REPORTABLE
2023 INSC 976
IN THE SUPREME COURT OF INDIA
CIVIL ORIGINAL JURISDICTION
ARBITRATION PETITION NO. 43 OF 2022
LOMBARDI ENGINEERING LIMITED …PETITIONER(S)
VERSUS
UTTARAKHAND JAL VIDYUT NIGAM LIMITED …RESPONDENT(S)
J U D G M E N T
J. B. PARDIWALA, J.:
1. This is a petition under Section 11(6) of the Arbitration and Conciliation
Act, 1996 (for short, “the Act 1996”) filed at the instance of a company based in
Switzerland and engaged in the business of design consultancy seeking
appointment of an arbitrator for the adjudication of disputes and claims
emanating from the Contract dated 25.10.2019 entered into between the
petitioner and respondent i.e., Uttarakhand Vidyut Nigam Limited (a wholly
Signature Not Verified
Digitally signed by
CHETAN KUMAR
Date: 2023.11.06
17:20:53 IST
Reason:
owned corporation of the Government of Uttarakhand).
1
FACTUAL MATRIX
2. The petitioner is a design consultancy firm based in Switzerland, having
its registered office at Via Del Tiglio 2, PO Box 934, CH 934, CH 6512,
st
Bellinzona-Guibiasco, Switzerland and local Indian address at B3/61, 1 Floor,
Safdarjung Enclave, Delhi – 110029.
3. The respondent is a wholly owned corporation of the Government of
Uttarakhand having its registered office at Maharani Bagh, GMS Road,
Dehradun, Uttarakhand, India and is engaged in the business of operating hydro
power plants in the State of Uttarakhand.
4. The petitioner entered into a contract with the Uttarakhand Project
Development and Construction Corporation Limited (hereinafter referred to as
“UPDCC”) for “Providing consultancy services and preparation of modified
comprehensive and bankable Detailed Project Report of Arakot Tiuni Hydro
Electric Project on river Pabar in district Uttarkashi of Uttarakhand” dated 25.10.
2019 (Tender Reference No. 01/DGM/UPDCC/2018-19) (hereinafter referred to
as, ‘the Contract’ or ‘the Project’). The Project was valued at Rs. 1,39,45,000/-
(Rupees One Crore Thirty-Nine Lac Forty-Five Thousand only) (hereinafter
referred to as the “Contract Value”). The petitioner was to commence work on
the date of the execution of the Contract, i.e., 25.10.2019 and complete the work
within 24 months, i.e., by 25.09.2021.
2
5. The Schedule A to Clause 5 of the Special Conditions of Contract (SCC)
(hereinafter referred to as the “Schedule A”) provided for the completion period
of all works that the petitioner was required to carry out under the Project.
Further, the Schedule B to Clause 5 of the SCC (hereinafter referred to as the
“Schedule B”) provided for the payment that was to be released to the petitioner
upon the completion of each stage of work.
6. The respondent took over the said Project from the UPDCC pursuant to
an order dated 08.05.2020, passed by the Government of Uttarakhand, which
directed that the Project be transferred from UPDCC to the respondent. The
takeover of the Project was done by virtue of a tripartite agreement dated
06.10.2020 (hereinafter referred to as the “Tripartite Agreement”), whereby the
Contract was novated to the extent that the respondent stepped into the shoes of
UPDCC and took over all the obligations under the Contract.
7. The Clause 53 read with Clause 55 of the General Conditions of Contract
(hereinafter referred to as “GCC”), which forms part and parcel of the Contract
between the petitioner and the respondent, set out the Arbitration Agreement.
The said clauses are reproduced hereinbelow for reference:
“ CLAUSE-53: PROCEDURE FOR CLAIMS:
53.1 If a dispute of any kind, whatsoever, arises between the
Employer and contractor in connection with or arising out of the
contract for the execution of this works, whether during the
execution of the works or after their completion and whether
before or after repudiation or termination of the contract,
including any disagreement by either party with any action,
3
inaction, opinion, instruction determination, certificate or
valuation of the Engineer, the matter in dispute shall, be referred
to in accordance with the provisions of the Arbitration and
Conciliation Act, 1996 or any statutory modification or re-
enactment thereof and the rules made the under and for the time
being in force, shall apply to the arbitration proceedings.
53.2 The contractor shall submit the details of his claims in
writing including:
(i) Particulars concerning the events on which the claim is based;
(ii) the legal basis for the claim, whether based on a term of the
Contract or otherwise, and if based on a term of the Contract,
clearly identifying the specific term;
vii) the facts relied upon in support of the Claim in sufficient
detail to permit verification; and
viii) details of the amount claimed and how it has been
calculated.
Xxx xxx xxx
CLAUSE-55: ARBITRATION:
(a) All question and disputes relating to the meaning of the
specification design, drawing and instructions herein and as
to the quality of workmanship or materials used on the work
or as to any other question claim, right, matter or thing,
whatsoever in any way arising out of or relating to the
contract, designs, drawings, specification, estimates
instructions, orders or these condition or otherwise
concerning the works or the execution or failure to execute
the same, whether arising during the progress of the work or
after the cancellation, termination, completion or
abandonment thereof, shall be conducted in accordance with
the provisions of the Arbitration and Conciliation Act, 1996
or any statutory modification or re-enactment thereof and the
rules made the under and for the time being in force, shall
apply to the arbitration proceedings. However, the Party
initiating the arbitration claim shall have to deposit 7% of
the arbitration claim in the shape of Fixed Deposit Receipt
as security deposit.
(b) On submission of claims the Arbitrator shall be appointed as
per the following procedure:
4
I) For claim amount upto 10.00 Crores, the case shall be
referred to Sole Arbitrator to be appointed by the Principal
Secretary/Secretary (Irrigation), GoU,…”
(Emphasis supplied)
8. In the wake of various disputes that arose between the parties, the
petitioner herein issued a notice of arbitration dated 06.05.2022, calling upon the
respondent to appoint an arbitrator in terms of the arbitration clause contained in
the GCC referred to above. The relevant part of the arbitration notice reads thus:
“26. The Respondent’s failure to pay the Claimant’s outstanding
dues, therefore, entitles the Claimant to invoke the arbitration
clause contained in 53 and 55 of the GCC for settlement of the
Claimant’s claims of a total of INR 1,04,32.664.86/- (Indian Rupees
One Crore Four Lacs Thirty-two Thousand Six Hundred and Sixty-
Four and Eighth-Six Paise only), i.e. INR 32,91,020/- (Indian Rupees
Thirty Two Lakh Ninety One Thousand and Twenty only) towards
Invoice dated 27 July 2020 and INR. 71,41,644.86/- (Indian Rupees
Seventy-One Lacs Forty-One Thousand Six Hundred and Forty-Four
and Eighty Six Paise only) for financial loss suffered by the Claimant
on account of abandonment of the Contract by the Respondent. This
Notice is without prejudice to the Claimant’s rights to
correct/amend/update/add any other additional figure/facts that may
come to its notice in support of its claim, which rights are expressly
reserved.
27. Since the Claimant’s claim is for an amount less than INR 10
Crores, under Clause 55(b)(I) of the GCC, a sole arbitrator is to be
appointed by the Principal Secretary/ Secretary (Irrigation),
Government of Uttarakhand. Notwithstanding the foregoing, the
Claimant submits that in light of recent amendments to the Arbitration
and Conciliation Act, 1996 and settled prevalent law laid down by the
Hon’ble Supreme Court in the case of Perkins Eastman Architects
DPC and Another v. HSCC (India) Limited [(2020) 20 SCC
760], the unilateral right of appointment given to the Respondent
under the Contract, is not enforceable as on date. Therefore, the
Claimant will propose the name of an arbitrator in this Notice, for
5
| |
| 9. It is the case of the petitioner that instead of appropriately responding to | |
| |
| the aforesaid notice of arbitration, the respondent issued a letter dated | |
| |
| 09.05.2022, terminating the Contract alleging non-compliance of work and non- | |
| |
| fulfilment of the contractual obligation. | |
10. In such circumstances referred to above, the petitioner has preferred the
present application for appointment of an arbitrator invoking Section 11(6) of
the Act 1996.
| SUBMISSIONS ON BEHALF OF THE PETITIONER | | |
|---|
| | |
| 11. Mr. Sidhant Goel, the learned counsel appearing for the petitioner | | |
| | |
| submitted that the case on hand, is one of “international commercial | | |
| | |
| arbitration” within the meaning of Section 2(f) of the Act 1996 as his client is | | |
| | |
| incorporated outside India. He submitted that under Section 11(12)(a) of the Act | | |
| | |
| 1996, this Court has the requisite jurisdiction to take necessary measures for the | | |
| | |
6
constitution of an arbitral tribunal under Section 11(6) of the Act 1996 as the
case is one of international commercial arbitration.
| |
|---|
| 12. The learned counsel submitted that Clause 55.1(b)(I) of the Contract | |
| |
| which provides for appointment of a sole arbitrator by the Principal | |
| |
| Secretary/Secretary (Irrigation), Government of Uttarakhand is in teeth of the | |
| |
| decision of this Court in Perkins Eastman Architects DPC and Another v. | |
| |
| HSCC (India) Limited reported in (2020) 20 SCC 760. He submitted that the | |
| |
| unilateral right of appointment of the arbitrator given to the respondent under the | |
| |
| Contract is unenforceable as on date. | |
13. The learned counsel further submitted that the condition for pre-deposit
of 7% of the claimed amount to initiate arbitration in accordance with Clause
55.1(b)(I) of the Contract is contrary to the decision of this Court in the case of
ICOMM Tele Limited v. Punjab State Water Supply and Sewerage Board and
Another reported in (2019) 4 SCC 401.
14. It was argued that such a clause could be termed as arbitrary being
violative of Article 14 of the Constitution in the sense of being unfair and unjust.
It was also argued that such clauses in the Contract do not have any nexus in
preventing any frivolous or vexatious claims in determination to such claims.
7
15. In such circumstances referred to above, the learned counsel prayed that
there being merit in this petition the same may be allowed and a sole arbitrator
be appointed to resolve the disputes between the parties.
| |
|---|
| SUBMISSIONS ON BEHALF OF THE RESPONDENT | |
| |
| 16. Mr. Amit Anand Tiwari, the learned counsel appearing for the respondent | |
| |
| vehemently submitted that the present petition deserves to be outright rejected | |
| |
| as the petitioner has failed to comply with the two pre-conditions: (i) the pre- | |
| |
| deposit of 7% of the claimed amount and (ii) failure on the part of the petitioner | |
| |
| to approach the Principal Secretary/Secretary (Irrigation), Government of | |
| |
| Uttarakhand for appointment of an arbitrator as provided under Clause 55 of the | |
| |
| Contract. | |
17. In the aforesaid context, he strongly relied upon the decisions of this Court
in the cases of Iron & Steel Co. Ltd. v. Tiwari Road Lines reported in (2007) 5
SCC 703, National Highways Authority of India and Another v. Bumihiway
DDB Ltd. (JV) and Others reported in (2006) 10 SCC 763 and Yashwith
Constructions (P)Ltd. v. Simplex Concrete Piles India Ltd. and Another
reported in (2006) 6 SCC 204.
18. He submitted that the respondent cannot be said to have failed to act as
required under the prescribed procedure. He invited the attention of a three-
Judge Bench of this Court to a decision in the case of S.K. Jain v. State of
Haryana and Another reported in (2009) 4 SCC 357, wherein a similar clause
8
requiring a security deposit of certain percentage of the claim amount was held
to be valid. He argued that the reliance on the decision of this Court in the case
of ICOMM Tele Limited (supra) by the petitioner is completely misconceived
as the relevant arbitration clause therein was quite differently worded vis-a-vis
the pre-deposit clause provided in the case of S.K. Jain (supra).
19. He submitted that in the absence of any clause to the contrary, the security
deposit is refundable by virtue of being only a deposit for “security”. The object
of such a clause is to ensure that only valid and bona fide claims are made by the
parties, and that the project is not hindered by frivolous and baseless claims. He
submitted that a three-Judge Bench of this Court in S.K. Jain (supra) found the
clause providing for pre-deposit to be logical and containing a balancing factor
to prevent frivolous and inflated claims. The relevant clause in S.K. Jain (supra)
provided that on the termination of arbitration proceedings, the sum would be
adjusted against the costs awarded by the arbitrator and the balance amount
would be refunded. In ICOMM Tele Limited (supra), the contract expressly
provided for forfeiture of the security deposit, even in the event of the award
going in favour of the party which made the deposit. In such circumstances, this
Court held such a clause to be arbitrary being violative of Article 14 of the
Constitution. In the present case, the Contract does not provide for any such
forfeiture under Clause 55 and by virtue of the terminology used, the amount is
to be deposited as a “security”. It was submitted that the same should be
9
understood to be refundable upon completion of the proceedings between the
parties. It was argued that in any case, Clause 4 of the GCC stipulates that the
security deposit is to be refunded to the contractor on demand, after 14 days of
expiry of Defects Liability Period. It does not exclude the security deposit made
under Clause 55 from its purview.
20. He submitted that as such there is no challenge to the pre-deposit clause
in the petition and the present petition under Section 11(6) of the Act 1996 is
only for appointment of an arbitrator. The judgments in S.K. Jain (supra) and
ICOMM Tele Limited (supra), relied upon on behalf of the petitioner were
delivered in appeals arising out of writ petitions before the respective High
Courts, where substantive challenges were made to the pre-deposit clause.
21. It was also argued that the petitioner having consented to the pre-deposit
clause cannot be permitted to turn around and question its validity at the stage
when a petition under Section 11(6) of the Act, 1996 is being considered, thereby
circumventing the principle of “party autonomy”.
22. In the last, it was argued that any order passed by this Court under Section
11(6) of the Act 1996 cannot be treated as a binding precedent in view of the
decision of this Court in State of West Bengal and Others v. Associated
Contractors reported in (2015) 1 SCC 32.
23. In such circumstances referred to above, the learned counsel appearing for
the respondent prayed that there being no merit in the petition, the same be
rejected.
10
ANAYLSIS
24. Having heard the learned counsel appearing for the parties and having
gone through the materials on record, the following issues fall for the
consideration of this Court:
(i) Whether the dictum as laid down in ICOMM Tele Limited (supra) can be
made applicable to the case in hand more particularly when Clause 55 of the
General Conditions of Contract provides for a pre-deposit of 7% of the total
claim for the purpose of invoking the arbitration clause?
(ii) Whether there is any direct conflict between the decisions of this Court in
S.K. Jain (supra) and ICOMM Tele Limited (supra)?
(iii) Whether this Court while deciding a petition filed under Section 11(6) of
the Act 1996 for appointment of a sole arbitrator can hold that the condition of
pre-deposit stipulated in the arbitration clause as provided in the Contract is
violative of the Article 14 of the Constitution of India being manifestly arbitrary?
(iv) Whether the arbitration Clause No. 55 of the Contract empowering the
Principal Secretary/Secretary (Irrigation), State of Uttarakhand to appoint an
arbitrator of his choice is in conflict with the decision of this Court in the case of
Perkins Eastman (supra)?
JURISDICTION OF THE COURT UNDER SECTION 11(6) OF THE
ACT 1996
11
25. In the wake of a few decisions of this Court, the legislature thought fit to
add sub section (6A) to Section 11 of the Act 1996 by way of the Arbitration and
Conciliation (Amendment) Act, 2015 (hereinafter referred to as “Amendment
2015”). The same reads thus:
“(6A) The Supreme Court or, as the case may be, the High Court,
while considering any application under subsection (4) or sub-
section (5) or sub-section (6), shall, notwithstanding any
judgment, decree or order of any court, confine to the
examination of the existence of an arbitration agreement.”
(Emphasis supplied)
26. Taking cognizance of the legislative change, this Court in Duro Felguera,
S.A. v. Gangavaram Port Limited reported in (2017) 9 SCC 729, noted that post
the 2015 Amendment, the jurisdiction of the court under Section 11(6) of the
Act, 1996 is limited to examining whether an arbitration agreement exists
between the parties - “ nothing more, nothing less ”.
27. The entire case law on the subject was considered by a three-judge bench
of this Court in Vidya Drolia and Others v. Durga Trading Corporation
reported in (2021) 2 SCC 1, and an overarching principle with respect to the pre-
referral jurisdiction under Section 11(6) of the Act was laid down. The relevant
portion of the judgment is as follows:
“153. Accordingly, we hold that the expression “existence of an
arbitration agreement” in Section 11 of the Arbitration Act,
would include aspect of validity of an arbitration agreement,
albeit the court at the referral stage would apply the prima facie
test on the basis of principles set out in this judgment. In cases of
debatable and disputable facts, and good reasonable arguable
12
case, etc., the court would force the parties to abide by the
arbitration agreement as the Arbitral Tribunal has primary
jurisdiction and authority to decide the disputes including the
question of jurisdiction and non-arbitrability.
154. Discussion under the heading “Who Decides
Arbitrability?” can be crystallised as under:
154.1. Ratio of the decision in Patel Engg. Ltd. [SBP &
Co. v. Patel Engg. Ltd., (2005) 8 SCC 618] on the scope of
judicial review by the court while deciding an application under
Sections 8 or 11 of the Arbitration Act, post the amendments by
Act 3 of 2016 (with retrospective effect from 23-10-2015) and
even post the amendments vide Act 33 of 2019 (with effect from
9-8-2019), is no longer applicable.
154.2. Scope of judicial review and jurisdiction of the court
under Sections 8 and 11 of the Arbitration Act is identical but
extremely limited and restricted.
154.3. The general rule and principle, in view of the legislative
mandate clear from Act 3 of 2016 and Act 33 of 2019, and the
principle of severability and competence-competence, is that the
Arbitral Tribunal is the preferred first authority to determine and
decide all questions of non-arbitrability. The court has been
conferred power of “second look” on aspects of non-arbitrability
post the award in terms of sub-clauses (i), (ii) or (iv) of
Section 34(2)(a) or sub-clause (i) of Section 34(2)(b) of
the Arbitration Act.
154.4. Rarely as a demurrer the court may interfere at Section 8
or 11 stage when it is manifestly and ex facie certain that the
arbitration agreement is non-existent, invalid or the disputes are
non-arbitrable, though the nature and facet of non-arbitrability
would, to some extent, determine the level and nature of judicial
scrutiny. The restricted and limited review is to check and protect
parties from being forced to arbitrate when the matter is
demonstrably “non-arbitrable” and to cut off the deadwood. The
court by default would refer the matter when contentions relating
to non-arbitrability are plainly arguable; when consideration in
summary proceedings would be insufficient and inconclusive;
when facts are contested; when the party opposing arbitration
adopts delaying tactics or impairs conduct of arbitration
13
| proceedings. This is not the stage for the court to enter into a | | |
|---|
| mini trial or elaborate review so as to usurp the jurisdiction of | | |
| the Arbitral Tribunal but to affirm and uphold integrity and | | |
| efficacy of arbitration as an alternative dispute resolution | | |
| mechanism.” | | |
| (Emphasis supplied) | |
| | |
through the test of a prima facie review. This is explained as under:
“133. Prima facie case in the context of Section 8 is not to be
confused with the merits of the case put up by the parties which
has to be established before the Arbitral Tribunal. It is restricted
to the subject-matter of the suit being prima facie arbitrable
under a valid arbitration agreement. Prima facie case means that
the assertions on these aspects are bona fide. When read with the
principles of separation and competence-competence and
Section 34 of the Arbitration Act, the referral court without
getting bogged down would compel the parties to abide unless
there are good and substantial reasons to the contrary.
134. Prima facie examination is not full review but a primary
first review to weed out manifestly and ex facie non-existent and
invalid arbitration agreements and non-arbitrable disputes. The
prima facie review at the reference stage is to cut the deadwood
and trim off the side branches in straightforward cases where
dismissal is barefaced and pellucid and when on the facts and
law the litigation must stop at the first stage. Only when the court
is certain that no valid arbitration agreement exists or the
disputes/subject-matter are not arbitrable, the application under
Section 8 would be rejected. At this stage, the court should not
get lost in thickets and decide debatable questions of facts.
Referral proceedings are preliminary and summary and not a
mini trial…
xxx xxx xxx
138…On the other hand, issues relating to contract formation,
existence, validity and non-arbitrability would be connected and
intertwined with the issues underlying the merits of the respective
14
| disputes/claims. They would be factual and disputed and for the | | |
|---|
| Arbitral Tribunal to decide. | | |
| | |
| 139. We would not like to be too prescriptive, albeit observe that | | |
| the court may for legitimate reasons, to prevent wastage of public | | |
| and private resources, can exercise judicial discretion to conduct | | |
| an intense yet summary prima facie review while remaining | | |
| conscious that it is to assist the arbitration procedure and not | | |
| usurp jurisdiction of the Arbitral Tribunal. Undertaking a | | |
| detailed full review or a long-drawn review at the referral stage | | |
| would obstruct and cause delay undermining the integrity and | | |
| efficacy of arbitration as a dispute resolution | | |
| mechanism. Conversely, if the court becomes too reluctant to | | |
| intervene, it may undermine effectiveness of both the arbitration | | |
| and the court. There are certain cases where the prima facie | | |
| examination may require a deeper consideration. The court's | | |
| challenge is to find the right amount of and the context when it | | |
| would examine the prima facie case or exercise restraint. The | | |
| legal order needs a right balance between avoiding arbitration | | |
| obstructing tactics at referral stage and protecting parties from | | |
| being forced to arbitrate when the matter is clearly non- | | |
| arbitrable. | | |
| | |
| 140. Accordingly, when it appears that prima facie review would | | |
| be inconclusive, or on consideration inadequate as it requires | | |
| detailed examination, the matter should be left for final | | |
| determination by the Arbitral Tribunal selected by the parties by | | |
| consent. The underlying rationale being not to delay or defer and | | |
| to discourage parties from using referral proceeding as a ruse to | | |
| delay and obstruct. In such cases a full review by the courts at | | |
| this stage would encroach on the jurisdiction of the Arbitral | | |
| Tribunal and violate the legislative scheme allocating | | |
| jurisdiction between the courts and the Arbitral Tribunal. | | |
| Centralisation of litigation with the Arbitral Tribunal as the | | |
| primary and first adjudicator is beneficent as it helps in quicker | | |
| and efficient resolution of disputes.” | | |
| (Emphasis supplied) | |
| | |
Drolia (supra), this Court has consistently been holding that the arbitral tribunal
is the preferred first authority to determine and decide all questions of non-
15
arbitrability. In Pravin Electricals Private Limited v. Galaxy Infra and
Engineering Private Limited reported in (2021) 5 SCC 671, Sanjiv
Prakash v. Seema Kukreja and Others reported in (2021) 9 SCC 732
and Indian Oil Corporation Limited v. NCC Limited reported in (2023) 2 SCC
539, the parties were referred to arbitration, as the prima facie review in each of
these cases on the objection of non-arbitrability was found to be inconclusive.
Following the exception to the general principle that the court may not refer
parties to arbitration when it is clear that the case is manifestly and ex facie non-
arbitrable, in Bharat Sanchar Nigam Limited and Another v. Nortel Networks
India Private Limited reported in (2021) 5 SCC 738, Secunderabad
Cantonment Board v. B. Ramachandraiah and Sons reported in (2021) 5 SCC
705 and B and T AG v. Ministry of Defence reported in 2023 SCC OnLine SC
657, arbitration was refused as the claims of the parties were demonstrably time-
barred.
30. In the case on hand, we are not concerned with the issue relating to the
arbitrability of the dispute. It is not even the case of the respondent that the
dispute is ex facie non-arbitrable. The case put up by the respondent is that there
is definitely an arbitrable dispute and the same should be referred to the arbitral
tribunal, however, the petitioner should abide by Clause 55 of the Contract.
31. In the case on hand, we are concerned first with the validity of the
arbitration clause which provides for 7% pre-deposit of the total claim for the
16
purpose of invoking arbitration and secondly, the discretion vested with the
Principal Secretary/Secretary (Irrigation) to appoint a sole arbitrator.
RE: ISSUE NOS. 1 AND 2
| 32. Before, we proceed to answer the issues framed by us, we must look into | | |
|---|
| few decisions referred to by us as aforesaid. | | |
| S.K. JAIN V. STATE OF HARYANA | | |
| 33. In S.K. Jain (supra), the challenge was to an order passed in a writ petition | | |
| filed by the appellant, wherein it had prayed to quash a memo directing it to | | |
| deposit 7% of the claimed amount before the arbitral tribunal. The civil appeal | | |
| was dismissed by a three-Judge Bench of this Court and the memo was | | |
| accordingly upheld. | | |
| 34. In S.K. Jain (supra), the relevant arbitration clause reads as | | |
| under: | | |
| “25-A. (7) It is also a term of this contract agreement that where | |
| the party invoking arbitration is the contractor, no reference for | |
| arbitration shall be maintainable unless the contractor | |
| furnishes to the satisfaction of the Executive Engineer in charge | |
| of the work, a security deposit of a sum determined according to | |
| details given below and the sum so deposited shall, on the | |
| termination of the arbitration proceedings be adjusted against | |
| the costs, if any, awarded by the arbitrator against the claimant | |
| party and the balance remaining after such adjustment in the | |
| absence of any such costs being awarded, the whole of the sum | |
| will be refunded to him within one month from the date of the | |
| award— | |
| | |
Rate of security
Amount of claim
deposit
17
1. For claims below Rs
10,000
2% of amount
claimed
2. For claims of Rs
10,000 and above and
below Rs 1,00,000 and
5% of amount
claimed
| (Emphasis supplied) |
| |
| 35. The relevant observations made by the Court in S.K. Jain (supra), more | |
| particularly, para 14 reads thus: | |
| “14. It has been submitted by learned counsel for the appellant |
| that there should be a cap in the quantum payable in terms of |
| sub-clause (7) of Clause 25-A. This plea is clearly without |
| substance. It is to be noted that it is structured on the basis of |
| the quantum involved. Higher the claim, the higher is the |
| amount of fee chargeable. There is a logic in it. It is the |
| balancing factor to prevent frivolous and inflated claims. If the |
| appellants' plea is accepted that there should be a cap in the |
| figure, a claimant who is making higher claim stands on a better |
| pedestal than one who makes a claim of a lesser amount.” |
| |
| MUNICIPAL CORPN., JABALPUR AND OTHERS V. RAJESH | |
| |
| CONSTRUCTION CO., (2007) 5 SCC 344 | |
36. In the said case, the appellants had floated a notice inviting tender for
construction of a road. Some portion of the work was awarded to the respondent
therein by entering into a contract on the terms and conditions as contained in
the tender. The tender contained various clauses; one amongst the same being
clause 29 which pertained to arbitration in case any dispute arose between the
parties and reads thus:
18
| “29. Except as otherwise provided in this contract all questions | |
|---|
| and disputes relating to the meaning of the specifications, | |
| drawing and instructions hereinbefore mentioned and as to thing | |
| (sic anything) whatsoever, in any way arising out or relating to | |
| the contract, designs, drawings, specifications, estimates | |
| concerning the works or the execution or failure to execute the | |
| same, whether arising during the progress of the work or after | |
| the completion or abandonment thereof shall be referred to the | |
| City Engineer in writing for his decision, within a period of 30 | |
| days of such occurrence. Thereupon the City Engineer shall give | |
| his written instructions and/or decisions within a period of 60 | |
| days of such request. This period can be extended by mutual | |
| consent of the parties. | |
| |
| Upon receipt of written instructions of decisions, the parties shall | |
| promptly proceed without delay to comply with such instructions | |
| or decisions. If the City Engineer fails to give his instructions or | |
| decisions in writing within a period of 60 days or mutually | |
| agreed time after being requested if the parties are aggrieved | |
| against the decision of the CE, the parties may within 30 days | |
| prefer an appeal of MPL Com who shall afford an opportunity to | |
| the parties of being heard and to offer evidence in support of his | |
| appeal. MPL Com will give his decision within 90 days. If any | |
| party is not satisfied with the decision of MPL Com, he can refer | |
| such disputes for arbitration to an Arbitration Board to be | |
| constituted by the Corporation, which shall consist of three | |
| members of whom one shall be chosen from among the officers | |
| belonging to the Urban Administration and Development | |
| Department not below the rank of BE, one retired Chief Engineer | |
| of any technical department and City Engineer, Nagar Nigam, | |
| Jabalpur. | |
| |
| The following are also the terms of this contract, namely: | |
| |
| (a) No person other than the aforesaid Arbitration Board |
| constituted by the Corporation (to handle cases of all technical |
| departments) shall act as arbitrator and if for any reason that |
| is not possible the matter shall not be referred to arbitration |
| at all. |
| |
| (b) The Corporation may at any time effect any change in the |
| personnel of the Board and the new members or members |
19
| appointed to the Arbitration Board shall be entitled to proceed<br>with the reference from the stage it was left by his or their<br>predecessors.<br>(c) The party invoking arbitration shall specify the dispute or<br>disputes to be referred to arbitration under this clause together<br>with the amount or amounts claimed in respect of each such<br>dispute(s).<br>(d) Where the party invoking arbitration is the contractor no<br>reference for arbitration shall be maintainable, unless the<br>contractor furnishes a security deposit of a sum determined<br>according to the table given below, and the sum so deposited<br>shall on the determination of arbitration proceeding, be<br>adjusted against the costs, if any awarded by the Board against<br>the party and the balance remaining after such adjustment or<br>in the absence of the such costs being awarded the whole of<br>the sum shall be refunded to him within one month from the<br>date of the award.<br>Amount of claim Rate of security<br>deposits<br>For claim below Rs 10,000 5% of amount claimed<br>For claim of Rs 10,000 and 3% of amount claimed<br>above but below Rs 1,00,000 subject to minimum of<br>Rs 500<br>For claims of Rs 1,00,000 2% of the amount<br>and above claimed subject to a<br>minimum of Rs 3000” | | | | appointed to the Arbitration Board shall be entitled to proceed | | | |
|---|
| | | | with the reference from the stage it was left by his or their | | | |
| | | | predecessors. | | | |
| | | | | | | |
| | | | (c) The party invoking arbitration shall specify the dispute or | | | |
| | | | disputes to be referred to arbitration under this clause together | | | |
| | | | with the amount or amounts claimed in respect of each such | | | |
| | | | dispute(s). | | | |
| | | | | | | |
| | | | (d) Where the party invoking arbitration is the contractor no | | | |
| | | | reference for arbitration shall be maintainable, unless the | | | |
| | | | contractor furnishes a security deposit of a sum determined | | | |
| | | | according to the table given below, and the sum so deposited | | | |
| | | | shall on the determination of arbitration proceeding, be | | | |
| | | | adjusted against the costs, if any awarded by the Board against | | | |
| | | | the party and the balance remaining after such adjustment or | | | |
| | | | in the absence of the such costs being awarded the whole of | | | |
| | | | the sum shall be refunded to him within one month from the | | | |
| | | | date of the award. | | | |
| | | | | | | |
| Amount of claim | | Amount of claim | | | Rate of security | |
| | | | | | deposits | |
| | | For claim below Rs 10,000 | | | 5% of amount claimed | |
| For claim of Rs 10,000 and<br>above but below Rs 1,00,000 | | For claim of Rs 10,000 and | | | 3% of amount claimed | |
| | | above but below Rs 1,00,000 | | | subject to minimum of | |
| | | | | | Rs 500 | |
| For claims of Rs 1,00,000<br>and above | | For claims of Rs 1,00,000 | | | 2% of the amount | |
| | | and above | | | claimed subject to a | |
| | | | | | minimum of Rs 3000” | |
| (Emphasis supplied) | | | | | | | (Emphasis supplied) |
| 37. The relevant findings recorded in Rajesh Constructions Co. (supra) are | | | | | | | |
as under:
| “20. Clause 29 specifically stipulates, as indicated herein | |
|---|
| earlier, that if any dispute arises between the parties, the party | |
| seeking invocation of the arbitration clause, shall first approach | |
| the Chief Engineer and on his failure to arbitrate the dispute, the | |
| party aggrieved may file an appeal to MPL Com, failing which, | |
| the Corporation shall constitute an Arbitration Board to resolve | |
| the disputes in the manner indicated in clause 29. However, | |
20
| before doing so, the party invoking arbitration clause is required | | | |
|---|
| to furnish security of a sum to be determined by the Corporation. | | | |
| | | |
| 21. In this case, admittedly, the security has not been furnished | | | |
| by the respondent to the Corporation. We, in fact, asked Mr | | | |
| Sharma, appearing on behalf of the respondent to ascertain on | | | |
| the date of the hearing of the appeal, whether the security deposit | | | |
| was made or not. On instruction, Mr Sharma informed us that | | | |
| such security has not yet been deposited. Such being the position | | | |
| even today, we hold that the obligation of the Corporation to | | | |
| constitute an Arbitration Board to resolve disputes between the | | | |
| parties could not arise because of failure of the respondent to | | | |
| furnish security as envisaged in clause 29(d) of the contract. | | | |
| Therefore, we are of the opinion, that on account of non- | | | |
| furnishing of security by the respondent, the question of | | | |
| constituting an Arbitration Board by the Corporation could not | | | |
| arise at all. Accordingly, we hold that the High Court was not | | | |
| justified in appointing a retired Chief Justice of a High Court as | | | |
| arbitrator by the impugned order. | | | |
| | | |
| 22. It is not disputed before us that the learned Arbitrator | | | |
| appointed by the High Court has already commenced the | | | |
| arbitration proceeding. Mr Mukherjee, appearing on behalf of | | | |
| the Corporation, on instruction, had submitted before us that they | | | |
| shall constitute an Arbitration Board as soon as the respondent | | | |
| furnishes security in terms of clause 29(d) of the contract and if | | | |
| any direction is given to the Arbitration Board to proceed from | | | |
| the stage the learned arbitrator had already reached, that would | | | |
| not be objected to. That is to say, Mr Mukherjee contended that | | | |
| the Arbitration Board may be directed to take over the arbitration | | | |
| proceedings from the stage the learned arbitrator had already | | | |
| reached. | | | |
| | | |
| 23. Such being the stand taken by the Corporation, we direct the | | | |
| respondent to furnish the security of a sum to be determined by | | | |
| the Corporation within six weeks from this date and in the event | | | |
| security determined by the Corporation is furnished within the | | | |
| time mentioned herein earlier, the Corporation shall constitute | | | |
| an Arbitration Board in compliance with clause 29 of the | | | |
| contract. It is directed that the Arbitration Board shall proceed | | | |
| from the stage the learned arbitrator appointed by the High | | | |
| Court had already reached. | | | |
| | | |
21
| 24. That apart, it has to be kept in mind that it is always the duty | | |
|---|
| of the court to construe the arbitration agreement in a manner so | | |
| as to uphold the same. Therefore we must hold that the High | | |
| Court ought not to have appointed an arbitrator in a manner, | | |
| which was inconsistent with the arbitration agreement.” | | |
| (Emphasis supplied) | | | |
| | | |
| ICOMM TELE LIMITED V. PUNJAB STATE WATER SUPPLY | | | |
| AND SEWERAGE BOARD | | | |
| | | |
| 38. Nature of the Clause: Clause 25(viii) of Notice Inviting Tender provided | | | |
| that: | | | |
| | | |
| “viii. It shall be an essential term of this contract that in order | | |
| to avoid frivolous claims the party invoking arbitration shall | | |
| specify the dispute based on facts and calculations stating the | | |
| amount claimed under each claim and shall furnish a “deposit- | | |
| at-call” for ten per cent of the amount claimed, on a schedule | | |
| bank in the name of the arbitrator by his official designation who | | |
| shall keep the amount in deposit till the announcement of the | | |
| award. In the event of an award in favour of the claimant, the | | |
| deposit shall be refunded to him in proportion to the amount | | |
| awarded with reference to the amount claimed and the balance, | | |
| if any, shall be forfeited and paid to the other party.” | | |
| (Emphasis supplied) | | |
| | | |
| 39. In 2008, the Punjab State Water Supply & Sewerage Board, Bhatinda | | | |
| | | |
| issued notice inviting tender for extension and augmentation of water supply, | | | |
| | | |
| sewerage scheme, pumping station and sewerage treatment plant for various | | | |
| | | |
| towns mentioned therein on a turnkey basis. On 25.09.2008, the appellant | | | |
| | | |
| company, which was involved in civil/electrical works in India, was awarded the | | | |
| | | |
| said tender after having been found to be the best suited for the task. On | | | |
| | | |
22
16.01.2009, a formal contract was entered into between the appellant and
respondent No. 2 therein.
40. On 08.03.2017, the appellant approached the High Court of Punjab and
Haryana challenging the validity of this part of the arbitration clause by filing
Civil Writ Petition No. 4882 of 2017. The High Court merely followed its earlier
judgment and dismissed the writ petition as well. The matter was carried to this
Court.
| 41. The relevant observations made by this Court are as under: | | | | | | | | |
|---|
| | | | | | | | |
| “12. In S.K. Jain v. State of Haryana [(2009) 4 SCC 357 : (2009)<br>2 SCC (Civ) 163], this Court dealt with an arbitration clause in an<br>agreement which read as follows:<br>Xxx xxx xxx<br>13. In upholding such a clause, this Court referred to the judgment<br>in Central Inland Water Transport Corpn. [Central Inland Water<br>Transport Corpn. Ltd. v. Brojo Nath Ganguly, (1986) 3 SCC 156<br>: 1986 SCC (L&S) 429] and distinguished this judgment, stating<br>that the concept of unequal bargaining power has no application<br>in the case of commercial contracts. …<br>14. It will be noticed that in this judgment there was no plea that<br>the aforesaid condition contained in an arbitration clause was<br>violative of Article 14 of the Constitution of India as such clause<br>is arbitrary. The only pleas taken were that the ratio of Central<br>Inland Water Transport Corpn. [Central Inland Water Transport<br>Corpn. Ltd. v. Brojo Nath Ganguly, (1986) 3 SCC 156 : 1986 SCC<br>(L&S) 429] would apply and that there should be a cap in the<br>quantum payable by way of security deposit, both of which pleas<br>were turned down by this Court. Also, the security deposit made<br>would, on the termination of the arbitration proceedings, first be<br>adjusted against costs if any awarded by the arbitrator against the<br>claimant party, and the balance remaining after such adjustment<br>then be refunded to the party making the deposit. This clause is<br>materially different from Clause 25(viii), which, as we have seen, | “12. In S.K. Jain v. State of Haryana [(2009) 4 SCC 357 : (2009) | | | | | | | |
| 2 SCC (Civ) 163], this Court dealt with an arbitration clause in an | | | | | | | |
| agreement which read as follows: | | | | | | | |
| | | | | | | | |
| | | Xxx xxx xxx | | | | | |
| | | | | | | | |
| 13. In upholding such a clause, this Court referred to the judgment | | | | | | | |
| in Central Inland Water Transport Corpn. [Central Inland Water | | | | | | | |
| Transport Corpn. Ltd. v. Brojo Nath Ganguly, (1986) 3 SCC 156 | | | | | | | |
| : 1986 SCC (L&S) 429] and distinguished this judgment, stating | | | | | | | |
| that the concept of unequal bargaining power has no application | | | | | | | |
| in the case of commercial contracts. … | | | | | | | |
| | | | | | | | |
| 14. It will be noticed that in this judgment there was no plea that | | | | | | | |
| the aforesaid condition contained in an arbitration clause was | | | | | | | |
| violative of Article 14 of the Constitution of India as such clause | | | | | | | |
| is arbitrary. The only pleas taken were that the ratio of Central | | | | | | | |
| Inland Water Transport Corpn. [Central Inland Water Transport | | | | | | | |
| Corpn. Ltd. v. Brojo Nath Ganguly, (1986) 3 SCC 156 : 1986 SCC | | | | | | | |
| (L&S) 429] would apply and that there should be a cap in the | | | | | | | |
| quantum payable by way of security deposit, both of which pleas | | | | | | | |
| were turned down by this Court. Also, the security deposit made | | | | | | | |
| would, on the termination of the arbitration proceedings, first be | | | | | | | |
| adjusted against costs if any awarded by the arbitrator against the | | | | | | | |
| claimant party, and the balance remaining after such adjustment | | | | | | | |
| then be refunded to the party making the deposit. This clause is | | | | | | | |
| materially different from Clause 25(viii), which, as we have seen, | | | | | | | |
23
| makes it clear that in all cases the deposit is to be 10 per cent of<br>the amount claimed and that refund can only be in proportion to<br>the amount awarded with respect to the amount claimed, the<br>balance being forfeited and paid to the other party, even though<br>that other party may have lost the case. This being so, this<br>judgment is wholly distinguishable and does not apply at all to the<br>facts of the present case.<br>xxx xxx xxx<br>20. The first important thing to notice is that the 10 per cent<br>“deposit-at-call” of the amount claimed is in order to avoid<br>frivolous claims by the party invoking arbitration. It is well settled<br>that a frivolous claim can be dismissed with exemplary costs. …<br>21. It is therefore always open to the party who has succeeded<br>before the arbitrator to invoke this principle and it is open to the<br>arbitrator to dismiss a claim as frivolous on imposition of<br>exemplary costs.<br>xxx xxx xxx | makes it clear that in all cases the deposit is to be 10 per cent of | | | | | | |
|---|
| the amount claimed and that refund can only be in proportion to | | | | | | |
| the amount awarded with respect to the amount claimed, the | | | | | | |
| balance being forfeited and paid to the other party, even though | | | | | | |
| that other party may have lost the case. This being so, this | | | | | | |
| judgment is wholly distinguishable and does not apply at all to the | | | | | | |
| facts of the present case. | | | | | | |
| | | | | | | |
| | | xxx xxx xxx | | | | |
| | | | | | | |
| 20. The first important thing to notice is that the 10 per cent | | | | | | |
| “deposit-at-call” of the amount claimed is in order to avoid | | | | | | |
| frivolous claims by the party invoking arbitration. It is well settled | | | | | | |
| that a frivolous claim can be dismissed with exemplary costs. … | | | | | | |
| | | | | | | |
| 21. It is therefore always open to the party who has succeeded | | | | | | |
| before the arbitrator to invoke this principle and it is open to the | | | | | | |
| arbitrator to dismiss a claim as frivolous on imposition of | | | | | | |
| exemplary costs. | | | | | | |
| | | | | | | |
| | | xxx xxx xxx | | | | |
| | | | | | | |
| 23. The important principle established by this case is that unless | | | | | | |
| it is first found that the litigation that has been embarked upon is | | | | | | |
| frivolous, exemplary costs or punitive damages do not follow. | | | | | | |
| Clearly, therefore, a “deposit-at-call” of 10 per cent of the amount | | | | | | |
| claimed, which can amount to large sums of money, is obviously | | | | | | |
| without any direct nexus to the filing of frivolous claims, as it | | | | | | |
| applies to all claims (frivolous or otherwise) made at the very | | | | | | |
| threshold. A 10 per cent deposit has to be made before any | | | | | | |
| determination that a claim made by the party invoking arbitration | | | | | | |
| is frivolous. This is also one important aspect of the matter to be | | | | | | |
| kept in mind in deciding that such a clause would be arbitrary in | | | | | | |
| the sense of being something which would be unfair and unjust and | | | | | | |
| which no reasonable man would agree to. Indeed, a claim may be | | | | | | |
| dismissed but need not be frivolous, as is obvious from the fact that | | | | | | |
| where three arbitrators are appointed, there have been known to | | | | | | |
| be majority and minority awards, making it clear that there may | | | | | | |
| be two possible or even plausible views which would indicate that | | | | | | |
| the claim is dismissed or allowed on merits and not because it is | | | | | | |
| frivolous. Further, even where a claim is found to be justified and | | | | | | |
| correct, the amount that is deposited need not be refunded to the | | | | | | |
| successful claimant. Take for example a claim based on a | | | | | | |
24
| termination of a contract being illegal and consequent damages<br>thereto. If the claim succeeds and the termination is set aside as<br>being illegal and a damages claim of Rupees One crore is finally<br>granted by the learned arbitrator at only ten lakhs, only one-tenth<br>of the deposit made will be liable to be returned to the successful<br>party. The party who has lost in the arbitration proceedings will<br>be entitled to forfeit nine-tenths of the deposit made despite the<br>fact that the aforesaid party has an award against it. This would<br>render the entire clause wholly arbitrary, being not only excessive<br>or disproportionate but leading to the wholly unjust result of a<br>party who has lost an arbitration being entitled to forfeit such part<br>of the deposit as falls proportionately short of the amount awarded<br>as compared to what is claimed.<br>xxx xxx xxx<br>27. Deterring a party to an arbitration from invoking this<br>alternative dispute resolution process by a pre-deposit of 10 per<br>cent would discourage arbitration, contrary to the object of de-<br>clogging the court system, and would render the arbitral process<br>ineffective and expensive.<br>28. For all these reasons, we strike down Clause 25(viii) of the<br>notice inviting tender...” | termination of a contract being illegal and consequent damages | | | | | | | | |
|---|
| thereto. If the claim succeeds and the termination is set aside as | | | | | | | | |
| being illegal and a damages claim of Rupees One crore is finally | | | | | | | | |
| granted by the learned arbitrator at only ten lakhs, only one-tenth | | | | | | | | |
| of the deposit made will be liable to be returned to the successful | | | | | | | | |
| party. The party who has lost in the arbitration proceedings will | | | | | | | | |
| be entitled to forfeit nine-tenths of the deposit made despite the | | | | | | | | |
| fact that the aforesaid party has an award against it. This would | | | | | | | | |
| render the entire clause wholly arbitrary, being not only excessive | | | | | | | | |
| or disproportionate but leading to the wholly unjust result of a | | | | | | | | |
| party who has lost an arbitration being entitled to forfeit such part | | | | | | | | |
| of the deposit as falls proportionately short of the amount awarded | | | | | | | | |
| as compared to what is claimed. | | | | | | | | |
| | | | | | | | | |
| | | xxx xxx xxx | | | | | | |
| | | | | | | | | |
| 27. Deterring a party to an arbitration from invoking this | | | | | | | | |
| alternative dispute resolution process by a pre-deposit of 10 per | | | | | | | | |
| cent would discourage arbitration, contrary to the object of de- | | | | | | | | |
| clogging the court system, and would render the arbitral process | | | | | | | | |
| ineffective and expensive. | | | | | | | | |
| | | | | | | | | |
| 28. For all these reasons, we strike down Clause 25(viii) of the | | | | | | | | |
| notice inviting tender...” | | | | | | | | |
| (Emphasis supplied) | | | | | | | | | |
| | | | | | | | | |
| 42. The principles of law discernible from the aforesaid observations made by | | | | | | | | | |
| | | | | | | | | |
| this Court in ICOMM Tele Limited (supra) are as under: | | | | | | | | | |
(a) That the pre-deposit condition in an arbitration clause is violative of
Article 14 of the Constitution of India being arbitrary.
(b) Unless it is first found or prima facie established that the litigation that has
been embarked upon is frivolous, the exemplary costs or punitive damages
cannot follow.
(c) Deterring a party to an arbitration from invoking the Alternative Dispute
Resolution Process by pre-deposit of certain percentage would discourage
25
arbitration. This would run contrary to the object of de-clogging the court system
and would render the arbitral process ineffective and expensive.
| |
|---|
| FEW DECISIONS OF THE HIGH COURTS ON THE SUBJECT | |
| |
| 43. Lite Bite Foods Pvt. Ltd. v. Airports Authority of India reported in | |
| SCC OnLine Ker 4736, | | | | | | |
|---|
| Nature of the Clause: | | | | | | |
| | | | | | |
| “5.15. Dispute Resolution<br>….The Concessionaire by means of a written application can<br>seek appointment of an Arbitrator and Authority would appoint<br>such an Arbitrator within 30 days of receipt of the application,<br>subject to fulfilling, the pre-requisites for appointment of the<br>Arbitrator as laid hereunder:—<br>i. The case shall be referred to the Sole Arbitrator as per<br>AA1 delegation of powers in vogue subject to the condition<br>that the Concessionaire shall have to deposit the disputed<br>amount with AA1 as condition precedent and the consent<br>shall have to be obtained from the concessionaire for<br>acceptance of the recommendations of Arbitrator before<br>making reference to the Arbitrator for adjudication of<br>dispute.”<br>(Emphasis supplied) | “5.15. Dispute Resolution | | | | | |
| ….The Concessionaire by means of a written application can | | | | | |
| seek appointment of an Arbitrator and Authority would appoint | | | | | |
| such an Arbitrator within 30 days of receipt of the application, | | | | | |
| subject to fulfilling, the pre-requisites for appointment of the | | | | | |
| Arbitrator as laid hereunder:— | | | | | |
| | | | | | |
| | | i. The case shall be referred to the Sole Arbitrator as per | | | |
| | | AA1 delegation of powers in vogue subject to the condition | | | |
| | | that the Concessionaire shall have to deposit the disputed | | | |
| | | amount with AA1 as condition precedent and the consent | | | |
| | | shall have to be obtained from the concessionaire for | | | |
| | | acceptance of the recommendations of Arbitrator before | | | |
| | | making reference to the Arbitrator for adjudication of | | | |
| | | dispute.” | | | |
| | | | | (Emphasis supplied) | |
| | | | | | |
| 44. The | | relevant extract from the Judgment reads thus: | | | | |
| | | | | | |
| “11…the conditions in clause 5.15 of the RFP, that require the | | | | | |
| petitioner to choose an Arbitrator from among a panel suggested | | | | | |
| by the respondent, as also the condition that requires the | | | | | |
| petitioner to make a pre-deposit of amounts as a condition for | | | | | |
| invoking the arbitration, would fall foul of the law declared by | | | | | |
| the Supreme court in the decisions reported as Perkins Eastman | | | | | |
| Architects DPC v. HSCC (India) Ltd. - [2019 SCC OnLine SC | | | | | |
| 1517] and ICOMM Tele Ltd. v. Punjab State Water Supply and | | | | | |
| Sewerage Board - [(2019) 4 SCC 401] respectively. I am not | | | | | |
| persuaded to accept the contention of the learned senior counsel | | | | | |
| for the respondent that it is only in the event of a challenge to | | | | | |
26
clause 5.15 of the RFP on the ground that it is violative of the
fundamental rights of the petitioner under Article 14 of the
Constitution of India, that this Court can hold the said clause, in
the RFP, as illegal. After the amendment of the 1996 Act in 2015,
the law must be taken to be that any clause in an agreement, that
requires one of the contracting parties to make a deposit of
amount as a precondition for invoking the arbitration, has to be
seen as rendering the entire clause arbitrary, being not only
excessive or disproportionate but leading to a wholly unjust
situation in arbitration proceedings, that are ordinarily to be
encouraged on account of the high pendency of cases in courts
and the ever-increasing cost of litigation. I am therefore of the
opinion that even if the clause in the RFP is to be treated as
supplementing Article 22 of the Concessionaire Agreement, the
offending conditions in the RFP would have to be ignored in view
of the declaration of law by the Supreme Court in the cases
referred above.”
(Emphasis supplied)
45. In the aforesaid decision of the Kerala High Court, the learned Single
Judge after due consideration of the decisions of this Court in Perkins Eastman
(supra) and ICOMM Tele Limited (supra), held that any clause in the agreement
that requires one of the contracting parties to make a deposit of an amount as a
pre-condition for invoking the arbitration should be seen as one rendering the
entire clause arbitrary being not only excessive or disproportionate but
something that may lead to a wholly unjust situation. Ultimately Article 22 of
the concessionaire agreement therein was ignored while appointing an arbitrator
in an application filed under Section 11(6) of the Act 1996.
46. The Assan Co-Op. L & C Society v. Haryana Vidyut Prasaran Nigam
Ltd ., ARB-127-2019 (Section 11 Petition) and CWP-13539-2021 (Civil Writ
Petition)
27
| Date of Order: 03.112021 | | | |
|---|
| Forum: High Court of Punjab and Haryana (Single-Judge) | | | |
| | | |
| Nature of the Clause: | | | |
| | | |
| “Clause 25A of the Contract (Annexure P-1) reads as under:- “If<br>any question, dispute, difference of opinions whatsoever arises in<br>any way connected with or arising out of instrument for meaning<br>or operation of any part thereof or the rights, duties or liabilities<br>of either party, including the termination of the contract by either<br>party and correctness thereof at any stage whatsoever it shall be<br>referred to arbitration of MD/Chief Engineer of HVPNL or his<br>nominee not below the rank of Superintending Engineer subject to<br>the following conditions:-<br>xxx xxx xxx<br>7. In case the party invoking the arbitration is the contractor, the<br>reference for arbitration shall be maintainable only after the<br>contractor furnishes to the satisfaction of Engineering-In Charge<br>a case security fee deposited @ 3% of the total amount claimed by<br>him. The sum so deposited by the contractor shall on the<br>termination of the arbitration proceedings be adjusted against the<br>cost and any amount awarded against the contractor. The<br>remaining amount shall be refunded to the contractor with-in one<br>month from the date of the award.”<br>(Emphasis supplied) | “Clause 25A of the Contract (Annexure P-1) reads as under:- “If | | |
| any question, dispute, difference of opinions whatsoever arises in | | |
| any way connected with or arising out of instrument for meaning | | |
| or operation of any part thereof or the rights, duties or liabilities | | |
| of either party, including the termination of the contract by either | | |
| party and correctness thereof at any stage whatsoever it shall be | | |
| referred to arbitration of MD/Chief Engineer of HVPNL or his | | |
| nominee not below the rank of Superintending Engineer subject to | | |
| the following conditions:- | | |
| | | |
| xxx xxx xxx | | |
| | | |
| 7. In case the party invoking the arbitration is the contractor, the | | |
| reference for arbitration shall be maintainable only after the | | |
| contractor furnishes to the satisfaction of Engineering-In Charge | | |
| a case security fee deposited @ 3% of the total amount claimed by | | |
| him. The sum so deposited by the contractor shall on the | | |
| termination of the arbitration proceedings be adjusted against the | | |
| cost and any amount awarded against the contractor. The | | |
| remaining amount shall be refunded to the contractor with-in one | | |
| month from the date of the award.” | | |
| | (Emphasis supplied) | |
| | | |
| 47. The relevant observations from the Judgment are as under: | | | |
| | | |
| “23. Resultantly, the issue of pre-deposit now arises. Counsel for | | |
| the petitioner has heavily relied upon the judgment passed in M/s | | |
| ICOMM Tele Ltd. (supra), which has been rightly distinguished by | | |
| the learned counsel for the respondent … | | |
| | | |
| 24. Thereafter, in 'S.K. Jain Vs. State of Haryana and another', | | |
| 2008 AIR (Punjab) 30 the challenge was to the clause of 7% of the | | |
| total amount claimed. While placing reliance upon the judgment | | |
| of the Apex Court in 'Municipal Corporation, Jabalpur & others | | |
| Vs. M/s Rajesh Construction Co.', 2007 (5) SCC 344, the writ | | |
| petition was dismissed. The said judgment was upheld by the Apex | | |
| Court in 'S.K. Jain Vs. State of Haryana and another' 2009 (2) | | |
28
| SCC (Civil) 163 by holding that there is logic in providing the said | |
|---|
| cap. … | |
| | |
| 25. In M/s ICOMM Tele Ltd. (supra) the objectionable clause 25 | |
| (viii) was struck down which was for 10% deposit. In the event of | |
| an award in favour of the claimant, the deposit was to be refunded | |
| to him in proportion to the amount awarded with regard to the | |
| amount claimed and the balance if any was to be forfeited and paid | |
| to the other party. Resultantly, the Apex Court came to the | |
| conclusion that nine times of the deposit could be forfeited by the | |
| parties who lost in the arbitration proceedings and despite the fact | |
| that the party has an award against it. Thus, the clause was held | |
| to be wholly arbitrary … | |
| | |
| 26. It was on such account the observations were made that the | |
| pre-deposit would discourage arbitration and the said clause as | |
| such was struck down by the distinguishing the judgment passed | |
| in S.K. Jain (supra). …” | |
| (Emphasis supplied) | |
| | |
| 48. In the aforesaid decision, a learned Single Judge of the Punjab and | | |
| | |
| Haryana High Court looked into both the decisions of this Court i.e., S.K. Jain | | |
| | |
| (supra) and ICOMM Tele Limited (supra). The High Court went on to look into | | |
| | |
| the relevant arbitration clause contained in both the decisions of this Court | | |
| | |
| referred to above and thought fit to follow the dictum as laid in S.K. Jain’s case | | |
| | |
| being a decision rendered by a Bench of three Judges. | | |
| | |
|---|
| 49. Garg and Company v. State of Haryana & Ors., CWP Nos. 21840 of | | |
| 2020, 21857 of 2020 and 21858 of 2020 (O&M) (Civil Writ Petitions) | | |
| Date of Order : 08.04.2022 | | |
| | |
| Forum: High Court of Punjab and Haryana (Single-Judge Bench) | | |
| | |
| Nature of the Clause: | | |
| | |
29
| “33(7). It is also a term of this arbitration agreement that where | | | |
|---|
| the party invoking arbitration is the contractor, no reference for | | | |
| Arbitrator shall be maintainable unless the contractor furnishes | | | |
| to the satisfaction of the Executive Engineer of the work, a | | | |
| security deposit of a sum determined according to details given | | | |
| below and the sum so deposited shall, on the termination of the | | | |
| arbitration proceedings, be adjusted against the cost, if any, | | | |
| awarded by the Arbitrator against the claimant party and the | | | |
| balance remaining after such adjustment, in the absence of any | | | |
| such cost being awarded the whole of the sum will be refunded | | | |
| to him within one month from the date of the award: | | | |
| | | | |
| Sr. No. | Amount Claims | Rate of<br>Security<br>Deposit | |
| i. | For claims below Rs. 10,000/ | 2% of<br>amount<br>claimed | |
| ii. | For claims of Rs. 10,000/- &<br>above but below Rs.<br>1,00,000/- | 5% of<br>amount<br>claimed | |
| iii. | For claims of Rs. 1,00,000/-<br>and above | 7.5% of<br>amount<br>claimed” | |
| (Emphasis supplied) | | | |
| | | | |
| | | | |
| 50. The relevant observations from the Judgment are as under: | | | | |
| “All the questions and grounds sought to be raised by learned | | | |
| counsel for the petitioner are succinctly answered by the Hon'ble | | | |
| Supreme Court in M/s. ICOMM Tele Limited's case (supra) itself | | | |
| while discussing S.K. Jain's case (supra). It is obvious that a clear | | | |
| cut distinction has been made in respect to the type of pre-deposit | | | |
| clause. Discussion of the judgment of S.K. Jain's case (supra) | | | |
| makes it crystal clear that such like clauses, which provide for | | | |
| adjustment and refund to the party making the deposit after the | | | |
| passing of the award are materially different from the clause | | | |
| which was under challenge in M/s. ICOMM Tele Limited's case | | | |
| (supra). In case of M/s. ICOMM Tele Limited's case (Supra), the | | | |
| objectionable clause 25(viii) was struck down finding the same to | | | |
| be arbitrary… | | | |
| | | | |
30
| It is in the said factual matrix that the observations regarding the<br>clause of pre-deposit discouraging arbitration was made and the<br>said clause was struck down while distinguishing the earlier<br>judgment passed by the Hon'ble Supreme Court in S.K. Jain's case<br>(supra).<br>Learned counsel for the petitioner is unable to deny that Clause<br>33(7) of the Agreement in the present writ petitions is identical to<br>Clause 25(7) of the Agreement, which was under consideration in<br>S.K. Jain's case (supra). Though learned senior counsel for the<br>petitioner/s was at pains to submit that the ratio of M/s. ICOMM<br>Tele Limited's case (supra) suggests that any kind of pre-deposit<br>has to be set aside as it necessarily leads to deterring a party to<br>an arbitration from invoking this alternate dispute resolution<br>system and in-fact renders the entire arbitral process ineffective,<br>however, keeping in view the specific discussion by the Hon'ble<br>Supreme Court in its decision in M/s. ICOMM Tele Limited's case<br>(supra) of S.K. Jain's case (supra), I do not find any merit in the<br>argument raised by learned counsel for the petitioner. The same is<br>accordingly rejected as it is clear that this Court is bound by the<br>judgment of the Hon'ble Supreme Court in S.K. Jain's case<br>(supra), which has not been overruled till date.”<br>(Emphasis Supplied) | It is in the said factual matrix that the observations regarding the | | |
|---|
| clause of pre-deposit discouraging arbitration was made and the | | |
| said clause was struck down while distinguishing the earlier | | |
| judgment passed by the Hon'ble Supreme Court in S.K. Jain's case | | |
| (supra). | | |
| | | |
| Learned counsel for the petitioner is unable to deny that Clause | | |
| 33(7) of the Agreement in the present writ petitions is identical to | | |
| Clause 25(7) of the Agreement, which was under consideration in | | |
| S.K. Jain's case (supra). Though learned senior counsel for the | | |
| petitioner/s was at pains to submit that the ratio of M/s. ICOMM | | |
| Tele Limited's case (supra) suggests that any kind of pre-deposit | | |
| has to be set aside as it necessarily leads to deterring a party to | | |
| an arbitration from invoking this alternate dispute resolution | | |
| system and in-fact renders the entire arbitral process ineffective, | | |
| however, keeping in view the specific discussion by the Hon'ble | | |
| Supreme Court in its decision in M/s. ICOMM Tele Limited's case | | |
| (supra) of S.K. Jain's case (supra), I do not find any merit in the | | |
| argument raised by learned counsel for the petitioner. The same is | | |
| accordingly rejected as it is clear that this Court is bound by the | | |
| judgment of the Hon'ble Supreme Court in S.K. Jain's case | | |
| (supra), which has not been overruled till date.” | | |
| | (Emphasis Supplied) | |
| | | |
| 51. In the aforesaid decision of the Punjab and Haryana High Court, both the | | | |
| | | |
| decisions of this Court i.e., ICOMM Tele Limited (supra) as well as S.K. Jain | | | |
| | | |
| (supra) were looked into and the Court thought fit to follow the dictum as laid in | | | |
| | | |
| S.K. Jain (supra). | | | |
| | |
|---|
| 52. Brij Gopal Construction Co. Pvt. Ltd. v. Haryana Shehri Vikas | | |
| Pradhikaran, CWP-14587-2022 (O&M) (Civil Writ Petition) | | |
| Date of Order: 02.08.2022 | | |
| | |
| Forum: High Court of Punjab and Haryana (Single-Judge) | | |
| | |
| Nature of the Clause: | | |
| | |
31
| “25(A)(vii) It is also a term of this arbitration agreement that | |
|---|
| where the party invoking arbitration is the contractor, no | |
| reference for Arbitrator shall be maintainable unless the | |
| contractor, furnishes to the satisfaction of the Engineer In charge | |
| of the work, a security deposit of a sum determined according to | |
| details given below and the sum so deposited shall, on the | |
| termination of the arbitration proceedings, be adjusted against the | |
| cost, if any, awarded by the Arbitrator against the claimant party | |
| and the balance remaining after such adjustment or whole sum in | |
| the absence of any such cost being awarded the whole of the sum | |
| will be refunded to him within one month from the date of the | |
| award. | |
| | |
| AMOUNT OF CLAIMS | RATE OF SECURITY<br>DEPOSIT |
| i) For claims below Rs.<br>10,000/- | 2% of amount<br>claimed |
| ii) For claims of Rs. 10,000/-<br>& above & below Rs.<br>1,00,000/- | 5% of amount<br>claimed |
| iii) For claims of Rs.<br>1,00,000/- | 7.5 % of amount<br>claimed and<br>above” |
| | |
| 53. The relevant observations from the Judgment are as under: | | |
| | |
| “A similar controversy was sought to be raised in CWP-21840- | |
| 2020 and other connected writ petitions, which have been | |
| dismissed on 08.04.2022. Question raised for adjudication in | |
| the said writ petitions was also whether the clause in question | |
| requiring a pre-deposit for invocation of Arbitration is | |
| unreasonable, unconscionable and liable to set aside. Clause in | |
| question in the abovesaid writ petitions was identical as clause | |
| 25(A)(vii) involved in the instant writ petition. Reliance had | |
| been placed on M/s ICOMM Tele Limited (supra) as is the case | |
| in the present writ petition. However, while dealing with the | |
| contentions as raised and dismissing the said writ petitions, | |
| judgment of the Three Judge Bench of the Hon’ble Supreme | |
| Court in S.K. Jain v. State of Haryana, (2009) 4 SCC 357 was | |
| duly considered. It was also noticed that Hon’ble Supreme | |
| Court itself in the case of M/s ICOMM Tele Limited (supra) | |
| referred to the case of S.K. Jain (supra) and infact upheld the | |
| clause regarding pre-deposit in S.K. Jain’s case (supra).” | |
32
| xxx xxx xxx<br>Similar view in regard to such a pre-deposit clause has also<br>been taken by a Co-ordinate Bench in decision dated<br>03.11.2020 passed in ARB-127- 2019 and in CWP No. 13539 of<br>2021, titled as M/s The Assan Co-op L&C Society,<br>Bahadurgarh, District Jhajjar Vs. Haryana Vidyut Prasaran<br>Nigam Limited (HVPNL). Thus, in view of judgment of the<br>Hon’ble Supreme Court in S.K. Jain vs. State of Haryana,<br>2009(2) RCR (Civil) 202 as discussed in M/s ICOMM Tele<br>Limited(supra), order dated 15.01.2022 (Annexure P9) and<br>dated 02.04.2022 (Annexure P11) have been correctly passed.<br>This Court is clearly bound by the judgment of the Hon’ble<br>Supreme in the case of S.K. Jain (supra) which has admittedly<br>not been over ruled till date.”<br>(Emphasis supplied) | | | |
|---|
| | xxx xxx xxx | |
| | | |
| Similar view in regard to such a pre-deposit clause has also | | |
| been taken by a Co-ordinate Bench in decision dated | | |
| 03.11.2020 passed in ARB-127- 2019 and in CWP No. 13539 of | | |
| 2021, titled as M/s The Assan Co-op L&C Society, | | |
| Bahadurgarh, District Jhajjar Vs. Haryana Vidyut Prasaran | | |
| Nigam Limited (HVPNL). Thus, in view of judgment of the | | |
| Hon’ble Supreme Court in S.K. Jain vs. State of Haryana, | | |
| 2009(2) RCR (Civil) 202 as discussed in M/s ICOMM Tele | | |
| Limited(supra), order dated 15.01.2022 (Annexure P9) and | | |
| dated 02.04.2022 (Annexure P11) have been correctly passed. | | |
| This Court is clearly bound by the judgment of the Hon’ble | | |
| Supreme in the case of S.K. Jain (supra) which has admittedly | | |
| not been over ruled till date.” | | |
| (Emphasis supplied) | | |
| | | |
| 54. In the aforesaid decision of the Punjab and Haryana High Court, both the | | | |
| | | |
| decisions of this Court i.e., ICOMM Tele Limited (supra) and S.K. Jain (supra) | | | |
| | | |
| were taken into consideration and ultimately, the Court followed the dictum as | | | |
| | | |
| laid down in S.K. Jain (supra). | | | |
| 55. Bathinda Railway Transhipment Cooperative L&C Society Ltd. v. | | |
|---|
| Punjab Mandi Board & Ors., Civil Writ Petition No. 28981 of 2019 (O&M) | | |
| Date of Order : 27.03.2023 | | |
| Forum: High Court of Punjab and Haryana (Division Bench) | | |
| Nature of Clause: | | |
| “8. … 25(viii) It shall be an essential term of this contract that | |
| in order to avoid frivolous claims, the party invoking arbitration | |
| shall specify the disputes based upon facts and calculations | |
| stating the amount claimed under each claim and shall furnish | |
| a “deposit-at call” for ten percent of the amount claimed, on a | |
| scheduled bank in the name of the Arbitrator/Chairman of the | |
| Arbitral Tribunal, by his official designation who shall keep the | |
33
| amount in deposit till the announcement of the award. In the<br>event of an award in favour of the claimant, the deposit shall be<br>refunded to him in proportion to the amount awarded with<br>respect to the amount claimed and the balance, if any, shall be<br>forfeited and paid to the other party.”<br>(Emphasis supplied) | amount in deposit till the announcement of the award. In the | | | |
|---|
| event of an award in favour of the claimant, the deposit shall be | | | |
| refunded to him in proportion to the amount awarded with | | | |
| respect to the amount claimed and the balance, if any, shall be | | | |
| forfeited and paid to the other party.” | | | |
| | | (Emphasis supplied) | |
| | | | |
| | | | |
| 56. The relevant observations from the Judgment are as under: | | | | |
| | | | |
| “10. From a perusal of the aforesaid two clauses (supra) i.e. | | | |
| one that has been assailed by the petitioner and the other that | | | |
| has been quashed by the Supreme Court in juxta position makes | | | |
| it absolutely clear that they are identical containing the same | | | |
| stipulations. The Supreme Court in the case of M/s Icomm Tele | | | |
| Ltd. (supra) after considering the validity of the said clause has | | | |
| held as under:- | | | |
| | | | |
| | “28. For all these reasons, we strike down clause 25(viii) | | |
| | of the notice inviting tender. This clause being severable | | |
| | from the rest of clause 25 will not affect the remaining | | |
| | parts of Clause 25. The judgment of the High Court is set | | |
| | aside and the appeal allowed.” | | |
| | | | |
| 11. In the light of the aforesaid decision rendered by the | | | |
| Supreme Court in M/s Icomm Tele Ltd. (supra), which has | | | |
| considered absolutely an identical clause contained in the | | | |
| agreement between the parties and after doing so has struck | | | |
| down the said clause, it is not for this Court i.e. the High Court | | | |
| to consider the contention of the respondent and take a different | | | |
| view as that would be not just beyond the authority of this Court | | | |
| but would also be an act of impropriety. This Court being bound | | | |
| by the decision rendered by the Supreme Court in M/s Icomm | | | |
| Tele Ltd. (supra) allowed the present petition filed by the | | | |
| petitioner and declares the arbitration clause 25(viii) of the | | | |
| tender conditions, quoted above, as unconstitutional and passes | | | |
| the same orders in similar terms as were passed by the Supreme | | | |
| Court in paragraph-28 of the decision rendered in M/s Icomm | | | |
| Tele Ltd. (supra).” | | | |
| | | (Emphasis supplied) | |
| | | | |
34
57. In the aforesaid decision of the Punjab and Haryana High Court, the
decisions of this Court in the case of ICOMM Tele Limited (supra) as well as
S.K. Jain (supra) were taken into consideration and ultimately, the Court
followed the dictum as laid in ICOMM Tele Limited (supra), as the relevant
arbitration clause in the said matter was almost identical to the one in ICOMM
Tele Limited (supra).
| | | |
|---|
| 58. Amazing India Contractors Pvt. Ltd. v. Airport Authority of India and | | | |
| Others reported in 2023 SCC OnLine Cal 1704, C.O. 66 of 2022 (Section 11 | | | |
| Petition) | | | |
| High Court of Calcutta (Single Judge) | | | |
| | | |
| Nature of the Clause: | | | |
| | | |
| “33(iii). All disputes and differences arising out of or in any | | |
| way touching or concerning this Agreement (except those the | | |
| decision whereof is otherwise herein before expressly provided | | |
| for or to which the public premises [Eviction of Unauthorized | | |
| Occupants] Act and the rules framed there under which are now | | |
| enforced or which may hereafter come into force are | | |
| applicable), shall, in the first instance, be referred to a Dispute | | |
| Resolution Committee (DRC) setup at the airports, for which a | | |
| written application should be obtained from the party and the | | |
| points clearly spelt out. In case the dispute is not resolved within | | |
| 45 days of reference, then the case shall be referred to sole | | |
| arbitration of a person to be appointed by the | | |
| Chairman/Member of the Authority. The award of the arbitrator | | |
| so appointed shall be final and binding on the parties. | | |
| The Arbitration & Conciliation Act, 1996 shall be applicable. | | |
| Once the arbitration clause has been invoked, the DRC process | | |
| will cease to be operative. It will be no bar that the Arbitrator | | |
| appointed as aforesaid is or has been an employee of the | | |
| Authority and the appointment of the Arbitrator will not be | | |
35
| challenged; or be open to Question in any Court of Law, on this | | |
|---|
| account.” | | |
| | | |
| 59. The relevant observations from the Judgment are as under: | | | |
“25. …
That part of Clause 33 of the agreement between the parties
providing for constitution of a Dispute Resolution Committee
with a stipulation that before availing of dispute resolution, the
disputed amount has to be deposited, is invalid and contrary to
law for more than one reason. The first and foremost is that it
fetters the right of the petitioner, a party to the arbitration
agreement to avail of arbitration which is a statutory right.
[ICOMM Tele Ltd. v. Punjab State Water Supply and Sewerage
Board reported in (2019) 4 SCC 401]. Secondly, it is most
ambiguous. If the petitioner is making a claim which is then and
there disputed by the respondent, why should the petitioner,
being the claimant be asked to deposit the disputed amount?
When the petitioner is making a claim against the respondent,
it is unable, at that point of time, to know whether the whole
claim or part of it would be admitted, or the whole of it denied
by the latter. Hence, it is unable to gauge the disputed amount.
Even if it were possible for the respondent to notify the disputed
amount immediately, the clause would only be operative if the
respondent was simultaneously making a counter claim more
than the petitioner's claim which was being denied by the
petitioner, by seeking reference of the dispute to arbitration. If
the respondent was first making the claim which was disputed
by the petitioner, still the matter could not be referred to the
Committee in as much as the clause suggests an application for
dispute resolution by the petitioner only. For all these reasons,
this clause itself is vague for uncertainty and invalid.”
(Emphasis supplied)
60. In the aforesaid decision of the Calcutta High Court, ICOMM Tele
Limited (supra) and Perkins Eastman (supra) were relied upon and ultimately,
it was held that Clause 33 of the agreement therein between the parties providing
for constitution of a “Dispute Resolution Committee” with a stipulation that
36
before availing of dispute resolution clause, the disputed amount has to be
deposited, was held to be invalid and contrary to law.
61. We are of the view that as such there is no conflict between S.K. Jain
(supra) and ICOMM Tele Limited (supra), as the relevant arbitration clauses that
fell for the consideration of this Court in both the cases stood completely on a
different footing. What is relevant to note are the points of law on which S.K.
Jain (supra) was distinguished and explained in ICOMM Tele Limited (supra).
62. The Court while distinguishing S.K. Jain (supra) in ICOMM Tele Limited
(supra) made some relevant observations in para 14 of the Judgment. Para 14
reads thus:
| “ | 14. It will be noticed that in this judgment there was no plea that |
|---|
| the aforesaid condition contained in an arbitration clause was | |
| violative of Article 14 of the Constitution of India as such clause | |
| is arbitrary. The only pleas taken were that the ratio of Central | |
| Inland Water Transport Corpn. [Central Inland Water Transport | |
| Corpn. Ltd. v. Brojo Nath Ganguly, (1986) 3 SCC 156 : 1986 | |
| SCC (L&S) 429] would apply and that there should be a cap in | |
| the quantum payable by way of security deposit, both of which | |
| pleas were turned down by this Court. Also, the security deposit | |
| made would, on the termination of the arbitration proceedings, | |
| first be adjusted against costs if any awarded by the arbitrator | |
| against the claimant party, and the balance remaining after such | |
| adjustment then be refunded to the party making the deposit. This | |
| clause is materially different from Clause 25(viii), which, as we | |
| have seen, makes it clear that in all cases the deposit is to be 10 | |
| per cent of the amount claimed and that refund can only be in | |
| proportion to the amount awarded with respect to the amount | |
| claimed, the balance being forfeited and paid to the other party, | |
| even though that other party may have lost the case. This being | |
| so, this judgment is wholly distinguishable and does not apply at | |
| all to the facts of the present case. | |
37
(Emphasis supplied)
63. In para 16 of ICOMM Tele Limited (supra), the court ultimately
considered whether Clause 25(viii) could be said to be arbitrary and violative of
Article 14 of the Constitution of India. Para 16 reads thus:
| “ | 16. Thus, it must be seen as to whether the aforesaid Clause | |
|---|
| 25(viii) can be said to be arbitrary or discriminatory and | | |
| violative of Article 14 of the Constitution of India. | | ” |
64. Thereafter, the Court proceeded to observe that Clause 25(viii) therein
could not be said to be discriminatory as the same applied equally to both the
parties, however, arbitrariness could be said to be a separate and distinct facet
of Article 14 of the Constitution. Saying so, the Court referred to and relied
upon para 19 of this Court’s decision in A.L. Kalra v. Project and Equipment
Corporation of India Ltd. reported in (1984) 3 SCC 316. Para 19 reads thus:
| “19. The scope and ambit of Article 14 have been the subject- | |
|---|
| matter of a catena of decisions. One facet of Article 14 which has | |
| been noticed in E.P. Royappa v. State of Tamil Nadu [(1974) 2 | |
| SCR 348 : (1974) 4 SCC 3 : 1974 SCC (L&S) 165 : AIR 1974 SC | |
| 555 : (1974) 1 LLJ 172] deserves special mention because that | |
| effectively answers the contention of Mr Sinha. The Constitution | |
| Bench speaking through Bhagwati, J. in a concurring judgment | |
| in Royappa case [(1974) 2 SCR 348 : (1974) 4 SCC 3 : 1974 SCC | |
| (L&S) 165 : AIR 1974 SC 555 : (1974) 1 LLJ 172] observed as | |
| under: [SCC para 85, p. 38: SCC (L&S) p. 200] | |
| |
| “The basic principle which, therefore, informs both Articles |
| 14 and 16 is equality and inhibition against discrimination. |
| Now, what is the content and reach of this great equalising |
| principle? It is a founding faith, to use the words of Bose, |
| J., “a way of life”, and it must not be subjected to a narrow |
| pedantic or lexicographic approach. We cannot |
38
| countenance any attempt to truncate its all-embracing |
|---|
| scope and meaning, for to do so would be to violate its |
| activist magnitude. Equality is a dynamic concept with |
| many aspects and dimensions and it cannot be “cribbed, |
| cabined and confined” within traditional and doctrinaire |
| limits. From a positivistic point of view, equality is |
| antithetic to arbitrariness. In fact equality and arbitrariness |
| are sworn enemies; one belongs to the rule of law in a |
| republic while the other, to the whim and caprice of an |
| absolute monarch. Where an act is arbitrary, it is implicit |
| in it that it is unequal both according to political logic and |
| constitutional law and is therefore violative of Article 14, |
| and if it affects any matter relating to public employment, it |
| is also violative of Article 16. Articles 14 and 16 strike at |
| arbitrariness in State action and ensure fairness and |
| equality of treatment.” |
| |
| This view was approved by the Constitution Bench in Ajay Hasia | |
| case [(1981) 2 SCR 79 : (1981) 1 SCC 722 : 1981 SCC (L&S) | |
| 258 : AIR 1981 SC 487 : (1981) 1 LLJ 103]. It thus appears well- | |
| settled that Article 14 strikes at arbitrariness in | |
| executive/administrative action because any action that is | |
| arbitrary must necessarily involve the negation of equality. One | |
| need not confine the denial of equality to a comparative | |
| evaluation between two persons to arrive at a conclusion of | |
| discriminatory treatment. An action per se arbitrary itself denies | |
| equal of (sic) protection by law. The Constitution Bench | |
| pertinently observed in Ajay Hasia case [(1981) 2 SCR 79 : | |
| (1981) 1 SCC 722 : 1981 SCC (L&S) 258 : AIR 1981 SC 487 : | |
| (1981) 1 LLJ 103] and put the matter beyond controversy when | |
| it said “wherever therefore, there is arbitrariness in State action | |
| whether it be of the Legislature or of the executive or of an | |
| ‘authority’ under Article 12, Article 14 immediately springs into | |
| action and strikes down such State action”. This view was further | |
| elaborated and affirmed in D.S. Nakara v. Union of | |
| India [(1983) 1 SCC 305 : 1983 SCC (L&S) 145 : (1983) UPSC | |
| 263 : AIR 1983 SC 130]. In Maneka Gandhi v. Union of India [ | |
| (1978) 2 SCR 621 : (1978) 1 SCC 248 : AIR 1978 SC 597] it was | |
| observed that Article 14 strikes at arbitrariness in State action | |
| and ensures fairness and equality of treatment. It is thus too late | |
| in the day to contend that an executive action shown to be | |
| arbitrary is not either judicially reviewable or within the reach | |
39
| of Article 14. The contention as formulated by Mr Sinha must | |
|---|
| accordingly be negatived. ” | |
| (Emphasis supplied) | |
| | |
| 65. The Court thereafter, took notice of the fact that the 10 % “deposit-at- | | |
| call” of the amount claimed therein was to avoid frivolous claims by the party | | |
| invoking arbitration. This Court went on to say that a frivolous claim can | | |
| always be dismissed with exemplary costs. | | |
| 66. Keeping the aforesaid in mind, if we look into the 7% pre-deposit | | |
| condition in the case on hand, as contained in Clause 55 of the GCC it is evident | | |
| that nothing has been provided as to how this amount of 7% is to be ultimately | | |
| adjusted at the end of the arbitral proceedings. With a view to salvage this | | |
| situation, the learned counsel appearing for the respondent invited the attention | | |
| of this Court to Clause 3 of the GCC, which relates to the security deposit for | | |
| performance. Clause 3 reads thus: | | |
“ CLAUSE-3: SECURITY DEPOSIT FOR PERFORMANCE:
3.1 The Security Deposit shall comprise of following:
(i) Performance Security Deposit/Performance Guarantee to be
furnished by the Contractor at the time of Award of Work.
(ii) Retention Money/Security Deposit to be recovered from
Interim bills of the Contractor.
3.2 The Contractor within 28 (Twenty Eight) days from the date
of issue of Letter of Acceptance, shall furnish a Performance
security deposit of 10% (Ten percent) of the Contract Price for
due performance of contract, in any one of the following forms:
(a) Demand draft on any Nationalized/scheduled Bank of India
in the name of Employer; or FDR/CDR in the manner as
specified in Section-I.
40
(b) Bank Guarantee from an Indian Nationalized/Scheduled
Bank of India or a foreign bank through its branch located in
India acceptable to Employer in the prescribed proforma.”
67. Thereafter our attention was drawn to Clause 4 which provides for refund
of security deposit. Clause 4 reads thus:
“ CLAUSE-4: REFUND OF SECURITY DEPOSIT :
The Security Deposit less any amount due shall, on demand, be
returned to the contractor after 14 days of expiry of Defects
Liability Period (referred in Clause 43 hereof). No interest on the
amount of Security Deposit shall be paid to the Contractor at the
time of release of Security Deposit as stated above.”
68. We are of the view that Clauses 3 and 4 respectively as above relating to
security deposit for performance and refund of the same has no nexus at all with
the pre-deposit amount of 7% as stipulated in Clause 55 of the GCC. Such vague
and ambiguous condition of 7% pre-deposit of the total claim makes the same
more vulnerable to arbitrariness thereby violating Article 14 of the Constitution.
Even otherwise, as explained in ICOMM Tele Limited (supra) if the claim of the
petitioner herein is ultimately found to be frivolous the arbitral tribunal can
always award costs in accordance with Section 31A of the Act 1996, which reads
thus:
| “31A. Regime for costs.— (1) In relation to any arbitration | |
|---|
| proceeding or a proceeding under any of the provisions of this | |
| Act pertaining to the arbitration, the Court or arbitral tribunal, | |
| notwithstanding anything contained in the Code of Civil | |
| Procedure, 1908 (5 of 1908), shall have the discretion to | |
| determine— | |
41
| Explanation.—For the purpose of this sub-section, "costs" means | |
|---|
| reasonable costs relating to— | |
| (i) the fees and expenses of the arbitrators, Courts and witnesses; | | | |
|---|
| (ii) legal fees and expenses; | | | |
| (iii) any administration fees of the institution supervising the | | | |
| arbitration; and | | | |
| (iv) any other expenses incurred in connection with the arbitral | | | |
| or Court proceedings and the arbitral award. | | | |
| (2) If the Court or arbitral tribunal decides to make an order as | |
|---|
| to payment of costs,- | |
| (a) the general rule is that the unsuccessful party shall be ordered | | |
|---|
| to pay the costs of the successful party; or | | |
| (b) the Court or arbitral tribunal may make a different order for | | |
| reasons to be recorded in writing. | | |
| (3) In determining the costs, the Court or arbitral tribunal shall | |
|---|
| have regard to all the circumstances, including- | |
| (a) the conduct of all the parties; | | |
|---|
| (b) whether a party has succeeded partly in the case; | | |
| (c) whether the party had made a frivolous counterclaim leading | | |
| to delay in the disposal of the arbitral proceedings; and | | |
| (d) whether any reasonable offer to settle the dispute is made by | | |
| a party and refused by the other party. | | |
| (4) The Court or arbitral tribunal may make any order under this | |
|---|
| section including the order that a party shall pay- | |
| (a) a proportion of another party's costs; | |
|---|
| (b) a stated amount in respect of another party's costs; | |
| (c) costs from or until a certain date only; | |
| (d) costs incurred before proceedings have begun; | |
| (e) costs relating to particular steps taken in the proceedings; | |
| (f) costs relating only to a distinct part of the proceedings; and | |
| (g) interest on costs from or until a certain date. | |
42
| (5) An agreement which has the effect that a party is to pay the | |
|---|
| whole or part of the costs of the arbitration in any event shall be | |
| only valid if such agreement is made after the dispute in question | |
| has arisen.” | |
decision of the Supreme Court of Canada in the case of Uber Technologies Inc.,
Uber Canada, Inc., Uber B.V. and Rasier Operations B.V. v. David Heller
reported in 2020 SCC OnLine Can SC 13 . We quote the relevant observations
as under:
| “42. In our view, there are ways to mitigate this concern that | |
|---|
| make the overall calculus favour departing from the general rule | |
| of referring the matter to the arbitrator in these situations. Courts | |
| have many ways of preventing the misuse of court processes for | |
| improper ends. Proceedings that appear vexatious can be | |
| handled by requiring security for costs and by suitable awards of | |
| costs. In England, courts have awarded full indemnity costs | |
| where a party improperly ignored arbitral jurisdiction (Hugh | |
| Beale, ed., Chitty on Contracts (33rd ed. 2018), vol. II, Specific | |
| Contracts, at para. 32-065; A. v. B. (No. 2), [2007] EWHC 54 | |
| (Comm.) : [2007] 1 All ER 633 (Comm.), at para. 15; Kyrgyz | |
| Mobil Tel Limited v. Fellowes International Holdings Limited, | |
| [2005] EWHC 1329 : 2005 WL 6514129 (Q.B.), at paras. 43-44). | |
| Further, if the party who successfully enforced an arbitration | |
| agreement were to bring an action, depending on the | |
| circumstances they might be able to recover damages for breach | |
| of contract, that contract being the agreement to arbitrate (Beale, | |
| at para. 32-052; West Tankers Inc. v. Allianz SpA, [2012] | |
| EWHC 854 (Comm.) : [2012] 2 All ER 395 (Comm.), at para. | |
| 77).” | |
| (Emphasis supplied) | |
WHETHER THE VALIDITY OF THE PRE-DEPOSIT CONDITION AS
CONTAINED IN CLAUSE 55 OF THE AGREEMENT CAN BE
43
LOOKED INTO AND DECIDED ON THE ANVIL OF ARTICLE 14 OF
THE CONSTITUTION IN A PETITION UNDER SECTION 11(6) OF
THE ACT 1996?
70. The vociferous submission on the part of the learned counsel appearing
for the respondent, that this Court while considering an application under
Section 11(6) of the Act 1996 for the appointment of arbitrator should not test
the validity or reasonableness of the conditions stipulated in the arbitration
clause on the touchstone or anvil of Article 14 of the Constitution, is without
any merit or substance.
71. It would be too much for the respondent to say that it is only the writ
court in a petition under Article 226 of the Constitution that can consider
whether a particular condition in the arbitration clause is arbitrary.
72. It is not for the first time that this Court is looking into the arbitration
clause falling foul of Article 14 of the Constitution while deciding Section
11(6) application.
73. In the case of TRF Limited v. Energo Engineering Projects Limited
reported in (2017) 8 SCC 377, this Court observed as under: -
“ In this batch of appeals, by special leave, the seminal issues that
emanate for consideration are; whether the High Court [TRF
Ltd. v. Energo Engg. Projects Ltd., 2016 SCC OnLine Del 2532]
, while dealing with the applications under Section 11(6) of the
Arbitration and Conciliation Act, 1996 (for brevity, “the Act”), is
justified to repel the submissions of the appellants that once the
44
person who was required to arbitrate upon the disputes arisen
under the terms and conditions of the contract becomes ineligible
by operation of law , he would not be eligible to nominate a
person as an arbitrator, and second, a plea that pertains to
statutory disqualification of the nominated arbitrator can be
raised before the court in application preferred under Section
11(6) of the Act, for such an application is not incompetent. For
the sake of clarity, convenience and apposite appreciation, we
shall state the facts from Civil Appeal No. 5306 of 2017.”
xxx xxx xxx
54. In such a context, the fulcrum of the controversy would be,
can an ineligible arbitrator, like the Managing Director,
nominate an arbitrator, who may be otherwise eligible and a
respectable person. As stated earlier, we are neither concerned
with the objectivity nor the individual respectability. We are only
concerned with the authority or the power of the Managing
Director. By our analysis, we are obligated to arrive at the
conclusion that once the arbitrator has become ineligible by
operation of law, he cannot nominate another as an arbitrator .
The arbitrator becomes ineligible as per prescription contained
in Section 12(5) of the Act. It is inconceivable in law that person
who is statutorily ineligible can nominate a person. Needless to
say, once the infrastructure collapses, the superstructure is bound
to collapse. One cannot have a building without the plinth. Or to
put it differently, once the identity of the Managing Director as
the sole arbitrator is lost, the power to nominate someone else as
an arbitrator is obliterated. Therefore, the view expressed by the
High Court is not sustainable and we say so .”
(Emphasis supplied)
74. In Perkins Eastman (supra), this Court held as under:
“This application under Section 11(6) read with Section
11(12)(a) of the Arbitration and Conciliation Act, 1996 (“the
Act”) and under the Appointment of Arbitrators by the Chief
Justice of India Scheme, 1996 (“the Scheme”) prays for the
following principal relief:
45
“(a) appoint a sole arbitrator, in accordance with Clause 24
of the contract dated 22-5-2017 executed between the
parties and the sole arbitrator so appointed may adjudicate
the disputes and differences between the parties arising
from the said contract.”
xxx xxx xxx
21. But, in our view that has to be the logical deduction from TRF
Ltd. [TRF Ltd. v. Energo Engg. Projects Ltd., (2017) 8 SCC 377
: (2017) 4 SCC (Civ) 72] Para 50 of the decision shows that this
Court was concerned with the issue, “whether the Managing
Director, after becoming ineligible by operation of law, is he
still eligible to nominate an arbitrator” The ineligibility
referred to therein, was as a result of operation of law, in that a
person having an interest in the dispute or in the outcome or
decision thereof, must not only be ineligible to act as an
arbitrator but must also not be eligible to appoint anyone else
as an arbitrator and that such person cannot and should not
have any role in charting out any course to the dispute
resolution by having the power to appoint an arbitrator. The
next sentences in the paragraph, further show that cases where
both the parties could nominate respective arbitrators of their
choice were found to be completely a different situation. The
reason is clear that whatever advantage a party may derive by
nominating an arbitrator of its choice would get counter-
balanced by equal power with the other party. But, in a case
where only one party has a right to appoint a sole arbitrator, its
choice will always have an element of exclusivity in determining
or charting the course for dispute resolution. Naturally, the
person who has an interest in the outcome or decision of the
dispute must not have the power to appoint a sole arbitrator. That
has to be taken as the essence of the amendments brought in by
the Arbitration and Conciliation (Amendment) Act, 2015 (3 of
2016) and recognised by the decision of this Court in TRF
Ltd. [TRF Ltd. v. Energo Engg. Projects Ltd., (2017) 8 SCC 377
: (2017) 4 SCC (Civ) 72]”
(Emphasis supplied)
46
75. In Voestalpine Schienen GMBH v. Delhi Metro Rail Corporation
Limited reported in (2017) 4 SCC 665, this Court held as under:
“28. Before we part with, we deem it necessary to make certain
comments on the procedure contained in the arbitration
agreement for constituting the Arbitral Tribunal. Even when
there are a number of persons empanelled, discretion is with
DMRC to pick five persons therefrom and forward their names to
the other side which is to select one of these five persons as its
nominee (though in this case, it is now done away with). Not only
this, DMRC is also to nominate its arbitrator from the said list.
Above all, the two arbitrators have also limited choice of picking
upon the third arbitrator from the very same list i.e. from
remaining three persons. This procedure has two adverse
consequences. In the first place, the choice given to the opposite
party is limited as it has to choose one out of the five names that
are forwarded by the other side. There is no free choice to
nominate a person out of the entire panel prepared by DMRC.
Secondly, with the discretion given to DMRC to choose five
persons, a room for suspicion is created in the mind of the other
side that DMRC may have picked up its own favourites. Such a
situation has to be countenanced. We are, therefore, of the
opinion that sub-clauses (b) & (c) of Clause 9.2 of SCC need to
be deleted and instead choice should be given to the parties to
nominate any person from the entire panel of arbitrators.
Likewise, the two arbitrators nominated by the parties should be
given full freedom to choose the third arbitrator from the whole
panel .”
(Emphasis supplied )
76. What is relevant to note in all the above referred decisions of this Court is
the phrase “operation of law”. This phrase is of wider connotation and covers
the Act 1996 as well as the Constitution of India and any other Central or State
Law.
47
77. In the aforesaid context, we should look into and discuss the Kelson’s Pure
Theory of Law on the basic norm that he called “Grundnorm”.
78. Kelson’s pure theory of law has its pyramidical structure of hierarchy
based on the basic norm of Grundnorm. The word ‘Grundnorm’ is a German
word meaning fundamental norm. He has defined it as ‘ the postulated ultimate
rule according to which the norms of this order are established and annulled,
receive or lose their validity ’. It is the Grundnorm which determines the content
and validates the other norms derived from it. But from where it derives its
validity, was a question which Kelson did not answer, stating it to be a meta-
physical question. Grundnorm is a fiction, rather than a hypothesis as proposed
by the jurist. The Grundnorm is the starting point in a legal system and from this
base; a legal system broadens down in gradation becoming more and more
detailed and specific as it progresses. This is a dynamic process. At the top of
the pyramid is the Grundnorm, which is independent. The subordinate norms are
controlled by norms superior to them in hierarchical order. The system of norms
proceeds from downwards to upwards and finally closes at Grundnorm.
(Reference: Application of Grundnorm in India, Zainab Arif Khan, Aligarh
Muslim University)
79. Our Constitution is the paramount source of law in our country. All other
laws assume validity because they are in conformity with the Constitution. The
Constitution itself contain provisions that clearly provide that any law which is
48
in violation of its provisions is unlawful and is liable to be struck down. As
contained in Article 13 , which provides that all laws which were made either
before the commencement of the Constitution, or are made after it, by any
competent authority, which are inconsistent with the fundamental rights
enshrined in the Constitution, are, to the extent of inconsistency, void. This again
unveils the principle of Grundnorm which says there has to be a basic rule. The
Constitution is the basic and the ultimate source of law.
80. In the aforesaid context, we must look into view decisions of the High
Courts explaining the theory of Grundnorm.
(i) In the case of Squadron Leader H. S. Kulshrestha v Union of India
reported in 1999 SCC OnLine All 270, the court held that ‘ According to the
theory of the eminent jurist Kelson, in every country there is a hierarchy of laws,
and the highest law is known as the grundnorm of law. In our country the
grundnorm is the Constitution. ’
(ii) In another case of Abdur Sukur & Another v State of West Bengal &
others reported in 2019 SCC Online Cal 5455, the court held that ‘ …enshrined
in the Constitution of India, which is the grundnorm of all Indian statutes. ’
(iii) In another case of Om Prakash Gupta v Hindustan Petroleum
Corporation Ltd. & Anr. reported in 2009 SCC OnLine Raj 1381, it was again
49
| held that ‘Since the limits have been defined by the Constitution, they are, in | |
|---|
| jurisprudential term, ‘the grundnorm’.’ | |
| (iv) In another case of Sunil v State of M. P. & Another reported in 2016 SCC | 2016 SCC |
| OnLine MP 8551, | |
the grundnorm – the paramount law of the country. All other laws derive their
origin and are supplementary and incidental to the principles laid down in the
Constitution. ’
(v) In the case of Government of Andhra Pradesh & Ors vs Smt. P. Laxmi
Devi reported in (2008) 4 SCC 720, this Court observed, ‘ According to Kelson,
in every country there is a hierarchy of legal norms, headed by what he calls as
the ‘grundnorm ’ . If a legal norm in a higher layer of this hierarchy conflicts with
a legal norm in a lower layer the former will prevail. In India the Grundnorm is
the Indian Constitution .’
81. Thus, in the context of the Arbitration Agreement, the layers of the
Grundnorm as per Kelsen's theory would be in the following hierarchy:
(i) Constitution of India, 1950;
(ii) Arbitration and Conciliation Act, 1996 & any other Central/State Law;
(iii) Arbitration Agreement entered into by the parties in light of s. 7 of the
Arbitration and Conciliation Act, 1996.
50
82. Thus, the Arbitration Agreement, has to comply with the requirements of
the following and cannot fall foul of:
(i) Section 7 of the Arbitration and Conciliation Act;
(ii) any other provisions of the Arbitration and Conciliation Act, 1996 &
Central/State Law;
(iii) Constitution of India, 1950.
83. The observations of this Court in para 236 of Vidya Drolia (supra) should
clinch the issue. Para 236 reads thus:
| “236. Having established the threshold standard for the court to | |
|---|
| examine the extent of validity of the arbitration agreement, as a | |
| starting point, it is necessary to go back to Duro Felguera [Duro | |
| Felguera, S.A. v. Gangavaram Port Ltd., (2017) 9 SCC 729 : | |
| (2017) 4 SCC (Civ) 764], which laid down : (SCC p. 759, para | |
| 48) | |
| |
| “48. … From a reading of Section 11(6-A), the intention of |
| the legislature is crystal clear i.e. the court should and need |
| only look into one aspect—the existence of an arbitration |
| agreement. What are the factors for deciding as to whether |
| there is an arbitration agreement is the next question. The |
| resolution to that is simple—it needs to be seen if the |
| agreement contains a clause which provides for arbitration |
| pertaining to the disputes which have arisen between the |
| parties to the agreement.” |
| |
| At first blush, the Court seems to have read the existence of the | |
| arbitration agreement by limiting the examination to an | |
| examination of its factual existence. However, that is not so, as | |
| the existence of arbitration agreement does not mean anything | |
| unless such agreement is contractually valid. This view is | |
| confirmed by Duro Felguera case [Duro Felguera, | |
| S.A. v. Gangavaram Port Ltd., (2017) 9 SCC 729 : (2017) 4 SCC | |
| (Civ) 764], wherein the reference to the contractual aspect of | |
| arbitration agreement is ingrained under Section 7 analysis. A | |
| mere agreement is not legally binding, unless it satisfies the core | |
| contractual requirements, concerning consent, consideration, | |
| legal relationship, etc.” | |
51
(Emphasis supplied)
84. The concept of “party autonomy” as pressed into service by the
respondent cannot be stretched to an extent where it violates the fundamental
rights under the Constitution. For an arbitration clause to be legally binding it
has to be in consonance with the “operation of law” which includes the
Grundnorm i.e. the Constitution. It is the rule of law which is supreme and forms
parts of the basic structure. The argument canvassed on behalf of the respondent
that the petitioner having consented to the pre-deposit clause at the time of
execution of the agreement, cannot turn around and tell the court in a Section
11(6) petition that the same is arbitrary and falling foul of Article 14 of the
Constitution is without any merit.
85. It is a settled position of law that there can be no consent against the law
and there can be no waiver of fundamental rights. The Constitution Bench of this
Court speaking through Chief Justice Y.V. Chandrachud (as His Lordship then
was) in Olga Tellis and Others v. Bombay Municipal Corporation and Others
reported in (1985) 3 SCC 545 observed something very illuminating on the said
aspect:
“28. It is not possible to accept the contention that the
petitioners are estopped from setting up their fundamental
rights as a defence to the demolition of the huts put up by them
on pavements or parts of public roads. There can be no estoppel
against the Constitution. The Constitution is not only the
paramount law of the land but, it is the source and sustenance
52
of all laws. Its provisions are conceived in public interest and
are intended to serve a public purpose. The doctrine of estoppel
is based on the principle that consistency in word and action
imparts certainty and honesty to human affairs. If a person
makes a representation to another, on the faith of which the
latter acts to his prejudice, the former cannot resile from the
representation made by him. He must make it good. This
principle can have no application to representations made
regarding the assertion or enforcement of fundamental rights.
For example, the concession made by a person that he does not
possess and would not exercise his right to free speech and
expression or the right to move freely throughout the territory
of India cannot deprive him of those constitutional rights, any
more than a concession that a person has no right of personal
liberty can justify his detention contrary to the terms of Article
22 of the Constitution. Fundamental rights are undoubtedly
conferred by the Constitution upon individuals which have to be
asserted and enforced by them, if those rights are violated. But,
the high purpose which the Constitution seeks to achieve by
conferment of fundamental rights is not only to benefit
individuals but to secure the larger interests of the community.
The Preamble of the Constitution says that India is a democratic
Republic. It is in order to fulfil the promise of the Preamble that
fundamental rights are conferred by the Constitution, some on
citizens like those guaranteed by Articles 15, 16, 19, 21 and 29
and, some on citizens and non-citizens alike, like those
guaranteed by Articles 14, 21, 22 and 25 of the Constitution. No
individual can barter away the freedoms conferred upon him by
the Constitution. A concession made by him in a proceeding,
whether under a mistake of law or otherwise, that he does not
possess or will not enforce any particular fundamental right,
cannot create an estoppel against him in that or any subsequent
proceeding. Such a concession, if enforced, would defeat the
purpose of the Constitution. Were the argument of estoppel
valid, an all-powerful State could easily tempt an individual to
forego his precious personal freedoms on promise of transitory,
immediate benefits . Therefore, notwithstanding the fact that the
petitioners had conceded in the Bombay High Court that they
have no fundamental right to construct hutments on pavements
and that they will not object to their demolition after October
15, 1981, they are entitled to assert that any such action on the
part of public authorities will be in violation of their
fundamental rights. How far the argument regarding the
53
existence and scope of the right claimed by the petitioners is
well-founded is another matter. But, the argument has to be
examined despite the concession.
29. The plea of estoppel is closely connected with the plea of
waiver, the object of both being to ensure bona fides in day-to-
day transactions. In Basheshar Nath v. CIT [1959 Supp 1 SCR
528 : AIR 1959 SC 149 : (1959) 35 ITR 190], a Constitution
Bench of this Court considered the question whether the
fundamental rights conferred by the Constitution can be waived.
Two members of the Bench (Das, C.J. and Kapoor, J.) held that
there can be no waiver of the fundamental right founded on
Article 14 of the Constitution. Two others (N.H. Bhagwati and
Subba Rao, JJ.) held that not only could there be no waiver of the
right conferred by Article 14, but there could be no waiver of any
other fundamental right guaranteed by Part III of the
Constitution. The Constitution makes no distinction, according to
the learned Judges, between fundamental rights enacted for the
benefit of an individual and those enacted in public interest or on
grounds of public policy.”
(Emphasis supplied)
Issue No. IV
86. The issue as regards, the validity of arbitration clause empowering the
Principal Secretary/Secretary (Irrigation), Government of Uttarakhand to
appoint an arbitrator of his choice is concerned, the same could be said to be
covered by the decision of this Court in Perkins Eastman (supra):
87. If circumstances exist giving rise to justifiable doubts as to the
independence and impartiality of the person nominated or if other circumstances
warrant appointment of an independent arbitrator by ignoring the procedure
prescribed, the Chief Justice or his designate may, for reasons to be recorded
54
ignore the designated arbitrator and appoint someone else. [See: IOC v. Raja
Transport Pvt. Ltd , (2009) 8 SCC 520]
| 88. In the aforesaid context, we must look into the amended Section 12 of the | |
|---|
| 1996 Act. Section 12 reads thus: | |
| “12. Grounds for challenge. |
| (1) When a person is approached in connection with his |
| possible appointment as an arbitrator, he shall disclose in |
| writing any circumstances,— |
| (a) such as the existence either direct or indirect, of any past or | |
|---|
| present relationship with or interest in any of the parties or in | |
| relation to the subject-matter in dispute, whether financial, | |
| business, professional or other kind, which is likely to give rise | |
| to justifiable doubts as to his independence or impartiality; and | |
| (b) which are likely to affect his ability to devote sufficient time | |
| to the arbitration and in particular his ability to complete the | |
| entire arbitration within a period of twelve months. | |
| Explanation 1.—The grounds stated in the Fifth Schedule shall | |
| guide in determining whether circumstances exist which give | |
| rise to justifiable doubts as to the independence or impartiality | |
| of an arbitrator. | |
| Explanation 2.—The disclosure shall be made by such person | |
|---|
| in the form specified in the Sixth Schedule.] | |
| (a) circumstances exist that give rise to justifiable doubts as to | | |
|---|
| his independence or impartiality, or | | |
| (b) he does not possess the qualifications agreed to by the | | |
| parties. | | |
55
| (5) Notwithstanding any prior agreement to the contrary, any | |
|---|
| person whose relationship, with the parties or counsel or the | |
| subject-matter of the dispute, falls under any of the categories | |
| specified in the Seventh Schedule shall be ineligible to be | |
| appointed as an arbitrator: | |
| | |
| Provided that parties may, subsequent to disputes having arisen | |
| between them, waive the applicability of this sub-section by an | |
| express agreement in writing.” | |
| | |
| 89. The Amendment 2015 is also based on the recommendation of the Law | | |
| Commission which specifically dealt with the issue of “Neutrality of | | |
| Arbitrators” and a discussion in this behalf is contained in paras 53 to 60 of the | | |
| Law Commission’s Report No. 246 published in the August 2004. We reproduce | | |
| the entire discussion hereinbelow: | | |
EUTRALITY OF RBITRATORS
“ N A
53. It is universally accepted that any quasi-judicial process,
including the arbitration process, must be in accordance with
principles of natural justice. In the context of arbitration,
neutrality of arbitrators viz. their independence and impartiality,
is critical to the entire process.
54. In the Act, the test for neutrality is set out in Section 12(3)
which provides—
‘ 12. (3) An arbitrator may be challenged only if—
(a) circumstances exist that give rise to justifiable doubts as
to his independence or impartiality.…’
55. The Act does not lay down any other conditions to identify the
“circumstances” which give rise to “justifiable doubts”, and it
is clear that there can be many such circumstances and
situations. The test is not whether, given the circumstances, there
is any actual bias for that is setting the bar too high; but, whether
56
the circumstances in question give rise to any justifiable
apprehensions of bias.
56. The limits of this provision has been tested in the Indian
Supreme Court in the context of contracts with State entities
naming particular persons/designations (associated with that
entity) as a potential arbitrator. It appears to be settled by a
series of decisions of the Supreme Court (see Executive
Engineer, Irrigation Division v. Gangaram
Chhapolia [Executive Engineer, Irrigation
Division v. Gangaram Chhapolia, (1984) 3 SCC 627]
, Transport Deptt. v. Munuswamy Mudaliar [Transport
Deptt. v. Munuswamy Mudaliar, 1988 Supp SCC 651]
, International Airports Authority v. K.D. Bali [International
Airports Authority v. K.D. Bali, (1988) 2 SCC 360] , S.
Rajan v. State of Kerala [S. Rajan v. State of Kerala, (1992) 3
SCC 608] , Indian Drugs & Pharmaceuticals Ltd. v. Indo Swiss
Synthetics Gem Mfg. Co. Ltd. [Indian Drugs & Pharmaceuticals
Ltd. v. Indo Swiss Synthetics Gem Mfg. Co. Ltd., (1996) 1 SCC
54] , Union of India v. M.P. Gupta [Union of India v. M.P.
Gupta, (2004) 10 SCC 504] and ACE Pipeline Contracts (P)
Ltd. v. Bharat Petroleum Corpn. Ltd. [ACE Pipeline Contracts
(P) Ltd. v. Bharat Petroleum Corpn. Ltd., (2007) 5 SCC 304] that
arbitration agreements in government contracts which provide
for arbitration by a serving employee of the department, are valid
and enforceable. While the Supreme Court, in Indian Oil Corpn.
Ltd. v. Raja Transport (P) Ltd. [Indian Oil Corpn. Ltd. v. Raja
Transport (P) Ltd., (2009) 8 SCC 520 : (2009) 3 SCC (Civ) 460]
, carved out a minor exception in situations when the arbitrator
‘was the controlling or dealing authority in regard to the subject
contract or if he is a direct subordinate (as contrasted from an
officer of an inferior rank in some other department) to the officer
whose decision is the subject-matter of the dispute’ (SCC p. 533,
para 34)
and this exception was used by the Supreme Court in Denel
(Proprietary) Ltd. v. Ministry of Defence [Denel (Proprietary)
Ltd. v. Ministry of Defence, (2012) 2 SCC 759 : (2012) 2 SCC
(Civ) 37 : AIR 2012 SC 817] and Bipromasz Bipron Trading
Sa v. Bharat Electronics Ltd. [Bipromasz Bipron Trading
Sa v. Bharat Electronics Ltd., (2012) 6 SCC 384 : (2012) 3 SCC
(Civ) 702] , to appoint an independent arbitrator under Section
11, this is not enough.
57
57. The balance between procedural fairness and binding nature
of these contracts, appears to have been tilted in favour of the
latter by the Supreme Court, and the Commission believes the
present position of law is far from satisfactory. Since the
principles of impartiality and independence cannot be discarded
at any stage of the proceedings, specifically at the stage of
constitution of the Arbitral Tribunal, it would be incongruous to
say that party autonomy can be exercised in complete disregard
of these principles — even if the same has been agreed prior to
the disputes having arisen between the parties. There are certain
minimum levels of independence and impartiality that should be
required of the arbitral process regardless of the parties'
apparent agreement. A sensible law cannot, for instance, permit
appointment of an arbitrator who is himself a party to the dispute,
or who is employed by (or similarly dependent on) one party,
even if this is what the parties agreed. The Commission hastens
to add that Mr P.K. Malhotra, the ex officio member of the Law
Commission suggested having an exception for the State, and
allow State parties to appoint employee arbitrators. The
Commission is of the opinion that, on this issue, there cannot be
any distinction between State and non-State parties. The concept
of party autonomy cannot be stretched to a point where it negates
the very basis of having impartial and independent adjudicators
for resolution of disputes. In fact, when the party appointing an
adjudicator is the State, the duty to appoint an impartial and
independent adjudicator is that much more onerous — and the
right to natural justice cannot be said to have been waived only
on the basis of a “prior” agreement between the parties at the
time of the contract and before arising of the disputes.
58. Large-scale amendments have been suggested to address this
fundamental issue of neutrality of arbitrators, which the
Commission believes is critical to the functioning of the
arbitration process in India. In particular, amendments have
been proposed to Sections 11, 12 and 14 of the Act.
59. The Commission has proposed the requirement of having
specific disclosures by the arbitrator, at the stage of his
possible appointment, regarding existence of any relationship or
interest of any kind which is likely to give rise to justifiable
doubts. The Commission has proposed the incorporation of the
58
| Fourth Schedule, which has drawn from the red and orange lists | | |
|---|
| of the IBA Guidelines on Conflicts of Interest in International | | |
| Arbitration, and which would be treated as a “guide” to | | |
| determine whether circumstances exist which give rise to such | | |
| justifiable doubts. On the other hand, in terms of the proposed | | |
| Section 12(5) of the Act and the Fifth Schedule which | | |
| incorporates the categories from the red list of the IBA | | |
| Guidelines (as above), the person proposed to be appointed as | | |
| an arbitrator shall be ineligible to be so appointed, | | |
| notwithstanding any prior agreement to the contrary. In the event | | |
| such an ineligible person is purported to be appointed as an | | |
| arbitrator, he shall be de jure deemed to be unable to perform his | | |
| functions, in terms of the proposed Explanation to Section 14. | | |
| Therefore, while the disclosure is required with respect to a | | |
| broader list of categories (as set out in the Fourth Schedule, and | | |
| as based on the red and orange lists of the IBA Guidelines), the | | |
| ineligibility to be appointed as an arbitrator (and the consequent | | |
| de jure inability to so act) follows from a smaller and more | | |
| serious sub-set of situations (as set out in the Fifth Schedule, and | | |
| as based on the red list of the IBA Guidelines). | | |
| | |
| 60. The Commission, however, feels that real and genuine party | | |
| autonomy must be respected, and, in certain situations, parties | | |
| should be allowed to waive even the categories of ineligibility as | | |
| set in the proposed Fifth Schedule. This could be in situations of | | |
| family arbitrations or other arbitrations where a person | | |
| commands the blind faith and trust of the parties to the dispute, | | |
| despite the existence of objective “justifiable doubts” regarding | | |
| his independence and impartiality. To deal with such situations, | | |
| the Commission has proposed the proviso to Section 12(5), where | | |
| parties may, subsequent to disputes having arisen between them, | | |
| waive the applicability of the proposed Section 12(5) by an | | |
| express agreement in writing. In all other cases, the general rule | | |
| in the proposed Section 12(5) must be followed. In the event the | | |
| High Court is approached in connection with appointment of an | | |
| arbitrator, the Commission has proposed seeking the disclosure | | |
| in terms of Section 12(1) and in which context the High Court or | | |
| the designate is to have “due regard” to the contents of such | | |
| disclosure in appointing the arbitrator.” | | |
| (Emphasis supplied) | |
59
90. Although, the Law Commission discussed the aforesaid aspect under the
heading “Neutrality of Arbitrators”, yet the focus of discussion was on
impartiality and independence of the arbitrators which has relation to or bias
towards one of the parties. In the field of international arbitration, neutrality is
generally related to the nationality of the arbitrator. In the international sphere,
the “appearance of neutrality” is considered equally important, which means that
an arbitrator is neutral if his nationality is different from that of the parties.
However, that is not the aspect which is being considered and the term
“neutrality” used is relatable to impartiality and independence of the arbitrators,
without any bias towards any of the parties. In fact, the term “neutrality of
arbitrators” is commonly used in this context as well. (See: Voestalpine
Schienen GMBH (supra))
91. Keeping in mind the aforequoted recommendation of the Law
Commission, with which spirit, Section 12 has been amended by the Amendment
Act, 2015, it is manifest that the main purpose for amending the provision was
to provide for neutrality of arbitrators. In order to achieve this, sub-section (5)
of Section 12 lays down that notwithstanding any prior agreement to the
contrary, any person whose relationship with the parties or counsel or the
subject-matter of the dispute falls under any of the categories specified in the
Seventh Schedule, he shall be ineligible to be appointed as an arbitrator. In such
an eventuality i.e. when the arbitration clause finds foul with the amended
provisions extracted above, the appointment of an arbitrator would be beyond
60
pale of the arbitration agreement, empowering the court to appoint such
arbitrator(s) as may be permissible. That would be the effect of the non obstante
clause contained in sub-section (5) of Section 12 and the other party cannot insist
on appointment of the arbitrator in terms of the arbitration agreement. (See:
Voestalpine Schienen GMBH (supra))
92. There are a plethora of judgments of this Court even prior to the
amendment of Section 12, where courts have appointed the arbitrators, giving a
go-by to the agreed arbitration clause in certain contingencies and situations,
having regard to the provisions of unamended Section 11(8) of the Act which,
inter alia , provided that while appointing the arbitrator, Chief Justice, or the
person or the institution designated by him, shall have regard to the other
conditions as are likely to secure the appointment of an independent and
impartial arbitrator. See Datar Switchgears Ltd. v. Tata Finance Ltd reported
in (2000) 8 SCC 151, Punj Lloyd Ltd. v. Petronet MHB Ltd. reported in (2006)
2 SCC 638, Union of India v. Bharat Battery Mfg. Co. (P) Ltd. reported in
(2007) 7 SCC 684, Deep Trading Co. v. Indian Oil Corpn. reported in (2013) 4
SCC 35, Union of India v. Singh Builders Syndicate reported in (2009) 4 SCC
523 and North Eastern Railway v. Tripple Engg. Works reported in (2014) 9
SCC 288.
93. Taking note of the aforesaid judgments, this Court in Union of India and
Others v . Uttar Pradesh State Bridge Corporation Limited reported in (2015) 2
SCC 52 summed up the position in the following manner:
61
| “13. No doubt, ordinarily that would be the position. The moot | |
|---|
| question, however, is as to whether such a course of action has | |
| to be necessarily adopted by the High Court in all cases, while | |
| dealing with an application under Section 11 of the Act or is there | |
| room for play in the joints and the High Court is not divested of | |
| exercising discretion under some circumstances? If yes, what are | |
| those circumstances? It is this very aspect which was specifically | |
| dealt with by this Court in Tripple Engg. Works [North Eastern | |
| Railway v. Tripple Engg. Works, (2014) 9 SCC 288 : (2014) 5 | |
| SCC (Civ) 30]. Taking note of various judgments, the Court | |
| pointed out that the notion that the High Court was bound to | |
| appoint the arbitrator as per the contract between the parties has | |
| seen a significant erosion in recent past. In paras 6 and 7 of the | |
| said decision, those judgments wherein departure from the | |
| aforesaid “classical notion” has been made are taken note of. It | |
| would, therefore, be useful to reproduce the said paragraph | |
| along with paras 8 and 9 hereinbelow: (SCC pp. 291-93) | |
| |
| “6. The ‘classical notion’ that the High Court while |
| exercising its power under Section 11 of the Arbitration and |
| Conciliation Act, 1996 (hereinafter for short ‘the Act’) must |
| appoint the arbitrator as per the contract between the parties |
| saw a significant erosion in ACE Pipeline Contracts (P) |
| Ltd. v. Bharat Petroleum Corpn. Ltd. [(2007) 5 SCC 304], |
| wherein this Court had taken the view that though the |
| contract between the parties must be adhered to, deviations |
| therefrom in exceptional circumstances would be |
| permissible. A more significant development had come in a |
| decision that followed soon thereafter in Union of |
| India v. Bharat Battery Mfg. Co. (P) Ltd. [(2007) 7 SCC 684] |
| wherein following a three-Judge Bench decision in Punj |
| Lloyd Ltd. v. Petronet MHB Ltd. [(2006) 2 SCC 638], it was |
| held that once an aggrieved party files an application under |
| Section 11(6) of the Act to the High Court, the opposite party |
| would lose its right of appointment of the arbitrator(s) as per |
| the terms of the contract. The implication that the Court |
| would be free to deviate from the terms of the contract is |
| obvious. |
| |
| 7. The apparent dichotomy in ACE Pipeline [(2007) 5 SCC |
| 304]and Bharat Battery Mfg. Co. (P) Ltd. [(2007) 7 SCC |
| 684] was reconciled by a three-Judge Bench of this Court |
62
| in Northern Railway Admn., Ministry of Railway v. Patel | |
|---|
| Engg. Co. Ltd. [(2008) 10 SCC 240], wherein the jurisdiction | |
| of the High Court under Section 11(6) of the Act was sought | |
| to be emphasised by taking into account the expression ‘to | |
| take the necessary measure’ appearing in sub-section (6) of | |
| Section 11 and by further laying down that the said | |
| expression has to be read along with the requirement of sub- | |
| section (8) of Section 11 of the Act. The position was further | |
| clarified in Indian Oil Corpn. Ltd. v. Raja Transport (P) | |
| Ltd. [(2009) 8 SCC 520 : (2009) 3 SCC (Civ) 460]. Para 48 | |
| of the Report wherein the scope of Section 11 of the Act was | |
| summarised may be quoted by reproducing sub-paras (vi) | |
| and (vii) hereinbelow: (Indian Oil case [(2009) 8 SCC 520 : | |
| (2009) 3 SCC (Civ) 460], SCC p. 537) | |
| |
| ‘48.(vi) The Chief Justice or his designate while |
| exercising power under sub-section (6) of Section |
| 11 shall endeavour to give effect to the appointment |
| procedure prescribed in the arbitration clause. |
| |
| (vii) If circumstances exist, giving rise to justifiable |
| doubts as to the independence and impartiality of the |
| person nominated, or if other circumstances warrant |
| appointment of an independent arbitrator by ignoring the |
| procedure prescribed, the Chief Justice or his designate |
| may, for reasons to be recorded, ignore the designated |
| arbitrator and appoint someone else.” |
| |
| 8. The above discussion will not be complete without | |
| reference to the view of this Court expressed in Union of | |
| India v. Singh Builders Syndicate [(2009) 4 SCC 523 : | |
| (2009) 2 SCC (Civ) 246], wherein the appointment of a | |
| retired Judge contrary to the agreement requiring | |
| appointment of specified officers was held to be valid on the | |
| ground that the arbitration proceedings had not concluded | |
| for over a decade making a mockery of the process. In fact, | |
| in para 25 of the Report in Singh Builders Syndicate [(2009) | |
| 4 SCC 523 : (2009) 2 SCC (Civ) 246] this Court had | |
| suggested that the Government, statutory authorities and | |
| government companies should consider phasing out | |
| arbitration clauses providing for appointment of serving | |
| officers and encourage professionalism in arbitration. | |
63
| | |
|---|
| | 9. A pronouncement of late in Deep Trading Co. v. Indian Oil |
| | Corpn. [(2013) 4 SCC 35 : (2013) 2 SCC (Civ) 449] followed |
| | the legal position laid down in Punj Lloyd Ltd. [Punj Lloyd |
| | Ltd. v. Petronet MHB Ltd., (2006) 2 SCC 638] which in turn |
| | had followed a two-Judge Bench decision in Datar |
| | Switchgears Ltd. v. Tata Finance Ltd. [(2000) 8 SCC 151]. |
| | The theory of forfeiture of the rights of a party under the |
| | agreement to appoint its arbitrator once the proceedings |
| | under Section 11(6) of the Act had commenced came to be |
| | even more formally embedded in Deep Trading Co. [(2013) |
| | 4 SCC 35 : (2013) 2 SCC (Civ) 449] subject, of course, to the |
| | provisions of Section 11(8), which provision in any event, had |
| | been held in Northern Railway Admn. [(2008) 10 SCC 240] |
| | not to be mandatory, but only embodying a requirement of |
| | keeping the same in view at the time of exercise of jurisdiction |
| | under Section 11(6) of the Act.” |
| | (emphasis in original) |
| 14. Speedy conclusion of arbitration proceedings hardly needs to | | |
| be emphasised. It would be of some interest to note that in | | |
| England also, Modern Arbitration Law on the lines | | |
| of UNCITRAL Model Law, came to be enacted in the same year as | | |
| the Indian law which is known as the English Arbitration Act, | | |
| 1996 and it became effective from 31-1-1997. It is treated as the | | |
| most extensive statutory reform of the English arbitration law. | | |
| Commenting upon the structure of this Act, Mustill and Boyd in | | |
| their Commercial Arbitration, 2001 companion volume to the | | |
| 2nd Edn., have commented that this Act is founded on four | | |
| pillars. These pillars are described as: | | |
| (a) The first pillar: Three general principles. | |
| (b) The second pillar: The general duty of the Tribunal. | |
| (c) The third pillar: The general duty of the parties. | |
| (d) The fourth pillar: Mandatory and semi-mandatory | |
| provisions. | |
Insofar as the first pillar is concerned, it contains three general
principles on which the entire edifice of the said Act is structured.
These principles are mentioned by an English Court in its
judgment in Deptt. of Economics, Policy and Development of the
City of Moscow v. Bankers Trust Co. [2005 QB 207 : (2004) 3
WLR 533 : (2004) 4 All ER 746 : 2004 EWCA Civ 314]. In that
case, Mance, L.J. succinctly summed up the objective of this Act
in the following words: (QB p. 228, para 31)
64
“31. … Parliament has set out, in the Arbitration Act,
1996, to encourage and facilitate a reformed and more
independent, as well as private and confidential, system
of consensual dispute resolution, with only limited
possibilities of court involvement where necessary in the
interests of the public and of basic fairness.”
Section 1 of the Act sets forth the three main principles of
arbitration law viz. (i) speedy, inexpensive and fair trial by an
impartial tribunal; (ii) party autonomy; and (iii) minimum court
intervention. This provision has to be applied purposively. In
case of doubt as to the meaning of any provision of this Act,
regard should be had to these principles.
15. In the book O.P. Malhotra on the Law and Practice of
Arbitration and Conciliation (3rd Edn. revised by Ms Indu
Malhotra), it is rightly observed that the Indian Arbitration Act
is also based on the aforesaid four foundational pillars.
16. First and paramount principle of the first pillar is “fair,
speedy and inexpensive trial by an Arbitral Tribunal”.
Unnecessary delay or expense would frustrate the very purpose
of arbitration. Interestingly, the second principle which is
recognised in the Act is the party autonomy in the choice of
procedure. This means that if a particular procedure is
prescribed in the arbitration agreement which the parties have
agreed to, that has to be generally resorted to. It is because of
this reason, as a normal practice, the court will insist the parties
to adhere to the procedure to which they have agreed upon. This
would apply even while making the appointment of substitute
arbitrator and the general rule is that such an appointment of a
substitute arbitrator should also be done in accordance with the
provisions of the original agreement applicable to the
appointment of the arbitrator at the initial stage. [See Yashwith
Constructions (P) Ltd. v. Simplex Concrete Piles India Ltd. [
(2006) 6 SCC 204]. However, this principle of party autonomy in
the choice of procedure has been deviated from in those cases
where one of the parties have committed default by not acting in
accordance with the procedure prescribed. Many such instances
where this course of action is taken and the Court appoint the
arbitrator when the persona designata has failed to act, are taken
note of in paras 6 and 7 of Tripple Engg. Works [North Eastern
Railway v. Tripple Engg. Works, (2014) 9 SCC 288 : (2014) 5
65
| SCC (Civ) 30]. We are conscious of the fact that these were the | |
|---|
| cases where appointment of the independent arbitrator made by | |
| the Court in exercise of powers under Section 11 of account of | |
| “default procedure”. We are, in the present case, concerned with | |
| the constitution of substitute Arbitral Tribunal where earlier | |
| Arbitral Tribunal has failed to perform. However, the above | |
| principle of default procedure is extended by this Court in such | |
| cases as well as is clear from the judgment in Singh Builders | |
| Syndicate [Union of India v. Singh Builders Syndicate, (2009) 4 | |
| SCC 523 : (2009) 2 SCC (Civ) 246]. | |
| | |
| 17. In the case of contracts between government | |
| corporations/State-owned companies with private | |
| parties/contractors, the terms of the agreement are usually | |
| drawn by the government company or public sector | |
| undertakings. Government contracts have broadly two kinds of | |
| arbitration clauses, first where a named officer is to act as sole | |
| arbitrator; and second, where a senior officer like a Managing | |
| Director, nominates a designated officer to act as the sole | |
| arbitrator. No doubt, such clauses which give the Government a | |
| dominant position to constitute the Arbitral Tribunal are held to | |
| be valid. At the same time, it also casts an onerous and | |
| responsible duty upon the persona designata to appoint such | |
| persons/officers as the arbitrators who are not only able to | |
| function independently and impartially, but are in a position to | |
| devote adequate time in conducting the arbitration. If the | |
| Government has nominated those officers as arbitrators who are | |
| not able to devote time to the arbitration proceedings or become | |
| incapable of acting as arbitrators because of frequent transfers, | |
| etc., then the principle of “default procedure” at least in the | |
| cases where Government has assumed the role of appointment of | |
| arbitrators to itself, has to be applied in the case of substitute | |
| arbitrators as well and the Court will step in to appoint the | |
| arbitrator by keeping aside the procedure which is agreed to | |
| between the parties. However, it will depend upon the facts of a | |
| particular case as to whether such a course of action should be | |
| taken or not. What we emphasise is that Court is not powerless | |
| in this regard.” | |
| (Emphasis supplied) | |
| | |
66
94. In the context of independence and impartiality of the arbitrator more
particularly keeping in mind the amended Section 12 of the Act 1996, we must
refer to and rely upon the observations made by this Court in paras 20 to 25 of
the decision in the case of Voestalpine Schienen (supra):
| “20. Independence and impartiality of the arbitrator are the<br>hallmarks of any arbitration proceedings. Rule against bias is<br>one of the fundamental principles of natural justice which<br>applied to all judicial and quasi-judicial proceedings. It is for<br>this reason that notwithstanding the fact that relationship<br>between the parties to the arbitration and the arbitrators<br>themselves are contractual in nature and the source of an<br>arbitrator's appointment is deduced from the agreement entered<br>into between the parties, notwithstanding the same non-<br>independence and non-impartiality of such arbitrator (though<br>contractually agreed upon) would render him ineligible to<br>conduct the arbitration. The genesis behind this rational is that<br>even when an arbitrator is appointed in terms of contract and<br>by the parties to the contract, he is independent of the parties.<br>Functions and duties require him to rise above the partisan<br>interest of the parties and not to act in, or so as to further, the<br>particular interest of either parties. After all, the arbitrator has<br>adjudicatory role to perform and, therefore, he must be<br>independent of parties as well as impartial. The United<br>Kingdom Supreme Court has beautifully highlighted this aspect<br>in Hashwani v. Jivraj [(2011) 1 WLR 1872 : 2011 UKSC 40] in<br>the following words: (WLR p. 1889, para 45)<br>“45. … the dominant purpose of appointing an arbitrator<br>or arbitrators is the impartial resolution of the dispute<br>between the parties in accordance with the terms of the<br>agreement and, although the contract between the parties<br>and the arbitrators would be a contract for the provision<br>of personal services, they were not personal services under<br>the direction of the parties.”<br>21. Similarly, Cour de Cassation, France, in a judgment<br>delivered in 1972 in Consorts Ury [Fouchard, Gaillard,<br>Goldman on International Commercial Arbitration 562<br>(Emmanuel Gaillard & John Savage eds., 1999) {quoting Cour | “20. Independence and impartiality of the arbitrator are the | | |
|---|
| hallmarks of any arbitration proceedings. Rule against bias is | | |
| one of the fundamental principles of natural justice which | | |
| applied to all judicial and quasi-judicial proceedings. It is for | | |
| this reason that notwithstanding the fact that relationship | | |
| between the parties to the arbitration and the arbitrators | | |
| themselves are contractual in nature and the source of an | | |
| arbitrator's appointment is deduced from the agreement entered | | |
| into between the parties, notwithstanding the same non- | | |
| independence and non-impartiality of such arbitrator (though | | |
| contractually agreed upon) would render him ineligible to | | |
| conduct the arbitration. The genesis behind this rational is that | | |
| even when an arbitrator is appointed in terms of contract and | | |
| by the parties to the contract, he is independent of the parties. | | |
| Functions and duties require him to rise above the partisan | | |
| interest of the parties and not to act in, or so as to further, the | | |
| particular interest of either parties. After all, the arbitrator has | | |
| adjudicatory role to perform and, therefore, he must be | | |
| independent of parties as well as impartial. The United | | |
| Kingdom Supreme Court has beautifully highlighted this aspect | | |
| in Hashwani v. Jivraj [(2011) 1 WLR 1872 : 2011 UKSC 40] in | | |
| the following words: (WLR p. 1889, para 45) | | |
| | “45. … the dominant purpose of appointing an arbitrator | |
| | or arbitrators is the impartial resolution of the dispute | |
| | between the parties in accordance with the terms of the | |
| | agreement and, although the contract between the parties | |
| | and the arbitrators would be a contract for the provision | |
| | of personal services, they were not personal services under | |
| | the direction of the parties.” | |
| | | |
| 21. Similarly, Cour de Cassation, France, in a judgment | | |
| delivered in 1972 in Consorts Ury [Fouchard, Gaillard, | | |
| Goldman on International Commercial Arbitration 562 | | |
| (Emmanuel Gaillard & John Savage eds., 1999) {quoting Cour | | |
67
| de cassation [Cass.] [Supreme Court for judicial | | |
|---|
| matters] Consorts Ury v. S.A. des Galeries Lafayette, Cass. 2e | | |
| civ., 13-4-1972, JCP, Pt. II, No. 17189 (1972) (France)}.] , | | |
| underlined that: | | |
| “an independent mind is indispensable in the exercise of | | |
| judicial power, whatever the source of that power may be, and | | |
| it is one of the essential qualities of an arbitrator.” | | |
| | |
| 22. Independence and impartiality are two different concepts. | | |
| An arbitrator may be independent and yet, lack impartiality, or | | |
| vice versa. Impartiality, as is well accepted, is a more subjective | | |
| concept as compared to independence. Independence, which is | | |
| more an objective concept, may, thus, be more | | |
| straightforwardly ascertained by the parties at the outset of the | | |
| arbitration proceedings in light of the circumstances disclosed | | |
| by the arbitrator, while partiality will more likely surface | | |
| during the arbitration proceedings. | | |
| | |
| 23. It also cannot be denied that the Seventh Schedule is based | | |
| on IBA guidelines which are clearly regarded as a | | |
| representation of international based practices and are based | | |
| on statutes, case law and juristic opinion from a cross-section | | |
| on jurisdiction. It is so mentioned in the guidelines itself. | | |
| | |
| 24. Keeping in view the aforesaid parameters, we advert to the | | |
| facts of this case. Various contingencies mentioned in the | | |
| Seventh Schedule render a person ineligible to act as an | | |
| arbitrator. Entry 1 is highlighted by the learned counsel for the | | |
| petitioner which provides that where the arbitrator is an | | |
| employee, consultant, advisor or has any other past or present | | |
| business relationship with the party, would not act as an | | |
| arbitrator. What was argued by the learned Senior Counsel for | | |
| the petitioner was that the panel of arbitrators drawn by the | | |
| respondent consists of those persons who are government | | |
| employees or ex-government employees. However, that by itself | | |
| may not make such persons ineligible as the panel indicates that | | |
| these are the persons who have worked in the Railways under | | |
| the Central Government or the Central Public Works | | |
| Department or public sector undertakings. They cannot be | | |
| treated as employee or consultant or advisor of the respondent | | |
| DMRC. If this contention of the petitioner is accepted, then no | | |
| person who had earlier worked in any capacity with the Central | | |
| Government or other autonomous or public sector | | |
68
| undertakings, would be eligible to act as an arbitrator even | | |
|---|
| when he is not even remotely connected with the party in | | |
| question, like DMRC in this case. The amended provision puts | | |
| an embargo on a person to act as an arbitrator, who is the | | |
| employee of the party to the dispute. It also deprives a person | | |
| to act as an arbitrator if he had been the consultant or the | | |
| advisor or had any past or present business relationship with | | |
| DMRC. No such case is made out by the petitioner. | | |
| | | |
| 25. Section 12 has been amended with the objective to induce | | |
| neutrality of arbitrators viz. their independence and | | |
| impartiality. The amended provision is enacted to identify the | | |
| “circumstances” which give rise to “justifiable doubts” about | | |
| the independence or impartiality of the arbitrator. If any of | | |
| those circumstances as mentioned therein exists, it will give rise | | |
| to justifiable apprehension of bias. The Fifth Schedule to the Act | | |
| enumerates the grounds which may give rise to justifiable | | |
| doubts of this nature. Likewise, the Seventh Schedule mentions | | |
| those circumstances which would attract the provisions of sub- | | |
| section (5) of Section 12 and nullify any prior agreement to the | | |
| contrary. In the context of this case, it is relevant to mention that | | |
| only if an arbitrator is an employee, a consultant, an advisor or | | |
| has any past or present business relationship with a party, he is | | |
| rendered ineligible to act as an arbitrator. Likewise, that person | | |
| is treated as incompetent to perform the role of arbitrator, who | | |
| is a manager, director or part of the management or has a single | | |
| controlling influence in an affiliate of one of the parties if the | | |
| affiliate is directly involved in the matters in dispute in the | | |
| arbitration. Likewise, persons who regularly advised the | | |
| appointing party or affiliate of the appointing party are | | |
| incapacitated. A comprehensive list is enumerated in Schedule | | |
| 5 and Schedule 7 and admittedly the persons empanelled by the | | |
| respondent are not covered by any of the items in the said list.” | | |
| (Emphasis supplied) | | | |
FEW FOREIGN COURT JUDGMENTS ON THE SUBJECT
95. We also looked into a very lucid and erudite judgement on the issue of
unconscionable pre-condition in the arbitration agreement delivered by a 9 Judge
69
Bench of the Supreme Court of Canada in the case of Uber Technologies v.
Heller (supra).
96. In the aforesaid case, Mr. Heller (driver) was required to accept the terms
of Uber’s standard form service agreement, which stipulated that to resolve any
dispute through arbitration or mediation with Uber, the claimant would have to
pay an up-front administrative and filing fee of USD 14,500.
97. The Supreme Court of Canada held the aforesaid pre-condition to be
unconscionable and unenforceable by a majority of 8:1. The majority speaking
through Abella and Rowe JJ., while explaining the doctrine of unconscionability
held as under:
| “ | 53. We agree with Mr. Heller that the arbitration agreement is | |
|---|
| unconscionable. The parties and interveners focused their | | |
| submissions on unconscionability in accordance with this Court's | | |
| direction in TELUS Communications Inc. v. Wellman, [2019] 2 | | |
| SCR 144, at para. 85, that “arguments over any potential | | |
| unfairness resulting from the enforcement of arbitration clauses | | |
| contained in standard form contracts are better dealt with | | |
| directly through the doctrine of unconscionability”. | | |
70
| accomplishments of modern contract law, representing a | |
|---|
| renaissance in the doctrinal treatment of contractual fairness” | |
| (Peter Benson, Justice in Transactions : A Theory of Contract | |
| Law (2019), at p. 165; see also Angela Swan, Jakub Adamski and | |
| Annie Y. Na, Canadian Contract Law (4th ed. 2018), at p. 925). | |
| |
| 55. Unconscionability is widely accepted in Canadian contract | |
| law, but some questions remain about the content of the | |
| doctrine, and it has been applied inconsistently by the lower | |
| courts (see, among others, Morrison v. Coast Finance Ltd., | |
| (1965) 55 DLR 710 (2d) (B.C.C.A.); Harry v. Kreutziger, | |
| (1978) 9 B.C.L.R. 166 (C.A.), at p. 177, per Lambert | |
| J.A.; Downer v. Pitcher, 2017 NLCA 13 : 409 DLR 542 (4th), | |
| at para. 20; Input Capital Corp. v. Gustafson, 2019 SKCA 78 : | |
| 438 DLR 387 (4th); Cain v. Clarica Life Insurance Co., 2005 | |
| ABCA 437 : 263 DLR 368 (4th); Titus v. William F. Cooke | |
| Enterprises Inc., 2007 ONCA 573 : 284 DLR 734 | |
| (4th); Birch v. Union of Taxation Employees, Local 70030, | |
| 2008 ONCA 809 : 305 DLR 64 (4th); see also Swan, Adamski | |
| and Na, at p. 982; McInnes, at pp. 518-19). These questions | |
| require examining underlying contractual theory (Rick | |
| Bigwood, “Antipodean Reflections on the Canadian | |
| Unconscionability Doctrine” (2005) 84 Can. Bar Rev. 171, at | |
| p. 173). | |
| |
| 56. The classic paradigm underlying freedom of contract is the | |
| “freely negotiated bargain or exchange” between “autonomous | |
| and self-interested parties” (McCamus, at p. 24; see also Swan, | |
| Adamski and Na, at pp. 922-23; P.S. Atiyah, Essays on | |
| Contract (1986), at p. 140). At the heart of this theory is the | |
| belief that contracting parties are best-placed to judge and | |
| protect their interests in the bargaining process (Atiyah, at pp. | |
| 146-48; Bigwood, at pp. 199-200; Alan Brudner, | |
| “Reconstructing contracts” (1993) 43 U.T.L.J. 1, at pp. 2-3). It | |
| also presumes equality between the contracting parties and that | |
| “the contract is negotiated, freely agreed, and therefore fair” | |
| (Mindy Chen-Wishart, Contract Law (6th ed. 2018), at p. 12) | |
| (emphasis in original). | |
| |
| 57. In cases where these assumptions align with reality, the | |
| arguments for enforcing contracts carry their greatest weight | |
| (Melvin Aron Eisenberg, “The Bargain Principle and Its | |
| Limits” (1982) 95 Harv. L. Rev. 741, at pp. 746-48). But these | |
71
arguments “may speak more or less forcefully depending on the
context” (Wellman, at para. 53; see also B.J. Reiter,
“Unconscionability : Is There a Choice? A Reply to Professor
Hasson” (1980) 4 Can. Bus. L.J. 403, at pp. 405-6). As
Professor Atiyah has noted:
The proposition that a person is always the best judge of his
own interests is a good starting-point for laws and institutional
arrangements, but as an infallible empirical proposition it is an
outrage to human experience. The parallel moral argument,
that to prevent a person, even in his own interests, from binding
himself is to show disrespect for his moral autonomy, can ring
very hollow when used to defend a grossly unfair contract
secured at the expense of a person of little understanding or
bargaining skill.
[Emphasis added; p. 148]
58. Courts have never been required to take the ideal
assumptions of contract theory as “infallible empirical
proposition[s]”. Equitable doctrines have long allowed judges
to “respond to the individual requirements of particular
circumstances …. humaniz[ing] and contextualiz[ing] the law's
otherwise antiseptic nature” (Leonard I. Rotman, “The
‘Fusion’ of Law and Equity? : A Canadian Perspective on the
Substantive, Jurisdictional, or Non-Fusion of Legal and
Equitable Matters” (2016) 2 C.J.C.C.L. 497, at pp. 503-4).
Courts, as a result, do not ignore serious flaws in the
contracting process that challenge the traditional paradigms of
the common law of contract, such as faith in the capacity of the
contracting parties to protect their own interests. The elderly
person with cognitive impairment who sells assets for a fraction
of their value (Ayres v. Hazelgrove, Q.B. England, February 9,
1984); the ship captain stranded at sea who pays an
extortionate price for rescue (The Mark Lane, [L.R.] 15 P.D.
135); the vulnerable couple who signs an improvident mortgage
with no understanding of its terms or financial implications
(Commercial Bank of Australia Ltd. v. Amadio, [1983] HCA 14
: 151 CLR 447) — these and similar scenarios bear little
resemblance to the operative assumptions on which the classic
contract model is constructed.
59. In these kinds of circumstances, where the traditional
assumptions underlying contract enforcement lose their
72
justificatory authority, the doctrine of unconscionability
provides relief from improvident contracts. When unfair
bargains cannot be linked to fair bargaining — when they
cannot be attributed to one party's “donative intent or assumed
risk”, as Professor Benson puts it — courts can avoid the
inequitable effects of enforcement without endangering the core
values on which freedom of contract is based (p. 182; see also
Eisenberg, at pp. 799-801; S.M. Waddams, “Good Faith,
Unconscionability and Reasonable Expectations” (1995) 9
J.C.L. 55, at p. 60). This explains how unconscionability lines
up with traditional accounts of contract theory while
recognizing the doctrine's historical roots in equity, which has
long operated as a “corrective to the harshness of the common
law” (McCamus, at p. 10; see also Rotman, at pp. 503-4).
60. This Court has often described the purpose of
unconscionability as the protection of vulnerable persons in
transactions with others (Hodgkinson v. Simms, [1994] 3 SCR
377, at pp. 405 and 412; Hunter Engineering Co. v. Syncrude
Canada Ltd., [1989] 1 SCR 426, at p. 462, per Dickson C.J.,
and p. 516, per Wilson J.; Norberg v. Wynrib, [1992] 2 SCR
226, at p. 247; see also Bhasin v. Hrynew, [2014] 3 SCR 494,
at para. 43). We agree. Unconscionability, in our view, is meant
to protect those who are vulnerable in the contracting
process from loss or improvidence to that party in the bargain
that was made (see Mindy Chen-Wishart, Unconscionable
Bargains (1989), at p. 109; see also James Gordley, “Equality
in Exchange” (1981) 69 Cal. L. Rev. 1587, at pp. 1629-
34; Birch, at para. 44). Although other doctrines can provide
relief from specific types of oppressive contractual terms,
unconscionability allows courts to fill in gaps between the
existing “islands of intervention” so that the “clause that is not
quite a penalty clause or not quite an exemption clause or just
outside the provisions of a statutory power to relieve will fall
under the general power, and anomalous distinctions … will
disappear” (S.M. Waddams, The Law of Contracts (7th ed.
2017), at p. 378).
Xxx xxx xxx
70. The classic example of a “necessity” case is a rescue at sea
scenario (see The Medina, [L.R.] 1 P.D. 272). The
circumstances under which such agreements are made indicate
73
| |
|---|
| 84. Unconscionability, moreover, can be established without | |
| proof that the stronger party knowingly took advantage of the | |
| weaker. Such a requirement is closely associated with theories | |
| of unconscionability that focus on wrongdoing by the defendant | |
| (see Boustany, at p. 6). But unconscionability can be triggered | |
| without wrongdoing. As Professor Waddams compellingly | |
| argues: | |
| |
| The phrases ‘unconscionable conduct’, ‘unconscionable |
| behaviour’ and ‘unconscionable dealing’ lack clarity, are |
| unhistorical insofar as they imply the need for proof of |
| wrongdoing, and have been unduly restrictive. |
74
(Waddams (2019), at pp. 118-19; see also Benson, at p. 188;
Smith, at pp. 360-62.)
85. We agree. One party knowingly or deliberately taking
advantage of another's vulnerability may provide strong
evidence of inequality of bargaining power, but it is not
essential for a finding of unconscionability. Such a requirement
improperly emphasizes the state of mind of the stronger party,
rather than the protection of the more vulnerable. This Court's
decisions leave no doubt that unconscionability focuses on the
latter purpose. Parties cannot expect courts to enforce
improvident bargains formed in situations of inequality of
bargaining power; a weaker party, after all, is as disadvantaged
by inadvertent exploitation as by deliberate exploitation. A rigid
requirement based on the stronger party's state of mind would
also erode the modern relevance of the unconscionability
doctrine, effectively shielding from its reach improvident
contracts of adhesion where the parties did not interact or
negotiate.
86. In our view, the requirements of inequality and
improvidence, properly applied, strike the proper balance
between fairness and commercial certainty. Freedom of
contract remains the general rule. It is precisely because the
law's ordinary assumptions about the bargaining process do not
apply that relief against an improvident bargain is justified.
87. Respecting the doctrine of unconscionability has
implications for boiler plate or standard form contracts. As
Karl N. Llewellyn, the primary drafter of the Uniform
Commercial Code, explained:
Instead of thinking about “assent” to boiler-plate clauses, we
can recognize that so far as concerns the specific, there is no
assent at all. What has in fact been assented to, specifically, are
the few dickered terms, and the broad type of the transaction,
and but one thing more. That one thing more is a blanket assent
(not a specific assent) to any not unreasonable or indecent
terms the seller may have on his form, which do not alter or
eviscerate the reasonable meaning of the dickered terms. The
fine print which has not been read has no business to cut under
the reasonable meaning of those dickered terms which
75
constitute the dominant and only real expression of agreement,
but much of it commonly belongs in.
There has been an arm's-length deal, with dickered terms. There
has been accompanying that basic deal another which … at
least involves a plain expression of confidence, asked and
accepted, with a corresponding limit on the powers granted :
the boiler-plate is assented to en bloc, “unsight, unseen,” on the
implicit assumption and to the full extent that (1) it does not
alter or impair the fair meaning of the dickered terms when read
alone, and (2) that its terms are neither in the particular nor in
the net manifestly unreasonable and unfair.
(The Common Law Tradition : Deciding Appeals (1960), pp.
370-71)
88. We do not mean to suggest that a standard form contract,
by itself, establishes an inequality of bargaining power
(Waddams (2017), at p. 240). Standard form contracts are in
many instances both necessary and useful. Sophisticated
commercial parties, for example, may be familiar with contracts
of adhesion commonly used within an industry. Sufficient
explanations or advice may offset uncertainty about the terms
of a standard form agreement. Some standard form contracts
may clearly and effectively communicate the meaning of clauses
with unusual or onerous effects (Benson, at p. 234).
89. Our point is simply that unconscionability has a meaningful
role to play in examining the conditions behind consent to
contracts of adhesion, as it does with any contract. The many
ways in which standard form contracts can impair a party's
ability to protect their interests in the contracting process and
make them more vulnerable, are well-documented. For
example, they are drafted by one party without input from the
other and they may contain provisions that are difficult to read
or understand (see Margaret Jane Radin, “Access to Justice
and Abuses of Contract” (2016) 33 Windsor Y.B. Access Just.
177, at p. 179; Stephen Waddams, “Review Essay : The
Problem of Standard Form Contracts : A Retreat to
Formalism” (2013) 53 Can. Bus. L.J. 475, at pp. 475-476; Thal,
at pp. 27-28; William J. Woodward, Jr., “Finding the Contract
in Contracts for Law, Forum and Arbitration” (2006) 2
Hastings Bus. L.J. 1, at p. 46). The potential for such contracts
76
to create an inequality of bargaining power is clear. So too is
their potential to enhance the advantage of the stronger party
at the expense of the more vulnerable one, particularly through
choice of law, forum selection, and arbitration clauses that
violate the adhering party's reasonable expectations by
depriving them of remedies. This is precisely the kind of
situation in which the unconscionability doctrine is meant to
apply.
90. This development of the law of unconscionability in
connection with standard form contracts is not radical. On the
contrary, it is a modern application of the doctrine to situations
where “the normative rationale for contract enforcement … [is]
stretched beyond the breaking point” (Radin, at p. 179). The
link between standard form contracts and unconscionability has
been suggested in judicial decisions, textbooks, and academic
articles for years (see, e.g., Douez, at para.
114; Davidson v. Three Spruces Realty Ltd., (1977) 79 DLR
481 (3d) (B.C.S.C.); Hunter, at p. 513; Swan, Adamski and Na,
at pp. 992-93; McCamus, at p. 444; Jean Braucher,
“Unconscionability in the Age of Sophisticated Mass-Market
Framing Strategies and the Modern Administrative State”
(2007) 45 Can. Bus. L.J. 382, at p. 396). It has also been present
in the American jurisprudence for more than half a century
(see Williams v. Walker-Thomas Furniture Company, 350 F.2d
445 (1965), at pp. 449-50).
91. Applying the unconscionability doctrine to standard form
contracts also encourages those drafting such contracts to make
them more accessible to the other party or to ensure that they
are not so lop-sided as to be improvident, or both. The virtues
of fair dealing were explained by Jean Braucher as follows:
Businesses are driven to behave competitively in their framing
of market situations or otherwise they lose to those who do. Only
if there are meaningful checks on what might be considered
immoral behavior will persons in business have the freedom to
act on their moral impulses. An implication of this point is that,
absent regulation, business culture will become ever more
ruthless, so that the distinctions between “reputable
businesses” and fringe marketers gradually wither away…. [p.
390]
77
92. This brings us to the appeal before us and whether Mr.
Heller's arbitration clause with Uber is unconscionable.
93. There was clearly inequality of bargaining power between
Uber and Mr. Heller. The arbitration agreement was part of a
standard form contract. Mr. Heller was powerless to negotiate
any of its terms. His only contractual option was to accept or
reject it. There was a significant gulf in sophistication between
Mr. Heller, a food deliveryman in Toronto, and Uber, a large
multinational corporation. The arbitration agreement,
moreover, contains no information about the costs of mediation
and arbitration in the Netherlands. A person in Mr. Heller's
position could not be expected to appreciate the financial and
legal implications of agreeing to arbitrate under ICC Rules or
under Dutch law. Even assuming that Mr. Heller was the rare
fellow who would have read through the contract in its entirety
before signing it, he would have had no reason to suspect that
behind an innocuous reference to mandatory mediation “under
the International Chamber of Commerce Mediation Rules” that
could be followed by “arbitration under the Rules of Arbitration
of the International Chamber of Commerce”, there lay a
US$14,500 hurdle to relief. Exacerbating this situation is that
these Rules were not attached to the contract, and so Mr. Heller
would have had to search them out himself.
94. The improvidence of the arbitration clause is also clear. The
mediation and arbitration processes require US$14,500 in up-
front administrative fees. This amount is close to Mr. Heller's
annual income and does not include the potential costs of travel,
accommodation, legal representation or lost wages. The costs
are disproportionate to the size of an arbitration award that
could reasonably have been foreseen when the contract was
entered into. The arbitration agreement also designates the law
of the Netherlands as the governing law and Amsterdam as the
“place” of the arbitration. This gives Mr. Heller and other Uber
drivers in Ontario the clear impression that they have little
choice but to travel at their own expense to the Netherlands to
individually pursue claims against Uber through mandatory
mediation and arbitration in Uber's home jurisdiction. Any
representations to the arbitrator, including about the location
of the hearing, can only be made after the fees have been paid.
78
95. The arbitration clause, in effect, modifies every other
substantive right in the contract such that all rights that Mr.
Heller enjoys are subject to the apparent precondition that he
7
travel to Amsterdam, initiate an arbitration by paying the
required fees and receive an arbitral award that establishes a
violation of this right. It is only once these preconditions are
met that Mr. Heller can get a court order to enforce his
substantive rights under the contract. Effectively, the
arbitration clause makes the substantive rights given by the
contract unenforceable by a driver against Uber. No reasonable
person who had understood and appreciated the implications of
the arbitration clause would have agreed to it.
96. We add that the unconscionability of the arbitration clause
can be considered separately from that of the contract as a
whole. As explained in Bremer Vulkan Schiffbau und
Maschinenfabrik v. South India Shipping Corporation
Ltd., [1981] A.C. 909 (H.L.), an arbitration agreement
“constitutes a self-contained contract collateral or ancillary to
the [main] agreement” (p. 980; see also p. 998, per Lord
Scarman). Further support comes from the severability clause
of the Uber Rasier and Uber Portier agreements, and s. 17(2)
of the AA.”
(Emphasis supplied)
98. Brown J. in his separate but concurring opinion held that such a pre-
condition as mentioned in the agreement was opposed to public policy as it
impeded the claimant from resolving his dispute effectively. The relevant
observations are as under:
“ 110. The ground upon which I proceed is that which precludes
an ouster of court jurisdiction or, more broadly, which protects
the integrity of the justice system. As Lord Atkin stated
in Fender v. St. John-Mildmay, [1938] A.C. 1 (H.L.), at p. 12,
ousting the jurisdiction of the courts is harmful in itself and
“injurious to public interests” (see also Kain and Yoshida, at pp.
20-23). A provision that penalizes or prohibits one party from
enforcing the terms of their agreement directly undermines the
administration of justice. There is nothing novel about the
proposition that contracting parties, as a matter of public policy,
79
cannot oust the court's supervisory jurisdiction to resolve
contractual disputes (see e.g. Kill v. Hollister, (1746) 1 Wils.
K.B. 129 : 95 E.R. 532; Scott v. Avery, (1856) 5 H.L.C. 811 : 10
E.R. 1121; Deuterium of Canada Ltd. v. Burns & Roe
Inc., [1975] 2 SCR 124). Indeed, irrespective of the value placed
on freedom of contract, courts have consistently held that a
contracting party's right to legal recourse is “a right inalienable
even by the concurrent will of the parties” (Scott, at p. 1133).
111. This head of public policy serves to uphold the rule of law,
which, at a minimum, guarantees Canadian citizens and
residents “a stable, predictable and ordered society in which to
conduct their affairs” (Reference re Secession of Quebec, [1998]
2 SCR 217, at para. 70). Such a guarantee is meaningless without
access to an independent judiciary that can vindicate legal
rights. The rule of law, accordingly, requires that citizens have
access to a venue where they can hold one another to account
(Jonsson v. Lymer, 2020 ABCA 167, at para. 10 (CanLII)).
Indeed, “[t]here cannot be a rule of law without access,
otherwise the rule of law is replaced by a rule of men and women
who decide who shall and who shall not have access to justice”
(B.C.G.E.U. v. British Columbia (Attorney General), [1988] 2
SCR 214, at p. 230). Unless private parties can enforce their
legal rights and publicly adjudicate their disputes, “the rule of
law is threatened and the development of the common law
undermined” (Hryniak v. Mauldin, 2014 SCC 7 : [2014] 1 SCR
87, at para. 26). Access to civil justice is paramount to the public
legitimacy of the law and the legitimacy of the judiciary as the
institution of the state that expounds and applies the law.
112. Access to civil justice is a precondition not only to a
functioning democracy but also to a vibrant economy, in part
because access to justice allows contracting parties to enforce
their agreements. A contract that denies one party the right to
enforce its terms undermines both the rule of law and commercial
certainty. That such an agreement is contrary to public policy is
not a manifestation of judicial idiosyncrasies, but rather an
instance of the self-evident proposition that there is no value in a
contract that cannot be enforced. Thus, the harm to the public
that would result from holding contracting parties to a bargain
they cannot enforce is “substantially incontestable” (Millar
Estate, at p. 7, quoting Fender, at p. 12). It really is this simple :
unless everyone has reasonable access to the law and its
80
| processes where necessary to vindicate legal rights, we will live | |
|---|
| in a society where the strong and well-resourced will always | |
| prevail over the weak. Or, as Frederick Wilmot-Smith puts it, | |
| “[l]egal structures that make enforcement of the law practically | |
| impossible will leave weaker members of society open to | |
| exploitation at the hands of, for example, unscrupulous | |
| employers or spouses.” (Equal Justice : Fair Legal Systems in an | |
| Unfair World (2019), at pp. 1-2). | |
| |
| 113. The reference to making enforcement of the | |
| law practically impossible leads to a further, related point : there | |
| is no good reason to distinguish between a clause | |
| that expressly blocks access to a legally determined resolution | |
| and one that has the ultimate effect of doing so. That this is so is | |
| illustrated by the judgment of Drummond J. in Novamaze Pty | |
| Ltd. v. Cut Price Deli Pty Ltd., (1995) 128 ALR 540 (F.C.A.). | |
| In Novamaze, the terms of a franchise agreement permitted the | |
| franchisor to take control of the franchisee's business if either | |
| party threatened to commence, or commenced, legal proceedings | |
| against the other. This clause, Drummond J. explained, was | |
| “capable of operating as a powerful disincentive to the | |
| franchisee to take proceedings of any kind against [the | |
| franchisor], no matter how strong a case the franchisee may have | |
| that it has suffered wrong” (p. 548). Summarizing the relevant | |
| principle, Drummond J. continued: | |
| |
| … the citizen is entitled to have recourse to the court for an |
| adjudication on his legal rights. A contractual agreement to |
| deny a person that “inalienable right” contravenes this |
| public policy and is void. A disincentive to a person to |
| exercise this right of recourse to the court can, depending |
| upon how powerfully it operates to discourage litigation, |
| amount to a denial of this right just as complete as an |
| express contractual prohibition against litigation. [pp. 548- |
| 49] |
| |
81
| First, the purpose of arbitration is to ensure that contracting | |
|---|
| parties have access to “a ‘good and accessible method of seeking | |
| resolution for many kinds of disputes’ that ‘can be more | |
| expedient and less costly than going to court’” (Wellman, at | |
| para. 83, quoting Legislative Assembly of Ontario, March 27, | |
| 1991, at p. 245). Second, courts have accepted arbitration as an | |
| acceptable alternative to civil litigation because it can provide a | |
| resolution according to law. As this Court observed in Sport | |
| Maska Inc. v. Zittrer, [1988] 1 SCR 564, at p. 581: | |
| |
| The legislator left … various procedures for settling |
| disputes to be resolved freely by litigants when recourse to |
| the courts was still possible. If judicial intervention was |
| ruled out, however, the legislator had to ensure that the |
| process would guarantee litigants the same measure of |
| justice as that provided by the courts, and for this reason, |
| rules of procedure were developed to ensure that the |
| arbitrator is impartial and that the rules of fundamental |
| justice … are observed. The arbitrator will make an award |
| which becomes executory by homologation. This indicates |
| the similarity between the arbitrator's real function and that |
| of a judge who has to decide a case. |
| [Emphasis added.] | |
| |
| In other words, any means of dispute resolution that serves as a | |
| final resort for contracting parties must be just. This is important | |
| because, unlike the submission of existing disputes to arbitration, | |
| and contrary to my colleague Côté J.'s assertion, an agreement | |
| to submit all future unknown disputes to arbitration is not simply | |
| a substitute for the parties' negotiations (para. 250). Rather, it | |
| serves as a transfer of dispute resolution authority away from | |
| public adjudicators (W.G. Horton, “A Brief History of | |
| Arbitration” (2017) 47 Adv. Q. 12, at p. 14; Sport Maska, at p. | |
| 581; Wellman, at para. 48; Desputeaux, [2003] 1 SCR 178, at | |
| para. 40). The legitimacy of such a transfer rests upon whether it | |
| can provide a comparable measure of justice. | |
| |
82
intervention in arbitration proceedings (paras. 307, 312 and
316). Common law courts have long recognized the right to
resolve disputes according to law. The law has simply evolved to
embrace arbitration as means of achieving that resolution.
Contractual stipulations that prohibit such resolution altogether,
whether by express prohibition or simply by effect, continue to be
unenforceable as a matter of public policy.”
(Emphasis supplied)
99. The Majority ultimately concluded observing the following in paragraphs
97 and 98 respectively of the judgement as under:
“ 97. Respect for arbitration is based on it being a cost-effective
and efficient method of resolving disputes. When arbitration is
realistically unattainable, it amounts to no dispute resolution
mechanism at all. As our colleague Justice Brown notes, under
the arbitration clause, “Mr. Heller, and only Mr. Heller, would
experience undue hardship in attempting to advance a claim
against Uber, regardless of the claim's legal merit” (para. 136).
The arbitration clause is the only way Mr. Heller can vindicate
his rights under the contract, but arbitration is out of reach for
him and other drivers in his position. His contractual rights are,
as a result, illusory.
98. Based on both the disadvantages faced by Mr. Heller in his
ability to protect his bargaining interests and on the unfair terms
that resulted, the arbitration clause is unconscionable and
therefore invalid.”
(Emphasis supplied)
100. The courts in the United States of America have also deliberated upon the
doctrine of unconscionability on numerous occasions. The Court of Appeal of
California in the case of Patterson v. ITT Consumer Financial Corporation
reported in 18 Cal. Rptr. 2d 563 (Cal. Ct. App. 1993), had the occasion to
consider whether the requirement for the claimants to pay a filing fee along with
hearing fees for the purpose of resolving the matter could be said to be
83
unconscionable. The Court of Appeals held that such a condition was
“incomprehensible” and discouraged the borrowers from pursuing their claims.
The relevant observations are as under:
“B. Unconscionability
2. Two alternative analyses exist under California law for
determining whether a contractual provision will be
unenforceable because it is unconscionable. (Perdue v. Crocker
National Bank (1985) 38 Cal.3d 913, 925, fn. [216 Cal. Rptr.
345, 702 P.2d 503] ["Both analytical pathways should lead to
the same result."].) The first model set out in Graham v. Scissor-
Tail, Inc. (1981) 28 Cal.3d 807 [171 Cal.Rptr. 604, 623 P.2d
165] asks initially whether the contract is one of adhesion. (Id.
at p. 819.) Since a contract of adhesion is still fully enforceable,
the inquiry then turns to whether enforcement should be denied.
First, enforcement will be denied if the contract or provision falls
outside the reasonable expectations of the weaker party. (Id. at
p. 820.) Second, enforcement will be denied even if it does fall
within the reasonable expectations of the parties, but it is unduly
oppressive or unconscionable. (Ibid.)
The alternative analytical model was set out in A M Produce Co.
v. FMC Corp., supra, 135 Cal.App.3d 473. It sought to define
what rendered a contract or a contractual provision
unconscionable and hence unenforceable under Civil Code
section 1670.5 (135 Cal.App.3d at p. 485.) A M concluded that
unconscionability has a procedural and a substantive
component. (Id. at p. 486.) The procedural component focuses on
the factors of oppression and surprise. (Ibid.) Oppression results
where there is no real negotiation of contract terms because of
unequal bargaining power. (Ibid.) "`Surprise' involves the extent
to which the supposedly agreed-upon terms of the bargain are
hidden in a prolix printed form drafted by the party seeking to
enforce the disputed terms." (Ibid.) The substantive component
of unconscionability looks to whether the contract allocates the
risks of the bargain in an objectively unreasonable or unexpected
manner. (Id. at p. 487.) To be unenforceable there must be both
substantive and procedural unconscionability, though there may
be an inverse relation between the two elements. (Ibid.)
84
3. A contract of adhesion is "a standardized contract, which,
imposed and drafted by the party of superior bargaining
strength, relegates to the subscribing party only the opportunity
to adhere to the contract or reject it." (Neal v. State Farm Ins.
Cos. (1961) 188 Cal.App.2d 690, 694 [10 Cal.Rptr. 781].)
4. The record before us indicates that plaintiffs are individuals of
modest means, some self-employed or temporarily jobless, who
borrowed relatively small amounts of money, often in response
to advertising promising "guaranteed loans." The loan
agreement which they signed included a preprinted form
containing an arbitration clause either as the final paragraph on
a page entitled "Agreement for Dispute Resolution" or at
midpage on a sheet of text, but set apart by the use of boldface
type. On both versions of the form the provision was clearly titled
"Arbitration." None of the preprinted clauses had been modified
in any manner, which suggests that they were nonnegotiable.
Several of the borrowers stated that they believed they would not
have been able to obtain a bank loan. In these circumstances we
think it indisputable that the contract was one of adhesion.
ITT argues that arbitration has become such a common means of
dispute resolution that it must be considered within the
reasonable expectation of the borrowers. While arbitration per
se may be within the reasonable expectation of most consumers,
it is much more difficult to believe that arbitration in Minnesota
would be within the reasonable expectation of California
consumers. The arbitration clause says only that the dispute will
be "resolved by binding arbitration by the National Arbitration
Forum, Minneapolis, Minnesota.”
xxx xxx xxx
In order to obtain a participatory hearing, however, the
responding party must make a prompt demand for one and
accompany it with prepayment of fees. Prepayment of hearing
fees can be waived for individuals, but only after filing an
affidavit of indigency. However, the rule explaining the fee
waiver process is, as the trial court aptly noted,
"incomprehensible," since it requires compliance with rules
concerning involuntary dismissals.
85
The likely effect of these procedures is to deny a borrower against
whom a claim has been brought any opportunity to a hearing,
much less a hearing held where the contract was signed, unless
the borrower has considerable legal expertise or the money to
hire a lawyer and/or prepay substantial hearing fees. The latter
is especially unlikely given the small dollar amounts at issue. In
a dispute over a loan of $2,000 it would scarcely make sense to
spend a minimum of $850 just to obtain a participatory hearing.
In short the procedure seems designed to discourage borrowers
from responding at all. In the event that they do not respond, an
award may be entered against them if the documents submitted
by ITT support its claim.”
(Emphasis supplied)
101. Similarly, the United States District Court, W.D. Michigan in the case of
Vegter v. Forecast Financial Corporation reported in 2007 WL 4178947, while
discussing the principle of procedural and substantive unconscionability in
arbitration agreements, held as under:
“ B. Unconscionability
Generally applicable contract defenses, such as
unconscionability, can invalidate an arbitration agreement
consistent with the FAA. Doctor's Assocs., Inc. v. Casarotto,
517 U.S. 681, 687 (1996). Whether an arbitration clause is
unconscionable is governed by state law. Stutler v. T.K.
th
Constructors, Inc., 448 F.3d 343, 345 (6 Cir. 2006). Under
Michigan law, in order to invalidate a contract provision for
unconscionability, the Court must find the provision is both
procedurally and substantively unconscionable. Pichey v.
Ameritech Interactive Media Servs., Inc., 421 F. Supp. 2d 1038,
1044-45 (W.D. Mich. 2006) (Bell, C.J.). The inquiries for
finding procedural and substantive unconscionability have been
phrased as: "(1) What is the relative bargaining power of the
parties, their relative economic strength, the alternative sources
of supply, in a word, what are their options?; (2) Is the
challenged term substantively reasonable?" Id. at 1045
(quoting Allen v. Mich. Bell. Tel. Co., 18 Mich. App. 632, 637,
171 N.W.2d 689 (1969)).
86
As to procedural unconscionability, the Court finds that this
was a contract of adhesion. The terms of the contract were not
negotiated and Plaintiff had relatively little economic strength
in the transaction.
As to substantive unconscionability, the arbitration clause is
unreasonable insofar as it requires Plaintiff to travel to
Okaloosa County, Florida for the arbitration. In many
circumstances requiring a consumer to travel a substantial
distance to arbitrate a claim has been found to be unreasonable.
DeOrnellas v. Aspen Square Mgmt., Inc., 295 F. Supp. 2d 753,
765-66 (E.D. Mich. 2003); Garrett v. Hooters-Toledo, 295 F.
Supp. 2d 774, 783 (N.D. Ohio 2003); Comb v. PayPal, Inc., 218
F. Supp. 2d 1165, 1176-77 (N.D. Cal. 2002). In determining
whether requiring the arbitration to be held in Florida is
unreasonable, the Court must ask whether the "provision would
deter a substantial number of similarly situated potential
litigants. . . ."Morrison, 317 F.3d at 663. See Stutler, 448 F.3d
at 346 (indicating that the test from Morrison is applicable "to
the question of whether an arbitration clause is enforceable
where federal statutorily provided rights are affected.").
Requiring a consumer who is experiencing financial distress to
travel to Florida would effectively deter such a consumer from
pursuing arbitration. At the time the contract was signed
Defendants knew that Plaintiff was experiencing financial
difficulty and presumably knew that it would be difficult for
Plaintiff to arbitrate in Florida. Given those circumstances, the
Court finds that requiring Plaintiff to arbitrate in Florida would
effectively bar Plaintiff from brining a claim and is
substantively unreasonable.
The Court finds that the provision in the arbitration clause that
designates Okaloosa County, Florida as the site of the
arbitration is both procedurally and substantively
unconscionable under Michigan law. Therefore, the Court
severs and declares unenforceable the provision in the
arbitration clause that designates Okaloosa, Florida as the site
of the arbitration.”
102. In view of the aforesaid discussion, we have reached to the conclusion that
we should ignore the two conditions contained in Clause 55 of the GCC, one
87
relating to 7% deposit of the total amount claimed and the second one relating to
the stipulation empowering the Principal Secretary (Irrigation) Government of
Uttarakhand to appoint a sole arbitrator and proceed to appoint an independent
arbitrator.
| 103. In the result, this application stands allowed. | |
|---|
| |
| 104. We appoint Mr. V.K. Bist, the Former Chief Justice of the High Court of | |
| |
| Sikkim to act as the sole arbitrator. The fees of the arbitrator including other | |
| |
| modalities shall be fixed in consultation with the parties. | |
| | | | | | | |
|---|
| …...……..….………….……………CJI.<br>(Dr. Dhananjaya Y. Chandrachud)<br>…….…..….…….…..…………………J.<br>(J.B. Pardiwala)<br>…………...…...……………………….J.<br>(Manoj Misra) | | | | …...……..….………….……………CJI. | | | |
| | | | (Dr. Dhananjaya Y. Chandrachud) | | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | …….…..….…….…..…………………J. | | | |
| | | | | (J.B. Pardiwala) | | |
| | | | | | | |
| | | | | | | |
| | | | | | | |
| | | | …………...…...……………………….J. | | | |
| | | | | (Manoj Misra) | | |
| New Delhi; | | | | | | | |
| November 6, 2023. | | | | | | | |
88