Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
Civil Appeal No 4914 of 2022
(Arising out of SLP(C) No 1098 of 2020)
Mahanadi Coalfields Ltd & Anr .... Appellant(s)
Versus
M/s IVRCL AMR JOINT VENTURE ....Respondent(s)
J U D G M E N T
Dr Dhananjaya Y Chandrachud
1. Leave granted.
1
2. The appellant, Mahanadi Coalfields Ltd., is a subsidiary of Coal India Limited . The
respondent, IVRCL AMR Joint Venture, is a joint venture of engineering contractors
engaged in the business of infrastructure development. On 11 October 2010, the
appellant floated an e-tender for the work of strengthening and widening of a coal
transportation road at the Talcher Coalfields in the State of Orissa. The respondent
was the successful bidder and was awarded a work order on 14 December 2011. A
Signature Not Verified
Digitally signed by
Sanjay Kumar
Date: 2022.08.02
16:50:22 IST
Reason:
‘Contract Agreement’ was entered into between the parties on 30 January 2012, in
terms of which the work order was to be executed between 16 January 2012 and 14
1
“CIL”
1
January 2015.
3. In a meeting held on 28 June 2012, the appellant advised the respondent to
expedite the mobilization of resources to start the work immediately. Later, the
appellant sent a series of letters to the respondent requesting it to expedite the work
as per the work schedule. In 2013 and 2014, the appellant served several notices to
the respondent when the latter failed to adhere to the work schedule. Ultimately,
the appellant terminated the work order on 15 May 2014 allegedly on account of
delay in completing the work and the inability of the respondent to meet the work
schedule.
4. Thereafter, on 12 October 2017 the respondent raised a claim of Rs. 128,65,12,688
enumerating the latches and delays on the part of the appellant. The claim was
rejected by the appellant on 18 December 2017. Subsequently, the respondent
issued a notice of arbitration to the appellant by a letter dated 9 April 2018 in terms
of clause 15 of the Contract Agreement. Through the said arbitration notice, the
respondent called upon the appellant to give its consent to the appointment of
Justice Asok Kumar Ganguly as the sole arbitrator. Having received no response
from the appellant to the arbitration notice within 15 days, the respondent filed an
2
application under Section 11(6) of the Arbitration and Conciliation Act, 1996 before
the High Court of Orissa.
5. On 29 November 2019, a Single Judge of the High Court of Orissa allowed the
application under Section 11 of the 1996 Act by appointing a sole arbitrator. The
relevant extracts of the High Court’s decision read as follows:
“3. Learned counsel for both the sides do not
2
“1996 Act”
2
dispute the fact that Clause 15 of the contract
agreement provides for “Settlement of
dispute/Arbitration” in case there is any dispute or
difference between the parties.
4. Mr. R Sharma, learned counsel for the opposite
party has taken different contentions on merit. He
has also brought to the notice of this Court clause
19 of the letter dated 14.12.2011 (Annexure-3),
which reads as under:
“19. That matters relating to any dispute or
difference arising out of the tender, work order
and subsequent contract agreement entered
into, based on this tender and work order shall be
subject to the jurisdiction of District Court, Angul
only.”
5. However, in view of the decisions of the Hon’ble
Supreme Court in the case of Mayavati Trading
Private Limited vs. Pradyuat Deb Burman,
reported in (2019) 8 SCC 714, the Court has to
look into the arbitration clause. In that view of the
matter, the matter is required to be referred to
the arbitrator.”
6. Mr K K Venugopal, learned Attorney General for India, appears on behalf of the
appellants, while Mr S Niranjan Reddy, learned Senior Counsel, appears on
behalf of the respondent.
7. The submission which has been urged on behalf of the appellants by the learned
Attorney General is that clause 15 of the Contract Agreement dated 30 January
2012 does not constitute an arbitration agreement. Hence, it has been urged
that in the absence of an arbitration agreement within the meaning of Sections
2(b) and 7 of the 1996 Act, the very invocation of the jurisdiction under Section
11(6) was not valid. In order to appreciate the submission, it would be necessary
to extract clause 15 of the Contract Agreement. The provision reads as follows:
3
“15. Settlement of Disputes/Arbitration:
15.1 It is incumbent upon the contractor to avoid
litigation and disputes during the course of
execution. However, if such disputes take place
between the contractor and the department,
effort shall be made first to settle the disputes at
the company level. The contractor should make
request in writing to the Engineer-in-Charge for
settlement of such disputes/claims within 30
(thirty) days of arising of the case of dispute/claim
failing which no disputes/claims of the contractor
shall be entertained by the company.
15.2 If differences still persist, the settlement of the
dispute with Govt. Agencies shall be dealt with as
per the Guidelines issued by the Ministry of
Finance, Govt. of India in this regard. In case of
parties other than Govt. Agencies, the redressal
of the disputes may be sought in the Court of
Law.”
8. Section 2(b) of the 1996 Act defines an arbitration agreement to mean an
agreement as referred to in Section 7. In terms of Section 7, an arbitration
agreement is an agreement by the parties to submit to arbitration all or certain
disputes which have arisen or which may arise between them in respect of a
defined legal relationship, whether contractual or not. Sub-section (2) of Section 7
stipulates that an arbitration agreement may be in the form of an arbitration clause
in a contract or in the form of a separate agreement. In terms of sub-section (3) of
Section 7, the arbitration agreement has to be in writing. Sub-section (4) of Section
7 then stipulates that:
“(4) An arbitration agreement is in writing if it is
contained in-
(a) a document signed by the parties;
(b) an exchange of letters, telex, telegrams or other
4
means of telecommunication including
communication through electronic means which
provide a record of the agreement; or
(c) an exchange of statements of claim and defence
in which the existence of the agreement is alleged
by one party and not denied by the other.”
3
9. In Jagdish Chander v. Ramesh Chander , a two-judge bench of this Court, while
4
relying upon the earlier decisions in K. K. Modi v. K. N. Modi , Bharat Bhushan Bansal
5
v. U.P. Small Industries Corpn. Ltd , Bihar State Mineral Development Corpn v. Encon
6 7
Builders (I) (P) Ltd ., and State of Orissa v. Damodar Das , enumerated the principles
governing what constitutes an arbitration agreement. Justice R V Raveendran,
speaking on behalf of the bench, held that the words used in an arbitration
agreement should disclose a determination and obligation on behalf of parties to
refer disputes to arbitration. This court held:
“8 (i) The intention of the parties to enter into an
arbitration agreement shall have to be gathered from
the terms of the agreement. If the terms of the
agreement clearly indicate an intention on the part
of the parties to the agreement to refer their disputes
to a private tribunal for adjudication and a willingness
to be bound by the decision of such tribunal on such
disputes, it is arbitration agreement. While there is no
specific form of an arbitration agreement, the words
used should disclose a determination and obligation
to go to arbitration and not merely contemplate the
possibility of going for arbitration. Where there is
merely a possibility of the parties agreeing to
arbitration in future, as contrasted from an obligation
to refer disputes to arbitration, there is no valid and
binding arbitration agreement.
3
( 2007) 5 SCC 719
4
(1998) 3 SCC 573
5
(1999) 2 SCC 166
6
(2003) 7 SCC 418
7
(1996) 2 SCC 216
5
(ii) Even if the words “arbitration” and “Arbitral
Tribunal (or arbitrator)” are not used with reference to
the process of settlement or with reference to the
private tribunal which has to adjudicate upon the
disputes, in a clause relating to settlement of disputes,
it does not detract from the clause being an
arbitration agreement if it has the attributes or
elements of an arbitration agreement. They are: (a)
The agreement should be in writing. (b) The parties
should have agreed to refer any disputes (present or
future) between them to the decision of a private
tribunal. (c) The private tribunal should be
empowered to adjudicate upon the disputes in an
impartial manner, giving due opportunity to the
parties to put forth their case before it. (d) The parties
should have agreed that the decision of the private
tribunal in respect of the disputes will be binding on
them.
(iii) Where the clause provides that in the event of
disputes arising between the parties, the disputes shall
be referred to arbitration, it is an arbitration
agreement. Where there is a specific and direct
expression of intent to have the disputes settled by
arbitration, it is not necessary to set out the attributes
of an arbitration agreement to make it an arbitration
agreement. But where the clause relating to
settlement of disputes, contains words which
specifically exclude any of the attributes of an
arbitration agreement or contains anything that
detracts from an arbitration agreement, it will not be
arbitration agreement. For example, where an
agreement requires or permits an authority to decide
a claim or dispute without hearing, or requires the
authority to act in the interests of only one of the
parties, or provides that the decision of the authority
will not be final and binding on the parties, or that if
either party is not satisfied with the decision of the
authority, he may file a civil suit seeking relief, it
cannot be termed as an arbitration agreement .
(iv) But mere use of the word “arbitration” or
“arbitrator” in a clause will not make it an arbitration
agreement, if it requires or contemplates a further or
fresh consent of the parties for reference to
arbitration. For example, use of words such as “parties
6
can, if they so desire, refer their disputes to
arbitration” or “in the event of any dispute, the
parties may also agree to refer the same to
arbitration” or “if any disputes arise between the
parties, they should consider settlement by
arbitration” in a clause relating to settlement of
disputes, indicate that the clause is not intended to
be an arbitration agreement. Similarly, a clause which
states that “if the parties so decide, the disputes shall
be referred to arbitration” or “any disputes between
parties, if they so agree, shall be referred to
arbitration” is not an arbitration agreement. Such
clauses merely indicate a desire or hope to have the
disputes settled by arbitration, or a tentative
arrangement to explore arbitration as a mode of
settlement if and when a dispute arises. Such clauses
require the parties to arrive at a further agreement to
go to arbitration, as and when the disputes arise. Any
agreement or clause in an agreement requiring or
contemplating a further consent or consensus before
a reference to arbitration, is not an arbitration
agreement, but an agreement to enter into an
arbitration agreement in future .”
(emphasis supplied)
10. In the present case, clause 15 of the Contract Agreement is titled “Settlement of
Disputes/Arbitration”. However, the substantive part of the provision makes it
abundantly clear that there is no arbitration agreement between the parties
agreeing to refer either present or future disputes to arbitration.
11. Clause 15.1 contains a reference to the steps to be taken for settlement of disputes
between the parties. Clause 15.2 stipulates that if differences still persist, the
settlement of the disputes with government agencies shall be dealt with in
accordance with the guidelines of the Ministry of Finance. In the case of parties
other than government agencies, the redressal of disputes has to be sought in a
court of law.
12. A clause similar to clause 15 of the Contract Agreement in the present case was
7
considered by a bench of this Court in IB Valley Transport, Vijay Laxmi (P) Ltd . v.
8
Mahanadi Coalfields Ltd consisting of J Chelameswar and A. K. Sikri, JJ. In the said
case, the clause was interpreted as an alternative remedy at the company level to
be exhausted before taking recourse to other suitable legal remedies. It was
observed:
“10. From the aforesaid narration of facts, it
becomes clear that Clause 12 of the general terms
and conditions provides for a mechanism of
dispute resolution before resorting to the legal
remedies . This clause specifically states that it is
incumbent upon the contractor to avoid litigation
and disputes during the course of execution. If any
dispute takes place between the contractor and
the department, effort shall be made first to settle
the disputes at the company level. Further, this
clause states that the contractors should make
request in writing to the Engineer Incharge for
settlement of such dispute/claim within 30 days of
arising of cause of dispute/claim. ”
(emphasis supplied)
13. The above extract makes it abundantly clear that clause 15 of the Contract
Agreement is a dispute resolution mechanism at the company level, rather than
an arbitration agreement. Consequently, in case of a dispute, the respondent
was supposed to write to the Engineer-in-charge for resolving the dispute. Clause
15 does not comport with the essential attributes of an arbitration agreement in
terms of section 7 of the 1996 Act as well as the principles laid down under
Jagdish Chander (supra). A plain reading of the above clause leaves no manner
of doubt about its import. There is no written agreement to refer either present or
future disputes to arbitration. Neither does the substantive part of the clause
8
(2014) 10 SCC 630.
8
refer to arbitration as the mode of settlement, nor does it provide for a reference
of disputes between the parties to arbitration. It does not disclose any intention
of either party to make the Engineer-in-Charge, or any other person for that
matter, an arbitrator in respect of disputes that may arise between the parties.
Further, the said clause does not make the decision of the Engineer-in-Charge,
or any other arbitrator, final or binding on the parties. Therefore, it was wrong on
the part of the High Court to construe clause 15 of the Contract Agreement as
an arbitration agreement.
14. However, it has been urged on behalf of the respondent by Mr S Niranjan Reddy
that the first appellant is a subsidiary of CIL. It has been submitted that on 7 April
2017, CIL issued a policy document to its General Managers for the settlement of
disputes or differences arising out of works and services contracts through
arbitration. Clause 5 of the above communication provides as follows:
“Past/existing work order/contract:
5. With regards to dispute/differences cropping up in existing
work order/contract, employer (department) shall adopt
procedure for settlement of the same, through arbitration
process. As you are aware that neither the CIL Manuals nor
contract document at present contains any clause regarding
arbitration, therefore, dispute/differences cannot be referred
to arbitration straight away. Hence, before referring the matter
to arbitration, consent of the other party (contractor) is
necessary for redressal of dispute/differences through
arbitration. Once, the contractor agrees for settlement of
dispute/differences arising out of contracts through arbitration,
an agreement may be signed between employer and
contractor for referring the dispute/differences to Sole
Arbitration by a person appointed by Competent Authority of
CIL/CMD of Subsidiaries (as the case may be). The rest of the
procedure shall be as per the Arbitration and Conciliation Act,
1996 as amended by Amendment Act of 2015 and also as per
instruction incorporated in clause “Settlement of Disputes
through Arbitration”.”
9
15. Hence, it is urged that the first appellant being a subsidiary of CIL and being a
public sector undertaking may well consider as to whether the disputes which have
arisen between the appellants and the respondent should be referred to arbitration.
In this context, the appellants and the respondent placed reliance on an order
dated 20 July 2018 of the Chief Justice of the High Court of Orissa in Arbitration
Petition No 59 of 2016.
16. We are unable to subscribe to the submission which has been urged on behalf of
the respondent based on the policy letter dated 7 April 2017. The communication
which has been issued by CIL refers to the possibility of a consensual resolution of
disputes or differences through arbitration as neither the CIL manuals nor the
contract document, at the time, contained a clause regarding arbitration.
However, it has been submitted that once the contractor has agreed to settle a
dispute through arbitration, the agreement may be signed between the employer
and the contractor for reference to arbitration, by a person to be appointed by the
competent authority of CIL or, as the case may be, the Chairman and Managing
Director of the subsidiaries.
17. The communication dated 7 April 2017 merely indicates a desire on behalf of CIL to
have disputes related to work contracts settled by arbitration. It requires both the
parties to arrive at a further agreement to proceed to arbitration when the dispute
arises. Therefore, in view of the principles laid down in Jagdish Chander (supra),
following a line of precedent, clause 5 in the aforesaid communication cannot be
construed as an arbitration agreement between the appellants and the respondent
in terms of section 7 of the 1996 Act so as to compel the appellants to appoint an
arbitrator.
18. The order of the Chief Justice of the High Court of Orissa dated 20 July 2018
10
proceeds on an understanding that the learned counsel for both the sides did not
dispute the fact that clause 15 of the Contract Agreement and clause 5 of the
policy decision 7 April 2017 taken by CIL provide for appointment of an arbitrator in
case there is any dispute or difference between the parties. The order has,
therefore, proceeded on an understanding of counsel, which in any event cannot
be regarded as a binding statement of law on the existence of an arbitration
agreement.
19. For the above reasons, we have come to the conclusion that the invocation of the
jurisdiction of the High Court under Section 11(6) of the 1996 Act was not valid and
there being no arbitration agreement between the appellants and the respondent,
no reference to arbitration could have been made. We accordingly allow the
appeal and set aside the impugned judgment and order of the High Court dated
29 November 2019. The respondent would, however, be at liberty to seek recourse
to the remedy available in law to pursue the redressal of its grievances.
20. Pending application, if any, stands disposed of.
…..…..…....…........……………….…........J.
[Dr Dhananjaya Y Chandrachud]
…..…..…....…........……………….…........J.
[A S Bopanna]
New Delhi;
July 25, 2022
-S-
11