Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
CASE NO.:
Appeal (civil) 5197 of 2000
PETITIONER:
Punjab State and Ors
RESPONDENT:
Dina Nath
DATE OF JUDGMENT: 14/05/2007
BENCH:
Tarun Chatterjee & Altamas Kabir
JUDGMENT:
J U D G M E N T
W I T H
CIVIL APPEAL NO.5198 OF 2000
The Executive Engineer, Anandpur
Sahib Hydel Construction Division
VERSUS
Dina Nath and Ors. Respondents
TARUN CHATTERJEE, J.
1. The crucial question that needs to be decided in these
appeals is whether Clause 4 of Work Order No.114 dated 16th of
May, 1985 (in short ’Work Order’) which says that: "Any dispute
arising between the department and the contractor/society shall be
referred to the Superintending Engineer, Anandpur Sahib, Hydel
Circle No. 1 Chandigarh for orders and his decision will be final
and acceptable/binding on both the parties" constituted an
arbitration agreement.
2. Before proceeding further, we may bring it on record
that though the facts in both the appeals are identical, but for
purposes of disposal of these appeals, the facts in CA No. 5197 are
being considered which are as follows:
3. The parties entered into a contract for the work of
dowel drain and wire crate at RD No. 9400 to 10400 kms. in the
State of Punjab. The appellants made running payments to the
respondent during the period of execution of the works in terms of
the Work Order. However, after completion of the work, the final
measurements were not made, nor the final bills were prepared.
The dispute remained pending with the department for which the
respondent called upon the appellants to finalise the dispute and
prepare the final bill as per the rates quoted by the respondent and
accepted by the appellants. A final notice was issued on 16th April,
1990, calling upon the appellants to refer the dispute to an
arbitrator as per Clause 4 of the Work Order. Since the appellants
had failed to appoint an Arbitrator, the respondent filed an
application before the Additional Senior Subordinate Judge, Ropar,
Punjab under Section 20 of the Arbitration Act, 1940 (in short ’the
Act’) seeking appointment of an Arbitrator.
4. By an order dated 20th October, 1993 the learned
Additional Senior Subordinate Judge, Ropar, Punjab after hearing
both the parties, allowed the application filed by the respondent
and referred the dispute for decision to the Superintending
Engineer, Anandpur Sahib, Hydel Circle No. 1 Chandigarh. The
Additional Senior Subordinate Judge, Ropar, while allowing the
application, held that Clause 4 of the Work Order must be
construed to be an arbitration agreement within the meaning of
Section 2(a) of the Act and that the application filed under Section
20 of the Act was filed within the period of limitation. According
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
to the learned Additional Senior Subordinate Judge, Ropar, the
cause of action arose from the date the final notice of demand was
sent, i.e., 16th April 1990, which was well within the period of 3
years from the date of filing the application as contemplated under
Article 137 of the Limitation Act 1963. Feeling aggrieved by the
aforesaid order, the appellants preferred an appeal in the Court of
the District Judge, Roopnagar, Punjab, which by an order dated
24th April, 1997 was allowed, inter alia, on a finding that Clause 4
of the Work Order could not be held to be an ’arbitration
agreement’ nor the dispute was covered within the ambit of the
Act. On the question of limitation in filing the application under
Section 20 of the Act, the appellate court held that the application
under Section 20 of the Act was barred by limitation. Feeling
aggrieved by the order of the learned Additional District Judge,
Roopnagar, Punjab, reversing the order of the Additional Senior
Subordinate Judge, Ropar, the respondent filed a Civil Revision
Case before the High Court of Punjab and Haryana at Chandigarh,
which by the impugned order was allowed and the order of the
Additional Subordinate Judge, Ropar was restored. Dissatisfied
with this order of the High Court, a special leave petition was filed
by the appellants, which on grant of leave was heard in the
presence of the learned counsel for the parties.
5. Having heard the learned counsel for the parties and
after going through the impugned order of the High Court as well
as the orders of the appellate court and the trial court and the
materials on record and considering the clauses in the Work Order,
we are of the view that the High Court was fully justified in setting
aside the order of the appellate court and restoring the order of the
Additional Subordinate Judge by which the dispute was referred to
arbitration for decision. Before proceeding further, we may,
however, take note of some of the relevant clauses in the Work
Order which read as under: -
"Clause 13 of the Work Order: - "If the contractor does not carry
out the work as per the registered specifications, the department
will have the option to employ its own labour or any other agency
to being the work to the departmental specification and recover the
cost therefrom."
Clause 4: "Any dispute arising between the department and the
contractor/society shall be referred to the Superintending Engineer,
Anandpur Sahib, Hydel Construct Circle No. 1, Chandigarh for
orders and his decision will be final and acceptable/binding on both
parties."
6. As pointed out herein earlier, the trial court on
consideration of Clause 4 of the Work Order held that Clause 4 of
the Work Order must be held to be an arbitration agreement and
accordingly an arbitrator was appointed in compliance with Clause
4 of the Work Order At this stage we feel it appropriate to
examine in detail whether clause 4 of the Work Order can be held
to be an arbitration agreement within the meaning of Section 2(a)
of the Act.
7. Section 2[a] of the Act defines ’arbitration agreement’
which means a written agreement to submit present or future
differences to arbitration whether arbitrator is named therein or not.
Mr. Tathore learned Additional Solicitor General appearing on
behalf of the appellants contended that although the Work Order
was allotted to the respondent on 16th May, 1985, the respondent
had failed to execute the work allotted to him and the appellants
had got the work executed at its own cost in terms of clause 13 of
the Work Order which, as noted herein earlier, provides that in case
the contractor does not execute the allotted work, the department
could get the same executed by other agencies or by itself. He
further contended that owing to such failure on the part of the
respondent, final bills were not prepared nor were the final
measurements taken for the purpose of payment to the respondent.
Accordingly, Mr. Tathore contended that there was no existence of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
any dispute and accordingly the question of referring such disputes
in terms of Clause 4 of the Work Order could not arise at all. This
submission of Mr. Tathore was contested by the learned counsel
for the respondent. Therefore, a dispute arose as to whether the
respondent had completed the work allotted to him under the Work
Order. This is an issue, according to the High Court as well as the
Subordinate Court, which should be referred for decision to an
arbitrator.
8. A bare perusal of the definition of arbitration
agreement would clearly show that an arbitration agreement is not
required to be in any particular form. What is required to be
ascertained is whether the parties have agreed that if any dispute
arises between them in respect of the subject matter of the contract,
such dispute shall be referred to arbitration. In that case such
agreement would certainly spell out an arbitration agreement. [See
Rupmani Bai Gupta v. Collector of Jabalpur AIR 1981 SC 479]
However, from the definition of the arbitration agreement, it is also
clear that the agreement must be in writing and to interpret the
agreement as an ’arbitration agreement’ one has to ascertain the
intention of the parties and also treatment of the decision as final. If
the parties had desired and intended that a dispute must be referred
to arbitration for decision and they would undertake to abide by
that decision, there cannot be any difficulty to hold that the
intention of the parties to have an arbitration agreement; that is to
say, an arbitration agreement immediately comes into existence.
9. In the case of Bihar State Mineral Development
Corporation v. Encon Building, [(2003) 7 SCC 418], this Court
held that "there is no dispute with regard to the proposition that for
the purpose of construing an arbitration agreement, the term
"arbitration" is not required to be specifically mentioned therein."
Looking to the opinion of the Hon’ble Judges in the said case and
also considering clause 4 of the Work Order in depth, we are of the
opinion that Clause 4 of the Work Order between the parties can be
interpreted to be an arbitration agreement even though the term
"arbitration" is not expressly mentioned in the agreement. In this
decision of this Court the test of ’dispute’ and ’reference’ was
again reiterated. In Para 17, it was stated that there cannot be any
doubt whatsoever that an arbitration agreement must contain broad
consensus between the parties that the disputes and differences
should be referred to a domestic tribunal.
10. We have already noted Clause 4 of the Work Order as
discussed hereinabove. It is true that in the aforesaid Clause 4 of
the Work Order the words "arbitration" and "arbitrator" are not
indicated; but in our view, omission to mention the words
"arbitration" and "arbitrator" as noted herein earlier cannot be a
ground to hold that the said clause was not an arbitration agreement
within the meaning of Section 2[a] of the Act. The essential
requirements as pointed out herein earlier are that the parties have
intended to make a reference to an arbitration and treat the decision
of the arbitrator as final. As the conditions to constitute an
’arbitration agreement’ have been satisfied, we hold that clause 4
of the Work Order must be construed to be an arbitration
agreement and dispute raised by the parties must be referred to the
arbitrator. In the case of K.K. Modi v. K.N. Modi [(1998) 3 SCC
573], this Court had laid down the test as to when a clause can be
construed to be an arbitration agreement when it appears from the
same that there was an agreement between the parties that any
dispute shall be referred to the arbitrator. This would be clear when
we read Para 17 of the said judgment and points 5 and 6 of the
same which read as under:
"5. That the agreement of the parties to refer their
disputes to the decision of the tribunal must be intended to
be enforceable in law; and
6. Agreement must contemplate that the tribunal will
make a decision upon a dispute, which is already formulated
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
at the time when reference is made to tribunal."
11. That apart, in Para 23 of the decision in the case of
K.K. Modi (supra), this Court also noticed its earlier decision in the
case of State of U.P. v Tippar Chand [1980 (3) SCC 241]. In that
case, the test as indicated above was also recorded in which it was
stated that "this court said that there was no mention in this clause
in any dispute much less any reference thereof."
12. Keeping the ingredients as indicated by this Court in
the case of K. K. Modi (supra) in mind for holding a particular
agreement as an arbitration agreement, we now proceed to examine
the aforesaid ingredients in the context of the present case.
a. Clause 4 of the Work Order categorically states that the
decision of the Superintending Engineer shall be binding on the
parties.
b. The jurisdiction of the Superintending Engineer to decide
the rights of the parties has also been derived from the consent of
the parties to the Work Order.
c. The agreement contemplates that the Superintending
Engineer shall determine substantive rights of parties as the clause
encompasses all varieties of disputes that may arise between the
parties and does not restrict the jurisdiction of the Superintending
Engineer to specific issues only.
d. That the agreement of the parties to refer their disputes to
the decision of the Superintending Engineer is intended to be
enforceable in law as it is binding in nature.
13. In view of the aforesaid conditions being satisfied,
which were based on the principles laid down by this Court in K.K.
Modi’s case (supra), there cannot be any doubt in our mind that the
arbitration agreement does exist. Clause 4 of the Work Order is an
Arbitration Agreement. The learned Counsel appearing on behalf
of the appellants contended that the ingredients laid down in the
case of K.K. Modi are not satisfied in the present case and
therefore following the principles laid down in that case, this Court
must hold that clause 4 of the Work order cannot be construed as
an arbitration agreement. We are unable to accept this contention
of the learned counsel of the appellants for two reasons. First, in
view of our discussions herein earlier, to the effect that all the
ingredients to hold a particular agreement as an arbitration
agreement have been satisfied in the preset case. Secondly, the
factual situations in the case of KK Modi (supra) and in the case
before us are very different. That case dealt with the evaluation and
distribution of assets, which required expert decision rather than
arbitration. The clause in the K.K Modi case (supra) had a very
restricted operation as it dealt with only disputes regarding
implementation of contract whereas, in the case before us, Clause 4
is much wider in its ambit as it deals with any dispute between the
contractor and the department.
14. The words "any dispute" appears in Clause 4 of the
Work Order. Therefore only on the basis of the materials produced
by the parties in support of their respective claims a decision can be
arrived at in resolving the dispute between the parties. The use of
the words ’any dispute’ in Clause 4 of the Work Order is wide
enough to include all disputes relating to the said Work Order.
Therefore, when a party raises a dispute for non-payment of money
after completion of the work, which is denied by the other party,
such a dispute would come within the meaning of ’arbitration
agreement’ between the parties. Clause 4 of the Work Order also
clearly provides that any dispute between the department and the
contractor shall be referred to the Superintending Engineer, Hydel
Circle No. 1, Chandigarh for orders. The word ’orders’ would
indicate some expression of opinion, which is to be carried out, or
enforced and which is a conclusion of a body (in this case
Superintending Engineer, Hydel Circle No. 1, Chandigarh). Then
again the conclusion and decision of the Superintending Engineer
will be final and binding on both the parties. This being the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
position in the present case and in view of the fact that Clause 4 of
the Work Order is not under challenge before us, the decision that
would be arrived at by Superintending Engineer, Hydel Circle No.
1, Chandigarh must also be binding on the parties as a result
whereof Clause 4 must be held to be a binding arbitration
agreement.
15. In the decision of this Court in the case of State of UP
v. Tippar Chand (supra), this Court however held that the clause
in dispute in that decision between the parties did not amount to an
arbitration agreement. In that decision, this Court further held that
clause under consideration before them which provided that except
where otherwise specified in the contract the decision of the
Superintending Engineer for the time being shall be final,
conclusive and binding on all the parties to the contract upon all
questions relating to the meaning of the specifications etc and the
decision of the Superintending Engineer as to the quality,
workmanship etc. shall be final, conclusive and binding between
the parties does not constitute an arbitration agreement but while
arriving at such a conclusion this Court referred to a decision of the
Jammu and Kashmir High Court in the case of Dewan Chand v.
State of Jammu and Kashmir [AIR 1961 J & K 58]. In the
Dewan Chand case (supra) the relevant clause runs as follows:- "
For any dispute between the contractor and the Department the
decision of the Chief Engineer PWD Jammu and Kashmir, will be
final and binding upon the contractor. This Court in that decision
had put strong reliance on the expression "any dispute between the
contractor and the department" and approved the conclusions
arrived at by the J & K High Court. It came to the conclusion by
interpretation of that clause that there did not exist any arbitration
agreement as the decision of the Superintending Engineer in
connection with the work done by the contractor was meant for
supervision and execution of the work and administrative control
over it from time to time. However, in Clause 4 of the Work Order
in the present case, which specifically states that in case of any
dispute between the appellants and the contracting parties, the
matter shall be referred to the Superintending Engineer. Therefore,
the use of the words "any dispute" would clearly mean that it
would lead to conclude that the said agreement was in fact an
arbitration agreement and thus these words do not restrict the scope
of the contract.
16. Before parting with this aspect of the matter we may
note the decision of State of Orissa v. Damodar Das [1996(2)
SCC 216] on which strong reliance was placed before us by the
learned counsel for the appellants. This decision of this court may
not be helpful to the appellants as we find the agreement in
question in that case was different from Clause 4 of the Work
Order. For proper appreciation, we may reproduce the agreement in
the case of Damodar Das which reads as under:-
"25. Decision of Public Health Engineer to be final -
Except where otherwise specified in this contract, the
decision of the Public Health Engineer for the time being
shall be final, conclusive and binding on all parties to the
contract upon all questions relating to the meaning of the
specifications; drawings and instructions hereinbefore
mentioned and as to the quality of workmanship or materials
used on the work, or as to any other question, claim, right,
matter or thing, whatsoever in any way arising our of, or
relating to, the contract, drawings specifications estimates,
instructions, orders or these conditions, or otherwise
concerning the works or the execution or failure to execute
the same, whether arising during the progress of the work or
after the completion or the sooner determination thereof of
the contract."
17. A plain reading of this clause in the case of Damodar
Das, it is evident that the powers of the Public Health Engineer
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
were essentially to supervise and inspect. His powers were limited
to the questions relating to the meaning of the specifications;
drawings and instructions, quality of workmanship or materials
used on the work, or any other question, claim, right, matter,
drawings specifications estimates, instructions, orders or these
conditions, or otherwise concerning the works or the execution or
failure to execute the same. However, in the case before us, the
Superintending Engineer was given full power to resolve any
dispute arising between the parties which power in our view is
wide enough to cover any nature of dispute raised by the parties.
The Clause in the instant case categorically mentions the word
"dispute" which would be referred to him and states "his decision
would be final and acceptable/binding on both the parties."
18. That being the position, we are of the view that the
clause in the case of Damodar Das and Clause 4 of the Work Order
of the present case are totally different. We accordingly do not find
any reason to hold otherwise.
19. At the risk of repetition we may also say before
parting with this judgment that Clause 4 of the Work Order speaks
for a dispute between the parties. It also speaks of a dispute and all
such disputes between the parties to the Work Order shall be
decided by the Superintending Engineer, Anandpur Sahib Hydel
Circle No. 1. Obviously, such decision can be reached by the
Superintending Engineer, Anandpur Sahib Hydel Circle No. 1 only
when it is referred to him by either party for decision. The
reference is also implied. As the Superintending Engineer will
decide the matter on reference, there cannot be any doubt that he
has to act judicially and decide the dispute after hearing both the
parties and permitting them to state their claim by adducing
materials in support. In Clause 4 of the Work Order it is also
provided as noted herein earlier that the decision of the
Superintending Engineer shall be final and such agreement was
binding between the parties and decision shall also bind both the
parties. Therefore, the result would be that the decision of the
Superintending Engineer would be finally binding on the parties.
Accordingly, in our view, as discussed herein above that although
the expression "award" or "arbitration" does not appear in Clause 4
of the Work Order even then such expression as it stands in Clause
4 of the Work Order embodies an arbitration clause which can be
enforced.
20. For the reasons aforesaid, we are of the view that
Clause 4 of the Work Order can safely be interpreted to be an
arbitration agreement even though the term ’arbitration’ is not
expressly mentioned in the agreement. In view of our discussions
made herein earlier, we therefore conclude that Clause 4 of the
Work Order constitutes an arbitration agreement and if any dispute
arises, such dispute shall be referred to Superintendent Engineer for
decision which shall be binding on the parties.
21. Before parting with this judgment, we may consider a
short submission advanced at the Bar on the question of limitation
in filing the application under Section 20 of the Act. At the risk of
repetition, we may keep it on record that the Additional Senior
Subordinate Judge, Ropar, held that the application was filed in
time whereas the appellate court held that the application was
barred by limitation. However, the High Court in revision restored
the order of the Additional Senior Subordinate Judge, Ropar, by
holding that application was filed within the period of limitation.
22. For the purpose of deciding the question of limitation,
it may be stated that the application under Section 20 of the Act
was filed within 3 years from the date the demand notice was made
by the respondent as contemplated under Article 137 of the
Limitation Act.
23. In order to determine when the cause of action arose,
it is essential for us to refer to a case decided by this court. In the
case of S. Rajan v. State of Kerala [(1992) 3 SCC 608] it was
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
held by this Court that the right to apply for arbitration proceeding
under Section 20 of the Arbitration Act, 1940 runs from the date
when the dispute arises. It observed:
"Reading Article 137 and Sub-section (1) of Section 20
together, it must be said that the right to apply accrues when the
difference arises or differences arise, as the case may be, between
the parties. It is thus a question of fact to be determined in each
case having regard to the facts of that case."
24. Accepting the principles laid down in the case of S.
Rajan (supra), this Court in the case of Hari Shankar Singhania
and Ors. v. Gaur Hari Singhania and Ors. [(2006) 4 SCC 658]
again reiterated the principle that an application under section 20 of
the Act for filing the arbitration agreement in Court and for
reference of the dispute to arbitration in accordance therewith is
required to be filed within a period of three years when the right to
apply accrues and that the said right accrues when difference or
dispute arises between the parties to the arbitration agreement.
Keeping the principles in mind, let us now examine as to when
difference or dispute arises between the parties to the arbitration
agreement, when the right to apply accrues. As noted herein earlier,
demand notice was served on the appellants by the respondent on
16th April 1990 and the application under section 20 of the Act was
filed on 13th November 1990 which is admittedly within the period
of limitation as contemplated under Article 137 of the Limitation
Act.
25. The Additional District judge, Roopnagar, Punjab,
held on the question of limitation in filing the application under
section 20 of the Act that the cause of action did not arise when
notice of demand was served but arose when the respondent first
acquired either the right of action or the right to require that
arbitration takes place upon the dispute concerned.
26. Keeping the decisions of this court in the cases of S.
Rajan (supra) and Hari Shankar Singhania (supra) in mind, in our
opinion, the view of the Additional District Judge was totally
erroneous. In the aforesaid two decisions, it was held that the right
to apply accrued for the difference arising between the parties only
when service of demand notice was effective, which should be the
date for holding that the difference had already arisen between the
parties. Such being the settled law, we are of the view that the
application under section 20 of the Act was clearly filed within the
period of limitation.
27. For the reasons aforesaid we do not find any merit in
these appeals. Accordingly, the appeals are disposed of with no
orders as to cost.