Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
CASE NO.:
Appeal (civil) 4329 of 2003
PETITIONER:
Moradabad Development Authority
RESPONDENT:
Saurabh Jain and Ors
DATE OF JUDGMENT: 28/09/2007
BENCH:
Dr. ARIJIT PASAYAT & LOKESHWAR SINGH PANTA
JUDGMENT:
J U D G M E N T
CIVIL APPEAL NO. 4329 OF 2003
(With Contempt Petition No.239 of 2005)
Dr. ARIJIT PASAYAT, J.
1. Challenge in this appeal is to the judgment of a Division
Bench of the Allahabad High Court allowing the Writ Petition
(CMWP No.30433/2002) filed by respondents 1, 2 and 3.
2. Challenge in the writ petition was to the order passed by
the State Government dated 23.11.2001 Annexure-6 to the
writ petition and orders dated 11.12.2001 and 15.4.2002
Annexures 7 and 8 respectively passed by the appellant-
Moradabad Development Authority. The writ petitioners had
also prayed for a mandamus to direct the respondents in the
writ petition to forthwith return to the writ petitioners
possession of the land measuring 8116.65 sq. mtrs. of plot
No.454 situated in village Harthala Mustahkam Tehsil, District
Moradabad.
3. Background facts as highlighted in the writ petition were
that the proceedings under the Urban Land (Ceiling and
Regulation) Act, 1976 (in short the ’Act’) were initiated and in
the connected proceedings the land in question was declared
to be surplus land by the competent authority, Moradabad by
order dated 29.8.1977. A Revision was filed against the said
order and the State Government in exercise of power under
Section 34 of the Act by order dated 9.7.1998 held that the
land in dispute was agricultural land and was thus outside
the purview of the Act. Hence, land was directed to be released
in favour of the land holders. The matter was referred to the
State Government. Restoration of possession was demanded
since the appellant authority had taken possession of the land
in dispute and had developed a residential colony. The State
Government had detailed deliberation with the appellant
authority which informed that it had developed a residential
colony called Ram Ganga Vihar Colony and had allotted the
flats and houses to the allottees. The appellant authority sent
proposal for acquisition of the land but it was not acceptable
to the Government. However, the appellant authority proposed
to return 3605 sq.mts. of land which had not still been
transferred. By order dated 23.11.2001 the State Government
directed the appellant authority to return the land in question.
However, it directed that the development charges and cost of
construction over the area were to be charged from the writ
petitioners. But the State Government did not give any
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
direction regarding the balance 4511 sq. mtrs. out of the total
land.
4. Appellant authority on the basis of the aforesaid order of
the Government demanded Rs.62,24,534/- as development
charges and cost of construction in respect of the area
measuring 2312-82 sq. mtrs.
5. Stand in the writ petition was that in view of the order of
the State Government dated 9.7.1998, the decision of the
appellant authority could not claim any lawful title. The
appellant authority it was contended was duty bound to
restore the possession of the land to the respondents, and
since it did not do so the respondents were suffering huge
losses.
6. Stand of the appellant in the writ petition was that
possession of the land was delivered to it in June 1989 and at
that time it was surplus land under the Act. In the intervening
period residential colony was developed and many flats and
houses have been allotted and transferred to various persons.
7. The High Court had held that submissions of
respondents 1, 2 and 3 regarding the consent for the
development charges were not believable. There was no
specific reference to this aspect in the counter affidavit filed. If
it was really so, it should have found place in the counter
affidavit. It was held that demand for development charges
was illegal, arbitrary and unjustified. Accordingly, the writ
petition was allowed. The State Government and the appellant
authority were directed to give possession of the land
measuring 4511 sq. mtrs. in the vicinity of the land in dispute
or to pay compensation at full market value. In addition,
respondents in the writ petition were directed to pay
compensation for illegal use of the land since the date they
took possession. The compensation was directed to be
determined by the District Judge, Moradabad.
8. In support of the appeal, learned counsel for the
appellant submitted that the High Court’s order suffers from
various infirmities.
9. The High Court failed to notice that after 20 years from
the date when the declaration of surplus land was made, the
petition under Section 34 of the Act was filed without
explaining as to what was the cause for inaction of two
decades. Section 34 petition filed by the respondents 1, 2 and
3 was disposed of without notice to the appellant. Though the
appellant had the title over the land, the name of the appellant
was not included in the plaint as a party.
10. It is submitted that the proviso to Section 34 of the Act is
equally applicable and that has not been considered. The
High Court also did not take note of a letter written by the
predecessor-in-interest of the respondents 1, 2 and 3 on
28.12.2000 for release of 3598 sq.mtrs. of unutilized vacant
land in their favour in lien of the entire claim and there was
agreement to pay the development charges and betterment
charges.
11. In terms of the State Government’s directions the
appellant authority at the most has to release 3605 sq.mtrs. of
land on payment of development charges and construction of
cost at prevalent market rate. The High Court was not
justified in ignoring this vital aspect.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
12. The inaction nearly for two decades was not explained. A
statutory time limit is fixed for appeals. Only in case appeals
are not filed, the revisional jurisdiction can be resorted to.
That does not allow a party to move for relief without taking
any action for nearly two decades. The development charges
and construction charges are statutorily imposable under the
U.P. Urban Planning & Development Act, 1973 (in short the
’Development Act’). At the request of the respondents 1, 2 and
3 the State Government did not take steps for acquiring the
land. There was a clear agreement to pay the development
charges and other charges on the condition that there was no
need for acquiring the land. Sections 17 and 34 of the
Development Act are not dependant on the proceedings under
the Act.
13. It is pointed out that there was no illegal use by the
appellant authority and, therefore, the question of
compensation does not arise.
14. Learned counsel for the respondents 1, 2 and 3 on the
other hand submitted that without any authority of law use of
the land was deprived of them for nearly two decades. The
High Court, it was submitted, was justified giving the
directions and coming to the impugned conclusions.
15. It is clear that the High Court has not really considered
the true import of the concession made for payment of
development charges. As rightly contended by learned counsel
for the appellant there was no illegal use and, therefore, the
question of any compensation payable as directed by the High
Court does not arise.
16. Undisputedly also the revision before the State
Government was made nearly after two decades. In the instant
case the appellant was not heard by the revisional authority.
17. Section 33 of the Act relates to an appeal by a person
aggrieved by any order made by the competent authority
under the Act not being an order under Section 11 or an order
under sub-section (1) of Section 30. The appeal is to be filed
within 30 days from the date on which the order is
communicated to him. Under the proviso to Section 33 the
Appellate Authority may entertain the appeal after the expiry
of 30 days if it is satisfied that the appellant was prevented by
sufficient cause from filing the appeal in time. Every order
passed by the Appellate Authority under the statute is final.
18. Section 34 deals with revision by the State Government.
Under the said provision, the State Government may on its
own motion call for and examine the record of any order
passed or proceeding taken under the provisions of the Act
and against which no appeal has been preferred under Section
12 or Section 30 or Section 33 for the purpose of satisfying
himself as to the legality or propriety of such order or as to the
regularity of such procedure and pas such order as it may
deem fit.
19. As a bare reading of the provision shows that it relates to
suo motu action on the part of the State Government. In that
sense, a person aggrieved who had a remedy of appeal under
Section 33 has no statutory right to move in revision.
However, for the exercise of revisional power by the State
Government it is open to the State Government to examine a
petition and on the basis of material indicated therein to
decide whether any action in terms of Section 34 is called for.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
If the State Government decides to act on the basis of petition
filed by any person, it has to examine as to why the person
has not availed the remedy of filing an appeal. It is also
necessary to examine whether after a long lapse of time any
action is warranted. In this exercise, filing of petition within a
reasonable time is inbuilt. What would be reasonable time
would depend upon the facts of each case and no straight
jacket formula can be adopted or applied.
20. There is another statutory requirement under Section 34.
The proviso to Section 34 mandates grant of reasonable
opportunity of being heard to any person who is likely to be
affected by the order. These aspects have been highlighted in
Pune Municipal Corporation v. State of Maharashtra and Ors.
(2007 (5) SCC 211).
21. In view of the aforesaid, the impugned conclusions of the
High Court are not sustainable. Normally, we would have set
aside the order and remanded it to the High Court to decide
the matter afresh. But the learned counsel for respondents 1,
2 and 3 on instructions stated that they agree that 3570
sq.mtrs. of land may be returned to the respondents 1, 2 and
3 and development charges and other charges, as payable in
law, shall be paid by the said respondents.
22. In view of the aforesaid statement of learned counsel for
the respondents 1, 2 and 3, we dispose of the appeal with the
following directions:
(1) The appellant authority shall release 3570 sq.mtrs
of unutilized vacant land on payment of
development charges and other charges payable
under the Development Act.
(2) The respondents 1, 2 and 3 shall not be entitled for
any land beyond 3570 sq.mtrs relatable to the
present dispute.
23. The appeal is disposed of accordingly with no order as to
costs.
Contempt Petition 239 of 2005
24. In view of disposal of Civil Appeal No.4329 of 2003,
contempt petition is also disposed of.