REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 4021 OF 2022
(ARISING OUT OF SLP(CIVIL) NO. 12277 OF 2021)
| SWAMI SAMARTH SUGARS AND<br>AGRO INDUSTRIES LTD. | .....APPELLANT(S) |
|---|
| VERSUS | |
| LOKNETE MARUTRAO GHULE PATIL<br>DNYANESHWAR SAHAKARI SAKHAR<br>KARKHANA LTD & ORS. | .....RESPONDENT(S) |
W I T H
CIVIL APPEAL NO. 4022 OF 2022
(ARISING OUT OF SLP(CIVIL) NO. 12578 OF 2021)
A N D
CIVIL APPEAL NO. 4023 OF 2022
(ARISING OUT OF SLP(CIVIL) NO. 12579 OF 2021)
J U D G M E N T
HEMANT GUPTA, J.
1. The present appeals arise out of the three writ petitions which were
decided by a common order dated 23.07.2021. Two of the writ petitions
Signature Not Verified
were filed by the respondent herein – Loknete Marutrao Ghule Patil
Digitally signed by
SWETA BALODI
Date: 2022.07.13
16:56:24 IST
Reason:
1
Dnyaneshwar Sahakari Sakhar Karkhana Ltd. , whereas the third one
1 Existing Sugar Factory
1
was filed by the members of the existing sugar factory. Since the issue
raised in all the three writ petitions was common, therefore, the same
was decided by the High Court by a common order.
2. In the writ petitions, direction was sought that the Industrial
2
Entrepreneur Memorandum dated 8.9.2010 be de-
recognised/cancelled in view of the provisions of Clause 6C of the
3
Sugarcane (Control) Order, 1966 . The challenge was inter alia on the
ground that the time limit for a new factory to be set up was 2 years
and to commence production was within 4 years (2+4), but the
appellant failed to take any effective steps to set up and commence
production within such time frame contemplated by the Control Order.
Another ground was that the State of Maharashtra had issued a circular
on 03.12.2011 under Clause 6A of the Control Order that no sugar
factory shall be set up within the radius of 25 kms of any existing sugar
factory or any other new factory substituting the provisions that the
minimum distance was for 15 kms existing on the date of grant of IEM,
therefore, the proposed sugar factory does not meet the norm of 25
kilometers. Finally, it was contended that in the absence of steps for
setting up of a sugar factory and commencement of the commercial
production, the IEM stands de-recognised by operation of the provision
of the Control Order. Therefore, the grant of extensions to set up the
sugar factory issued on 14.11.2018 followed by another extension of
2 For short, ‘IEM’
3 For short, ‘Control Order’
2
time and to change the location on 17.10.2019 by the Central
Government was contrary to the Control Order.
3. The brief facts leading to the present appeals are that the existing
sugar factory was set up in the year 1974, claiming to have more than
15000 members with crushing capacity as 1250 M.T. in the year 1974-
75 which was increased to 7000 M.T. per day in the year 2014-15. The
said sugar factory had also set up a Distillery Plant, Co-generation
Plant, Ethanol Plant and enhanced its crushing capacity of 6000 M.T.
per day after a fresh IEM was issued on 01.05.2012.
4. The appellant applied for IEM on 08.09.2010, the same was
acknowledged by Government of India after Commissioner of Sugar,
Maharashtra issued a certificate regarding aerial distance between the
existing sugar factory and the nearby proposed sugar factory in
Ramdoh (Warkhed), Tehsil- Newasa, District- Ahmednagar. It was
reported that aerial distance between the sites of other sugar factories
adjacent to the proposed sugar factory at Ramdoh (Warkhed), Tehsil-
Newasa, District- Ahmednagar was more than 15 kms. On the basis of
such certificate, IEM was acknowledged after the appellant furnished a
bank guarantee of the sum of Rs. 1 crore which was to remain in force
up to 04.04.2016.
5. However, a writ petition was filed soon thereafter on 23.09.2010,
challenging the IEM granted to the appellant on the ground of aerial
distance of proposed sugar factory and existing sugar factory. Another
3
writ petition was filed on 17.03.2011 challenging the IEM on the ground
that the proposed sugar factory was not complying with the provisions
of Environmental Protection Act, 1986. Both the writ petitions were
decided on 27.01.2014 wherein the High Court passed the following
order:
“4. Bare perusal thereof indicates that no new sugar factory shall
be set up within the radius of 15 kms of any existing sugar
factory or another new sugar factory in a State or two or more
States. The proviso has also been inserted in the Control Order
to ensure that the restriction on setting up of two sugar factories
within the radius of 15 kms is complied with.
5. The petitioners have pointed out, and in all fairness, that a
certificate has been issued by the Commissioner of Sugar,
Maharashtra State, Pune pointing out that the aerial distance
between the sites of other sugar factories, adjacent to
respondent No.8 is more than 15 kms.
6. This certificate, dated 17.08.2010, therefore, is in compliance
with the requirement in Clause 6-A reproduced above. That is the
only aspect with which this Court is concerned so far as the
petitioners in this petition are concerned.
7. Now, the Writ petitioners and the PIL petitioners are raising
another issue, namely, the proposed sugar factory not complying
with the provisions of the Environmental Protection Act, 1986
and it would indicate as to how the same falls within the radius
of 500 meters from the bank of river and therefore, it is falling
within no development zone and hence it cannot be set up.
8. After hearing the petitioners on this point, merely because
Clause 6-A has been complied with, it does not mean that the
sugar factory or the proposed sugar factory have not to comply
with other laws. They are obliged to comply with the anti-
pollution laws in the field and the laws relating to preservation of
ecology and environment as well. It is only thereafter and other
laws and Rules in the field being complied with that any question
arises of these sugar factories becoming functional. For the
present, the stand taken in the affidavit by the authorities need
4
not be probed further. In the event, respondent No.6 carries out
construction and development, then needless to clarify that the
said respondent will have to comply with all laws including the
anti-pollution, environmental protection and ecology.
9. In such circumstances, the petitions need not be kept
pending. They are disposed of. However, the issue of aerial
distance certificate cannot be reopened at the instance of the
petitioner or any other party again.”
6. The sugar industry was deleted from the list of industries requiring
compulsory licensing under the provisions of the Industries
(Development and Regulation) Act, 1951 on 31.08.1998. However, the
condition of minimum distance of 15 kms as provided by the Control
4
Order issued under Section 3 of the Essential Commodities Act, 1955
was ordered to continue in order to avoid unhealthy competition
amongst sugar factories.
7. The Control Order was issued in exercise of the powers conferred under
Section 3 of the 1955 Act. Some of the relevant conditions, as
amended on 10.11.2006, read thus:
“ 6A. Restriction on setting of two sugar factories with in
the radius of 15 kms :-
Notwithstanding anything contained in Clause 6, no new
sugar factory shall be set up within the radius of 15 kms of any
existing sugar factory or another new sugar factory in a State or
two or more States:
Provided that State Government may with the prior
approval of the Central Government where it considers
necessary and expedient on public interest notify such minimum
distance higher than 15 kms or different minimum distances not
less than 15 kms for different regions in their respective States.
Xxx xxx xxx
4 1955 Act
5
Explanation 4: The effective steps shall mean the following steps
taken by the concerned person to implement than Industrial
Entrepreneur Memorandum for setting up of sugar factory:-
(a) Purchase of required land in the name of the factory.
(b) Placement of firm order for purchase of plant and machinery
for the factory and payment requisite advanced and opening of
irrevocable letter of credit with suppliers.
€ Commencement of civil works and construction of building for
the factory.
(d) Sanction of requisite terms loans from bank or financial
institutio€(e) Any others steps prescribed by the Central
Government in this regard through a notification.
xxx xxx xxx
6C. Time limit to implement Industrial Entrepreneur
Memorandum
The stipulated time for taking effective steps shall be two years
and commercial production shall commence within four years
with effect from the date of filing of Industrial Entrepreneur
Memorandum with the Central Government, failing which the
Industrial Entrepreneur Memorandum shall stand derecognized
as far as provisions of this Order are concerned and the
performance guarantee shall be forfeited.
Provided that the Chief Director (Sugar), Department of Food &
Public Distribution, Ministry of Consumer Affairs, Food & Public
Distribution, on the recommendation of the concerned State
Government, may give extension of one year not exceeding six
months at a time, for implementing the Industrial Entrepreneur
Memorandum and commencement of commercial production
thereof.
6D. Consequences of non-implementation of the
provision laid down in clauses 6B and 6C :-
If an Industrial Entrepreneur Memorandum remains
unimplemented within the time specified in clause 6C, the
performance guarantee furnished for its implementation shall be
forfeited after giving the concerned person a reasonable
opportunity of being heard.”
6
8. The Government of Maharashtra, after approval of the Central
Government, directed on 03.12.2011 that in terms of proviso to Clause
6A, no new sugar factory shall be set up within the radius of 25 kms of
any existing sugar factory or any other new factory.
9. On 24.08.2016, the Control Order was amended, when Clause 6C was
substituted and a proviso was inserted after Clause 6D. Such
amendment reads thus:
“ 6C. Time limit for implementing Industrial Entrepreneur
Memorandum - The stipulated time for taking effective steps
shall be three years and commercial production shall commence
within five years with effect from the date of filing the Industrial
Entrepreneur Memorandum with the Central Government, failing
which the Industrial Entrepreneur Memorandum shall stand de-
recognised as far as provisions of this Order are concerned and
the performance guarantee shall be forfeited:
Provided that the Chief Director (Sugar), Department of
Food and Public Distribution, Ministry of Consumer Affairs, Food
and Public Distribution may, after the expiry of the aforesaid
period, give extension of maximum two years, not exceeding
more than a year at a time, in cases involving delay due to any
unforeseen circumstances beyond control, such as natural
calamities, drought or non-availability of sugarcane (raw
material) during off season in a year wherein the extended
validity period terminates, non-financing of sugar sectors, stay
on permission for land use by the courts due to environmental or
other reason. In all such cases extension shall be granted in
consultation with respective State Governments, if necessary,
either for taking effective steps or for commencement of sugar
production.
xxx xxx xxx
6D.
Provided that the performance guarantee shall be returned if-
(i) the commercial production is commenced within the
stipulated period of seven years including two years of
extension;
7
(ii) the commercial production is not commenced even
after seven years for reasons not attributable to the
project proponent and the same is fully established on
merit and be recorded in writing;
(iii) the project proponent suomotu, opts to forego its
Industrial Entrepreneur Memorandum within two years
from the date of its filing and requests for return of
performance guarantee with due justification.”
10. The Control Order was subsequently amended on 12.08.2018, again
substituting Clause 6C which reads as thus:
“ 6C. Time limit for implementing Industrial Entrepreneur
Memorandum-
(1) The stipulated time for taking effective steps as
specified in explanation 4 to clause 6A shall be three
years and the commercial production of sugar shall
commence within five years from the date of filing of the
industrial entrepreneur memorandum with the Central
Government under sub-clause (1) of clause 6B failing
which the Industrial Entrepreneur Memorandum shall
stand Defendant-recognized as provided in sub-clause (2)
thereof, and the performance guarantee furnished
thereunder shall be forfeited:
(2) The time limit specified under sub-clause (1) may
be extended in the following manner, namely:-
(a) Where the delay is due to any unforeseen
circumstances beyond the control of the person
concerned such as natural calamities including drought,
non-availability of sugarcane (raw material) during off
season in the year in which the stipulated period
terminates and non-financing of sugar sectors, the Chief
Director (Sugar), Department of Food and Public
Distribution, Ministry of Consumer Affairs, Food and Public
Distribution may, after the expiry of five years’ period
stipulated under sub-clause (1) extend the period
stipulated under sub-clause (1) for a further period of two
years, not exceeding more than a year at a time;
Provided that such extension may be granted for
taking effective steps or for the commencement of
commercial production of sugar, in consultation with the
State Government concerned, if considered necessary.
8
Provided further that in case the commercial
production does not commence within such extended
period, the bank guarantee furnished under sub-clause (2)
of clause 6B shall be forfeited;
(b) Where the delay is due to any court case relating to
land use, environment or such other reason, that may
have arisen within five year from the date of filing of
Industrial Entrepreneur Memorandum, the Chief Director
(Sugar), Department of Food and Public Distribution,
Ministry of Consumer Affairs, Food and Public Distribution
may, after the expiry of five years’ period stipulated
under sub-clause (1), extend the period stipulated under
sub-clause (1) initially for a further period of two years,
not exceeding more than a year at a time;
Provided that such extension may be granted for taking
effective steps or for the commencement of commercial
production of sugar, in consultation with the State
Government concerned and the Department of Legal
Affairs in the Ministry of Law and Justice, if considered
necessary.
(c) in case where such delay due to Court case relating to
land use, environment or such other reason, continues
beyond the period extended under item (b), the Chief
Director (Sugar), Department of Food and Public
Distribution, Ministry of Consumer Affairs, Food and Public
Distribution may grant extension of such further period, as
he deems fit, no exceeding more than a year at a time,
subject to furnishing of a bank guarantee of rupees fifty
lakhs for each year for which the extension is sought,
which shall be in addition to the bank guarantee furnished
under sub-clause (2) of clause 6B;
Provided that such extension may be granted for taking
effective steps or for the commencement of commercial
production of sugar, in consultation with the State
Government concerned and the Department of Legal
Affairs in the Ministry of Law and Justice, if considered
necessary;
Provided further that in case the commercial production
does not commence within any such extended period of
9
one year, such bank guarantee of rupees fifty lakhs so
furnished for that one year of extension shall be forfeited
and if commercial production does not commence within
any of such extended period, the bank guarantee
furnished under sub-clause 6B shall also be forfeited.”
11. The appellant sought no-objection certificate on 14.04.2014 in view of
the order of the High Court that if the appellant (respondent No.6 in
the writ petition) wishes to carry out construction and development,
then the appellant would have to comply with all laws, including anti-
pollution, environmental protection and ecology but the Godawari
Marathwada Irrigation Development Corporation refused to grant no
objection certificate on 22.04.2014.
12. Hence, the appellant applied for extension of time and for change of
location within the same taluka and same group of gram panchayat
due to earlier location being no development zone, as noted by the
High Court in its order dated 27.01.2014 that the proposed sugar
factory falls within the radius of 500 meters from the bank of river.
Such request was submitted on 16.06.2014, soon after the order of the
High Court dated 27.1.2014. The appellant sought change of location
inter alia on the following grounds:
“6. ......... I state that as now the G.M.I.D.C. refused to
issue N.O.C this undersigned now to take steps to search
other land/location as per the earlier I.E.M and within the
Aerial Distance Certificate and therefore to take search for
another land which complies all the conditions and this
undersigned requires more time and therefore, the time as
stipulated as per the Sugarcane Control Order needs to be
extended and also considering the time spent on all the
legal proceeding the validity of the bank guarantee also
10
considering the time spent on all the legal proceeding the
validity of the bank guarantee also needs to be extended.
7. I further state that the proposed location complies all
the norms of the survey of India as well as Aerial Distance
as prescribed all the authorities including the GNIDC
Pollution Control Board and other State Authorities may
take time to issue necessary permission and no objection
certificates that’s the reason, the time needs to be
extended to set up the sugar factory as per the I.E.M.”
13. Even while the matter was pending with the State/Central Government
for amendment and extension of the IEM, the first writ petition was
filed in 2017 after the appellant had approached State Authorities to
measure aerial distance of the proposed location (Writ Petition No.
13836 of 2017). The second writ petition was filed on or about
26.2.2018 by the existing sugar factory after Aerial Distance Certificate
was issued to the appellant and report dated 02.01.2018 was
submitted by the State of Maharashtra to the Union recommending
grant of extension and change of location. The State in its comments
to the Central Government in response to the appellant’s seeking
extension and to change of location, stated as under:
“1. Extension of IEM
xxx xxx xxx
Recently Shri Eknath Bhanudas Barge & Ors has filed writ
petition no. 13836/2017 on 27.11.2017 in Hon’ble High Court
Bench Aurangabad regarding location. This office has no
objection for extension of IEM considering the intervening period
of litigation.
2. Change in Location
11
xxx xxx xxx
According to your office letter dated 15 September, 2015, this
office has intimated to Survey of India vide letter dated 17
October 2015 to measure the aerial/redial distance for the
location Malewadi Dumala, Tal. Newasa, Dist Ahmednagar of M/s
Swami Samarth Sugar & Agro Industries Ltd., the Survey of India
has submitted aerial distance report between pillars of proposed
sugar factory and chimney of existing sugar factories vide letter
dated 01 January, 2018. The copy of this letter is also enclosed
for reference. In this regard a Writ Petition No. 13836/2017 has
filed on 27.11.2017 before Hon’ble High Court Bench
Aurangabad. The request of factory regarding change in location
may be duly considered at your level.”
14. The Government of India on 14.11.2018, after considering the
comments of the State Government dated 2.1.2018, allowed the
extension by observing as under:
“4. The sugar factory of M/s. Swami Samarth Sugar & Agro
Industries Ltd. ( M/s. SSSAIL) was taken on record as New Sugar
Factory as provided in explanation 2 to clause 6A of Sugarcane
(Control) Order 1966, vide order dated 14.11.2018 in reference
of IEM No. 3033/SIA/IMO 2010 dated 08.09.2010 for
establishment of new sugar mill at Warkhed (Ramdoh) Tal.
Newasa, Distt. Ahmednagar, Maharashtra.
5. M/s. SSAIL vide their letters dated 04.01.2018 and 06.11.2018
have mentioned that they could not take effective steps,
primarily, due to involvement of court cases, severe drought
condition and reluctance of bank/financial institutions to finance
the project. Delay appears beyond the control of project
proponent.
6. Moreover, Commissioner of Sugar, Maharashtra State vide
their letter dated 02.01.2018 have, in principal, given permission
for extension of IEM No. 3033/SIA/IMO/2010 dated 08.09.2010
for establishment of new sugar mill at Warkhed (Ramdoh), Tal.
Newasa, Distt. Ahmednagar, Maharashtra.”
12
15. Further extensions were given in similar background on 15.11.2018,
12.04.2019 and 09.05.2019. The appellant submitted bank guarantees
of Rs.50,00,000/- on 09.09.2019 and of Rs.37,30,000/- on 10.10.2019.
Request for extension of time and for change of location was accepted
on 17.10.2019 and one year further extension was granted up to
07.09.2020 to implement the IEM dated 08.09.2010. On 14.08.2020,
the request for change of location was accepted and the existing
location was deleted and the new location, “Gat No. 18, Malewadi
Dumala, Tal. Newasa, Ahmednagar, Maharashtra” was inserted.
16. The third writ petition was filed on or about 1.10.2020 by the existing
sugar factory challenging the extension granted and change of location
permitted by the Central Government on 14.08.2020. It was averred in
the writ petition that the area of operation of the said existing sugar
factory is 92 villages in Newasa Taluka and 122 villages in Shevgaon
Taluka. In the counter affidavit filed on behalf of the appellant, it was
inter alia averred that the existing sugar factory is trying to create its
monopoly in respect of its geographical zone while there is ample
sugarcane available in the said area. The existing sugar factories are
not in a position to harvest the entire sugarcane cultivated in the area
on account of which the helpless farmers are forced to approach other
sugar factories in the district for getting their sugarcane harvested.
The existing sugar factory had even opposed the setting up of a
13
Gangamai Industries and Construction Limited in Taluka Shevgaon by
filing a Writ Petition No. 3063 of 2009. The writ petition was dismissed
on 16.11.2009. It was also pointed out that the sugarcane is being
cultivated in large area in view of the back waters of Jaikwadi Major
Irrigation Project and that there is a need for setting up of a unit.
17. The High Court on considering the respective contentions of the parties
found that the issue involved was the interpretation of Clause 6C of the
Control Order. It was observed that subsequent to the amendment in
the Control Order by the State in the year 2011, the minimum aerial
distance between the new sugar factory and the existing sugar factory
is 25 kms, as cluster of sugar factories near each other would not be a
viable proposition and may affect the survival of the existing sugar
factory. Therefore, if a new sugar factory is allowed to be established
on the terms of the IEM issued in the year 2010, it would render the
existing sugar factory unviable and both sugar factories may not be in
a position to survive.
18. The High Court further held that the appellant had not taken any
effective steps within the period of two years from the date of
acknowledgment of IEM. The appellant had neither purchased the land
for four years in the name of the factory, nor placed confirmed orders
for purchase of plant and machinery and even the civil work had not
commenced. There were no effective steps even five years of IEM. The
change of location was sought on 16.06.2014 whereas the land at the
14
changed location was purchased on or about the year 2017. The High
Court found that the amendment in the Sugar Control Order dated
24.08.2016 would not be helpful to the appellant as the IEM stood de-
recognized before the said amendment was carried out. The IEM stood
de-recognized on 08.09.2014 as the four years for commercial
production had lapsed. Thereafter, the maximum one-year extension
also lapsed on 08.09.2015. Therefore, the amended provision cannot
be applied to a de-recognized IEM. The High Court further found that
the recommendation of the State Government was not on record for
the extension of IEM. In other words, it was concluded by the High
Court that the IEM stood de-recognized before the Sugar Control Order
was amended on 26.08.2016. Therefore, no right accrues to the
appellant. It was further held that the judgment of this Court reported
5
as M/s Ojas Industries (P) Ltd v. M/s Oudh Sugar Mills Ltd .
relating to retrospective effect of the amendment in the Control Order
in the year 2006 would not be applicable to the present IEM which
stood de-recognized prior to the said amendment.
19. The High Court found that there was no stay on IEM, nor was there any
prohibition from taking effective steps, therefore, the appellant was not
prevented from taking steps on account of the orders of the Court in
the first round of litigation. On the other hand, in the second round, an
order was passed by the High Court on 27.03.2018 on an application
filed by the existing sugar factory that the appellant has started
5 AIR 2007 SC 1619
15
construction activity. The High Court ordered that if further
construction is made, the same would be at the risk of the appellant
and subject to the decision of the writ petition and that the appellant
would not be entitled to any equity in case the construction is carried
out, nor can seek any equity for extension of IEM on the ground that
the construction is being carried out. On 10.04.2018, an order was
passed that the earlier order passed on 27.03.2018 would take care of
any construction that would be carried out by the appellant
(Respondent No.6 in the writ petition). Therefore, the appellant could
not take benefit of the investment made on the land purchased and
the construction started. However, the High Court found that till
November 2018, the appellant has not undertaken any construction
work at the site and the stand of the appellant that it had invested in
the construction activity cannot be taken into consideration for the
reasons that extensions were granted in violation to the provisions of
the Rules and the Statute. The High Court also found that as per the
amendment, the new sugar factory had to be at a distance of not less
than 25 kms.
20. With this factual background, the questions required to be examined
are as follows:
(i) Whether in the absence of any interim order against the
appellant in the first round of litigation, the period during which
writ petitions were pending are liable to be excluded?
Alternatively, whether the State/ Central Government was
justified in excluding such period while granting extension of IEM.
16
(ii) Whether the lis initiated against the appellant is a sufficient
reason to exclude the period spent in such litigation and was a
reasonable ground for the State/Central Government to extend
IEM.
(iii) Whether the amended Control Order in terms of proviso to
Clause 6C as amended by the State of Maharashtra on
03.12.2011 would be applicable when the High Court in the
earlier writ petition has held that the issue of Aerial Distance
Certificate cannot be reopened at the instance of the appellant
or any other party again. Pertinently, when the order was passed
by the High Court, the amended Control Order was in force.
Therefore, what is the effect of the said order?
(iv) Whether the IEM stands lapsed on the failure on the part of
entrepreneur to set up the sugar factory and start production
within the time specified in Clause 6C or such lapsing would be
only after an order in terms of Clause 6D of the Control Order is
passed?
21. The undisputed facts are that a writ petition was filed on 23.09.2010,
soon after the acknowledgment of IEM on 08.09.2010. It may be
mentioned that there was no interim order against the appellant, but
the fact remains that the validity of IEM on the ground of aerial
distance was disputed. The writ petition filed against the grant of Aerial
Distance Certificate came to be dismissed on 27.01.2014 and
thereafter the appellant sought extension of time on 16.06.2014 for
implementation of the IEM in view of the litigation from 2010-2014.
22. A perusal of the Control Order shows that initially as per the Control
Order as amended in the year 2006, the time limit for implementing
the IEM was 2 + 4 years and that there was no specific Clause to
17
extend the period of implementation of IEM on account of delay due to
any unforeseen circumstances. The subsequent amendment to the
Control Order dated 24.08.2016 extended the period of
implementation to 3+5 years with a further condition to grant
extension for a maximum period of two years due to any unforeseen
circumstances “beyond control”. However, in the further subsequent
amendment on 12.08.2018, Clause 6C(2)(a) specified that where delay
is due to any unforeseen circumstances “beyond the control of person
concerned” such as natural calamities, the extension could be granted
for a further period of two years after the expiry of five years for
commencing the commercial production, not to exceed more than a
year at a time. However, Clause 6C(2)(b) provided that where delay
was due to any court case relating to land use, environment or “such
other reason” that may have arisen within five years from the date of
filing of IEM, the Ministry of Consumer Affairs may extend the period
stipulated under sub-clause (1) initially for a further period of two years
not to exceed more than a year at a time. Clause 6C(c) provided that
where delay is due to court case relating to land use, environment or
such other reason continues beyond the period extended under clause
(b), the Ministry of Consumer Affairs may grant extension or such
period as may deem fit, not to exceed more than a year at a time, but
subject to furnishing of bank guarantee of Rs. 50 Lakhs for each year
for which extension is sought, in addition to the bank guarantee
18
furnished under sub-clause (2) of Clause 6B of the Control Order. Such
Bank Guarantee is liable to forfeiture but only in terms of Clause 6D of
the Control Order.
23. With this undisputed factual and legal background, the first three
questions, which are interrelated are taken up for discussion first. The
latin maxim ‘Actus Curiae Neminem Gravabit’ i.e., the act of the Court
will not prejudice anyone, is well known, but the applicability of the
same to the facts of the present circumstances need to be examined.
We find that the appellant was justified in not taking any effective
steps pending such lis, as contemplated under Explanation 4 to Clause
6A of the Control Order. The arial distance is one of the foremost
requirements for a valid IEM. This Court in a judgment reported as
6
South Eastern Coalfields Ltd. v. State of M.P. and Others held
that injury, if any, caused by the act of the Court shall be undone and
the gain which the party would have earned, unless it was interdicted
by the order of the Court would be restored to or conferred on the
party by suitably commanding the party liable to do so. The Court
noticed that the litigation may turn into a fruitful industry. Though
litigation is not gambling yet there is an element of chance in every
litigation. Unscrupulous litigants may feel encouraged to approach the
courts, persuading the court to pass interlocutory orders favourable to
them by making out a prima facie case when the issues are yet to be
heard and determined on merits and if the concept of restitution is
6 (2003) 8 SCC 648
19
excluded from application . It was held as under:
“28. That no one shall suffer by an act of the court is not a rule
confined to an erroneous act of the court; the “act of the court”
embraces within its sweep all such acts as to which the court may form
an opinion in any legal proceedings that the court would not have so
acted had it been correctly apprised of the facts and the law. The factor
attracting applicability of restitution is not the act of the court being
wrongful or a mistake or error committed by the court; the test is
whether on account of an act of the party persuading the court to pass
an order held at the end as not sustainable, has resulted in one party
gaining an advantage which it would not have otherwise earned, or the
other party has suffered an impoverishment which it would not have
suffered but for the order of the court and the act of such party. The
quantum of restitution, depending on the facts and circumstances of a
given case, may take into consideration not only what the party
excluded would have made but also what the party under obligation
has or might reasonably have made. There is nothing wrong in the
parties demanding being placed in the same position in which they
would have been had the court not intervened by its interim order
when at the end of the proceedings the court pronounces its judicial
verdict which does not match with and countenance its own interim
verdict. Whenever called upon to adjudicate, the court would act in
conjunction with what is real and substantial justice. The injury, if any,
caused by the act of the court shall be undone and the gain which the
party would have earned unless it was interdicted by the order of the
court would be restored to or conferred on the party by suitably
commanding the party liable to do so. Any opinion to the contrary
would lead to unjust if not disastrous consequences. Litigation may
turn into a fruitful industry. Though litigation is not gambling yet there
is an element of chance in every litigation. Unscrupulous litigants may
feel encouraged to approach the courts, persuading the court to pass
interlocutory orders favourable to them by making out a prima facie
case when the issues are yet to be heard and determined on merits
and if the concept of restitution is excluded from application to interim
orders, then the litigant would stand to gain by swallowing the benefits
yielding out of the interim order even though the battle has been lost
at the end. This cannot be countenanced. We are, therefore, of the
opinion that the successful party finally held entitled to a relief
assessable in terms of money at the end of the litigation, is entitled to
be compensated by award of interest at a suitable reasonable rate for
the period for which the interim order of the court withholding the
release of money had remained in operation.” (Emphasis supplied)
20
24. In the present appeal, the lis initiated by the writ petitioners in the first
round was nothing less than gamble so as to scuttle the process of
commissioning of plant. The appellant was at the receiving end of the
writ petitions filed and was at the receiving end of such litigation and
the period spent in such lis cannot be used against the appellant.
25. In another judgment reported as Beg Raj Singh v. State of U.P. and
7
Others , this Court held that ordinary rule of litigation is that the rights
of the parties stand crystallized on the date of commencement of
litigation and the right to relief shall be decided by reference to the
date on which the petitioner entered the portals of the Court. That was
a case where the appellant was granted sand mining lease for a period
of one year but before the expiry of the term of lease, the appellant
sought renewal of lease for another period of two years. Around the
time when the appellant was allowed the extension of two years, the
Government had taken a decision to hold an auction of the sand
mining lease. It was in these circumstances, this Court held as under:
“6. Having heard the learned counsel for the petitioner,
as also the learned counsel for the State and the private
respondent, we are satisfied that the petition deserves to
be allowed. The ordinary rule of litigation is that the
rights of the parties stand crystallized on the date of
commencement of litigation and the right to relief should
be decided by reference to the date on which the
petitioner entered the portals of the court. A petitioner,
though entitled to relief in law, may yet be denied relief
in equity because of subsequent or intervening events
i.e. the events between the commencement of litigation
and the date of decision. The relief to which the petitioner
is held entitled may have been rendered redundant by
7 (2003) 1 SCC 726
21
lapse of time or may have been rendered incapable of
being granted by change in law. There may be other
circumstances which render it inequitable to grant the
petitioner any relief over the respondents because of the
balance tilting against the petitioner on weighing
inequities pitted against equities on the date of
judgment. Third-party interests may have been created or
allowing relief to the claimant may result in unjust
enrichment on account of events happening in-between.
Else the relief may not be denied solely on account of
time lost in prosecuting proceedings in judicial or quasi-
judicial forum and for no fault of the petitioner. A plaintiff
or petitioner having been found entitled to a right to
relief, the court would as an ordinary rule try to place the
successful party in the same position in which he would
have been if the wrong complained against would not
have been done to him. The present one is such a case.
The delay in final decision cannot, in any manner, be
attributed to the appellant. No auction has taken place.
No third-party interest has been created. The sand mine
has remained unoperated for the period for which the
period of operation falls short of three years. The
operation had to be stopped because of the order of the
State Government intervening which order has been
found unsustainable in accordance with stipulations
contained in the mining lease consistently with GO issued
by the State of Uttar Pradesh. Merely because a little
higher revenue can be earned by the State Government
that cannot be a ground for not enforcing the obligation
of the State Government which it has incurred in
accordance with its own policy decision.”
26. In the first round of litigation, two writ petitions were filed in public
interest to dispute the Aerial Distance Certificate. Though there was no
interim order passed in the writ petitions, such petitions created a
cloud on the right of the appellant to set up a sugar factory at the
location earmarked and to commence commercial production. The writ
petitions remained pending for a period of four years. Therefore, the
period spent in defending such writ petitions was validly taken into
consideration by the State/Central Government to grant extension of
time limit fixed in the Control Order. The Government of India granted
22
extension on 14.11.2018 when the Control Order as amended on
12.08.2018 was operative and effective. Since the amendments carried
out in Control Order were for the benefit of the entrepreneurs,
therefore, the Control Order as it is existed on the date of the
extension would be applicable. It is in terms of such Clause that the
appellant was called upon to furnish additional bank guarantee of Rs.
50 Lakhs. Hence, the power exercised by the Central Government is in
terms of the statutory Control Order as amended on 14.11.2018.
27. In the present case, the appellant was not the writ petitioner before the
High Court. Rather, he was defending the permissions granted by the
State and the Central Government. It was not prudent for the appellant
to proceed with the heavy investment required for installation of a
sugar factory and then to suffer the consequences depending on the
outcome of the litigation. The appellant opted for a safer option not to
erect the plant and commence production because of the pending
litigation. It was a reasonable and precautionary option exercised by
the appellant. The litigation initiated in public interest or by the rival
sugar factory cannot be used against the appellant when the writ
petition was disposed of with the condition that there cannot be any
development within 500 meters of river which necessitated the change
of location. The Aerial Distance Certificate was categorically declared
to be not open to challenge even though the State had amended the
Control Order on 03.11.2011 to increase the distance between the
23
existing sugar factory and the new factory was increased to 25
kilometers. Even though the Control Order was already amended by
the State, but the High Court held that the aerial distance would be as
applicable on the date of IEM acknowledged by the Central
Government. It is to be noted that there is no challenge to the order
passed by the High Court in the first round of the litigation. Therefore,
even the High Court in the second round of litigation was not within its
jurisdiction to hold that the amended distance regulations would be
applicable.
28. Still further, the State Government while recommending extension on
02.01.2018 did not dispute that the aerial distance between the
existing sugar factory and the proposed new sugar factory was less
than 25 kms, and rightly so for good reasons. The conditions provided
in the IEM acknowledged on 08.09.2010 would alone be applicable,
which was extended by the Central Government on 14.08.2018. The
appellant has to be restituted in terms of the order passed in South
Eastern Coalfields Ltd. as on the day when the lis was initiated, not
by the appellant but by the other persons. The litigation at the behest
of rival parties cannot be used against the appellants, more so when
they have substantially failed in the first round of lis.
29. The language of the Control Order has been amended time and again
with a view to enable the competent authority to grant extension of
time due to “unforeseen circumstances”. The Control Order amended
24
on 12.08.2018 contemplates more than one unforeseen circumstance
beyond the control of the person concerned. It also empowers the
competent authority to extend the validity of IEM where the delay is
due to any court case relating to land use, environment or “such other
reason”. Sub-clause (c) of Clause 6C empowers the competent
authority to grant further extension for a period of not exceeding a
year at a time subject to furnishing of a bank guarantee. Therefore, the
objective and purpose of such amended Control Order is that a sugar
mill should commence production by excluding the period spent in the
court cases. Though the appellant was the defender of the IEM granted
and there was no stay in the first round of litigation, but the extension
granted would fall under the category of “such other reason”. The
judgment of this Court in South Eastern Coalfields Ltd. is to the
effect that no one shall suffer by the act of the Court which embraces
within its sweep all such acts as to which the Court may form an
opinion in any legal proceedings but the Court would not have so acted
had it been correctly apprised of the facts and the law. In the first
round of litigation, challenge was to the Aerial Distance Certificate, the
writ petitioners have failed in such challenge but the High Court rightly
interdicted that the appellant is required to comply with the anti-
pollution laws in the field and the laws relating to preservation of
ecology and environment. Such order led to the appellant looking for
alternative location in view of the denial of no-objection certificate by
25
Godawari Marathwada Irrigation Development Corporation. Therefore,
the period spent in litigation for the years 2010-2014 has been rightly
excluded by the competent authority.
30. Another question which arises for consideration is whether the decision
of the Central Government based upon the recommendation of the
State Government is so arbitrary, irrational, unjust which warranted
interference in exercise of the power of judicial review in writ
jurisdiction. The High Court has not set aside the said order on only
such ground but also for the reason that the appellant has not
implemented IEM within the time prescribed. This Court in Tata
8
Cellular v. Union of India has held as under:
| “70. | It cannot be denied that the principles of judicial review | | | |
|---|
| would apply to the exercise of contractual powers by | | | | |
| Government bodies in order to prevent arbitrariness or | | | | |
| favouritism. However, it must be clearly stated that there are | | | | |
| inherent limitations in exercise of that power of judicial | | | | |
| review. | | | Government is the guardian of the finances of the State. | |
| It is expected to protect the financial interest of the State | | | | . The |
| right to refuse the lowest or any other tender is always available | | | | |
| to the Government. But, the principles laid down in Article 14 of | | | | |
| the Constitution have to be kept in view while accepting or | | | | |
| refusing a tender. There can be no question of infringement of | | | | |
| Article 14 if the Government tries to get the best person or the | | | | |
| best quotation. The right to choose cannot be considered to be | | | | |
| an arbitrary power. Of course, if the said power is exercised for | | | | |
| any collateral purpose the exercise of that power will be struck | | | | |
| down. | | | | |
77. The duty of the court is to confine itself to the question of
legality. Its concern should be:
8 (1994) 6 SCC 651
26
1. Whether a decision-making authority exceeded its powers?
2. Committed an error of law,
3. committed a breach of the rules of natural justice,
4. reached a decision which no reasonable tribunal would have
reached or,
5. abused its powers.
Therefore, it is not for the court to determine whether a
particular policy or particular decision taken in the fulfilment of
that policy is fair. It is only concerned with the manner in which
those decisions have been taken. The extent of the duty to act
fairly will vary from case to case. Shortly put, the grounds upon
which an administrative action is subject to control by judicial
review can be classified as under:
(i) Illegality : This means the decision-maker must understand
correctly the law that regulates his decision-making power and
must give effect to it.
(ii) Irrationality, namely, Wednesbury unreasonableness.
(iii) Procedural impropriety.
The above are only the broad grounds but it does not rule out
addition of further grounds in course of time. As a matter of fact,
in R. v. Secretary of State for the Home Department, ex
Brind [(1991) 1 AC 696] , Lord Diplock refers specifically to one
development, namely, the possible recognition of the principle of
proportionality. In all these cases the test to be adopted is that
the court should, “consider whether something has gone wrong
of a nature and degree which requires its intervention”.
94. The principles deducible from the above are:
(1) The modern trend points to judicial restraint in administra-
tive action.
27
| (2) The court does not sit as a court of appeal but merely re-<br>views the manner in which the decision was made. | |
|---|
| |
| (3) The court does not have the expertise to correct the ad-<br>ministrative decision. If a review of the administrative de-<br>cision is permitted it will be substituting its own decision,<br>without the necessary expertise which itself may be falli-<br>ble. | |
| |
| (4) The terms of the invitation to tender cannot be open to ju-<br>dicial scrutiny because the invitation to tender is in the<br>realm of contract. Normally speaking, the decision to ac-<br>cept the tender or award the contract is reached by<br>process of negotiations through several tiers. More often<br>than not, such decisions are made qualitatively by ex-<br>perts. | |
| |
| (5) The Government must have freedom of contract. In other<br>words, a fair play in the joints is a necessary concomitant<br>for an administrative body functioning in an administra-<br>tive sphere or quasi-administrative sphere. However, the<br>decision must not only be tested by the application of<br>Wednesbury principle of reasonableness (including its<br>other facts pointed out above) but must be free from arbi-<br>trariness not affected by bias or actuated by mala fdi es. | |
| |
| (6) Quashing decisions may impose heavy administrative bur-<br>den on the administration and lead to increased and un-<br>budgeted expenditure. | |
| |
31. In the absence of any finding by the High Court to the effect that the
decision of the Central Government is so arbitrary, irrational or unjust,
we find that the High Court has gravely erred in taking into
consideration that appellant was remiss in not implementing IEM
during the pendency of the writ petitions in the first round of litigation.
32. The second round of litigation began even before the Aerial Distance
28
Certificate was issued. The appellant was again the defender of the
issuance of the IEM. The High Court therein found that the amendment
carried out by the State of Maharashtra contemplating that no sugar
factory shall be set up within the radius of 25 kms would be applicable,
though it is not even the averment or objection of the State in its
communication dated 02.11.2018. Still further, the scheme of the
Control Order shows that once IEM is granted, the timeline has to be
determined keeping in view the date of the issuance of the IEM.
Therefore, subsequent amendment would be applicable in respect of
new sugar factory which may be proposed to be set up. It is conceded
that during the interregnum from 2010 till the hearing of the appeal
before this Court, no other entrepreneur has applied for IEM in the area
Taluka Newasa and Shevgaon. Since no other entrepreneur has applied
for IEM to set up a sugar factory in the area in question, it is not open
to the existing sugar factory to contend that the revised parameters by
the State Government should be made applicable. IEM fixes the
timeline from the date of issuance of the same and the subsequent
amendment in the Control Order would not have any application
towards the IEM already issued.
33. Mr. Chidambaram, learned Senior Advocate appearing for the existing
sugar factory relies upon the judgment of this Court reported as Ojas
Industries (P) Ltd. to argue that the concept of distance with regard
to the availability of sugarcane and the capacity of crushing of the
29
existing and new factory is of utmost importance.
34. In the said referred case, this Court was considering an application filed
by multiple sugar mills in the State of Uttar Pradesh. That was a case
where the proliferation of IEM to block the competition was the cause
of dispute. The IEM filed by the appellant for setting up of a sugar mill
at Village Baisagapur, Distt. Lakhimpur was acknowledged on
13.05.2004, whereas the respondent in the said appeal filed its IEM on
17.05.2004 for setting up of a sugar mill at Village Saidpur, Khurd,
Distt. Lakhimpur which was at a distance of 7.2 kms from the proposed
sugar mill of the appellant. The Government of India had approved the
IEM filed by the appellant on 30.06.2005 whereas IEM filed by the
respondent was disapproved. The respondent filed a writ petition
challenging the IEM approved in favor of the appellant and another IEM
in favor of the M/s Bajaj Hindustan Ltd. for setting up of a sugar mill at
Village Khambarkhera. This Court held as under:
| “ | 30. | | The Sugarcane (Control) (Amendment) Order, 2006 inserts |
|---|
| clauses 6-A to 6-E in clause 6 of the Sugarcane (Control) Order, | | | |
| 1966. It retains the concept of “distance”. This concept of | | | |
| “distance” has got to be retained for economic reasons. This | | | |
| concept is based on demand and supply. This concept has to be | | | |
| retained because the resource, namely, sugarcane, is limited. | | | |
| Sugarcane is not an unlimited resource. “Distance” stands for | | | |
| available quantity of sugarcane to be supplied by the farmer to | | | |
| the sugar mill. On the other hand, fli ing of bank guarantee for Rs | | | |
| 1 crore is only as a matter of proof of bona fdi es. An | | | |
| entrepreneur who is genuinely interested in setting up a sugar | | | |
| mill has to prove his bona fdi es by giving bank guarantee of Rs 1 | | | |
| crore. Further, giving of bank guarantee is also a proof that the | | | |
| businessman has the fni ancial ability to set up a sugar mill | | | |
| (factory). Therefore, giving of bank guarantee has nothing to do | | | |
30
with the distance certificate.
| 34. | | Before concluding on this issue we may reiterate that raising | |
|---|
| of resources and application of resources by a unit is difef rent | | | |
| from the condition of distance. The concept of “distance” is | | | |
| different from the concept of “setting up of unit” in the sense | | | |
| that setting up of a unit is the main concern of the businessman | | | |
| whereas a concept of “distance” is an economic concept which | | | |
| has to be taken into account by the Government because it is | | | |
| the Government which has to frame economic policies and which | | | |
| has to take into account factors such as demand and supply.” | | | |
35.
This Court approved the IEM filed by M/s Balrampur Chini Mills Ltd. at
Village Kumbi, where it had invested Rs.213 crores for its plant. The
said sugar factory had also invested Rs. 152 crores at Village Guleria.
The following observations were made by this Court:
| “37. | | We are of the view that out of two projects at Kumbhi and | |
|---|
| Guleria, Balrampur can be given milling permission for its factory | | | |
| (mill) at Kumbhi. In our present judgment we have taken the | | | |
| view that the Sugarcane (Control) (Amendment) Order, 2006 | | | |
| operates retrospectively. We have also taken the view that in | | | |
| applying the said 2006 Order there will be a bar on subsequent | | | |
| IEM-holders during the specifei d period when the earlier IEM- | | | |
| holder is taking effective steps. At the same time, we fni d that in | | | |
| the case of Kumbhi substantial investment has been made by | | | |
| Balrampur. Their projections are better than units proposed to be | | | |
| set up by Oudh. Moreover, the sugarcane crushing season ends | | | |
| on 15-5-2007, we do not want the cane-growers to suffer. | | | |
| Therefore, we grant milling permission only to Kumbhi Project. IA | | | |
| No. 2 of 2007 is made absolute. However, Guleria Project shall | | | |
| be governed by the principles laid down in this judgment, as | | | |
| indicated above.” | | | |
36. We find that the said judgment is relevant only to examine the
question as to whether the Control Orders are retrospective or not. The
31
finding about the distance while granting permission to Balrampur
Chini Mills is in the facts of that case. In the present appeal, after the
IEM was acknowledged in the year 2010, no other entrepreneur had
even sought or had been granted IEM in the area in question except
the existing sugar factory was permitted to enhance its crushing
capacity.
37. In view of the principles laid down in the aforesaid judgment, the
amendments carried out subsequently in the Control Order would also
be read as retrospective as they are not creating any right for the first
time. Clauses 6A to 6E were inserted by the amendment on
10.12.2006 to substitute the press notes which were found to be under
cloud by this Court. Subsequent amendments on 24.08.2016 and
12.10.2018 would also be retrospective being amendments dealing
with procedural aspects and clarificatory in nature in lieu of the press
notes issued earlier by the Central Government. Such amendments
were necessitated to take care of situation when IEM holder is not able
to take effective steps because of unforeseen circumstances.
38. The judgment reported as Babaji Kondaji Garad v. Nasik
9
Merchants Co-operative Bank Ltd., Nasik and Others and
10
Dhananjaya Reddy v. State of Karnataka were pressed to argue
that where the statute prescribes a procedure for doing a thing, it must
be done accordingly, unless there is any contrary indication. The said
9 (1984) 2 SCC 50
10 (2001) 4 SCC 9
32
judgments have no applicability to the facts of the present case as the
extension has been granted by the Central Government on the
recommendation of the State Government keeping in view of the
unforeseen circumstances faced by the appellant.
39. An argument has been raised that the validity of IEM was extended on
15.11.2018, 12.04.2019, 09.05.2019, 17.10.2019 and 18.02.2021.
Such frequent extensions of the IEM show that the extensions were
given at the asking without satisfying the pre-requisite conditions to
seek extensions. We do not find any merit in such arguments. The
extensions were given when the second round of litigation was pending
before the High Court due to which the appellant was not able to take
effective steps. The following tabular chart would show the date of
extensions and the period of extensions.
| Sr. No. | Central Government<br>Letter/Date of Extension | Date till extended |
|---|
| 1. | 15.11.2018 | 07.09.2017 |
| 2. | 12.04.2019 | 07.09.2018 |
| 3. | 09.05.2019 | 07.09.2019 |
| 4. | 17.10.2019 | 07.09.2020 |
| 5. | 18.02.2021 | 07.09.2021 |
40.
A perusal of the above table would show that the extensions granted
on 15.11.2018 and 12.04.2019 were for a period which had already
expired. The extension granted on 09.05.2019 was valid only till
07.09.2019 i.e. less than four months. All the extensions were granted
when the matter was still pending before the High Court and were
subject to the outcome of the writ petitions. Therefore, the objections
33
regarding frequent grant of extension of IEM are not of much
substance.
41. Hence, we find that the decision of the competent authority to grant
extension of time is proper exercise of the powers conferred on it and
cannot be said to be illegal, irrational or suffering from procedural
impropriety. Accordingly, in respect of Question nos. (i), (ii) and (iii), we
find that the findings recorded by the High Court are not sustainable in
law.
42. Learned counsel for the appellant argued that Clause 6C contemplates
that if the steps are not taken within the timeline stipulated under the
IEM, it shall stand de-recognized and the performance guarantee shall
be forfeited. However, the performance guarantee is liable to forfeiture
after giving the concerned person a reasonable opportunity of being
heard. Therefore, the use of word ‘shall’ in Clause C does not make the
provision mandatory but enables the competent authority to forfeit
bank guarantee on failure to comply with the timeline.
43. In the second round of writ petitions, objections were raised by the
existing sugar factory that the appellant has started construction. Such
construction was interdicted on the ground that no equity will follow on
the basis of any construction raised. The reasons which prevail with the
appellant in not setting up of the sugar factory or raise construction in
the first round of litigation are very well applicable in the second round
as well. The IEM was amended subject to the writ petitions filed in the
34
second round. Therefore, having objected to the construction and the
High Court passing an order that the appellant would not be entitled to
claim any equity, it is a reasonable and prudent decision taken by the
appellant not to proceed with the construction and set up a plant.
44. The existing sugar factory had argued that IEM stands lapsed as the
appellant has failed to set up the factory and to commence the
commercial production. However, we are unable to agree with such
interpretation. Though Clause 6C as applicable on 10.11.2006 as well
as on 24.08.2016 and 12.08.2018 contemplates the IEM shall stand de-
recognised and the performance guarantee shall be forfeited, the
performance guarantee is to be forfeited in terms of Clause 6D after
providing the reasonable opportunity of being heard. We find that twin
conditions have to be fulfilled- (i) failure to set up plant and to
commence production and then (ii) the forfeiture of the performance
guarantee. Second will not arise unless the first is satisfied and the
second step cannot be undertaken, without complying with an
opportunity of personal hearing in terms of Clause 6D of the Control
Order. Unless the performance guarantee is forfeited, there is no
lapsing of IEM. Thus, unless the necessary consequences of de-
recognition of IEM are undertaken, there is no automatic lapsing of IEM.
Such is the language in the subsequent amended Control Orders as
well. The appellant had furnished a performance guarantee of Rs. 1
crore, however no steps were taken either by the State Government or
35
by the Central Government to forfeit such performance guarantee
inasmuch as not even a show cause notice was issued. Thus, a
conclusion cannot be drawn that the IEM is deemed to be lapsed
automatically only on account of lapsing of time.
45. The State Government had filed an affidavit to provide information
regarding the sugarcane available and the capacity of the sugar mills
in the areas. It states that during the last five crushing seasons, four
sugar mills i.e., the existing sugar factory and three other mills had
crushed the entire cane available from Newasa and Shevgaon Talukas
and also crushed from neighbouring districts of Aurangabad, Jalana
and Beed. It also stated that in the years 2016-17 and 2019-20, the
cane was used for fodder purpose as crushing was less than the
available cane. It is stated that Newasa and Shevgaon Talukas are
drought prone and there is scarcity of sugarcane with regard to the
crushing capacity of four sugar mills. It submits that since sugarcane
area restrictions (zoning) are removed in Maharashtra since the year
1997, the sugarcane growers are at liberty to provide sugarcane to any
sugar mills as per their choice. In view of the said fact, the appellant
cannot be denied the benefit of setting up of a sugar mill only on the
basis of resistance from the competitor, who had only financial interest
in mind. In case of a competition, it is the consumer (farmer) who is
the beneficiary. In the present case, the farmers are not getting the
advantage of competition which could fetch them timely payment and
better services. In view of the said fact, we find that the order of the
36
High Court allowing the writ petition filed by the competitors is wholly
unjust and unfair and is liable to be set aside.
46. It may be stated that one I.A. has been filed on behalf of the farmers of
the area supporting the setting up of a sugar mill by the appellant. It is
not necessary to dwell on such I.A. except to state that the farmers are
also looking forward for some competition in the area.
47. We may further state that under the Chair of Dr. C. Rangarajan, the
then Chairman, Economic Advisory Council to the Prime Minister, in its
report dated 05.10.2012 has reported under the heading Executive
Summary as under:
“ 2. The highly perishable nature of sugarcane, the small land
holdings of sugarcane farmers and the need to keep the price of
sugar at a reasonably affordable level while also making it
available through the Public Distribution System (PDS) have
been the drivers for regulation. The principal aspects regulated
in the sugar sector are as under:
(i) Cane reservation area and bonding — Every designated mill is
obligated to purchase from cane farmers within the cane
reservation area, and conversely, farmers are bound to sell to
the mill. As a consequence of the area requirement (distance
criterion), setting up of a new mill requires approvals,
notwithstanding delicensing under the Industries Development &
Regulation Act.
(ii) xxx xxx
3. Cane area reservation and bonding are intended to serve the
twin purpose of giving a minimum assured supply of the highly-
perishable raw material to a mill, while committing the mill to
procure at a minimum price (FRP/SAP). However, this
arrangement may reduce the bargaining power of the farmer,
who is forced to sell to a mill even if there are cane arrears and
also reduces the farmer’s remuneration if the design mill has a
lower recovery rate. Mills also lose flexibility in augmenting cane
supplies, especially when there is a shortfall in sugarcane
production in the cane reservation area. Moreover, mills are tied
down to the quality of cane that is supplied by the farmers in the
37
area…..
4. The minimum distance criterion for setting up of a new mill is
expected to ensure a minimum availability of cane for all mills.
This can cause distortion in the market. The virtual monopoly
over a large area can give the mills power over farmers,
especially where landholdings are smaller.
This restriction inhibits entry and further investment, and
adversely impacts competition for purchase of sugarcane as well
as for improving mill efficiency. As such, it is not in the interest of
development of sugarcane farmers or the sugar sector, and may
be dispensed with as and when a state does away with cane
reservation area and bonding.”
48.
In respect of cane reservation area and minimum distance criteria, it
was stated in Chapter 2, while dealing with the “Cane Area Reservation
and the Minimum Distance Criterion” as under:
“2.1 Central Government has been protecting the interests of
sugarcane farmers and sugar mills through various policy
instruments. Sugarcane farmers are assured of a minimum price
for sugarcane, payable by mills. On the other hand, sugar mills
have been assured regular supply of sugarcane by providing that
a minimum distance be maintained between two mills and an
area be earmarked for each mill for drawal of cane. The
expectatons implicit in the extant system of cane area
reservation and the criterion for distance between mills could be
as under:
(i) ensuring adequate cane supply to mills and preventing
unhealthy competition to procure sugarcane;
(ii) ensuring crushing of the entire quantity of cane grown by
sugarcane farmers in the reserved area, with no cane
remaining uncrushed at the end of the season; and
(iii) increasing the productivity of sugarcane cultivation so as to
increase the income of farmers and enhance supplies and
sugar recovery for mills.
xxx xxx xxx
2.5 Those who suggest that the reservation of cane area be
done on a permanent basis argue that the system facilitates
sugar factories to undertake cane development work in
38
their respective areas. This argument of the industry may
be true in some selected pockets, but appears fallacious
when one looks at the trends of sugarcane productivity in
the country. Cane productivity was 68.57 tonnes/ha in 2000-
01 and stood at about the same level in 2010-11 (68.59
tonnes/ha), marginally declining thereafter to 68.09
tonnes/ha in 2011-12. Thus, for the country as a whole,
cane area reservation does not seem to have promoted
productivity.
xxx xxx xxx
2.7 Those in favour of scrapping the cane area reservation
reiterate the views of the Thorat Committee (2009). The
present system ties farmers to supply cane to a particular
mill whether or not s/he is satisfied with it. The moot
question is whether a farmer should remain “bonded” and
supply cane to a particular mill even if it has not made
payment for her/his earlier supplies. There is a case for
dispensing with cane area reservation and giving freedom
to the farmers to supply their cane to any mill of their
choice. There is no cane area reservation system in
Maharashtra and non-members of cooperative mills are free
to supply cane to any mill which they like.
2.8 The system of cane area reservation and maintaining a
minimum distance between mills has been shielding them
from competition and has created perpetual monopolies.
This policy does not allow a farmer to participate in a
competitive market and get the best price for her/his cane.
The farmer has no freedom to choose the buyer and is
more likely to get delayed payments and unfair price for
the cane than in a competitive set up. Thus, these policies
have led to the continued functioning of inefficient sugar
mills by giving them a guaranteed supply of cane and by
not allowing market forces to work towards a viable
equilibrium. For the growth of the sector and in the interest
of efficiency in this industry, policy should allow the
Schumpeterian “process of creative destruction” to work.”
49. The Ministry of Consumer Affairs, Food and Public Distribution has
referred to recommendations of Dr. C. Rangarajan Committee. The gist
39
of the recommendations of the Committee and Implementation of
Recommendations of Dr. Rangarajan Committee, is as under:
| Issues | Gist of Recommendations | Status |
|---|
| Cane Area<br>Reservation: | Over a period of time, states<br>should encourage development<br>of such market-based long-term<br>contractual arrangements, and<br>phase out cane reservation<br>area and bonding. In the<br>interim, the current system<br>may continue. | States have been<br>requested to consider<br>the recommendations<br>for implementation as<br>deemed fti . So far,<br>none of the States<br>have taken action,<br>current system<br>continues |
| Minimum<br>Distance<br>Criteria: | It is not in the interest of<br>development of sugarcane<br>farmers or the sugar sector, and<br>may be dispensed with as and<br>when a State does away with<br>cane reservation area and<br>bonding. | States have been<br>requested to consider<br>the recommendations<br>for implementation as<br>deemed fti . There is<br>no reservation of area<br>in Maharashtra. Rest<br>of the States have not<br>made any changes in<br>the current<br>arrangement. |
50.
We also note the reasoning given by the Central Government that in
order to avoid unhealthy competition, the licensing under the
Industries (Development and Regulation) Act, 1951 was done away
with on 31.08.1998. Unhealthy competition has two major aspects- one
relating to the existing and new sugar factory, and second in the
context of the farmers. On account of competition between the existing
and new sugar factory, it would be the farmers who will be the
beneficiary as they would have an option to select the sugar mill which
provides better service in the manner of payment of price. Keeping in
40
view the recommendations of the Rangarajan Committee and the fact
that the Central Government has exercised its jurisdiction to grant
extension in time, the ultimate beneficiary would be the farmer and not
the existing or the new sugar factory.
51. Thus, we find the order of the High Court to be unsustainable.
Consequently, the appeals are allowed and the writ petitions are
dismissed. The period spent in the second round of litigation shall also
be excluded while determining the period during which the plant had
to be set up and to commence commercial production.
.............................................J.
(HEMANT GUPTA)
.............................................J.
(V. RAMASUBRAMANIAN)
NEW DELHI;
JULY 13, 2022.
41