Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 13
PETITIONER:
KAMALUDDIN ANSARI & CO.
Vs.
RESPONDENT:
UNION OF INDIA
DATE OF JUDGMENT12/08/1983
BENCH:
MISRA, R.B. (J)
BENCH:
MISRA, R.B. (J)
DESAI, D.A.
ERADI, V. BALAKRISHNA (J)
CITATION:
1984 AIR 29 1983 SCR (3) 607
1983 SCC (4) 417 1983 SCALE (2)107
CITATOR INFO :
F 1989 SC1498 (28)
ACT:
Arbitration Act, 1940 - cls. (a) and (b) of s. 41-
Interpretation of-Court has power under cl. (b) to issue
interim injunctions only for the purpose of and in relation
to the arbitration proceedings before the Court.
Contracts with Government of India-cl. 18 of Standard
Form of Contract -Interpretation of- Whether for fulfillment
of a claim for payment of a sum of money arising under a
contract the Government has power to withhold sum due under
other contracts ?.
Interpretation- ’Headings’ cannot be used to give
different effect to clear words in the section.
HEADNOTE:
The DGS&D, representing the Government of India, had
entered into a contract with the appellant firm for supply
of some timber. Clause 18 of the standard form of contract,
under the head "Recovery of sums due", provided inter alia
that whenever any claim for payment of a sum of money arose
out of or under the contract against. the contractor, the
purchaser shall be entitled to recover such sum by
appropriating any sum then due or which at any time
thereafter may become due to the contractor under any other
contract with the purchaser. Clause 24 thereof provided for
arbitration in the event of any dispute arising between the
parties. The appellant failed to supply the timber. The
DGS&D cancelled the contract, made risk purchases at extra
cost and issued notice calling upon the appellant to pay the
extra cost incurred and threatening to withhold the amount
from the payments due under the pending bills of other
contracts. The appellant moved a petition under s. 33 of the
Arbitration Act, 1940 alleging that there was no concluded
contract in existence between the parties, containing any
arbitration clause and praying for an injunction restraining
the Union of India from appropriating, withholding or
recovering the amount claimed from its other bills. The High
Court held that under s. 41 of the Act it could only grant
an injunction restraining the Union of India from
appropriating or recovering the amount of damages claimed
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 13
from the other pending bills of the appellant, and rejected
the prayer for grant of injunction restraining the Union of
India from withholding payments of the other pending bills.
Dismissing the appeal,
^
HELD: 1. Clause 18 of the standard form of contract
confers ample power upon the Union of India to withhold the
amount and no injunction
608
order could be passed restraining the Union of India from
withholding the amount [623 B]
(i) The golden rule of construction is that when the
words of a statute are clear, plain and unambiguous, that
is, they are reasonably susceptible to only one meaning, the
Courts are bound to give effect to that meaning irrespective
of the consequences. ’The duty of a judge is to expound and
not to legislate a is fundamental rule. If this principle is
applied to the interpretation of cl. 18 of the standard form
of contract it would be clear that the clause unequivocally
contemplates a claim for payment. It does not contemplate
the amount due and, therefore, the heading of this clause
which talks of only ’Recovery of sums due’ will not control
cl. 18. Headings cannot be used to give a different effect
to clear words in the section where there cannot be any
doubt as to the ordinary meaning of the words. The clause
gives wide powers to the Union of India to recover the
amount claimed by appropriating any sum then due or which at
any time thereafter may become due to the contractor under
other contracts. [620 A-G]
(ii) Clause 18 was slightly differently worded earlier
when it read ’whenever under this contract any sum of money
is recoverable from and payable by the contractor’. But this
formula was deliberately and advisedly altered when the
present standard form was introduced by substituting the
words ’whenever any claim for payment of a sum of money
arises’ and this change in phraseology indicated that in
order to attract the applicability of the present cl. 18, it
was not necessary that there should be a sum of money due
and payable by the contractor to the purchaser, but it was
enough if there was a mere claim on the part of the
purchaser for payment of a sum of money by the contractor
irrespective of the fact whether such sum of money was
presently due and payable or not. Even after the change in
the language of cl 18 the Union of India cannot be injuncted
from withholding the amount under other bills of the
contractor. But it can certainly be injuncted from
recovering or appropriating it to the damages claimed. [620
H-621A, G]
Union of India v. Raman Iron Foundry, [1974] 3 S.C.R.
556 overruled.
2. An injunction order restraining the Union of India
from withholding the amount due to the contractor under
other pending bills virtually amounts to a direction to pay
the amount to the contractor-appellant. Such an order was
beyond the purview of cl. (b) of s. 41 of the Arbitration
Act. [621 H-622 A]
(i) Clause(b) of s. 41 confers power on the court to
pass orders in respect of any of the matters set out in the
Second Schedule which inter alia includes ‘interim
junction’. But this power to pass an order of injunction can
only be excercised ’for the purpose of and in relation to
arbitration proceedings’ before the Court. [61 5H]
In the instant case the proceedings before the Court
were pursuant to an application made under s. 33 of the Act
in which the appellant had taken the stand that there was no
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 13
concluded contract between the parties containing an
arbitration clause. Therefore, it is difficult to say that
the
609
application for injunction moved by the appellant was for
the purpose of and in relation to arbitration proceedings.
That apart, the amount due to the appellant under the
pending bills was not the subject-matter of the present
proceedings and, therefore, the injunction order restraining
the respondent from withholding the amount due to the
appellant under the pending bills in respect of other
contracts could not be said to be for the purpose of and in
relation to the present arbitration proceedings. [616 A, C,
617 A-B]
Union of India v. Raman Iron Foundry [1974] 3 S.C.R.
556, referred to.
Mohan Meaken Breweries v. Union of India, A.I.R. 1975
Delhi 248, approved.
(ii) The contention that cl. (a) of s. 41 makes the
Code of Civil Procedure applicable to all proceedings before
the Court and to all appeals under the Act and, therefore,
the appellant was entitled lo invoke o. 39 of the Code to
get an injunction order even if the conditions of cl. (b) of
s. 41 were not satisfied cannot be accepted. Clause (a) of
s. 41 makes only the procedural rules of the Code applicable
to the proceedings in court under the Arbitration Act. This
clause does not authorise the court to pass an order of
injunction. If the above contention is accepted, appeals
would lie under ss. 96, 100 or 104 of the Code. But the Act
itself provides for appeal under s. 39. Besides, if cl, -(a)
of s. 41 gave wide powers to pass all order of injunction,
cl. (b) of s. 41 would become otiose. [616 D-F]
(iii) If an order injuncted a party from withholding
the amount due to the other side under pending bills in
other contracts, the order necessarily means that the amount
must be paid. It will be a contradiction in terms to say
that a party is injuncted from withholding the amount and
yet it can withhold the amount as of right. In any case if
the injunction order is one which a party was not bound to
comply with, the Court would he loath and reluctant to pass
such an ineffective injunction order. In injunction order is
passed only for the purpose of being carried out. [618 D-E]
Union of India v. Raman lron Foundry, [1974] 3 S.C.R.
556; observations to the contrary held inconsistent with the
law laid down in the case.
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 2853
and 2863 of 1982.
From the Judgment and order dated the 24th January,
1980 of the Allahabad High Court in Civil Revision No. 3452
of 1978.
D.C. Singhania, Raju Ramachandran, Muhul Mudgal, JP
Gupta for the appellant in C.A. No. 2854/82.
S.N. Kacker, D.C. Singhania, Raju Ramachandran, Mukul
judgal J.P. Gupta for the appellant in C.A. No. 2863/82.
610
KG. Bhagat Addl. Solicitor General for the respondent
in C.A. No. 2853/82.
Girish Chandra, C. V. Subba Rao and R.N. Poddar for
respondent in C.A. No. 2863/82.
The Judgment of the Court was delivered by
MISRA J. These two connected appeals by special leave
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 13
are directed against the judgment and order of the Allahabad
High Court and Delhi High Court dated 24th January, 1980 and
13th November, 1979 respectively. The first one arises out
of proceedings under s 20 of the Arbitration Act while the
other arises out of proceedings under s. 33 of the
Arbitration Act.
These appeals raise a common question regarding the
inter pretation of cl. 18 of the general conditions of
contract contained in the standard from of contract entered
into by the parties and the ambit and scope of s. 41 of the
Arbitration Act. The facts giving rise to these appeals
follow a common pattern and it would, therefore, be
sufficient if we set out the facts relating to Civil Appeal
No. 2863 of 1982 to bring out clearly the points which arise
for consideration in these appeals.
The appellant in this appeal is a registered firm and
carries on the business of manufacturing and selling timber.
The Directorate General of Supplies and Disposals (for
short, DGS&D) functions as a purchase organisation for the
Government of India and makes purchases for various
departments. In response to an invitation for tender by the
DGS&D for the supply of Bijasal logs first class the
appellant firm made an offer to supply 1016 cubic metres at
a flat rate of Rs. 669 per cubic metre. The DGS&D accepted
the tender on 24th of December, 1973. Pursuant to the
acceptance of the tender a standard form of contract was
drawn up containing various clauses. Two important clauses
of that standard from of contract with which we are mainly
concerned are cls; 18 and 24, which read:
"18. Recovery of Sums Due: Whenever any claim
for the payment of a sum of money arises out of or
under the contract against the contractor, the
purchaser shall be entitled to recover such sum by
appropriating in whole or in part, the security,
if any, deposited by the contrac-
611
tor, and for the purpose aforesaid, shall be
entitled to sell and/or realise securities forming
the whole or part of any such security deposit. In
the event of the security being insufficient, the
balance and if no security has been taken from the
contractor, the entire sum recoverable shall be
recovered by appropriating any sum then due or
which at any time thereafter may become due to the
contractor under the contract or any other
contract with the purchaser or the Government or
any person contracting through the Secretary. If
such sum even be not sufficient to cover the full
amount recoverable, the contractor shall on demand
pay to the purchaser the balance remaining due
........."
"24. Arbitration: In the event of any
question, dispute or difference arising under
these conditions or any special conditions of
contract, or in connections with this contract
(except as to any matters the decision of which is
specially provided for by these or the special
conditions) the same shall be referred to the sole
arbitration of any officer in the Ministry of Law,
appointed to be the arbitrator by the Director
General of Supplies and Disposals. It will be no
objection that the arbitrator is a Government
servant, that he had to deal with the matters to
which the contract relates or that in the course
of his duties as a Government servant he has
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 13
expressed views on all or any of the matters in
dispute or difference. The award of the arbitrator
shall be final and binding on the parties to this
contract."
The appellant, however, ailed to supply the goods. The
contract was cancelled on 28th of August, 1974 at the risk
and cost of the appellant. The DGS&D claims to have made
risk purchases incurring an extra cost of Rs. 92,364. By
notice dated 27th December, 1974 the DGS&D called upon the
appellants to pay that amount failing which alternating
arrangements would be made to recover the same.
It appears that there were some other contracts between
the appellant and the respondent whereunder the appellant
has supplied goods and payments were due to it under pending
bills.
The appellant firm moved a petition under s 33 of the
Arbitration Act before the court alleging that there was no
concluded
612
contract in existence between the parties containing any
arbitration clause and prayed inter alia for determining
the. existence, validity and effect of the alleged
arbitration agreement. The stand of the Union of India on
the other hand is that there was a concluded contract
between the parties and the appellant firm was bound by the
acceptance of the tender.
As the Union of India threatened to withhold the amount
of Rs. 92,364 from the payments due under the pending bills
of other contracts, the appellant firm sought for an
injunction. Under s. 41 read with Second Schedule of the
Arbitration Act, and o. 39, rr. 1 and 2 read with s. 151 of
the Code of Civil Procedure, restraining the respondents
from appropriating, withholding or recovering the amount
claimed from its other bills in any manner whatsoever.
As there was cleavage of opinion between the Judges of
the same High Court on the question whether such an
injunction as prayed for could be issued under s. 41 of the
Arbitration Act, the learned Single Judge referred the
matter to a larger Bench. The learned Single Judge’s own
view was that such an injunction could be issued under s.
41. The Division Bench on reference, however, held that the
Court could grant an injunction restraining the respondent
from appropriating or recovering the amount of damages
claimed from appellant’s other pending bills, but No order
restraining the Union of India from withholding payments of
the other pending bills could be issued under s. 41 of the
Arbitration Act in as much as it would amount to a direction
to pay the amount due Under other bills and such a prayer
would virtually amount to seeking a relief for decreeing the
claim of the appellant in Those contracts. The appellant has
come up before this Court against this order by special
leave, as stated earlier.
It appears that a large number of applications under s.
33 of the Arbitration Act had been moved in Delhi High Court
in similar matters. In some of the cases injunctions were
also issued by the learned Single- Judge restraining the
respondents from recovering, appropriating or withholding
the amount from other bills of the contractors. One of these
matters Union of India v. Air Foam Industries was taken to
this Court, which was decided by the Court along with Union
of India v. Raman lron Foundry.(1) In that case
613
the Union of India put forward the extreme claim that by
virtue of cl. 18 of General Conditions of Contract it was
entitled to recover damages claimed by appropriating any sum
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 13
which may become due to the contractor under other pending
bills from the Union of India. This Court, however,
negatived the plea on the ground that the amount of damages
claimed by the Union was only a claim and unless there was
adjudication of the claim by Court or admission by the
contractor the Union of India had no authority to
appropriate the amount due under pending bills of the
contractor towards the satisfaction of its claim for
damages.
While construing the scope of s. 41 (b) of the
Arbitration Act this Court held:
"The Court has, therefore, power under s. 41
(b) read with Second Schedule to issue interim
injunction, but such interim injunction can only
be "for the purpose of and in relation to
arbitration proceedings". The arbitration
proceedings in the present case were for
determination of the mutual claims of the
appellant and the respondent arising out of the
contract contained in the acceptance of tender
dated 16th July, 1968. The question whether any
amounts were payable by the appellant to the
respondent under other contracts was not the
subject matter of the arbitration proceedings. The
Court obviously could not, therefore, make an
interim order which, though ostensibly in form an
order of interim injunction, in substance amounted
to a direction to the appellant to pay the amounts
due to the respondent under other contracts. Such
an interim order would clearly not be for the
purpose of or in relation to the arbitration
proceedings as required by s. 41 (b)."
Having laid down the above dictum on the interpretation
of s. 41 of the Arbitration Act this Court proceeded to
analyse the impugned order of injunction in that case. In
its opinion the order of injunction did not expressly or by
necessary implication carry any direction to the Union of
India to pay the amounts due to the respondent under other
contracts. It is not only in form but also in substance a
negative injunction. It has no positive content. What it
does is merely to injunct the appellant from recovering suo
motu the damages claimed by it from out of the pending bills
of the
614
respondent. It does not direct that the appellant shall pay
such amounts to the respondent. The appellant Union of India
can still refuse to pay such amounts if it thinks it has a
valid defence and if the appellant does so, the only remedy
to the respondent would be to take measures in an
appropriate forum for recovery of such amounts, where it
would be decided whether the appellant is liable to pay such
amounts to the respondent or not. No breach of the order of
interim injunction as such would be involved in nonpayment
of such amounts by the respondent to the appellant. The only
thing which the appellant is interdicted from doing is to
make recovery of its claim for damages by appropriating such
amounts in satisfaction of the claim. That is clearly within
the power of the Court under s. 41 (b) because the claim for
damages forms the subject matter of the arbitration
proceedings and. the Court can always say that until such
claim is adjudicated upon, the appellant shall be restrained
from recovering it by appropriating other amounts due to the
respondent. The order of interim injunction made by the
learned Judge cannot, therefore, be said to be outside the
scope of his power under s. 41 (b) read with the Second
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 13
Schedule.
Following this judgment of the Supreme Court the Delhi
High Court started modulating its injunctions accordingly
and refused to include the word "withholding" in the order
of injunction on the ground that the order in those terms
really Would mean an order to make the payment which was
specifically forbidden in terms of the above judgment of
this Court.
As some doubt was raised in the Delhi High Court as to
the exact scope of the ratio of the Union of India v. Raman
Iron Foundry (supra) the matter was referred to a full Bench
apparently to reconsider the earlier Division Bench
judgments in Marwar Tent Factory v. Union of India(1) and
Air Foam Industries v. Union & India.(2) The full Bench
Mohan Meakin Breweries v. Union of India(3) took the view
that though an injunction could be granted in those matters
restraining the Union of India from adjusting of recovering
any damages claimed by it from other pending bills of the
contractor no order of injunction restraining the Union of
India from withholding the payments due to the contractor
under other pending bills could be issued.
615
Following the Full Bench decision the Division Bench in
the present case held that the Court in arbitration
proceedings was not competent to issue an injunction
restraining the Union of India from withholding the amount
due to the appellant-contractor under other pending bills.
The only remedy of the appellant is to proceed outside the
arbitration proceedings for the payments due under the
pending bills, from the respondent. The Court can, however,
restrain the Union of India from recovering or appropriating
the amount due to the appellant-contractor under pending
bills towards the damages claimed by the Union, unless it
has been adjudicated upon or admitted by the other side.
The first question that falls for consideration in this
appeal is about the exact scope and ambit of s. 41 of the
Arbitration Act It will be appropriate at this stage to read
s. 41 in order to appreciate the contention raised on behalf
of the appellant:
"41. Procedure and powers of Court:- Subject
to the provisions of this Act and of rules made
thereunder-
(a) the provisions of the Code of Civil
Procedure, 1908 shall apply to all
proceedings before the Court, and to all
appeals, under this Act, and
(b) the Court shall have, for the purpose
of, and in relation to, arbitration
proceeding, the same power of making
orders in respect of any of the matters
set out in the Second Schedule as it has
for the purpose of, and in relation to,
any proceedings before the Court:-
provided that nothing in clause (b) shall be
taken to prejudice any power which may be vested
in an arbitrator or umpire for making orders with
respect to any of such matters."
In view of cl. (b) of s. 41 the Court has been given power
of passing orders in respect of any of the matters set out
in second Schedule for the purpose of and in relation to any
proceedings before the Court. The Second Schedule of the
Arbitration Act inter alia includes ‘interim injunction’ and
the ’appointment of receiver’. But the Court has got the
power to pass an order of injunction only ’for the purpose
of and in relation to arbitration proceedings’ before the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 13
Court.
616
The proceedings before the Court in the instant case
was an application under s. 33 of the Arbitration Act.
Section 33 of the Arbitration Act in so far as material for
the case, provides:
"33. Any party to an arbitration agreement or
any person claiming under him desiring to
challenge the existence or validity of an
arbitration agreement or an award or to have the
effect of either determined shall apply to the
Court and the Court shall decide the question on
affidavits."
The appellant in the instant case took the stand that
there was no concluded contract between the parties
including arbitration. Therefore, the order of injunction
passed in the instant case could not be for the purpose of
and in relation to arbitration proceedings. Faced with this
difficulty Shri S. N. Kacker, learned counsel for the
appellant, fell back upon cl. (a) of s. 41 to contend that
cl. (a) makes the Code of Civil Procedure applicable to all
proceedings before the Court and to all appeals under the
Act and, therefore, the appellant was entitled to invoke
order 39 of the Code to get an injunction order even if the
conditions of cl. (b) of s 41 were not satisfied. We are
afraid this contention cannot be accepted.
Clause (a) of s. 41 makes only the procedural rules of
the Code of Civil Procedure applicable to the proceedings in
Court under the Arbitration Act. This clause does not
authoritse the Court to pass an order of injunction. The
power is conferred by cl. (b) of s. 41. The source of power,
therefore, cannot be traced to cl. (a). If the contention of
Shri Kacker is accepted, the appeals would lie under ss. 96,
100 or 104 of the I.P.C. but the Arbitration Act itself
provides for appeal under s. 39. Besides, if cl.(a) of s.41
gave wide powers to pass an order of injunction, cl. (b) of
s.41 would become otiose.
The learned counsel for the appellant, however,
contends that the arbitration proceedings relate to the
claim for damages by the Union of India. Any act of the
Union of India which purports to enforce the said claim for
damages, before it has been duly adjudicated upon in
arbitration proceedings is an act which relates to such
arbitration proceedings.
On the own case of the appellant that there was no
concluded contract between the parties containing an
arbitration clause it will
617
be difficult to say that the application for injunction
moved by the appellant was for the purpose of and in
relation to arbitration proceedings. This apart, the amount
due under the pending bills to the appellant was not the
subject matter of the present proceedings and, therefore,
the injunction order restraining the respondents from
withholding the amount due to the appellant under the
pending bills in respect of other contracts could not be
said to be for the purpose of and in relation lo the present
arbitration proceedings. In this view of the matter it was
not open to the Court to pass the interim injunction
restraining the respondents from withholding the amount due
to the appellant under pending bills in respect of other
contracts.
The learned counsel Shri Kacker, however, strongly
relied on the following observations of the Court in Union
of India v. Raman Iron Foundry (supra):
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 13
"But here the order of interim injunction
made by the learned Judge does not, expressly or
by necessary implication carry any direction to
the appellant to pay the amounts due to the
respondent under other contracts. It is not only
in form but also in substance a negative in
Junction. It has no positive content. What it does
is merely to injunct the appellant from
recovering, suo moto, the damages claimed by it
from out of other amounts due to the respondent.
It does not direct that the appellant shall pay
such amounts to the respondents. The appellant can
still refuse to pay such amounts if it thinks it
has a valid defence and if the appellant does so,
the only remedy open to the respondent would be to
take measures in an appropriate forum for recovery
of such amounts where it would be decided whether
the appellant is liable to pay such amounts to the
respondent or not. No breach of the order of
interim injunction as such would be involved in
non-payment of such amounts by the appellant to
the respondent. The only thing which the appellant
is interdicted from doing is to make recovery of
its claim for damages by appropriating such
amounts in satisfaction of the claim. That is
clearly within the power of the Court under s. 41
(b) because the claim for damages forms the
subject matter of the arbitration proceedings and
the Court can always say that until such claim is
adjudicated upon, the appellant
618
shall be restrained from recovering it by
appropriating other amounts due to the respondent.
The order of interim injunction made by the
learned judge cannot, therefore, be said to be
outside the scope of his power under s. 41 (b)
read with the Second Schedule".
With profound respect we find that the aforesaid observation
is incongrous with the proposition of law laid down by this
Court just before this observation. We find it difficult to
agree with the observation of the Court that the impugned
order in form and substance being the negative the
respondent could refuse to pay such amounts if it thinks it
has a valid defence, and if it chooses to do so there would
be no breach of the injunction order.
It is true that the order of injunction in that case
was in negative form. But if an order injuncted a party from
withholding the amount due to the other side under pending
bills in other contracts, the order necessarily means that
the amount must be paid. If the amount ii withheld there
will be a defiance of the injunction order and that party
could be hauled up for infringing the injunction order. It
will be a contradiction in terms to say that a party is
injuncted from withholding the amount and yet it can
withhold the amount as of right. In any case if the
injunction order is one which a party was not bound to
comply with, the Court would be loath and reluctant to pass
such an ineffective injunction order. The court never passes
an order for the fun of passing it. It is passed only for
the purpose of being carried out. Once this Court came to
the conclusion that the Court has power under s. 41 (b) read
with Second Schedule to issue interim injunction but such
interim injunction can only be for the purpose of and in
relation to arbitration proceedings and further that the
question whether any amounts were payable by the appellant
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 13
to the respondent under other contracts, was not the subject
matter of the arbitration proceedings and, therefore, the
Court obviously could not make any interim order which
though ostensibly in form an order of interim injunction, in
substance amount to a direction to the appellant to pay the
amounts due to the respondent under other contracts, and
such an order would clearly be not for the purpose of and in
relation to the arbitration proceedings; the subsequent
observation of the Court that the order of injunction being
negative in form and substance, there was no direction to
the respondent to pay the amount due to the appellant under
pending bills of other contracts, is manifestly inconsistent
with the proposition of law laid down by this Court in the
same case.
619
This leads us to the question of interpretation of cl.
18 of tho standard contract. Clause 18 has been quoted in
extenso in the earlier part of the judgment.
The argument by Shri K. G. Bhagat, Addl. Solicitor
General on behalf of the Union of India is that what is
required for attracting the applicability of cl. 18 is a
mere claim for payment of a sum of money arising out of or
under the contract against the contractor and it is not
necessary that a sum of money must be actually due and
payable from the contractor to the purchaser. According to
him, if the purchaser has a claim for payment of a sum of
money against the contractor, he would be entitled to
exercise the right given under cl. 18, even though such a
claim may not be for a sum due and payable but may be for
damages and it may be disputed by the contractor and may not
have been adjudicated upon in a Court of law or by
arbitration. Shri Bharat further submits that if the claim
of the purchaser is not well founded and the appropriation
made by the Union of India is unjustified, the contractor
can always institute a suit or start arbitration proceedings
for recovering the sums due to him which have been wrongly
appropriated by the purchaser and in such suit or
arbitration proceedings, the court or the arbitrator, as the
case may be, would examine the validity of the claim against
which appropriation has been made by the purchaser and if
the claim is found to be unsustainable, set at naught the
appropriation and pass a decree or award for the sums due to
the contractor. But the court cannot and should not restrain
the Union of India from exercising its right of
appropriation merely because the claim against which
appropriation is sought to be made by the purchaser is
disputed by the contractor and is pending adjudication
before a court of law or arbitrator.
Shri Kacker on the other hand contends that though the
words used in the opening part of cl. 18 are "any claim for
the payment of a sum of money", which are general words of
apparently wide amplitude sufficient to cover even a claim
for damages arising out of the contract, a proper
construction of the clause read as a whole clearly suggests
that these words are intended to refer only to a claim for a
sum due and payable and do not take in a claim for damages
which is disputed by the contractor. It is only when a claim
for damages is adjudicated upon by a civil court or an
arbitrator and the breach of the contract is established and
the amount of damages ascertained and decreed that a debt
due and payable comes into
620
existence; till then it is nothing more than a mere right to
sue for damages, and it does not fall within the words of
cl. 18. Moreover, cl. 18 merely provides a mode of recovery
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 13
and it can have no application where a claim, even though it
be for a sum due and payable, is disputed by the contractor
and has to be established in a court of law or by
arbitration. Clause 18 applies only where a claim is either
admitted, or in case of dispute, substantiated by resort to
the judicial process. Therefore, when a purchaser has a
claim for damages which is disputed by the contractor, the
purchaser is not entitled under cl. 18 to recover the amount
of its claim for damages by appropriating other sums due to
the contractor until the claim for damages is adjudicated
upon and culminates in a decree. The respondent had
consequently no right under cl. 18 to appropriate sums due
to the appellant under other contracts in satisfaction of
its claim for damages against the appellant, when the claim
for damages was pending adjudication
This Court in Union v. Raman Iron Foundry (supra) while
construing cl. 18 of the standard contract observed:
"It is true that the words "any claim for the
payment of a sum of money" occurring in the
opening part of cl. 18 are words of great
amplitude, wide enough to cover even a claim for
damages, but it is a well settled rule of
interpretation applicable alike to instruments as
to statutes that the meaning of ordinary words is
to be found not so much in strict etymological
propriety of language nor even in popular use as
in the subject or occasion on which they are used
and the object which is intended to be attained.
The context and collocation of a particular
expression may show that it was not intended to be
used in the sense which it ordinarily bears.
Language is at best an imperfect medium of
expression and a variety of meanings may often lie
in a word or expression. The exact colour and
shape of the meaning of any word or expression
should not be ascertained by reading it in
isolation, but it should be read structurally and
in its context, for its meaning may vary with its
contextual setting. We must, therefore, read the
words ’any claim for the payment of a sum of
money’ occurring in the opening part of cl. 18 not
in isolation but in the context of the whole
clause, for the intention Of the parties is to be
gathered not from one part of the
621
clause or the other but from the clause taken as a
whole. It is in the light of this principle of
interpretation that we must determine whether the
words ’any claim for the payment of a sum of
money’ refer only to a claim for a sum due and
payable which is admitted or in case of disputes,
established in court of a law or by arbitration or
they also include a claim for damages which is
disputed by the contractor."
The headings prefixed to a section or a group of
sections in some modern statutes are regarded as preambles
to those sections. They cannot control the plain words of
the statutes but they may explain ambiguous words. The view
is now well settled that the headings or titles prefixed to
a section or a group of sections can be referred to in
determining the meaning of doubtful expressions. It is true
that the court is entitled to look at the headings in an Act
of Parliament to resolve any doubt they may have as to
ambiguous words. The law is clear that those headings cannot
be used to give a different effect to clear words in the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 13
section where there cannot be any doubt as to the ordinary
meaning of the words. The golden rule is that when the words
of a statute are clear, plain and unambiguous, that is, they
are reasonably susceptible to only one meaning, the courts
are bound to give effect to that meaning irrespective of the
consequences. The duty of a Judge is to expound and not to
legislate, is a fundamental rule. If we apply the same
principle to the interpretation of cl. 18 of the standard
form of contract, it would be clear that the clause
unequivocally contemplates a claim for the payment and it is
open to the Union of India to appropriate any amount due to
the contractor under other pending bills. It does not
contemplate the amount due and, therefore, the heading of
this clause which talks of only ’Recovery of sum due’ will
not control cl. 18. The clause in our opinion gives wide
powers to the Union of India to recover the amount claimed
by appropriating any sum then due or which at any time
thereafter may become due to the contractor under other
contracts.
Clause 18 of the standard form of contract earlier was
slightly differently worded and it read ’whenever under this
contract any sum of money is recoverable from and payable by
the contractor’. But this formula was deliberately and
advisedly altered when the present standard form was
introduced and instead the words ’whenever any claim for
payment of a sum of money arises’ were substituted and this
change in phraseology indicated that in order
622
to attract the applicability of the present cl. 18, it was
not necessary that there should be a sum of money due and
payable by the contractor to the purchaser, but it was
enough if there was a mere claim on the part of the
purchaser for payment of a sum of money ’t by the contractor
irrespective of the fact whether such sum of money was
presently due and payable or not. This Court, however, did
not attach importance to this aspect of the matter by
observing:
"We do not think it is legitimate to construe
cl. 18 of the contract between the parties by
reference to a corresponding clause which
prevailed in an earlier standard form of contract.
This is not a statute enacted by the legislature
where it can be said that if the legislature has
departed from the language used by it in an
earlier enactment, it would be a fair presumption
to make that the alteration in the language was
deliberate and it was intended to convey a
different meaning. It is a clause in a contract
which we are construing and there any reference to
a similar or dissimilar clause in another contract
would be irrelevant.
The Court itself while interpreting cl. 18 of the
contract has observed:
"It is true that the words "any claim for the
payment of a sum of money" occurring in the
opening part of cl. 18 are words of great
amplitude, wide enough to cover even a claim for
damages, but it is well settled rule of
interpretation applicable alike to instruments as
to statutes .......".
But while dealing with another aspect of cl. 18 observed to
the contrary that it should not be construed as a statute.
It may, however, be pointed out that even after the change
in the language of cl. 18 of the standard agreement the
Union of India cannot be injuncted from withholding the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 13
amount under other bills of the contractor. But it can
certainly be injuncted from recovering or appropriating it
to the damages claimed.
Shri D. C. Singhania appearing along with Shri Kackar
substantially reiterated the same argument in his written
note.
We are clearly of the view that an injunction order
restraining respondents from withholding the amount due
under other pending
623
bills to the contractor virtually amounts to a direction to
pay the amount to the contractor-appellant. Such an order
was clearly beyond the purview of cl. (b) of s. 41 of the
Arbitration Act. The Union of India has no objection to the
grant of an injunction restraining it from recovering or
appropriating the amount Lying with it in respect of other
claims of the contractor towards its claim for damages. But
certainly cl. 18 of the standard contract confers ample
power upon the Union of India to withhold the amount and no
injunction order could be passed restraining the Union of
India from withholding the amount.
We find no error in the impugned order passed by the
Allahabad or the Delhi High Courts in the two cases. The
appeals, therefore, must fail and they are accordingly
dismissed. In the circumstances of the case, however, we
direct that the parties should bear their own costs.
H.L.C. Appeals dismissed.
624