Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
CASE NO.:
Appeal (civil) 619 of 2005
PETITIONER:
National Insurance Company Ltd.
RESPONDENT:
Nipha Exports Pvt. Ltd.
DATE OF JUDGMENT: 29/09/2006
BENCH:
H.K. SEMA & P.K.BALASUBRAMANYAN
JUDGMENT:
J U D G M E N T
(with I.A. No. 2)
H.K.SEMA,J.
The challenge in this appeal is to the order dated 8th
September, 2004 passed by the National Consumer Disputes
Redressal Commission (hereinafter the Commission) in
Original Petition No. 42 of 1996. By the aforesaid order, the
Commission directed the appellant, National Insurance
Company Ltd., to pay interest @ 6% on Rs.70,38,038/- from
10th December 1990 till 8th June, 1994 within a period of eight
weeks by way of damages.
A limited notice was issued by this Court on
13.01.2005 on payment of interest @ 6% as damages by
reason of delay in payment.
The sole question to be determined in this appeal is,
as to whether there was any delay in making the payment of
Rs.70,38,038/- and if so, the insurance company, the
appellant is liable to pay interest @ 6% for delay in payment as
ordered by the Commission.
Few background facts may be noted:
In 1990, five transit insurance were obtained by the
respondent herein for covering their consignment to Sudan for
their principals i.e. M/s Sudan Gezire Rehabilitation Project,
Khartoum, Sudan. The policies were issued subject to the
terms and conditions. It was discovered that on arrival of the
consignment there was some damage on account of rust. The
investigations were carried out in respect of the transit of the
consignment at the destination port to find out as to at which
stage the damage to the consignment could have had
occurred. A dispute was also raised between the parties as
to who would be entitled to receive the claim amount as the
shipment was on C.I.F. basis. Ultimately, the matter was
resolved and the legalized documents of consignments were
furnished to the appellant on 21.5.1993. Thereafter, various
correspondences between the parties to accept the offer of the
claim amount as offered by M/s American President Lines. It
is alleged that till the letter dated 25.6.1993 written by the
appellant there was no acceptance of the offer by the
complainant-respondent herein and the matter was withheld
at the instance of the complainant. There was also a dispute
between the parties because in the policy, the machinery items
were subject to institute replacement clause, which provided
for the indemnity to be made only when the loss or damage
suffered by the goods to the extent of actual cost of repairs,
replacement and conditions effected and incurred. The
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
complainant was also claiming that they had incurred out of
pocket expenses and, therefore, the appellant was asking them
to provide and furnish the necessary bills in support of total
expenses incurred by them, which they failed to do and
therefore, the matter was again referred to M/s Webster & Co.
for making the investigation into the possible cost involved
from M/s Nipha and their local suppliers, respondent herein.
Ultimately, M/s Webster by its letter dated 8.4.1994
settled the claim on the basis of consignment as done by the
Surveyors.
In the facts and circumstances, as recited above, it
cannot be said that prior to the letter dated 8.4.1994 the claim
had been finally settled and the payment was withheld by the
appellant. After the settlement of the amount US $279158.40
equivalent to Rs.70,38,038/- was paid to the respondent on
8.6.1994. The respondent received the aforesaid amount and
gave a clean discharge to the appellant without any
qualification, signifying receipt of the amount in full and final
settlement of the claim.
Mr.Mahendra Anand, learned senior counsel,
appearing on behalf of the respondent, referred to a letter
dated 17.3.1991 and submitted that by the aforesaid letter
right, title and interest was vested with M/s Nipha Exports
Private Ltd. by Sudan Gezire Rehabilitation Project. In the
letter aforesaid, it is stated that they have no objection to
settle the claim in favour of M/s Nipha Exports Private Ltd.,
and advised to address the correspondence direct to them in
future. It is his contention that there is no explanation
whatsoever by the appellant for withholding the payment from
17.3.1991 to 8.4.1994, the date on which the matter was
settled. In view of the circumstances, as recited above, we are
unable to accept this contention. From the letter dated
17.3.1991, it is clear that it was not the settlement of the
claim but it was a no objection certificate that the claim may
be settled in favour of the respondent and advise that all
future correspondence be addressed to them directly.
Therefore, it cannot be said that the final settlement was
arrived at by the aforesaid letter.
The next question to be considered is as to whether
after giving a clean discharge certificate by accepting the
amount signing the voucher, the complainant-respondent can
raise the complaint?
As already noticed, the payment was made to the
respondent on 8.6.1994 and the respondent gave a clean
discharge to the appellant without any qualification, signifying
receipt of the amount in full and final settlement of the claim.
Thereafter, after a lapse of two months the respondent
addressed a letter dated 6.8.1994 to the appellant which is
extracted:
"Re:Marine Loss NO.101500/43/90-91/86-90
Ex.M.V. Eagle Nov/Fresia.
Dear Sir,
Thank you for your letter dated the 9th June,
1994 enclosing a Cheque for Rs.70,38,038/- in
discharge of your liability under the policies,
which, however, did not include interest."
In the letter, thus read there is no complaint that
the discharge voucher or receipt had been obtained from the
complainant respondent herein fraudulently or by exercise of
undue influence or by misrepresentation or the like or coercive
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
bargaining. In the case of United India Insurance Vs.
Ajmer Singh Cotton & General Mills, (1999) 6 SCC 400, it
was pointed out by this Court that mere execution of
discharge voucher would not always deprive the consumer
from preferring claim with respect to the deficiency in service
or consequential benefits arising out of the amount paid in
default of the service rendered. It was further pointed out that
despite execution of the discharge voucher, the consumer may
be in a position to satisfy the Tribunal or the Commission
under the Act that such discharge voucher or receipt had been
obtained from him under circumstances which can be termed
as fraudulent or exercise of undue influence or by
misrepresentation or the like, and if such a case is proved, the
authority before whom the complaint is made would be
justified in granting appropriate relief.
This Court in Polymat India P.Ltd. vs. National
Insurance Co.Ltd., 2004(10) Scale 99 also considered the
facts of a similar case as in the case in hand. In that case
the reason for delay had been explained. The fire took place on
13th January, 1993 in which the insured goods were reportedly
gutted by fire. The insurance company appointed the
Surveyor and Surveyor sent his report dated 5th November,
1993 which was received by the appellant on 9th November,
1993. As there were some discrepancies in the survey report,
the insurance company vides letter dated 14th December, 1993
sought for clarification from the Surveyor, which was replied
to on 22.4.1994 by the Surveyor. The insurance company
after that took the decision and informed the claimant by a
letter dated 1.7.1994 for approval of the claim under both the
policies. It is, in these circumstances, this Court held that
there was no delay in payment and the levy of interest @ 18%
by the Commission was set aside by this Court.
In the present case, the claim of the complainant
was finally settled by a letter dated 8.4.1994 and the payment
was made on 8.6.1994, which was accepted by the respondent
without any qualifications. It cannot, therefore, be said that
the payment was made belatedly. The important date to be
decided in such circumstances is the date on which the
quantum of compensation and to whom it should be paid is
finally decided and not from the dates on which the
correspondences ensued between the parties.
In the facts and circumstances, aforestated, we are
of the view, that the claim was finally settled by a letter dated
8.4.1994 and the payment was made on 8.6.1994, and
therefore, there was no delay in making the payment which
would warrant the award of interest on delayed payment. The
view taken by the Commission was, therefore, erroneous. The
Order dated 8th September, 2004 of the Commission is set
aside. The appeal is allowed. No costs.