Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 16
PETITIONER:
GHULAM DIN BUCH ETC.ETC.
Vs.
RESPONDENT:
STATE OF JAMMU & KASHMIR
DATE OF JUDGMENT: 03/04/1996
BENCH:
HANSARIA B.L. (J)
BENCH:
HANSARIA B.L. (J)
RAY, G.N. (J)
CITATION:
1996 AIR 1568 JT 1996 (4) 515
1996 SCALE (3)271
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
HANSARIA. J.
The 1975 accord with Sheikh Abdullah saw a dynamic
person from Ladakh coming to the fore. He was made a
Minister. He wanted to do many things for Ladakhis. One of
the projects which the Minister (Shri Sonam Narboo) wanted
to get fructified was electrification of tehsils of Leh and
Kargil. The fund for the same was to be provided by the
Central Government under Rural Electrification Scheme. To
see that the scheme was implemented within time, a separate
Electric Construction Division was created at Leh. This was
in February 1977. An Executive Engineer was put in charge of
the Division and he was one N.A. Salaria, who was selected
because of his dashing character which had come to light by
his getting established a generating station at Choglamsar
within record time. The electrification scheme was taken up
after Shri Narboo, who was Minister for Works, Power,Tourism
and Ladakh Affairs, had toured the area from 5.6.1976 to
13.7.1976. The idea was to electrify areas around Leh first
for which it was felt that 3100 bamboo poles would be
required. It was also noted that from September onwards the
fruit session starts and all available transport is diverted
to carry fruits to the plane and no transport is available
for Ladakh. This apart, food grains are required to be
stored in Kashmir valley and Ladakh to cater to the needs of
the people during winter season. This being high priority
ares, the concern of the Government is to see that this work
does not suffer for want of transport vehicles.
2. It is in the aforesaid situation and scenario that
Salaria took up work in right earnest from first week of
September 1977, after the Chief Engineer, Electric
Maintenance and RE, Kashmir had toured the two tehsils from
17th to 23rd August, 1977. The work was to arrange transport
vehicles to carry required number of poles to Leh before
November, after which Ladakh region becomes virtually
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 16
inaccessible. The allegation is that the situation permitted
persons in the Power Department to take advantage of the
same and a conspiracy was hatched to give contract of
transportation to such persons who showed their willingness
to share the booty with the officers. According to the
prosecution, these persons included even the highest officer
of the Power Department, namely, Power Development
Commissioner and it went down to the Sectional Officer. The
conspiracy came to the notice of none else than Shri Narboo
as some complaints were received by him in November, 1977
regarding giving of contract of transportation to private
firms on per kilometer per pole basis and the poles being
also of sub-standard quality. He wanted wanted information
about the same by writing a D.O. letter to the Power
Development Commissioner on 18.11.1977 followed by a
reminder on 5.12.1977. After receipt of reply, the Minister
asked for a report from the Chief Engineer. On receipt of
the same, he felt the matter required deeper probe and
appointed Qazi Mohd. Afzal as Enquiry Officer in December,
1977. His report was submitted on 3.4.1978 which highlighted
some serious irregularities. After considering the report,
the Government entrusted the matter for further probe to the
Anti-Corruption Organization set up under the (Jammu &
Kashmir) Prevention of Corruption Act, 2006, (hereinafter
the Act). A case was accordingly registered on 26.4.1978 and
a Senior Superintendent of Police, one Shri S.S. Ali, was
entrusted with the investigation, who after completion of
the same and after obtaining sanction from the Government,
submitted charge-sheet on 10.8.1978 against 42 accused.
3. It the trial which commenced, after discharge of one (a
labourer), 65 witnesses were examined by the prosecution and
2 by the defence. Great number of documents were also
exhibited. The trial court by its very exhaustive judgment
dated 29.9.1981, which runs into 420 pages, acquitted 11
persons including Power Development Commissioner, Shri
Ahangar and Chief Engineer, Shri Naqash; and convicted 30
under various sections of law including section 120-B Ranbir
Penal Code and section 5(2) of the Act.
4. On appeal being preferred, the High Court of Jammu &
Kashmir acquitted 19 more including Superintending Engineer
Shri Kaul and sustained conviction of 11 persons who are the
appellants in the 10 appeals at hand. Of them, 7 are
officials and 4 are contractors. The officials are : (1)
Executive Engineer, N.A. Salaria; (2) Assistant Engineer,
G.D. Buch; (3-4) two employees of the Chief Engineer’s
office - T.K. Kantroo and V.K. Razdan; (5-7) three officers
who had passed the poles-they being H.L. Dhar, Farooq Ahmed
Zadoo and Mohd. Siddiq. The four contractors are; (1)
Hafeezullah; (2) Farooq Ahmed Qurashi; (3) Abdul Rashid
Khan; and (4) Peer Gulam Nabi.
5. The appeals being by the convicted persons and there
being no appeal against acquittals either by the trial court
or the High Court, it is apparent that we have to see
whether the persons ultimately convicted by the High Court
had been rightly found guilty of the charges, inter alia, of
conspiracy. We have mentioned about this aspect at the
threshold because the principal charge being of conspiracy
and that too involving highest officer of the Power
Department, and he having been acquitted even by the trial
court along with the Chief Engineer, followed by acquittal
of Superintending Engineer by the High Court, we shall have
to see whether the links which have been left in the chain
of conspiracy do leave a thread to piece together the
actions of the convicted appellants so as to establish a
conspiracy by them.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 16
6. Many of the learned counsel appearing for the
appellants made a grievance that the State has allowed
higher ups to remain unavailable to this Court and has
thought it fit to press the case against small fry.
According to them if there was a conspiracy at all, the same
could not have been worked out without the connivance of at
least the Chief Engineer and Superintending Engineer. Shri
Handoo, appearing for the State, felt some what
uncomfortable at the non-filing of the appeals by the State,
first in the High Court and then in this Court against the
acquittals of higher-ups. But then, no appeal having been
filed, the ultimate submission was that the core of the
conspiracy had not been adversely affected by the acquittals
and the evil design resulting in causing wrongful loss to
the State Exchequer by causing wrongful gain to the
contractors and themselves has to be punished. Differently
put, the submission was that the inner circle of the two
concentric circles has not been damaged because of the outer
circle getting wiped out. According to Shri Handoo,
therefore, the acquittals of the higher-ups cannot per se
see the acquittals of the appellants.
7. To appreciate the aforesaid submission, we have
basically to note the key role assigned to appellant Salaria
who, according to the prosecution, was duly supported by
appellant Buch. These two according to Shri Handoo were the
main actors in the drama, which was enacted about two
decades back in an area which had not seen a conspiracy of
the type at hand causing loss of lacs to the State
Exchequer, which had drawn attention even of the State
Cabinet.
8. Loss of lacs (the total loss to the State Exchequer
having been estimated at Rs.1,62,117.89) was undoubtedly of
great concern two decades earlier and we can appreciate the
great consternation this case had caused in the State
requiring appointment of a senior Sessions Judge to
constitute the Special Court under the Act to try the case.
The heroic effort made by the prosecution to bring home the
guilt also speaks for itself. The lapse of time, therefore,
cannot be allowed to come to the aid up the appellants, as
has been one of the submissions on behalf of the appellants,
based on the fact of long suffering already undergone. We
would, therefore, examine the materials on record
objectively without being influenced by the hardship
undergone, which could be taken note of, if need would
arise, while dealing with the question of sentence. May it
be stated that we would undertake this exercise as we are
satisfied about the core of conspiracy, referred to by Shri
Handoo as inner circle of the conspiracy, having remained
unaffected despite aforesaid acquittals, as would appear
from what is being state later.
9. The first and foremost question which neeeds to be
looked into is whether the acts attributed to the appellants
were at all meant to cause wrongful loss to the State by the
alleged conspiracy. Almost all the learned counsel appearing
for the appellants were at pains to convince us that the
arrangement which was made with the contractors to carry
poles was not at all aimed to cause any wrongful gain to
them inasmuch as payment on the basis of per kilometer per
pole was not a new device adopted in 1977 for the first
time, but that had been in vogue at least since 1971. This
apart, the rates which were agreed upon was also quite
reasonable. The same was 30 or 35 paise per k.m. per pole
depending upon the size, which is in the close neighborhood
of what had been paid even in 1976 for carving poles to Leh
itself by the arrangement finalised by Shri Bassu, who was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 16
the immediate predecessor of Salaria. Shri Handoo seriously
contested this claim and urged that per k.m. basis had been
adopted for the first time in 1977 for long haulage; in
earlier years this was being accepted for carrying materials
to short distances. As to the reasonableness of rates, the
State’s case is that the amount agreed to be paid was almost
three times of what was being paid earlier.
10. We would, therefore, first examine the aforesaid
crucial question. We would then see whether the giving of
contract at the lowest tendered rate made any difference.
Reasonableness of the contractual rates.
11. There is no dispute before us that the Road Transport
Corporation (RTC) functioning in the State of Jammu &
Kashmir, which owns a fleet of vehicles, used to charge on
the basis of per truck, and not per k.m. This rate was Rs.
1400/- in the relevant year. The private transport carriers
also used to charge the same amount per truck. But then, the
number of poles to be carried by these trucks to a place
like Leh used to be around 25. This made a difference,
according to the learned counsel for the appellants, as the
number of poles carried by the trucks which had been engaged
by the contractors at hand used to be even 70. Shri Handoo
contended that though the number of poles carried were more,
the same did not really matter inasmuch as total cft (cubic
feet) transported was not in any significant manner more
than carried by the trucks of RTC or private transport
owners because each of those trucks used to carry about 280
cft, whereas from Statement No.2 filed by Shri Thakur it
would appear that the cft carried in the present case ranged
between 200 to 300, though in some cases it went upto 400
also. As to the contention that the rates of carriage per
pole came to 30.49 paise insofar as the transportation done
by Shri Bassu is concerned, Shri Handoo’s submission was
that this calculation as put on record on behalf of the
appellants is wrong. As per his contention the per pole rate
then was 9.36 paise as mentioned in the Charge-Sheet filed
in the case, a copy of which is from pages 1 to 86 of Volume
I of the Paper Book prepared by the appellants. This figure
has been mentioned at page 72 of this Volume.
12. As to the calculation furnished on behalf of the
appellants - the same being that the rate was Rs.30.49 per
pole if what was paid for the carriage to Leh in 1976 during
the incumbency of Shri Dassu - we would observe that that
calculation has been arrived at by showing, inter alia, that
the charge of loading and unloading per pole at Rs.52. When
Shri Thakur was questioned on this, the learned counsel had
referred us to the evidence of the Investigating Officer
(I.O.) finding place at page 230A of Volume IV. A reference
to that statement showed that the unloading charge came to
Rs.18 per pole and the loading charge to Rs.7.80. Thus the
total came to about Rs.26 from stocking site to the truck.
The learned counsel contended that this figure had to be
doubled because the same amount used to be incurred for
bringing poles at the stocking site from the forest. The
I.O. had not said anything about this on his own, nor was he
asked any such question in cross-examination. However, to
convince us that the figure of Rs.26 is required to be
doubled, in the written submissions filed on 21st/27th
March, the learned counsel appearing for the appellants
quoted the following evidence of PW 24 Bassu:-
"Expenses for loading and unloading
as well as the manual carriage from
loading site and unloading site.
For manual carriage of the poles we
have to pay extra. By referring to
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 16
the manual charges I mean the
lifting of poles by manual
labourers from Depo site to the
truck and also their removal after
unloading to the stock site.
Q/ When you took these poles for
installation from Choglamsar you
again had to incur expenses for
manual carriage, loading and
unloading of poles? A/ Yes."
12-A. From the above quoted evidence of PW 24, it is
not known how much had been paid during his incumbency as
total loading and unloading charges. It is not known which
instances the I.O. had in mind when he had stated about
loading and unloading charges. It deserves to be pointed out
that the poles which had been carried in 1977 had basically
been supplied by Mustaq & Company and it was the obligation
of this fir, as per Shri Handoo, to bring the poles from the
forest to the stocking/dumping site. What is more important
is that the decision which was taken in the joint meeting
held on 11.5.77 was that the poles would be carried from
Kangan and Sonmarg vide page 22 of Vol.III. Mention has been
made about this in para 69 of the charge-sheet also, which
is at pages 1-86 of Volume I. But for some inexplicable
reason, the stocking/dumping site was changed and poles were
carried from Waltab which resulted in additional burden on
the State exchequer. Shri Handoo made a serious grievance
about this change of site.
13. For the aforesaid reasons, we do not accept the
contention of the appellants that loading and unloading
charges when poles were carried during the incumbency of
Shri Bassu came to Rs.52. Therefore, we would not agree that
the rate of carriage per pole in 1976 was Rs.30.49. So, we
accept the prosecution case that the rates agreed to in the
present case were not reasonable. This is almost writ large
on the face as the carrying charge per pole came to Rs.
144.60. This has come out clearly in the Office Note, which
starts at page 12 of Volume IX. (This figure has been
mentioned at page 13). In this context, it would be apposite
to refer to what has been stated in the impugned judgment of
the High Court at page 158 of the volume containing this
judgment. It has been mentioned therein that the payment
made to the contractors showed that the same per truck
worked out to Rs.10,561.66, whereas the rates of the RTC
would have been Rs.1993.57. The same would have been even
less (Rs.1839.57) if trucks of private carrier would have
been engaged.
14. Being satisfied that the rates agreed to with the
contractors were not reasonable, let it be seen whether the
higher payment was motivated or was agreed upon to take care
of the exigency of the situation. Shri Thakur strenoully
urged that implementation of the rural electrification
scheme within the time spelt out by the Minister was the
need of the hour, for which purpose a dashing character like
that of Salaria was brought to the scene. The concerned
persons were duty bound to do all that could reasonably be
done to carry poles to Leh before the onset of winter season
which cuts off Ladakh from the Valley for a long period. The
fruit growing season being round the corner and the need for
storing food for the winter being the prime concern of the
Government, the concerned officers had to implement the
scheme before the onset of winter and had no alternative but
to engage trucks made available by the contractors as the
RTC had expressed difficulty in making the trucks available.
To satisfy us that there was no evil design in giving the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 16
contract of carriage to non-transport firms, it was also
urged that the rates had been fixed after tenders had been
invited and the lowest tender was accepted.
15. Shri Handoo would not like us to accept the aforesaid
statements because, according to him, large number of
Government trucks could be used for the purpose if proper
approach would have been made. In this connection, he
referred us to the communication from the office of the
Transport Commissioner to the Investigating Officer (I.O.)
dated 24.5.78, which is at pages 269 to 270A of Volume VII.
It has been mentioned therein that the State had about 4,000
trucks operating on J&K roads only and about 400 to 800
trucks used to lie idle everyday. This letter further
informed the I.O. that no officer of the Electric Department
had approached the officer of the Transport Commissioner for
arranging trucks for the carriage of poles. The further
statement was that the Minister for Ladakh had personally
contacted the writer on 5th November, 1977 stating about the
urgent need of transporting four lac liters of High Speed
Diesel to Leh and despite shortage of time they were able to
complete the massive operation within three weeks. We have
also been referred by Shri Handoo to the evidence of PW 29,
Shri SD Shangllo, Executive Engineer, Mechanical Division,
Srinagar, which is at page 48-49 of Volume IV that their
Department was having 39 trucks in its fleet and they had
received no requisition from REC Leh for carriage of poles.
16. The aforesaid does show that no efforts had really
been made by the concerned officers to get the Government
vehicles. Shri Thakur and Shri Jain, however, urged that
before floating of tender, RTC officials had been personally
contacted by Salaria and on being stated that trucks could
not be made available "at the present time", the exigency of
situation left no alternative but to invite tenders. This
information to Salaria was in the document which is at page
256 of Volume VII. The catch, however, is that when the
signatory of this letter, Sardar Jai Singh, appeared the
witness box as PW2 he deposed that on his being approached
by Salaria on 15th September, 1977 what he had really told
was that there was no objection to supply of trucks but due
to earlier commitments with other departments trucks could
not be supplied for "2 to 3 days". Salaria however did not
come subsequently asking for trucks and so no trucks got
supplied by the RTC. Shri Thakur contended that this gloss
put by Jai Singh does not merit acceptance, as, if that was
what was really told to Salaria, the same should have found
place in the aforesaid communication. In this context we
were taken through the various questions which were asked to
Jai Singh on this aspect and which find place from pages 50
to 55 of Volume III. If the evidence of Jai Singh alone
would have been on record, we could have perhaps agreed to
what was submitted by the learned counsel for the appellants
in this regard; but having noted what had been stated by the
Transport Commissioner in the afore-noted letter and what
had been the evidence of the Executive Engineer, Mechanical
Division, we are of the view that Notice Inviting Tender
(NIT) came to be issued as pre-arranged, to which aspect of
the matter we shall advert now.
Issuance of NIT and subsequent happenings.
17. Under normal circumstances, giving of contract,
following issuance of tender notice, to the lowest tenderer
cannot be regarded as objectionable in any way. In the case
at hand, however, issuance of NIT was as per pre-arranged
plan, as already mentioned. We have said so because the same
came to be issued, not in the wake of denial, even if there
was any, by the RTC official to make their vehicles
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 16
available. That tenders would be invited had been stated
even by 8.9.77 by Much to appellants Hafeezullah and
Qurashi. The letter of Much of 8th September addressed to
Salaria, which is at pages 50 and 51 of Volume X, mentioned
that the former had negotiated with M/s. Arfa Electrical
Company (which is the name of the concern of appellant
Hafizullah) and M/s Farooq Ahmed Qurashi and they had
accepted to carry poles from Srinagar Valley to Kargil and
Leh on the condition that the rates of carriage charges
could be those which would be found lowest after floating
tender. Much further stated in the letter that the firms had
been advised to start the carriage of poles: of course, the
charges to be paid would be known after receipt of tender to
be floated in this regard. There is thus nothing to doubt
that a decision had been taken with the consent of Salaria
to float tenders even by 8th September. The contact with the
RTC official at Srinagar was on 15th and the obtaining of
the aforesaid letter from Jai Singh may, therefore, just be
a ruse for issuance of the NIT. What has made the matter
worse for the appellants is that a copy of NIT was sent even
to M/s Khan Electric and General Stores, the firm of
appellants Abdul Rashid Khan and Peer Gulam Nabi, whose
tender was ultimately accepted, which, apparently was not a
firm engaged in the business of transport.
18. Shri Handoo, therefore, rightly submitted that an
understanding had been arrived at between these
firms/persons and the tender exercise was a camouflage. This
conclusion gets fortified when it is noted that though
according to the officials, tenders had been received from
some transport carriers, to wit, Sopore Transport Workers’
Union, in fact it was not so. This has transpired from the
evidence of PWs 21 and 22, who were the Manager and
President respectively of the Sopore Transport Workers’
Union. Both of them stated that their Society had not
submitted any tender and the one which was said to have been
filed in its name had really not emanated from their office.
Even the seal put in the tender was not theirs and the
tender had not been signed by any authorised person. Shri
Thakur urged that the tender might have been signed by the
Accountant, who was in employment at Srinagar Branch, as
admitted by PW 22 had stated that the Accountant was not
authorised to submit quotations. We are inclined to think
that similar must have been the position qua some other
transporters who had purportedly submitted tenders. Shri
Handoo further contended that the NIT had been issued to
selected persons as would appear from the evidence of PW 19
(at page 220 of Volume II) to the effect that his firm had
not received any tender notice. The firm of this witness,
named Diamond Motors, was a leading transporter of Srinagar
as about 100 trucks were attached to his firm.
19. At this stage we may indicate that the firms styled as
Arfa Electrical Company and Khan Electrical and General
Stores are closely knit, as would appear from the evidence
of DW 1 Farooq Uddin, who stated about his being a partner
in the firm of Arfa Electrical Company, alongwith
Hafeezullah. Though he stated in the examination-in-chief
that his firm had nothing to do with the firm of Khan
Electric and General Stores, from the statements made by
him in cross-examination it appeared that Arfa Electrical
Company was not running a shop and that firm had no
headquarter. He further stated that Hafeezullah used to run
his father’s shop named Khan Electric and General Stores and
correspondence for Arfa Electrical used to be from the shop
of Khan Electric. He further admitted that Afra Electrical
had no registration with the Sales Tax Department. Even the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 16
bill-head of Khan Electric and General Stores was used by
Arfa Electrical after erasing the name of the former and
overwriting name of the latter. These statements do show the
inter relationship and closeness of Arfa Electrical Company
and Khan Electric and General Stores.
20 The above is not all inasmuch as there is material on
record to show that Qurashi is related to Hafeezullah being
a son of his father’s brother-in-law. This would definitely
indicate that Qurashi too had acted in concert with
Hafeezullah.
21. The aforesaid facts leave no doubt in our mind that the
exercise of issuing the NIT and accepting the tender of Khan
Electric and General Stores were parts of pre-arranged plan.
We have reasons to believe that the lowest amounts tendered
were also those about which there had been a meeting of mind
between the tenderer and appellants Salaria and Buch, if not
others. We are inclined to think so because it is not
believable that without such an understanding, Arfa
Electrical and the firm of Qurashi would have undertaken the
work of transport even before the NIT was issued. They must
have done so, on being told what the lowest rates would be,
at least, could be. There is much merit in the submission of
Shri Handoo that the non-transporters were brought in the
picture even when firms of transporters were known to exist
and there was no dearth of trucks proved by the fact that
the three contractors could arrange 132 trucks within a
short span of 8.9.77 to 7.11.77, only because of some prior
understanding with them to share the extra profits with the
officials. And this extra profit was ensured by allowing
carriage per pole per k.m. basis, though the contractors
themselves engaged trucks on lumpsum basis. (This figure was
given as Rs.8000/- by DW 1). So, everything pieces well; all
acted concertedly to allow wrongful gain to the contractors
on the understanding that the booty would be appropriately
shared.
22. Having come to the aforesaid conclusion which does make
out a case of conspiracy to cause wrongful loss to the
State, let it be seen whether the appellants herein were the
conspirators; and, if so, whether the charges against them
have been brought home in accordance with law. We propose to
examine this qua each of the appellants separately. We would
first take up the case of the two persons, who had played
the key role in the conspiracy according to the prosecution.
They are appellants N.A. Salaria, the then Executive
Engineer; and G.D. Buch, the then Assistant Engineer.
Appellants N.A. Salaria and G.D.Buch
(Criminal Appeal Nos.521 and 530/1981)
23. There is no doubt, in view of what has been stated
above, that they played key role in giving of the contracts
and formed the inner circle of the conspiracy. There can
also be no doubt in view of what has already been held that
their actions were actuated by ill motive, and the same was
not inspired to get the poles at Leh to see that the
electrification scheme gets shape before winter sets in.
Apart from what has already been mentioned about the tainted
steps taken by them, Shri Handoo has brought to our notice
another facet of the case, which was to get transported
about 10,000 number of poles as against the need of about
4,700. The NIT itself had specified this number as about
6,000.
24. Shri Thakur, learned senior counsel who appeared for
Buch, contended that the total requirement for 1976-77 came
to about 12,400; and as during Bassu’s period only about
2,000 poles could be carried, no motive could be ascribed if
10,000 poles were transported during the period in question.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 16
25. We would have accepted the submission of Shri Thakur,
but having found that the rate at which the poles were
agreed to be carried were unreasonable, we read motive in
allowing carriage of poles beyond what was strictly needed.
The greater the number of poles carried, the higher would be
amount which would become payable to the contractors because
of the rate being per pole; and the high profit would
benefit the appellants also.
26. Nothing further remains to be said to come to the
conclusion that these appellants were rightly found quilty
of the charges, which qua them were commission of offences
under section 5(2) of the Act and 120-B/ 109/116/119 Ranbir
Penal Code. At this stage we say something about the
submission made by Shri Jethmalani, who had appeared for two
of the contractors namely Hafizullah and Farooq Ahmed
Qurashi, that the charge having only mentioned about section
5(2) was not quite explicit inasmuch as it did not spell out
which particular misconduct specified in sub-section (1) of
section 5 was being attributed. The learned counsel further
submitted that of all the four types of misconducts taken
care of by sub-section (1) in its four clauses, it is the
one mentioned in clause (do which could apply, which speaks
of abuse of the position by a public servant by "corrupt or
illegal means". The contention as to this clause was that no
corrupt or illegal means had been adopted by the public
servants because the contract had been given following
invitation to submit tenders which is a known and legal mode
of giving contracts; it was in also not a corrupt means.
There is no force in this contention, as the undertaking
given to the aforesaid two contractors that they would be
allowed to carry poles at the lowest tendered rates followed
by how the NIT was issued and what happened thereafter,
there can be no dispute that the public servants in question
did abuse their position. It so deserves to be noted that
clause (d) does not speak only about "corrupt or illegal
means" but also takes within its fold obtaining by public
servant for himself or for any other person any pecuniary
advantage "otherwise" as well. We, therefore, do not find
any infirmity in the charges as framed.
27. So, we uphold the conviction as awarded against these
appellants. Coming to the question of sentence, we have
noted that section 5(2) of the Act has stated that the
punishment shall not be less than one vear’s imprisonment
but may extend to seven years. The trial court, being
satisfied about the need of deterrent punishment had awarded
imprisonment for four years and a fine of Rs.25,000/-. The
High Court has, however, reduced the sentence to two years
and fine too has been reduced to Rs.15,000/-, despite of
having noted that evil of corruption had of late assumed
menacing proportion and was the deadliest enemy of a free
civilised society.
28. According to us, it would be too harsh to award even
the minimum punishment at this length of time keeping in
view the hardship already undergone and the amount which the
State had ultimately to lose because of the conspiracy - the
same being a sum of Rs.1,62,117.89. As about two decades
have passed since the commission of the offence and as
during the interregnum the appellants had undoubtedly
suffered in body and mind, according to us, it is a fit case
where the proviso to sub-section (2) of section 5 of the Act
should be invoked which states that for special reasons
recorded in writing, the court may refrain from imposing a
sentence of imprisonment or impose a sentence of
imprisonment of less than one year. Though the proviso
permits not to impose a sentence of imprisonment at all and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 16
confine the sentence to fine only, we do not think if
present is a case where the punishment to be awarded should
be only fine, as any softness in this regard could produce
an undesirable result, namely, encouragement to adoption of
corruption means by public servants which has indeed to be
checked, and not allow to be encouraged. Keeping in view all
the attending circumstances, we are of the view that a
sentence of RI for two months would be adequate sentence,
apart from the fine of Rs.15,000/-. On failure to pay the
fine, each of the appellants would suffer imprisonment for
two months.
29. Crl. Appeal Nos. 521 and 530 of 1981 therefore, stand
dismissed, subject to the aforesaid modification in
sentence.
Appellants T.K. Kantroo and V.K. Razdan
(Criminal Appeal Nos.523 and 526/1981)
30. These appellants were working at the relevant time as
Assistant Engineer and Sectional Officer in the office of
the Chief Engineer and, according to the prosecution, they
had affected cost analysis and had justified the proposal
which had been submitted by appellant Salaria to the Chief
Engineer seeking his approval to the rates tendered by khan
Electric and General Stores.
31. What had happened was that after the bills had been
submitted by the contractors for payment, an objection was
raised by the Accountant relating to non-approval of the
contract by the Chief Engineer. This needed clearance of the
Chief Engineer for which purpose Salaria addressed a
communication on 4.10.1977 to the Chief Engineer (a copy of
which is at pp.10 and 11 of Volume IX) seeking his approval
to the tender rates in question. In the memo of the
aforesaid date, which was endorsed to the Chief Engineer
Salaria had mentioned in its margin (and this endorsement,
according to Shri Handoo, is not to be found in the original
of the letter) stating, inter alia, that the tender rates
were as per the Superintending Engineer Memo dated
27.5.1975, a copy of which was also enclosed. After receipt
of this letter on 22nd October, the Chief Engineer desired
processing of the matter. The file was endorsed to Assistant
Engineer Kantroo by Technical PA to the Chief Engineer on
22nd itself; and Kantroo, in turn endorsed the letter to
Razdan on 24th.
32. An office note running into 3 and 1/2 pages was
prepared by Razdan on 25th which came to be signed by
Kantroo also on that date The Technical PA to the Chief
Engineer submitted the office note on the same date to the
Chief Engineer. The Chief Engineer, however, found that the
standing procedure regulating invitation of the tenders and
processing the case thereafter had not ben followed strictly
due to extreme urgency involved as stated by the Executive
Engineer. The Chief Engineer in his note, asked the
Superintending Engineer to get the case processed at his
level and to obtain the observation of FA (Financial
Adviser) and to get the agenda put up thereafter by the
Executive Engineer for discussing and deciding in a
committee of the Superintending Engineer, Executive
Engineer, FA and CAO (or his representative) and himself
within a week.
33. The aforesaid shows the extreme hurry in which the
matter was dealt by the appellants Kantroo and Razdan. A
perusal of the office note, which is at pages 12 to 15 of
volume IX, shows that they regarded the accepted tender
rates as justified solely because of the approval by the
Superintending Engineer, REST (Rural Electrification and
Sub-Trans) Circle of the carriage rates in 5/75 ranging
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 16
between 51 to 75 per km. per pole. (This document is at page
99 of Volume VII).
34. Shri Handoo contended that the complicity of these two
appellants is apparent from the fact that they had confined
their attention only to the one time approval given by the
aforesaid Superintending Engineer without at all trying to
know as to under what circumstances the rates were approved
and, what is more, without trying to know what were the
other accepted mode of carrying poles and what were the
rates thereof.
35. Shri Sushil Kumar, learned senior counsel appearing for
these appellants, submitted that no other data or material
was available in the office of the Chief Engineer, and so,
the appellants confined their attention to the rate about
which mention had been made in the communication of the
Executive Engineer. That no other material was available in
the office of the Chief Engineer is the evidence of PW.1 who
was the Inquiry Officer. PW.26 who was the Technical PA to
the Chief Engineer and, last but not the least, the IO,
PW.65, also deposed the same.
36. The further submission of Shri Sushil kumar was that if
these appellants had omitted to make any further inquiry,
about which the observation of the trial court was that they
did not "conduct research", the same did not really show any
guilty mind, though that could be a case of negligence for
which departmental action may be merited but not a criminal
prosecution. In this connection our attention was invited to
the recommendation of the Inquiry Officer stating that these
appellants have to "explain their negligence in not traving
to ascertain and apprise the Chief Engineer of the vital
information appertaining to the carriage rates at which
poles had been carried to Ladakh by .........."(Page 105 of
Volume V).
37. To support him on the legal submission, we have been
referred to Abdulla Mohammed Pagarkar vs. State(Union
Territory of Goa, Daman & Diu), (1980) 3 SCC 110. That was
also a case where the appellants had been convicted, inter
alia, under Prevention of Corruption Act. While setting
aside the conviction and ordering for acquittal of the
appellants, this Court observed in paragraph 24, to which
our attention is invited in particular, that if the
appellants proceeded to execute the work in flagrant
disregard of the relevant rules of the General Financial
Rules and even of ordinary norms of procedural behaviour of
Government officials and contractors in the matter of
execution of work undertaken by the government such
disregard had not been shown to amount to any of the
offences for which the appellants convicted. The submission,
therefore, was that we may not read ingredients of any of
the offences for which the appellants have been convicted
merely because of their not having made some enquiries and
having acted against accepted norms.
38. We have found it difficult to agree with Shri Sushil
Kumar because a perusal of the aforementioned office note
clearly shows two things. First, the extreme hurry in which
the assigned work was completed, as the file came to Razdan
on 24th October and was sent back on 25th, after the same
had been examined, not only by him, but Kantroo also. There
was no occasion for hurry at that stage inasmuch as
transport of the bamboo poles had almost been completed and
what remained to be done was only the payment. Secondly, the
note discloses the these appellants knew that the cost of
carriage per pole even as per the lowest tenders would be
Rs.144.60. This must have shocked their conscience and they
must have tried to know what could have been the cost of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 16
poles were carried, not on the basis of per km. per pole,
but as per truck loads. Sitting in the office of the Chief
Engineer it would not have been difficult for these officers
to find out the rate either of the RTC or private carriers.
The omission to make these inquiries stares one at the face
and so they were rightly prosecuted the ultimately
convicted, because of their apparent complicity in
recommending the acceptance of the rates, characterizing the
same as justified.
39. Shri Sushil Kumar advanced yet another submission. He
urged that the acquittal of the Chief Engineer by the trial
court and of the Superintending Engineer by the High Court
show that these courts had not read any criminal intent in
the role they had played in the matter; and the same view is
merited qua the two appellants. We do not propose to examine
the justification or otherwise of the acquittals, because of
there being no appeal against acquittals before us. It would
be enough to point out that the Chief Engineer had been
acquitted as the trial court took the view that Salaria was
interested in keeping the Chief Engineer in dark about
salient features of the contract, because of which it was
stated that the Chief Engineer could not be a conspirator.
As to the acquittal of the Superintending Engineer what the
High Court stated was that he had neither been informed
about the floating of tenders on 17.9.1977, nor was taken
into confidence when tenders were opened on 27.9.1977. Even
a copy of the NIT had not been sent to him. This apart, the
High Court has referred to a communication addressed by the
Superintending Engineer to Salaria in which the former asked
the latter as to why poles were not carried by RTC trucks
and why the carriage contractors had been introduced. We do
not propose to dilate further.
40. We, therefore, conclude by stating that the two
appellants were rightly found guilty. As to the substantive
sentence awarded on them, we would reduce the same to RI for
one month, as we have sentenced the main culprits to
imprisonment for two months. The fine of Rs.3,000/- on each
of the appellants is left unaltered. In default of payment
of fine, each of them would undergo imprisonment for one
month.
41. Criminal Appeal Nos.523 and 526 of 1981 are, therefore,
dismissed, subject to the aforesaid modification in
sentence.
Appellants H.L.Dhar,F.A. Zadoo and Mohd.
Siddiq
(Criminal Appeal Nos. 522,528 and 529 of
1981)
42. The alleged role of these appellants was that they had
passed poles below specification inasmuch as poles below
the length of 20 feet were allowed to be transported. There
is no dispute that the contract was to transport poles whose
length was required to be between 20 feet to 30 feet. This
has its importance because poles of smaller size would not
have the required girth which would affect their strength
and they would not be able to withstand the normal wear and
tear. Of the aforesaid appellants, Dhar was a Sectional
Officer in the Power Development Department, Zadoo a Store-
keeper cum Clerk and Siddiq a Junior Clerk engaged on work
charged basis. Their defence was that as poles below the
length of 20 feet had ben transported earlier, they had
permitted the same this time as well, not knowing that the
contract was to carry poles of 20 feet and above. This
defence has to be rejected for two reasons: (1) It cannot be
believed that the Passing Officers would not know about the
size of poles to be transported; and (2) it is the case of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 16
appellant Buch that he had informed about the size of the
poles to be accepted.
43. The High Court has strongly criticized the role of the
Passing Officers by stating that had they not been parties
to the conspiracy, the entire conspiracy would have flopped
and the carriage contractors could not have carried such a
great number of poles in such short span of time and could
not have earned so much.
44. Shri Agarwal, learned senior counsel appearing for
these appellants, contended that even if it were to be
accepted that these officers were informed about the
contract being to carry poles of 20 feet and above, the
poles below 20 feet carried were small in number and the
percentage of the pole so carried was in the neighborhood of
what has been done earlier. From Statement No.4 filed in the
case by Shri Thakur, it appears that even RTC trucks and
private carriers, who too were supposed to carry poles of
the length of 20 feet and above, had transported some poles
below 20 feet, whose percentage came to 20.9, whereas the
percentage of such poles transported by the three carriers
contractors was 21.3.
45. We have also found from the judgment of the High Court
that the contractors had billed for those poles only which
were of 20 feet and above. This is admitted by Shri Handoo
and is apparent from the bills submitted by the carriers
which are on record. To bring home this point, it would be
enough to refer to the bill of Arfa Electrical Company which
is at page 286 of Volume XII. The total number of poles for
which bill was submitted comes to 822, of which 647 were
between 20 feet to 26 feet and the remaining 175 between 27
to 30. In all, however, the contractor had carried 1125
poles, as mentioned at page 75 of the High Court’s judgment.
There is no dispute that similar is the situation as regards
the two other carriers.
46. It thus appears that though these three appellants had
sought to assist the carriers to cause wrongful gain to them
by allowing transportation of poles below 20 feet,
ultimately no financial loss on this court was caused to the
State because the carriers had not been paid for poles
carried by them which were below 20 feet. We are, therefore,
of the view that these appellants also deserve to be
acquitted, as were some of the Field Officers, who had
accepted the under- sized pole at the receiving point had
been acquitted by the High Court. May it be mentioned that
the High Court had acquitted the Field Officers mainly
because of acquittal of the supplier, namely, Mustaq &
Company, by the trial court against which no appeal had been
filed. The High Court observed that if no offence had been
committed by the supplier on this score, the persons who had
received those poles cannot be faulted with. We would say
the same qua these three appellants.
47. Criminal Appeal Nos.522,528 and 529 of 1981 are,
therefore, allowed by setting aside the conviction of the
appellants and by ordering their acquittal.
Appellants Hafeezullah and F.A. Qurashi
(Criminal Appeal Nos. 524 and 525 of 1981)
48. These are the contractors who had been approached by
Buch and had started transportation work from 18.9.77 - the
date of the issuance of the NIT being 17.9.77. Appellant
Qurashi had executed the work from 18th for 6 days and had
transported 1038 poles. Appellant Hafizullah started
transportation work from 24th September and this continued
till 29th, during which period 1125 poles were carried.
49. Shri Jethmalani, learned senior counsel appearing for
these appellants, contended that there were some legal
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 16
infirmities in their conviction. He first stated in this
regard that the charges framed against them being one of
conspiracy with accused 5 and 6 (who are appellants Salaria
and Buch) and through them with accused 1 to 4 (who were the
Power Development Commissioner, the Chief Engineer, the
Superintendent Engineer and Technical PA to the Power
Development Officer), and accused 1 to 4 having been
acquitted, the charge of conspiracy against these appellants
has to fail on this count alone. Further leaf of this
argument was that there being no charge of conspiracy inter-
se among the three contract carriers, even if there was some
conspiracy between accused Rashid Khan and P. Gulam Nabi,
who were the partners of the firm of Khan Electric and
General Stores, no illegal act at all was committed by these
appellants, as after all what hey had agreed to do was to
transport poles at the rate to be found lowest on tender
being floated. It was also contended that there was wrong
use of section 10 of the Evidence Act because there is no
evidence alliunde about these appellants having "conspired
together" with others in which case alone section 10 becomes
operative. Final flaw mentioned was that the circumstances
which had come on record against these appellants had not
been put to them in their examination under section 313
Cr.P.C., because of which the circumstances have to be
excluded from consideration, as held by this Court in Sharad
Birdhichand v. State of Maharashtra, 1984 (4) SCC 116.
50. It is no doubt correct that accused 1 to 4 were
acquitted but accused 5 and 6 were not; and we too have
upheld their conviction. Though the charge stated about
ultimate conspiracy with accused 1 to 4, the same was
alleged through accused 5 and 6. We have already dealt as to
what is the effect of acquittal of accused 1 to 4 on the
charge of conspiracy, and it has been pointed out that the
acquittal did not affect the inner circle of the conspiracy
which remained intact inasmuch as appellants Salaria and
Buch are comprehended in that circle.
51. As to there having been no charge of conspiracy inter-
se between the three contractors, the same is not material
because of our finding that there was close inter-
relationship between the three firms and all of them had
acted in concert. The submission about non-applicability of
section 10 of the Evidence Act, therefore, fails. So, it is
not necessary to advert to what was held in this regard in
Natwarlal Sakarlal v. State of Bombay, 1963 Bombay Law
Reporter 660 to which we were referred by Shri Jethmalani to
support his submission relating to section 10 of the
Evidence Act.
52. This leaves for consideration the submission that the
circumstances coming on record were not put to the
appellants when they were examined under section 313 Cr.P.C.
for which reason the circumstances have to be excluded from
consideration. In support of this submission Shri Jethmalani
read out to us the questions asked to Hafeezullah, which
(alongwith his answers) are at page 283 of Volume II and
read as below:-
"Q. It has transpired in evidence
that without having anything to do
with Arfa Electrical Co. Red-Cross-
Srinagar you have submitted a bill
for Arfa Electrical Co., which was
originally shown to be a bill on
behalf of khan Electrical and
General Stores?
A/ I am a partner of Arfa with one
Farooq Ahmed Zargar. The bill was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 16
given for typing and the typist
committed a mistake, which was
corrected by hand. The bill was due
because of the arrangement made by
me and my partner with ECD Leh on
8.9.77.
Q/ Further that Farooq Ahmed
Qurashi S/O your Father’s Brothter-
in-Law had submitted quotation in
response to NIT issued by Xen. ECD
Leh as proprietor of Arfa Elec. Co.
with which you had no connections?
A/ That is not correct. The
quotation Ex PW3/10 which I have
seen today was signed by my partner
Farooq Ahmed Zargar and bears the
signature of said Farooq Ahmed
Zarqar and not of Farooq Ahmed
Qureshi.
Q/ Why you are being prosecuted?
A/ I do not know.
Q/ Why the witness are deposing
against you?
A/ No witness has deposed anything
against me.
Q/ Would you like to lead (sic,
make) any other submission?
A/ I am innocent.
Q/ Would you like to lead any
defence?
A/ Yes."
53. The aforesaid does show that Hafeezullah was not asked,
in any form, about his having entered into conspiracy with
anybody. He was not even asked that the rates at which poles
were carried by him were unreasonable or high. As these
allegations/circumstances are the crux of the prosecution
case insofar as he is concerned, the non-providing of
opportunity to him to explain the same has rendered his
conviction unsustainable. We, therefore, accept his appeal
and order for his acquittal.
54. Insofar as appellant Qurashi is concerned, a perusal of
his examination under 313 (at pages 280 to 282 of Vol.II),
however, shows that the facts which emerged against him were
put to him to enable him to explain the same. The law,
therefore, would not require us to exclude the circumstances
brought on record against him. His conviction, therefore,
has to be sustained as we are satisfied about his
complicity. But then, keeping in view the sentence which we
have awarded on the principal accused, namely, Salaria and
Buch, we would reduce his sentence to RI for one month. Fine
of Rs.20,000/- as awarded by the High Court is left
unchanged. In default of payment of fine, the appellant
would suffer imprisonment for two months.
55. Criminal Appeal No.524/81 is, therefore, allowed. But
Criminal Appeal No.525/81 is dismissed, subject to the
aforesaid modification in sentence.
Appellants A.R. Khan and P. Gulam Nabi
(Criminal Appeal No.527 of 1981)
56. These appellants are the partners of Khan Electrical
and General Stores. It is this firm whose tender being the
lowest was accepted on 27.9.1977 in the wake of issuance of
NIT on 17.9.1977.
57. In view of all that has been stated above there is
nothing to doubt about their involvement in the matter. Shri
Thakur, appearing for these appellants also, made no
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 16
independent submission relating to them. All that he had
urged was to bring out our notice the circumstances under
which their firm was given the contract and how the contract
having been given at the lowest tendered rates was not
tainted. We have expressed our opinion on these submissions
while dealing with the case of Salaria and Buch. We may not
repeat the same. We may only point out that from what has
been stated above we are satisfied that the contract given
to the firm of these appellants was as per pre-arranged plan
and the same was given to them to enable them to earn extra
profit for appropriate sharing afterwards.
58. We are, therefore, satisfied that they were rightly
found guilty both by the trial court and the High Court. As
to their substantive sentence, we would reduce the same to
RI for one month keeping in view the sentence we have
awarded on appellants Salaria and Buch, and what we have
done regarding the sentence of appellants Kantroo and
Razdan. We would, however, leave the sentence of fine as
awarded which is a sum of Rs.22,000/- on each unaltered. In
default of payment of fine, each of them would suffer
imprisonment for two months.
59. Criminal Appeal No.527/81 is, therefore, dismissed,
subject to the aforesaid modification in sentence.
Conclusions
60. We may sum up our conclusions. These are:
(1) Conviction of appellants N.A. Salaria and G.D. Buch is
upheld. Their substantive sentence is, however, reduced to
RI for two months. Fine of Rs.15,000/- as awarded by the
High Court, is left unaltered. In default of payment of
fine, each of these appellants would undergo imprisonment
for two months.
(2) Conviction of appellants T.K. Kantroo and V.K. Rajdan
has been confirmed. Their substantive sentence has, however,
been reduced to RI for one month. Fine of Rs.3,000/- as
awarded by the High Court is left unaltered. In default of
payment of fine, each of the appellants would undergo
imprisonment for one month.
(3) Conviction of appellants H.L. Dhar, F.A. Zadoo and
Mohd. Siddiq has been set aside and they have been
acquitted.
(4) Conviction of appellant Hafeezullah has been set aside
and he too stands acquitted.
(5) Conviction of appellant FA Qurashi is confirmed. His
substantive sentence has, however, been reduced to RI for
one month. Fine of Rs.20,000/- as awarded by the High Court
is left unaltered. In default of payment of fine, this
appellant would suffer imprisonment for two months.
(6) Conviction of appellants A.R. Khan and P. Gulam Nabi
has been confirmed. Their substantive sentence has, however,
been reduced to RI for one month. Fine of Rs.20,000/- as
awarded by the High Court is left unaltered. In default of
payment of fine, each of the appellants would suffer
imprisonment for two months.