Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 6
PETITIONER:
BIHAR STATE ELECTRICITY BOARD & ANR.
Vs.
RESPONDENT:
DHANAWAT RICE AND OIL MILLS
DATE OF JUDGMENT17/01/1989
BENCH:
OZA, G.L. (J)
BENCH:
OZA, G.L. (J)
SAIKIA, K.N. (J)
CITATION:
1989 AIR 1030 1989 SCR (1) 168
1989 SCC (1) 452 JT 1989 (1) 425
1989 SCALE (1)162
ACT:
Electricity (Supply) Act, 1948: Sections 18, 26, 28, 29,
49, 54 & 60--Agreement to supply electrical energy--Clauses
1, 4 and 13 of the agreement--Provision for constant supply
of electricity--Constant supply whether continuous
supply--Minimum annual guarantee payment-Tripping, load-
shedding and power cut--Failure to supply continuous elec-
tricity--Circumstances beyond control of Electricity
Board--Consequent non-consumption by consumer upto the level
of minimum guarantee--Consumer entitled to proportionate
reduction.
HEADNOTE:
Clause 1, of the agreement arrived at between the con-
sumerrespondents and the appellant-Electricity Board, pro-
vided for constant supply of electrical energy to the con-
sumers. Clause 4 provided that even if the consumer does not
consume electricity above the minimum guarantee then it will
be incumbent upon the consumer to pay annual minimum
charges. Clause 13 provided for the contingency that if the
consumer is prevented from receiving or using the electrical
energy due to strikes, riots, fire, floods, explosions, act
of God or any other case reasonably beyond the control of
the Board or if the Board is prevented from supplying such
electrical energy owing to any of the causes mentioned then
the consumer was entitled to a proportionate reduction of
the annual minimum guarantee bill as determined by the Chief
Engineer.
The respondents were served with the hills for annual
minimum guarantee for the years 1973-74 to 1982-83 by the
Electricity Supply Division. The respondents filed their
claims, under clause 13, with the Chief Engineer denying
their liability to pay any such charges because the Board
did not supply constant supply as provided in clause 1. It
was alleged that during the period in question due to trip-
pings, load-sheding and power-cut the respondents suffered a
great loss. The Chief Engineer negatived the claims of the
respondents.
A batch of writ petitions was filed in the High Court,
challenging the order of the Chief Engineer. Although in
these petitions relief sought was proportionate reduction of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 6
the annual minimum guarantee
169
bills but in view of the interpretation of clauses 1, 4 and
13 the High Court quashed the demand made by the Electricity
Board by holding that under clause 1 it was incumbent for
the Electricity Board to supply constant electricity supply
and that the consumers will be liable to pay annual minimum
guarantee charges only if the Board supplies the power as
provided in the agreement but the consumer does not utilise
the power.
In these appeals by Special Leave, it was contended on
behalf of the appellants that the ’constant supply’ men-
tioned in clause I cannot mean ’continuous supply’. The
respondent-consumers could not deny the liability to pay
annual minimum guarantee bills if the Electricity Board
could not supply power for all the 24 hours due to circum-
stances beyond the control of the Electricity Board. In case
of shortage of supply due to circumstances beyond the con-
trol of the Board the consumers were entitled to a propor-
tionate reduction under clause 13 of the agreement.
Allowing the appeals, the Court,
HELD: 1. The High Court was not right in coming to the
conclusion that the respondents were not liable at all to
pay the annual minimum guarantee charges. [175C]
1.1. The High Court in its judgment clearly stated the
hours every year in dispute when the power was not supplied
and on this basis the respondent*consumers will only be
entitled to proportionate reduction as ordinarily the con-
sumers are expected to have continuous power supply. Clause
13 clearly provides for the proportionate reduction of the
annual minimum guarantee bills. [175D]
2. Clause 1 talks of constant supply of electrical
energy providing for voltage, cycles, phases and wires. It
does not talk of either of continuous or non-continuons or
intermittent supply. [173E]
3. The Respondent consumers are entitled to a propor-
tionate reduction of the minimum guarantee bill. The inabil-
ity of the Electricity Board to supply electrical energy due
to power cut or any other circumstance beyond its control as
per the demand of the consumer according to the contract
will be reflected in and considered as a circumstance beyond
the control of the consumer which prevented it from consum-
ing electricity as per the contract and to the extent-it
wanted to consume. [173G]
170
Northern India Iron & Steel Co. etc. v. State of Haryana
JUDGMENT:
4. The Chief Engineer of the Electricity Board shall
accordingly assess the proportionate reduction of the annual
minimum guarantee bills in respect of disputed years on the
basis of non supply as indicated in the High Court Judgment.
[175D-E]
4.1. Pending assessment, the power supply of the consum-
ers will not be disconnected on the ground of failure to pay
the annual minimum guarantee bills. [175E]
4.2. The Electricity Board will be entitled to take
recourse to the normal procedure if the consumers fail to
pay after the proportionate reduction is made and fresh
demand is made. [175E-F]
Amalgamated Electricity Co. Ltd. v. Jalagaon Borough
Municipality, [1976] 1 SCR 636; M/s. Man Industrial Corpo-
ration v. Rajasthan State Electricity Board and others, AIR
1986 Rajasthan 137 and Mukand Iron and Steel Works Ltd. v.
Maharashtra State Electricity Board and another, AIR 1982
Bombay 580, referred to.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 6
&
CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 156164
of 1989.
From the Judgment and Order dated 24.7.1987 and 7.4.1988
of the Patna High Court in C.W.J.C. Nos. 253, 266,
262,255,260 265, 555,254 of 1986 and C.W.J.C. No. 17 of 1988
respectively.
Dr. Y.S. Chitale and Pramod Swarup for the Appellants.
N.R. Choudhary and L.R. Singh for the Respondents.
The Judgment of the Court was delivered by
OZA, J. Leave granted.
These special leave petitions have been filed against
the judgment of the High Court of Patna by which several
writ petitions were disposed of. All these special leave
petitions have been preferred in this Court aggrieved by
that judgment. The common question which arises in all these
SLPs is that under the agreement arrived at between the
consumers and the Bihar State Electricity Board there is a
clause
171
Of payment of minimum guarantee which indicates that even if
the consumer does not consume electricity above the minimum
guarantee that it will be incumbent upon the consumer to pay
charges for energy which is the annual minimum guarantee
provided in the agreement pertaining to Industrial units.
The relevant facts are that for the years 1973-74 to
1982-83 the bills for annual minimum guarantee were served
on the appellants by the Electricity Supply Division,
Forbesganj and on receipt thereto the appellants filed their
claims as provided under clause 13 of the agreement on the
ground that appellant was not liable to pay any such charges
because the appellant did not supply constant electricity as
provided in the agreement during the period in question and
there were tripping, load shedding, and power-cut which
resulted in a great loss to the petitioners and as the
supply was not in accordance with the agreement liability to
pay annual minimum guarantee bills could not be fastened on
the consumer. The Chief Engineer who was the authority under
the agreement negatived the claim and so they filed writ
petitions in the High Court.
The High Court by the impugned judgment came to the
conclusion that under clause 1 of the agreement it was
incumbent for the Electricity Board to supply constant
electricity and the consumer will be liable to pay annual
minimum guarantee charges only if in spite of the fact that
the Board supplies power as contemplated in the agreement
and the consumer does not utilise the power then the liabil-
ity to pay annual minimum guarantee charges will arise and
on this basis the High Court quashed the demands made for
these years on the basis of annual minimum guarantee as it
found that power was not supplied according to the agree-
ment.
Learned counsel appearing for the Electricity Board
contended that clause 1 of the agreement does not in any
manner mean that there should be a continuous supply. The
term used in clause 1 of the agreement only talks of con-
stant supply of electrical energy at the pressure of volts,
cycles, 3 phase, 3 wire etc. but it does not talk of contin-
uous supply without any break and it therefore could not be
contended that if there was no supply for a few minutes it
will amount to failure on the part of the Electricity Board
to provide constant supply. It was contended that the con-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 6
stant supply cannot mean continuous supply. It was also
contended that clause 4 of the agreement clearly talks of
the payment of annual minimum guarantee charges and there-
fore it could not be said that because of the power cut or
situations beyond the
172
control of the Electricity Board if the power could not be
supplied for all the 24 hours every day the respondent
consumer can deny the liability to pay annual minimum guar-
antee bills. It was also contended that in view of clause 13
of the agreement which provides that if there was shortage
of supply and that shortage resulted in short supply then
the consumer was entitled to a proportionate reduction of
the annual minimum guarantee bill as determined by the Chief
Engineer, Bihar State Electricity Board and consequently the
respondent in this case went to the Chief Engineer who
ultimately decided on the basis of facts that respondents
were not entitled to any proportionate reduction and it was
because of this that the petitions were filed before the
High Court. It was contended that the learned Judges of the
High Court have failed to appreciate clause 13 of the agree-
ment. Learned counsel also placed reliance on the decisions
in Amalgamated Electricity Co. Ltd. v. Jalgaon Borough
Municipality, [1976] 1 SCR 636; M/s Northern India Iron &
Steel Co. etc. v. State of Haryana & Anr., [1976] 2 SCR 677;
M/s Man Industrial Corporation v. Rajasthan State Electrici-
ty Board and others, AIR 1986 Rajasthan 137 and Mukand Iron
and Steel Works Ltd. v. Maharashtra State Electricity Board
and another, AIR 1982 Bombay 580.
Learned counsel for the respondents on the other hand
contended that clause 1 provides for constant supply of
power, the variations permitted have been indicated in this
clause itself and it is contended that it is only where the
electricity Board discharges its duty to supply power as
contemplated in clause 1 and the consumer because of his
difficulties is not able to utilise power even upto the
level of minimum guarantee that the liability to pay annual
minimum guarantee bills could be fastened on the consumer
but if the Board fails to discharge its responsibilities as
contemplated in clause 1 of the agreement it could not
compel the consumer to pay the annual minimum guarantee. It
was frankly conceded that in the petition itself originally
relief sought was proportionate reduction of the annual
minimum guarantee bills but in view of the interpretation of
clauses 1, 4 and 13 the High Court came to the conclusion
that there is no liability on the consumer to pay annual
minimum guarantee bills as the Electricity Board has failed
to supply power as contemplated in clause 1 of the agree-
ment. Learned counsel however contended that the Chief
Engineer in his order has misunderstood the whole situation
but before the High Court the facts were not disputed and in
each case average hours of supply per year during the dis-
puted period have been stated which have not been disputed
by the Electricity Board and if at all the High Court judg-
ment is not maintained the respondents are entitled to
173
proportionate reduction of the annual minimum guarantee
bills in the light of the hours of supply per year which
have been stated in the High Court judgment and is not
disputed.
Clause 1 of the agreement reads as under:
"1. (a) The Board shall furnish to the consum-
er and the consumer shall accept at the point
of supply mentioned in the schedule hereto, on
and from the date on which the said premises
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 6
shall be connected with the supply Distribut-
ing mains and during the continuance of the
agreement, a constant supply of electrical
energy at the pressure of ......
Volts, 50 cycles, 3 phases, 3 wires, alternat-
ing current system subject to standard varia-
tions as provided in Indian Electricity
Rules, 1956 or any other statutory modifica-
tion thereof as may be in force from time to
time for the purpose and upto the maximum
specified (hereinafter referred to as the
contract demand) and under the conditions laid
down in the Schedule."
This clause talks of constant supply of electrical energy
providing for voltage, cycles, phases and wires. It is clear
that it does not talk of continuous supply nor does it talk
of non-continuous or intermittent supply. In fact this
clause in our opinion is not very material for the decision
of the case as the sole controversy pertains to interpreta-
tion of clause 13.
Clause 4 of the agreement provides for the minimum
guarantee and there is no dispute that if the consumer is
not able to utilise electricity even upto the level of
minimum guarantee. This clause provides for payment of
charges of minimum guarantee. The real controversy pertains
to the interpretation of clause 13. In fact in Northern
India Iron & Steel Co. case. [1976] 2 SCR 677 this Court had
the occasion to consider a situation of this kind where this
Court on this aspect of the matter has observed that where
the Electricity Board fails to supply power because of
shortage of energy, power cut or any other circumstances as
per demand of the consumer according to the contract it will
be considered as a circumstance beyond the control of the
consumer which prevented it from consuming electricity as
per the contract.
Their Lordships observed as under:
174
"We are, therefore, of the view that
the inability of the Board to supply electric
energy due to power cut or any other circum-
stance beyond its control as per the demand of
the consumer according to the contract will be
reflected in and considered as a circumstance
beyond the control of the consumer which
prevented it from consuming electricity as per
the contract and to the extent it wanted to
consume. The monthly demand charge for a
particular month will have to be assessed in
accordance with subclause (b) of clause 4 of
the tariff and therefore from a proportionate
reduction will have to be made as per sub-
clause (f). We hope, in the light of the
judgment, there will be no difficulty in
working out the figures of the proportionate
reduction in any of the cases and for any
period. In case of any difference or dispute
as to the quantum of the demand charge or the
proportionate reduction, parties will be at
liberty to pursue their remedy as may be
available to them in accordance with law."
It appears that reading clause 13 in the present case clear-
ly provides for the contingency and it provides for the
failure on the part of the supplier and also failure on the
part of consumer in the circumstances like strike, riot,
fire, flood, explosion or act of God or any other reason
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 6
beyond the control of either of the parties. Clause 13 of
the agreement reads:
"If at any time the consumer is prevented from
receiving or using the electrical energy to be
supplied under this agreement either in whole,
or in part due to strikes, riots, fire,
floods, explosions, act of God or any other
case reasonably beyond control or if the Board
is prevented from supplying or unable to
supply such electrical energy owing to any or
all of the causes mentioned above then the
demand charge and guaranteed energy charge set
out in the schedule shall be reduced in pro-
portion to the ability of the consumer to take
or the Board to supply such power and the
decision of the Chief Engineer, Bihar State
Electricity Board, in this respect shall be
final."
In view of this language of the clause clearly providing for
the proportionate reduction of the annual minimum guarantee
bills it could not be doubted that the High Court was not
right in coming to the conclusion that the respondents were
not liable to pay annual minimum
175
guarantee bills at all. The judgment of this Court also
clearly indicated that the respondents consumers. are enti-
tled to a proportionate reduction of the minimum guarantee
bills. In clause 13 of the agreement this is clearly stated
that the authority competent to determine the proportionate
reduction is the Chief Engineer and it appears that it was
because of this that the respondents consumers approached
the Chief Engineer for consideration. But it appears that
the learned Chief Engineer also did not clearly understand
the meaning of clause 13. The judgment of the High Court on
which reliance is placed have only followed the judgment
referred to above.
In our opinion, therefore, the High Court was not right
in coming to the conclusion that the respondents were not
liable at all to pay annual minimum guarantee charges. In
fact they are only entitled to the proportionate reduction.
The judgment of the High Court clearly states the hours
every year in dispute when the power was not supplied and on
this basis the respondents consumers will be entitled to
proportionate reduction as ordinarily the consumers are
expected to have continuous power supply. It is therefore
directed that the Chief Engineer of the Electricity Board on
the basis of hours of non supply as indicated in the High
Court judgment and not disputed in the High Court will
assess the proportionate reduction of the annual minimum
guarantee bills in respect of disputed years indicated above
and it is also directed that until this is not done the
power supply will not be disconnected on the basis of fail-
ure to pay the annual minimum guarantee bills for the peri-
ods stated above. However,-after the proportionate reduction
is made and fresh demand is made, Electricity Board will be
entitled to take recourse to the normal procedure if the
consumers fail to pay.
In the circumstances no order as to costs.
T.N.A. Appeals allowed.
176