Full Judgment Text
1
NON-REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL No(s). 5976 OF 2019
(Arising out of SLP(C) No(s).18232 OF 2019
@ SLP(C) DIARY NO.27982 OF 2017)
HUCHANAGOUDA Appellant(s)
VERSUS
THE ASSISTANT COMMISSIONER AND
LAND ACQUISITION OFFICER & ANR. Respondent(s)
WITH
CIVIL APPEAL No(s).5977 OF 2019
(Arising out of SLP(C) No(s).18233 OF 2019
@ SLP(C) Diary No(s). 27981/2017)
J U D G M E N T
BANUMATHI, J:
(1) Leave granted.
(2) The Government notified the lands in-question for
acquisition for the purpose of rehabilitating the Veerapur
villagers on account of implementation of Hirehalla project on
16.10.2003. The Land Acquisition Officer passed the award
dated 08.03.2006 fixing the value of the land at the rate of
Rs.24,500/- per acre. In reference, the Court raised the
market value to Rs.1,26,500/- per acre. In appeal, the High
Court has taken into account the market value determined in
respect of acquisition under another Notification dated
24.11.1994, pointing out that the present notification is dated
Signature Not Verified
Digitally signed by
MAHABIR SINGH
Date: 2019.08.05
16:59:37 IST
Reason:
16.10.2003 and there being a gap of about eight years and ten
months and twenty two days from the earlier Notification dated
24.11.1994, the High court granted 5% escalation for the gap of
2
about nine years between 24.11.1994 and 16.10.2003 and arrived
at the market value of Rs.1,55,133/- which is rounded off to
Rs.1,56,000/- per acre. Being aggrieved, the claimants have
preferred these appeals seeking further enhancement.
(3) We have heard Mr. Sharanagouda Patil, learned counsel
appearing for the appellants and Mr. Navin R. Nath, learned
counsel appearing for respondent No.2 and also perused the
impugned judgment and the materials on record.
(4) Mr. Navin R. Nath, learned counsel appearing for the
respondent, has submitted that SLP(C)No.22784 of 2016 arising
out of the same project had been filed by another land owner.
The said special leave petition was mainly dismissed by this
Court vide Order dated 10.01.2018 mainly on the ground of delay
in filing the special leave petition.
(5) Mr. Sharanagouda Patil, learned counsel appearing for the
appellants-claimants, has placed reliance on the judgment of
this Court in Imrat Lal and Others v. Land Acquisition
Collector and Others, (2014) 14 SCC 133, and has submitted that
in case of land acquisition matters there is necessity to take
the judicial notice of the fact that in India villagers are by
and large poor and therefore the delay in filing the special
leave petition cannot be the reason to deny the just and fair
compensation to the claimants. It was submitted that the Court
should adopt liberal approach where there is a delay in filing
the special leave petition. This Court in para ‘11’ of Imrat
Lal (Supra) has held as under:
3
“11. We can take judicial notice of the fact
that villagers in our country are by and large
illiterate and are not conversant with the
intricacies of law. They are usually guided by
their co-villagers, who are familiar with the
proceedings in the Courts or the advocates with
whom they get in touch for redressal of their
grievance. Affidavits filed in support of the
applications for condonation of delay are
usually drafted by the advocates on the basis
of half baked information made available by the
affected persons. Therefore, in the acquisition
matters involving claim for award of just
compensation, the Court should adopt a liberal
approach and either grant time to the party to
file better affidavit to explain delay or suo
motu take cognizance of the fact that large
number of other similarly situated persons who
were affected by the determination of
compensation by the Land Acquisition Officer or
the Reference Court have been granted relief. ”
(6) We further take note that this Court in the case of Dhiraj
Singh (Dead) Thr. Lrs. And Others v. State of Haryana and
Others, (2014) 14 SCC 127, has considered the issue relating to
condonation of delay in land acquisition matters and the manner
in which the equities are to be balanced. It is held therein
as hereunder:
“15. Equities can be balanced by denying the
appellants’ interest for the period for which they
did not approach the Court. The substantive
rights of the appellants should not be allowed to
be defeated on technical grounds by taking
hypertechnical view of self-imposed limitations.
In the matter of compensation for land
acquisition, we are of the view that approach of
the court has to be pragmatic and not pedantic.
16. The principles regarding condonation of
delay particularly in land acquisition matters,
have been enunciated in Collector (LA) v. Katiji,
(1987) 2 SCC 107, wherein it is sated in para 3 as
under:
“3. The legislature has conferred the
power to condone delay by enacting
Section 5 of the Limitation Act of 1963
4
in order to enable the courts to do
substantial justice to parties by
disposing of matters on ‘merits’. The
expression ‘sufficient cause’ employed
by the legislature is adequately
elastic to enable the courts to apply
the law in a meaningful manner which
subserves the ends of justice – that
being the life-purpoe for the existence
of the institution of courts. It is
common knowledge that this Court has
been making a justifiably liberal
approach in matters instituted in this
Court. But the message does not appear
to have percolated down to all the
other courts in the hierarchy. And
such a liberal approach is adopted on
principle as it is realised that:
(1) Ordinarily a litigant does not
stand to benefit by lodging an appeal
late.
(2) Refusing to condone delay can
result in a meritorious matter being
thrown out at the very threshold and
cause of justice being defeated. As
against this when delay is condoned the
highest that can happen is that a cause
would be decided on merits after
hearing the parties.
(3) ‘Every day’s delay must be
explained’ does not mean that a
pedantic approach should be made. Why
not every hour’s delay, every second’s
delay? The doctrine must be applied in
a rational common sense pragmatic
manner.
(4) When substantial justice and
technical considerations are pitted
against each other, cause of
substantial justice deserved to be
preferred for the other side cannot
claim to have vested right in injustice
being done because of a non-deliberate
delay.
(5) There is no presumption that
delay is occasioned deliberately, or on
account of culpable negligence, or on
account of mala fides. A litigant does
not stand to benefit by resorting to
delay. In fact he runs a serious risk.
(6) It must be grasped that
judiciary is respected not on account
of its power to legalise injustice on
5
technical grounds but because it is
capable of removing injustice and is
expected to do so.”
Further, even if the consideration is made on merits after
condoning the delay, the determination of the market value will
in all event relate back to the date of preliminary
notification and as such there is no prejudice to the
acquisition authority nor added advantage to the land loser.
The aspect relating to interest can be taken care by denying it
to the land loser for the period of delay.
(7) Following the above judgment and for the further reasons
assigned above, in our view the delay of 2154 days in filing
and 252 days in refiling S.L.P.(C) Diary No.27982 of 2017 as
also the delay of 2109 days in filing and 250 days in refiling
S.L.P.(C)Diary No.27981 of 2017 cannot be a reason to deny the
consideration of the matter on merits regarding the claim of
the appellant for just and fair compensation.
(8) The High Court has granted 5% escalation for the gap of
about nine years between 24.11.1994 and 16.10.2003.
Admittedly, the acquisition of the land was for rehabilitating
the Veerapur villagers on account of implementation of
Hirehalla Project. Learned counsel appearing for the
appellants has submitted that though the acquired land on the
date of acquisition was agricultural land the very fact that it
is acquired for rehabilitation which is non-agricultural use,
the same has the potential for development for being converted
into building sites and had the potential of being put to
6
better use. Reliance was placed by learned counsel for the
appellants on the judgment of this Court in General Manager,
Oil and Natural Gas Corporation Limited v. Rameshbhai Jivanbhai
Patel and Another, (2008) 14 SCC 745. Pointing out that there
should be significant increases in the market value of the land
in para ‘14’ of Rameshbhai (supra) it was held by this Court
which reads as under :
“14. On the other extreme, in remote rural
areas where there was no chance of any
development and hardly any buyers, the prices
stagnated for years or rose marginally at a
nominal rate of 1% or 2% per annum. There is
thus a significant difference in increases in
market value of lands in urban/semi-urban areas
and increases in market value of lands in the
rural areas. Therefore if the increase in
market value in urban/semi-urban areas is about
10% to 15% per annum, the corresponding
increases in rural areas would at best be only
around half of it, that is about 5% to 7.5% per
annum. This rule of thumb refers to the general
trend in the nineties, to be adopted in the
absence of clear and specific evidence relating
to increase in prices. Where there are special
reasons for applying a higher rate of increase,
or any specific evidence relating to the actual
increase in prices, then the increase to be
applied would depend upon the same.”
(9) In the present case, though the land is stated to be an
agricultural land in Veerapur Village, considering the
potentiality of the land for development, the escalation is
granted at the rate of 10% with cumulative effect as under :
“1994 - Rs.1,00,000/-
1995 - Rs.1,10,000/-
1996 - Rs.1,21,000/-
1997 - Rs.1,33,100/-
1998 - Rs.1,46,410/-
1999 - Rs.1,61,051/-
2000 - Rs.1,77,156/-
2001 - Rs.1,94,872/-
2002 - Rs.2,14,359/-
2003 - Rs.2,35,795/-”
7
(10) Awarding 10% increase, the appellants-claimants are
entitled to Rs.2,35,795/- per acre. Accordingly, the
compensation awarded to the appellants-claimants is enhanced to
Rs.2,35,795/- per acre. Needless to point out that for the
period of delay in filing and in refiling the special leave
petitions the appellants-claimants shall not be entitled to any
interest on the enhanced compensation and statutory amount.
(11) The impugned judgment(s) of the High Court is modified to
the extent indicated above and the appeals are partly allowed.
There shall be no order as to costs.
..........................J.
(R. BANUMATHI)
..........................J.
(A.S. BOPANNA)
NEW DELHI,
JULY 30, 2019.