Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
PETITIONER:
STATE OF MADHYA PRADESH AND ORS.
Vs.
RESPONDENT:
ORIENT PAPER MILLS LTD.
DATE OF JUDGMENT07/12/1989
BENCH:
PUNCHHI, M.M.
BENCH:
PUNCHHI, M.M.
RANGNATHAN, S.
CITATION:
1989 SCR Supl. (2) 436 1990 SCC (1) 176
JT 1989 (4) 495 1989 SCALE (2)1290
ACT:
Administrative Law: Promissory estoppel--Industrialists
generating power through their own new generating
sets--Assurance given by Government--Electricity duty exemp-
tion--Effect of.
Constitution of India, 1950: Article 136--Interference
with factual findings--Only in exceptional cases.
Madhya Pradesh Electricity Duty Act, 1949: Section
3-B-Electricity duty--Exemption--Notification--High Court
granting relief without ordering issuance of
notification--Whether amounts to transgression.
HEADNOTE:
In its industrial policy, the State Government declared
on 1.8.1961 that where power has to be generated by indus-
trialists themselves, exemption from electricity duty would
be granted for a period of five years from the date of plant
goes into production, and that the concession would be
applicable only to new generating sets installed during the
Third Plan period.
The Respondent indicated to the Government on 3.5.1955
that about 5000 K.W. of electricity would be required by it
to run its paper plant and that it would by itself make
arrangements for obtaining the necessary generating equip-
ment. It also applied for import licence for the import of a
production plant as also a power plant to run it. The import
licence was granted and the Respondent started negotiation
with the foreign supplier. Since the price had gone up it
was rather impossible for the Respondent to import both the
production plant and the power plant, and if the power plant
was not purchased along with the production plant, it would
make the project unsound. Hence the Respondent was in two
minds whether to have the power plant or not. Meanwhile, the
above said industrial policy was announced and the Respond-
ent on installation of the power plant was able to start its
production w.e.f. 16.2.1965.
Thereafter to formalise the matter, the Respondent corre-
sponded
437
with the appellant for the grant of the requisite exemption,
which was rejected, and the Respondent approached the High
Court by way of a petition under Articles 226 and 227 of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
Constitution of India. The High Court held that the Peti-
tioner was entitled to invoke the doctrine of promissory
estoppel in order to claim exemption from payment of elec-
tricity duty for a period of five years from 16.2.1965 in
terms of the assurance of the State Government dated
1.8.1961.
Against this order of the High Court the State has come
in appeal by Special Leave.
On behalf of the appellant-State it was urged that there
was no occasion to invoke the doctrine of promissory estop-
pel, since the Respondent had not in any manner acted on the
assurance of the Government to its own prejudice but on its
own it was taking steps to set up a generating plant much
before the industrial policy was announced.
Dismissing the appeal, this Court,
HELD: 1. Whether the respondent was of one mind right
from the beginning to set up a power plant, with or without
the assurance of the State Government dated 1.8.1961, as
asserted by the State, is neither borne out nor is the view
of the High Court arrived at from the record. On the con-
trary, the view taken is that the respondent’s indecision in
that regard ended and it became decisive on the announcement
of the assurance dated 1.8.1961. Such view of the High Court
was a possible view to be taken on the material placed
before it and the inference drawn therefrom could be that
the respondent had acted on the basis of the assurance.
[441E-F]
2. This Court ordinarily does not interfere with factual
findings arrived at by the High Court and this case has not
been shown to be an exception. The view taken by the High
Court was unexceptional warranting it to be left uninter-
ferred with. [441F]
3. Without commanding the State Government to issue such
a Notification, the High Court has granted relief to the
respondent to which there was no bar. Accordingly no provi-
sion of Madhya Pradesh Electricity Duty Act, 1949 or any
other law can be said to have been transgressed. [442A]
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No 498 of
1975.
438
From the Judgment and Order dated 31.7.1974 of the
Madhya Pradesh High Court in Misc. Petition No. 3 16 of
1973.
Prithvi Raj, Satish K. Agnihotri and Ashok Singh for the
Appellants.
Shankar Ghosh, Vivek Gambhir and Parveen Kumar for the
Respondent.
The Judgment of the Court was delivered by
PUNCHHI, J. This is an appeal by special leave against
the judgment and order of the High Court of Madhya Pradesh
at Jabalpur whereby the petition under Articles 226 and 227
of the Constitution of India preferred by Orient Paper Mills
Ltd., the sole respondent herein, was allowed and sequally
the order dated 15.3.1973 of the State Government declining
to grant the respondent exemption from payment of electrici-
ty duty for the period from 16.2.1965 to 15.2.1970 and
pursuant demand notices dated 20.3.1973 and 3.4.1973 were
quashed. The aggrieved State of Madhya Pradesh and its
concerned Officers are the appellants challenging the same
The respondent had need to go to the High Court to have
an assurance dated 1.8.1961 regarding exemption from payment
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
of electricity duty given by the State of Madhya Pradesh in
its declared industrial policy observed, which may well be
reproduced here at the outset:
"Where power has to be generated by industri-
alists themselves, exemption from electricity
duty shah be granted for a period of five
years from the date of plant goes into produc-
tion. The concession shall be applicable only
to new generating sets installed during the
Third Plan period."
Factually it was not disputed before the High Court,
that the case of the respondent squarely fall within the
scope of the assurance reproduced above since the industrial
plant of the respondent had gone into production w.e.f.
16.2.1965, the generating set put up was new, and had been
installed during the Third Plan period. To formalise the
matter, the respondent had corresponded with the Government
for the grant of the requisite exemption. Since the same was
rejected and demands for payment of electricity duty creat-
ed, the High Court was requested to issue suitable writs,
directions and orders cancelling the
439
aforesaid orders and demand notices and granting exemption
from payment of electricity duty in respect of electricity
self-generated by the respondent during the said period of
five years, and also commanding the State to carry out the
assurance and promises made in the said industrial policy
dated 1.8.1961 extracted above and then requiring the State
to issue a Notification under Section 3-B of the Madhya
Pradesh Electricity Duty Act, 1949 granting exemption or
exception to the respondent from payment of electricity duty
and other allied consequential reliefs.
Before the High Court voluminous documentary evidence
was given by the parties in support of their respective
pleadings. The High Court, on consideration of the entire
material placed before it, spelled out a promissory estoppel
in favour of the respondent and concluded as follows:
"To conclude, we are of opinion that the
petitioner is entitled to invoke the doctrine
of promissory estoppel in order to claim
exemption from payment of electricity duty for
a period of five years from 16.2.1965 to
15.2.1970 in terms of the assurance of the
State Government, dated 1.8.1961. Of course,
as indicated earlier it is not for us to issue
any writ directing the State Government to
grant the petitioner exemption in terms of S.
3-A (vii) or Section 3-B of the M.P. Electric-
ity Duty (Amendment) Act, 1949. But in view of
the unambiguous and unequivocal assurance
given by the State Government on 1.8.1961 we
can certainly quash the order of the State
Government, dated 15.3.1973 as also the demand
notices, dated 20.3.1973 (Petitioner’s Annex-
ure-48) and dated 3.4.1973 (Petitioner’s
Annexure 50) and leave the matter at that. It
would be for the Government to work out its
own course of action on that basis. ’ ’
Mr. Prithvi Raj, learned counsel for the appellant urged
that on the facts and circumstances of the case there was no
occasion to invoke the doctrine of promissory estoppel. It
was asserted that though the industrial policy was published
by the State Government on 1.8.1961 containing the assurance
extracted above, the respondent had not in any manner acted
thereon to its own prejudice, but had rather on its own been
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
taking steps to set up a generating plant much before the
industrial policy was announced and had factually set up the
generating plant as per its earlier resolve. The facts
highlighted were that the
440
respondent Paper Mill, had been set up at Amlai in Vindhya
Pradesh, when a Part-C State under the administration of the
Central Government. It had in its application dated 3.5.
1955 to the Government indicated that about 5000 K.W. elec-
tricity would be required by it to run its paper plant and.
it would by itself make arrangements for obtaining the
necessary generating equipment. It appears that the State
Government had at that time its oven project in view for
installing a power plant. On that basis some correspondence
ensued between the respondent and the State Government with
regard to its annual requirement of electricity. That exer-
cise was abandoned for some reasons which are not relevant
here. Thereafter the respondent applied for import licence
for the import of a production plant as also a power plant
to run it. The respondent was granted an import licence on
the strength of which it started negotiation with an Ameri-
can supplier. While negotiations were in process the Ameri-
can supplier increased the price. It became impossible for
the respondent to import the production plant and the power
plant within the funds allotted to it by the World Bank and
in these circumstances, the American suppliers advised the
appellant to drop procurement of the power plant. At the
same time the American supplier warned the respondent that
if the power plant was not purchased along with the produc-
tion plant, it would make the project unsound and it would
not be able to fulfil its guarantees as desired by the
respondent. The respondent in these circumstances became of
two minds, whether to have the power plant or not. When it
was in that state of mind, the industrial policy was an-
nounced by the Government on 1.8.1961. Thereafter, on
21.8.1961, the respondent applied to the Government of India
for sanction of permission to import 3.5 million dollar
worth goods more than the sanctioned amount. Finally, the
respondent with the consent of the Government of India and
with the aid of the World Bank was able to import the pro-
duction plant and the power plant and after its installation
was able to go on production w.e.f. 16.2.1965.
The course of the events set out earlier were not dis-
puted as such by the appellants before the High Court but it
was maintained as now before us, that the respondent would
have on its own gone on to install the power plant even
without the announcement of the industrial policy dated
1.8.1961. Additionally, it was maintained, in the like
manner, that the respondent had not acted to its prejudice
on the basis of the aforesaid assurance dated 1.8.1961 and
so that doctrine of promissory estoppel was not invokable.
The defence of the State thus raised was rejected by the
High Court in the following words:
441
"We have already dealt with that aspect earli-
er and we have already held that the petition-
er’s action in setting up a power plant was
postponed on account of certain circumstances
and ultimately on the advise of the manufac-
turers who refused to continue the guarantee,
the petitioner decided to set up its own power
plant. In the meantime, the assurance of the
State Government, dated 1.8.1961 had already
been given and the petitioner’s action in
making a final decision to set up its own
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
power plant can be directly connected with the
State Government’s assurance dated 1.8. 1961.
No sooner the petitioner took the final deci-
sion in that behalf, it applied to the State
Government for grant of an exemption, although
that application was premature, because the
petitioner’s paper mill had not started func-
tioning. As such, the petitioner would cer-
tainly be entitled to claim exemption in terms
of the assurance of the State Government dated
1.8.1961 with effect from the date the paper
mill started functioning, namely, 16.2.1965
and the exemption would last for a period of
five years upto 15.2. 1970."
Whether the respondent was of one mind right from the
beginning to set up a power plant, with or without the
assurance of the State Government dated 1.8.1961, as assert-
ed by the State, is neither borne out nor is the view of the
High Court arrived at from the record. Rather, on the con-
trary, the view taken is that the respondent’s indecision in
that regard ended and it became decisive on the announcement
of the assurance dated 1.8.1961. Such view of the High Court
was a possible view to be taken on the material placed
before it and the inference drawn therefrom could be that
the respondent had acted on the basis of the assurance. The
effort here to re-do the exercise in this regard must inevi-
tably fail, for this Court ordinarily does not interfere
with factual findings arrived at by the High Court and this
case has not been shown to us to be an exception. In this
situation, the view taken by the High Court was unexception-
al warranting it to be left uninterferred with.
Some attempt was made by learned counsel for the appel-
lant to contend that the doctrine of promissory estoppel
could not be pressed into service to command the State
Government under Section 3-A (vii) (before its amendment)
and Section 3-B of the Madhya Pradesh Electricity Duty Act,
1949 (as amended) to issue a Notification exempting the
respondent from payment of electricity duty. The
442
answer to this argument is available in the conclusion
arrived at by the High Court extracted above. Without com-
manding the State Government to issue such a Notification,
it has granted relief to the respondent to which there was
no bar. Accordingly, no provision of Madhya Pradesh Elec-
tricity Duty Act, 1949 or any other law can be said to have
been transgressed. We thus reject this argument too.
Thus for the foregoing reasons this appeal fails and is
hereby dismissed. No costs.
G.N. Appeal dis-
missed
443