assessment of the value of
the tender. Therefore, he recommended that the tender of one of
the persons amongst respondents 4, 5 and 6 who had offered
Rs.40,29,600/- be accepted.
In view of the difference of opinion between the Tender
Committee and the Minister, the matter was referred to the Chief
Secretary, the Finance Department and the Law Department who
were all of the opinion that the matter should be referred to the
High Court as to whether the valuation made by the Tender
Acceptance Committee can be relied upon or not. But when the
file went to the Chief Minster he directed the acceptance of bid at
the level of the Minister himself.
At this juncture, since the time stipulated for compliance
by the High Court had expired, the respondent\026State made an
application for extension of time before the High Court. In the
said application the State had given the particulars of the bids
received by it and the reasons for not finalising the tender. The
Learned Single Judge while considering the said application for
grant of extension of time on 22.7.2002 took a decision to do
King Solomon’s justice and passed the following order :
"i) The settlement of the weigh bridge at
Mookyniang, Jaintia Hills be made to and in
favour of three bidders who bidded the same
amount in the following manner.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
ii) For the first year, the settlement be made
in favour of Smt. Nala Niangti,
iii) For the second year, the said weigh
bridge be settled in favour of Shri Arvotki
Sumer and
iv) For the third year, the weigh bridge be
settled to and in favour of Shri Sophiker
Pariat.
v) The aforesaid period of three years would
start from the date of issuance of necessary
orders by the competent authority for which
three weeks time is granted to the said
Applicants to do the needful for the ends of
justice."
Being aggrieved by the said arrangement made by the
learned Single Judge one of the aggrieved parties by name
Mr.Sastian Dkhar preferred a writ appeal against the said order of
the learned Single judge. In the said appeal the Division Bench of
the High Court set aside the order of the learned Single Judge
dated 22.7.2002 holding that the learned Single Judge could not
have exercised the power of settling this right by himself in an
application filed by the Government for extension of time. It also
held that positive directions issued by the learned Single Judge is
contrary to the directions issued previously, therefore, while
setting aside the order of the learned Single Judge, the Appellate
Bench granted three weeks’ further time to the respondent
authorities for settling the matter in accordance with the
directions issued by the High Court.
After the matter came back to the authorities, the authorities
decided to accept the tender of the 4th respondent herein which
was for a sum of Rs.40,29,600/- per annum on the ground that the
said respondent had proved his financial capacity while the other
two equivalent bidders had not done so.
Being aggrieved by the aforementioned order granting the
lease in favour of the 4th respondent the other 2 tenderers who
had offered identical amounts preferred two writ petitions before
the said High Court. The main contention of the writ petitioners
in the said petitions was that the acceptance of the bid of the 4th
respondent which was identical with theirs solely on the ground
of financial capacity was contrary to the guidelines.
Learned Single Judge by his judgment dated 7.11.2002
dismissed the said writ petition. The court held that the decision
of the authorities to choose the 4th respondent on the ground that
financial soundness is a relevant consideration for the purpose of
assessing suitability of a tenderer for the settlement of the
contract.
At this stage the appellant who had bid for Rs.62,70,797/-
having come to know of the acceptance of the lesser bid of the 4th
respondent filed a writ appeal against the judgment of the learned
Single Judge dated 7.11.2002 whereby he had approved the
acceptance of the offer of 4th respondent. It was the contention of
the appellant in the appeal filed by him that after the ofference of
the bids no intimation of the acceptance of the bid of any of the
persons was made public and since his bid was higher than that of
the 4th respondent and he being otherwise qualified, his bid ought
to have been accepted since no other qualified and higher bidder
had come forward making any such demand. The said appeal of
the appellant was opposed by the 4th respondent and the State on
the ground that the appellant not having challenged the
acceptance of the bid of 4th respondent before the Single Judge
cannot be permitted to challenge the same for the first time by
way of a writ appeal, hence, his appeal being not maintainable,
the same should be rejected. The Appellate Bench of the High
Court rejected that objection as to the maintainability of appeal
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
by a person who had not filed a writ petition and decided the
appeal on merit but upheld the judgment of the learned Single
Judge whereby the challenge to the acceptance of the bid of the
4th respondent was rejected. It is against the said judgment of the
Appellate Bench the appellant is now before us in this appeal.
Mr. R F Nariman, learned senior counsel appearing for the
appellant submitted that the finding of the learned Single Judge
that concept of predatory or speculative pricing applied to the
contract in hand is wholly erroneous. It is the argument of the
learned counsel that this is not a contract for supply of goods. He
stated this contract also did not involve public distribution system
or for that matter even supply of essential commodity. He
submitted this contract had no effect on the pricing of the coal
also which was the main good carried by the vehicles in this
region, hence this contract had no public interest involved except
the revenue of the State. He contends that this is a pure and
simple contract of leasing out a weigh bridge which is the
property of the State Government where one and the only criteria
for consideration would be the interest of revenue of the State.
He submitted the valuation made by the Transport Department is
only one of the materials to be relied upon for the purpose of
knowing the probable value of the lease and cannot be the sole
basis when there are other reliable materials which showed that
the volume of transport on the concerned route was much higher.
It is also contended even otherwise from the material on record
the Tender acceptance Committee was justified in coming to the
conclusion that the value of the tender would be as much as Rs.2
crores. In such a situation the respondent-State could not have
fixed the value of tender at Rs.40,29,600/- merely because the
High Court in the earlier judgment considered the said value as
reasonable value. It is the submission of the learned counsel that
fixation of value of the contract is within the jurisdiction of the
authorities concerned and the court ought not to have embarked
upon the exercise of this nature with the limited material
available to it. He also submitted that the Minster was wholly
wrong in coming to the conclusion that the Government was
bound by the figure of Rs.40,29,600/- merely because it was the
opinion expressed by the court.
Mr. Vijay Hansaria, learned senior counsel appearing for
the 4th respondent firstly contended that the appellant’s appeal
before the Division Bench was not maintainable inasmuch as he
had not challenged the order of acceptance of the 4th respondent’s
bid by filing a writ petition and it is only when the writ petitions
filed by 2 other bidders came to be rejected the appellant who
was sitting on fence all the time chose to file an appeal for the
first time as a speculatory litigation. He further submitted that the
learned Single Judge was justified in coming to the conclusion
that the reasonable bid value of the contract was Rs.40,29,600
which was an amount arrived at by the learned Judge on the basis
of the report of the Inspection Inspectorate of Motor Vehicles. He
also justified the finding of the learned Single Judge that any
amount over and above the said figure offered as a bid would be
predatory and speculatory in nature which would encourage
bidders to form cartels to oust the other genuine bidders from
offering their bids and would also amount to encouraging the
monopolistic trade practice. He further submitted that accepting
highly inflated bid would not be in public interest because to
recover the such huge amount the successful bidders would
indulge in malpractice of coercing the transporters to pay more
fees for the weighment of their vehicles. He also submitted that
the State while offering its largesse to public should not have
monetary consideration as the sole criteria but should also bear in
mind the interest of public at large. In the said view of the matter
the learned counsel submitted that the acceptance of bid of the 4th
respondent was justified.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
From the arguments addressed by the learned counsel
appearing for the parties, many issues arise for our consideration.
In this process of consideration of the issues involved in this
appeal, we will first consider whether the appeal filed before the
Appellate Bench of Guwahati High Court was maintainable or
not. It is an admitted fact that after the Single Judge by his order
dated 15.3.2002 set aside the earlier acceptance of bid on the
ground that the said bid was predatory or speculatory in nature a
fresh tender was called for and the appellant was one such person
who offered his bid. It is also not disputed that between the
appellant and respondents 4, 5 and 6 appellant’s bid is very much
higher. It is the case of the appellant which, of course, is disputed
by the other side that he had no knowledge whatsoever of any
one’s bid being accepted much less his bid being rejected.
Therefore, when he came to know of the acceptance of the bid of
the 4th respondent for the first time after the disposal of the
second round of litigation by the learned Single Judge, he
approached the Appellate Bench of the High Court because
rejection of his bid in preference to the bid of the 4th respondent
was arbitrary and contrary to law. The Appellate Bench of the
High Court has thought it fit to entertain the appeal of the
appellant by rejecting the objections raised by the 4th respondent
and the State. We find no reason to interfere with this finding as
to the maintainability of the appeal because if really the bid of the
appellant was rejected erroneously and the appellant had no
knowledge of such acceptance or rejection, the appellant has
every right to challenge the said rejection of his bid and also the
acceptance of the 4th respondent’s bid. And if it is a fact, which
we think it is, that the appellant had no knowledge of the same till
the disposal of the writ petitions of other two bidders, the
appellant was justified in filing the appeal against that judgment
because filing of another writ petition would only be an exercise
in futility.
The next question for our consideration is : whether the
value of the contract fixed at Rs.40,29,600/- by the High Court as
per its order dated 15.3.2002 was a final value or whether it was
open to the State to have re-fixed that value of contract on the
basis of fresh material available before it. Herein we must notice
that while setting aside the contract in the first round of litigation
the High Court in its order dated 15.3.2002 specifically directed
thus :
"It is, however, made clear that the
State-respondents shall take into
consideration the report submitted by
the Enforcement Inspectors regarding
the average number of trucks loaded
(including coal loaded trucks) and
unloaded plying from Jaintia Hills to
Guwahati and vice-versa, per day as
seen in the document marked as
Annexure-V to the writ petition while
making the re-tender of the said tender.
Liberty is also granted to the State-
respondents to re-examine and reassess
the value of the tender keeping in view
the observations of this Court in this
judgment." (emphasis supplied)
It is seen from the above directions issued by the Court that
the High Court left open the question of re-assessing the value of
the tender to the State Authorities. However, it directed them to
take into consideration the report submitted by the Enforcement
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
Inspectors of Motor Vehicles Department. It did not prohibit the
said authorities from taking into consideration any other material
which was also available. Therefore, in our opinion, it was open
to the authorities to rely upon such other material as was
available to it while re-assessing the value of the tender but, of
course, it also had to consider the report submitted by the
Enforcement Inspectors. By its order the High Court had also not
specifically held that the reasonable assessment of the tender
value made by it at Rs.40,29,600/- was a conclusive value and the
authorities were bound by the same, because if it was so then
there was no need to give the direction to the State authorities to
make a re-assessment on the material available to it. We think it
is clear from the above judgment that the reasonable assessment
of the tender value made by the High Court at Rs.40,29,600/- was
only a tentative expression of opinion. That apart fixation of a
value of the tender is entirely within the purview of the executive
and courts hardly have any role to play in this process except for
striking down such action of the executive as is proved to be
arbitrary or unreasonable. From the above findings of ours, it is
clear that the Tender Acceptance Committee had the necessary
authority to re-assess the value of the tender which it did by
fixing the value at Rs.2 crores. This value was fixed after taking
into consideration the report submitted by the Enforcement
Inspectors as also the report and data supplied by the PWD and if
the said authorities thought it fit and safe to rely upon the data
supplied by the PWD authorities we can find no fault with the
same. In this context in our opinion, the Minister who disagreed
with the recommendation of the Tender Acceptance Committee
was in error in coming to the conclusion that the figure of
Rs.40,29,600/- fixed by the learned Single Judge in his order was
a final value and the State Authorities had no right to differ from
the same.
The next question for our consideration is : does the
principle of predatory pricing apply to the contract of the like
involved in this appeal ? The learned Single Judge who applied
this principle had obviously in mind the law laid down by this
Court in the case of Union of India & Ors. vs. Hindustan
Development Corporation and Ors. (1993 (3) SCC 499) wherein
this court did discuss the principle of predatory pricing in the
context of carteling or creating monopolistic rights. The facts
involved in the said case pertain to formation of a cartel by some
of the manufacturers and under pricing their products which on
facts of that case was held to be amounting to unfair trade
practice. In our opinion, principles discussed in the said case do
not apply to the facts of this case.
It goes without saying that the Government while entering
into contracts is expected not to act like a private individual but
should act in conformity with certain healthy standards and
norms. Such actions should not be arbitrary, irrational or
irrelevant. The awarding of contracts by inviting tenders is
considered to be one of the fair methods. If there are any
reservations or restrictions then they should not be arbitrary and
must be justifiable on the basis of some policy or valid principles
which by themselves should be reasonable and not
discriminatory. [See para 7 of Hindustan Development case
(supra)]. The said judgment also states that any act which
excluded competition from any part of the trade or commerce by
forming cartels should not be permitted.
Probably from the above observations of this Court in the
case of Hindustan Development (supra) the learned Single Judge
in this case came to the conclusion that in the instant case any
offer made which is over and above the realistic value of the
contract would be predatory or speculatory in nature. The
question for our consideration is : Is there any factual basis for
coming to this conclusion that the bids offered in this case were
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
either predatory or is the bid of a cartel. For this purpose, we will
now examine what is the nature of contract involved in the
present case.
The respondent-State owns a weigh bridge at Morkjniange.
The income from this weigh bridge is received from the fees
charged for weighment of trucks which pass through route in
which this weigh bridge is situated. We are told that these trucks
mostly carry coal from Jaintia Hills to Guwahati. As per the
notification the person operating the weigh bridge can only
charge a sum of Rs.30/- for a loaded truck and Rs.10/- for an
unloaded truck. Therefore, the fee to be collected from the
transporters for weighment of their vehicles is fixed and it does
not vary with the amount of bid offered by the contractor. This is
not a contract of supply where a contractor by manipulating the
price may cause loss to public at large. This is not a contract
which would have any effect on the price of coal, since
weighment charges are fixed by the Government and the
contractor has no right to increase the same. Payment of bid
amount is purely a matter between the contractor and the State.
As a matter of fact obtaining higher revenue by accepting the
eligible highest bid would only be in public interest because State
stands to gain more revenue. The offering of the bid after
knowing the commercial value of the contract is a matter left to
the business acumen or prudence of the tenderer. No third party’s
interest is involved in such contract. Therefore, in our opinion,
application of principle of predatory pricing is wholly alien to
this type of contract. Mere offer of a fancy or high bid by itself
does not make the bid a predatory bid in this type of contract. If
the State decides to give its largesse to public it has an obligation
to see that it fetches the best possible value for the same,
provided otherwise it does not in any manner affects the rights of
other citizens. No bidder has any right in law to demand the State
to give away its largesse for an amount which he considers to be
reasonable even when there are bidders willing to pay more for it.
Principal of monopoly also does not come into play in these types
of contracts.
Therefore, in our opinion, the High Court was in error in
coming to the conclusion that because it felt the fair value of the
contract is Rs.40,29,600/- any bid over and above that would be
predatory.
Learned counsel for the 4th respondent had contended that
acceptance of speculatory bid can lead to abandonment of the
contract by such speculative bidders which would cause loss to
the State. On facts, this argument has no legs to stand. We find
from the terms of the contract that the successful bidder has to
deposit, apart from security amount, 6 months equivalent of
monthly lease amount in advance and the balance term of the
contract will be permitted only if the said contractor deposits in
advance the sum equivalent to the next six months lease amount
in advance. Hence the possibility of the contractor defaulting in
payment of lease amount is remote. Be that as it may State may
consider obtaining an indemnity bond from the successful bidder
to indemnify the State Government from any loss that it may
suffer because of the act of the contractor apart from the advance
amount payable as per the terms of the contract.
Therefore, we are of the opinion that the rejection of the bid
of the appellant or for that matter other bids which were more
than 4th respondent’s bid, is unsustainable so also the judgment of
the two courts below which have upheld the same.
It is seen from the records that pursuant to the acceptance of
the bid of the 4th respondent on 19.9.2002 the 4th respondent has
been operating the weigh bridge, and the tenure of the contract is
to come to an end in the normal course on 18.9.2004. Since the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
acceptance of the 4th respondent’s bid is held to be illegal by us
the same has to be set aside but we will not issue directions to the
respondent State Government to accept the bid of the appellant
because in our opinion it is in the interest of justice that a fresh
tender should be called for and based on the bids received
pursuant thereto, and in accordance with the guidelines, a fresh
contract will have to be entered into by the State Government in
regard to this weigh bridge. At the same time since this process is
likely to take sometime we do not want to create a void by
directing the 4th respondent to hand over possession of the weigh
bridge to the Government at this stage more so because of the fact
under the guidelines applicable the 4th respondent must have paid
the lease amount upto the period of 18.9.2004. Therefore we
direct the respondent State to call for fresh tenders and take a
decision in regard to acceptance of a fresh bid and grant new
contract on or before 1.7.2004. Till such time the 4th respondent
will be permitted to operate the weigh bridge and on the
acceptance of the tender by 1.7.2004 new contractor whose bid is
accepted shall be entitled to run the same for the period agreed
therein. On the effective termination of the contract of the 4th
respondent w.e.f. 30.6.2004 if any excess amount is paid by the
4th respondent the same shall be refundable to him by the
respondent Government.
For the reasons stated above this appeal succeeds. The
impugned orders of the courts below are set aside as also the
contract awarded to the 4th respondent by the respondent-State as
per its order dated 19.9.2002. The appeal is allowed.