Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
PETITIONER:
B.N. AGARWALLA
Vs.
RESPONDENT:
STATE OF ORISSA
DATE OF JUDGMENT16/10/1995
BENCH:
VERMA, JAGDISH SARAN (J)
BENCH:
VERMA, JAGDISH SARAN (J)
VENKATASWAMI K. (J)
CITATION:
1996 AIR 385 1995 SCC (6) 509
JT 1995 (7) 454 1995 SCALE (6)54
ACT:
HEADNOTE:
JUDGMENT:
JUDGMENT
J.S. VERMA, J. :
Leave granted.
By the impugned judgment the High Court allowed the
appeal against the judgment of the Subordinate Judge,
Bhubaneswar making an award dated 26.3.1983 the rule of the
court, by which a sum of Rs.95,003/- was directed to be paid
to the appellant by 24.6.1983 failing which it was to carry
interest at the rate of 12 per cent per annum from 27.3.1983
till the date of payment. On behalf of the resoondent, the
award was challenged on the ground that the arbitrator was
incompetent to make the award in view of Section 41A(7) of
the Arbitration (Orissa Amendment) Act, 1982 (Orissa Act 3
of 1983) which came into force w.e.f. 26.3.1983 and had the
effect of amending the Indian Arbitration Act, 1940. Since
the date of the award and the date of the enforcement of the
amending Act are the same, the question is of the
applicability of the said amendment. This is the only
question involved for decision in this appeal by special
leave.
The Arbitration (Orissa Amendment) Act, 1982 was an Act
to amend the Arbitration Act, 1940 in its application to the
State of Orissa. It received the assent of the president of
India on 21.3.1983 and came into force on publication in the
Orissa Gazette, Extraordinary, No.358 dated 26.3.1983. A new
Section 41-A was inserted in the principal Act relating to
constitution of and references to the Arbitration Tribunal.
Sub-section (1) of Section 41-A provided that
notwithstanding anything contained in the Act or any
contract or any other instrument, in all cases where the
State Government, a local or other authority controlled by
the State Government, statutory corporation or a Government
company is a party to the dispute, all references to
arbitration shall be made to the Arbitration Tribunal. Sub-
section (2) provided for constitution of an Arbitration
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
Tribunal by the State Government in the manner provided
therein. Sub-sections (3), (4), (5) and (6) relate to
ancillary matters pertaining to constitution of the
Arbitration Tribunal. Sub-section (7) relates to pending
proceedings and it is the construction of this provision
which is involved in this appeal. Sub-section (7) is as
under:-
"All arbitration proceedings relating to
a dispute of the nature specified in
sub-section (1) which are pending before
any arbitrator on the date of
commencement of the Arbitration (Orissa
Amendment) Act, 1982 and in which no
award has been made by the said date,
shall stand transferred to and disposed
of by Arbitration Tribunal."
The only question in the present case is: Whether the
arbitration proceeding in the present case was such a
pending proceeding before the arbitrator to be governed by
sub-section (7) of Section 41-A ? The controversy really
relates to the meaning of the expression "by the said date"
occurring in sub-section (7).
The contention of learned counsel for the appellant is
that the arbitration proceeding in the present case was not
pending before the arbitrator on 26.3.1983 which is the date
of commencement of the Act as the award had been made on
that day. He submits that the date of commencement of the
Act is to be included in the expression "by the said date"
and, therefore, the arbitrator was not divested of
jurisdiction to make the award on 26.3.1983. On the other
hand, learned counsel for the respondent contends that the
Act having come into force on 26.3.1983, an award made on
that day was without jurisdiction in a pending arbitration
proceeding which stood transferred to the Arbitration
Tribunal by virtue of sub-section (7) of Section 41-A.
Learned counsel for the respondent further submitted that
the object of the anactment was to prevent the mischief for
which the provision was enacted and, therefore, the
contemplated legislation being widely publicised with the
assent of the President being given on 21.3.1983, the
construction which he suggests would promote the object of
the legislation. It is well known that this amendment was
made in the Arbitration Act because of the realisation on
account of strong observations by the courts in several
arbitration cases from Orissa suggesting the desirability of
an Arbitration Tribunal to decide the arbitration disputes
in which the State Government, its instrumentalities or
other public bodies were parties.
Sub-section (7) of Section 41-A provides for automatic
transfer to the Arbitration Tribunal of all arbitration
proceedings of the kind specified in sub-section (1) which
were "pending before any arbitrator on the date of
commencement" of the said Act and "in which no award had
been made by the said date". Obviously, the expression "by
the said date" here means by the date of commencement of the
Arbitration (Orissa Amendment) Act, 1982. The first
expression clearly means an arbitration proceeding pending
before any arbitrator on the date of commencement of the
Act, namely, 26.3.1983. The meaning of the second expression
should be consistent with that of the first expression since
the two could not be used to create a conflict. The purpose
of sub-section (7) is to divest the arbitrator of authority
to make the award in all such arbitration proceedings which
were pending before the arbitrator on the date of
commencement of the said Act and to provide for their
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
automatic transfer to the Arbitration Tribunal. The General
Clauses Act. 1897 orovides that unless the contrary is
expressed, an Act shall be construed as coming into
operation immediately on the expiration of the day preceding
its commencement. There being no contrary indication in the
Act, it must be held that the said Act came into force on
the midnight on the expiration of the day preceding its
commencement, i.e., the midnight between 25th and 26th
March, 1983. There can be no doubt that if the second
expression "in which no award has been made by the said
date" was not also present in sub-section (7), then the
undoubted result of the first expression would be that an
arbitration proceeding in which no award had been made upto
the midnight between 25th and 26th March, 1983 would be a
pending arbitration proceeding which automatically stood
transferred to the Arbitration Tribunal. The question,
therefore, is whether the further words used in the second
expression in sub-section (7) must lead to a different
conclusion. The construction of the first expression being
unambiguous, the second expression must be construed
harmoniously unless that is not a permissible construction
of the expression "by the said date".
It does appear to us that the second expression,
namely, "in which no award has been made by the said date"
was further used in sub-section (7) ex abundante cautela to
clarify the meaning of pending proceedings by indicating
that only those arbitration proceedings in which the award
also had been made "by the said date" were excluded from the
operation of sub-section (7) and that every other
arbitration proceeding including those in which the award
alone remained to be made "by the said date" stood
transferred to the Arbitration Tribunal. In other words, if
the arbitration proceedings had been closed but the
arbitrator had not made the award till the midnight between
25th and 26th March, 1983 when the Act came into force, it
was a pending arbitration proceeding governed by sub-section
(7). Acceptance of the appellant’s contention would amount
to holding that even though the Act had come into force on
the midnight between 25th and 26th March, 1983, an award
made thereafter on 26th March, 1983 was not a pending
arbitration proceeding on the date of commencement of the
Act. Unless meaning of the expression "by the said date"
used in sub-section (7) be only that suggested by learned
counsel for the appellant, the construction which would
harmonise with the meaning of the earlier expression, must
be given to the provision.
We may now consider the meaning of the word ‘by’ for
ascertaining the meaning of the expression "by the said
date". Meaning of the word ‘by’ in some of the dictionaries
is :-
Black’s Law Dictionary (Sixth Edition)
"Before a certain time; .......... not
later than a certain time; on or before
a certain time; .........."
The New Shorter Oxford English
Dictionary
"........ On or before, not later than
.........."
No doubt the word ‘by’ means ‘before a certair time’ as
well as ‘on or before a certain time’. The question is :
whether, the word ‘by’ in the expression "by the said date"
would mean in other words ‘before’ or ‘on’ 26.3.1983 in the
present context? We have already indicated the meaning of
the first expression "pending before any arbitrator on the
date of commencement" to mean clearly and unambiguously
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
pending upto the midnight between 25th and 26th March, 1983,
i.e., before commencement of the date 26.3.1983 or at the
time of expiry of preceding day i.e. 25.3.1983. The other
expression must, therefore, be construed in this context and
since the word ‘by’ means ‘before’ also, in this context it
must be held to mean ‘before’ and not ‘on’ the date of
commencement of the Act. So construed, the second expression
would read as "in which no award has been made before the
said date" i.e. in which no award has been made before the
date of commencement of the Act, namely, 26.3.1983. This
would be the harmonious construction of the two expressions
in the provision.
Obviously, an award made on 26.3.1983 cannot be said to
be an award made before 26.3.1983 and, therefore, the award
in the preset case having been made on 26.3.1983 and not
before 26.3.1983, the date of commancement of the Act, the
arbitrator had no jurisdiction to make the award as it was a
pending arbitration proceeding which automatically stood
transferred to the Arbitration Tribunal.
Learned counsel for the appellant has referred to some
decisions wherein the word ’by’ has been construed to mean
that it includes the end or the expiry of the date or period
indicated. As we have indicated, the meaning of the word
’by’ is both ’before’ as well as ’on or before’ and,
therefore, the context in which it has been used becomes
decisive. Where the context does not exclude the date
specified and permits its inclusion the word ’by’ can be
construed to mean ’on’ and not ’before’; and in that
situation, specification of the limit of time by saying "by
that date" would require including the specified date upto
the expiry of that date for computation of the permitted
period. P.C. Muthu Chettiar vs. Narayanan Chettiar and
others, AIR 1928 Madras 528; Sheikh Nuroo vs. Seth Meghraj
Ramkaran Marwadi, AIR 1937 Nagpur 139; T.A. Janakuara Nainar
vs. Periaswamy Goundan and others, AIR 1949 Madras 376; and
Dharamraj Mahadeo vs. Additional Deputy Commissioner Akola
and others, AIR 1957 Bombay 154 are all decisions in which
the context required the word ‘by’ to be read as ‘on’ and
not ‘before’ to permit inclusion of the period upto the
expiry of the date specified. We have already indicated that
the context in the present case excludes the date specified
and, therefore, excludes the meaning ‘on’ and requires the
word ‘by’ to be read as ‘before’.
Eastaugh and others vs. Macpherson, [1954] 3 All E.R.
214 supports the view we have taken that the meaning of the
word ‘by’ in the phrase ‘by’ the date’ can mean ‘on or
before the date’ or ‘before the date’ depending on the
context in which the word ‘by’ has been used and the meaning
to be preferred should be that which it has in the given
context. We have indicated that in the context of the
provision made in sub-section (7) of Section 41-A meaning of
the word ‘by’ must be ‘before’ and not ‘on’ in order to
harmonise with the meaning of the earlier part of sub-
section (7) and to promote the object of its enactment. The
High Court’s conclusion that the arbitrator in the present
case had no jurisdiction on 26.3.1983 to make the award does
not suffer from any infirmity.
Consequently, the appeal fails and is dismissed.