Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 3
CASE NO.:
Appeal (civil) 4359-4361 of 2002
PETITIONER:
KANHAIYA LAL AGRAWAL
Vs.
RESPONDENT:
UNION OF INDIA & ORS.
DATE OF JUDGMENT: 29/07/2002
BENCH:
S. RAJENDRA BABU & P. VENKATARAMA REDDI.
JUDGMENT:
J U D G M E N T
RAJENDRA BABU, J. :
Leave granted.
The first respondent invited tenders for execution of five items of
work including supply, delivery and stacking of 75,000 cubic metre
Machine crushed track ballast as per specifications at its depot in
Naurozabad and loading it into railway wagons. The supply period was
for 24 months. The conditions in the tender notice required that the
rates at which supply was to be made had to be stated in words as well
as in figures against each item of work as per Schedule attached thereto;
that the tenders submitted with any omissions or alteration of the tender
document were liable to be rejected; however, permissible corrections
could be attached with due signature of tenderers; that the tenderer
should hold the offer open till such date as may be specified in the tender
which was for a minimum period of 90 days from the date of opening of
the tender; that contravention of the conditions would automatically
result in forfeiture of security deposit; that the tender was liable to be
rejected for non-compliance of any of the conditions in the tender form.
Five tenders were received. The appellant made his tender on
27.02.2001 with a covering letter that if his offer is accepted within the
stipulated time rebate would be offered by him to the effect that in case
the contract was given to him within 45 days, 60 days and 75 days, he
would extend rebate of 5%, 3% and 2% respectively on the rates tendered
by him. Respondent No. 5 had made a similar offer but after five days of
the opening of the tender, while the appellant had made such offer of
rebate even at the time of making the tender in the letter accompanying
the tender documents. However, respondent No. 5 offered to reduce rates
by 1.25% if accepted in 30 days and 1% if accepted in 45 days. The 1st
respondent accepted the tender offered by the appellant on the rates
subject to rebate. Agreement was entered into by him on 19.04.2001.
Respondent No.5 filed a writ petition claiming that his tender should
have been accepted, as the rates offered by him are the lowest.
The learned Single Judge, before whom acceptance of the tender
offered by the appellant was challenged, took the view that the tender
notice did not admit of an offer being made in the form of rebate as
offered by the appellant and it was also clear that an offer made by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 3
respondent No. 5 after the opening of the tender is of no consequence
and gave the direction of taking fresh offers from the appellant and
Respondent No. 5. The matter was carried in appeal to the Division
Bench. The Division Bench, after adverting to several decisions on the
question of award of contracts, stated that the tender notice did not
contemplate any attachment of conditions by giving rebate which would
amount to alteration of the tender document which is impermissible; that
the tender should be unconditional and relaxation, if any, should have
been notified to all the tenderers to enable them to change their rates;
that all the tenderers should have been treated equally and fairly, and on
that basis, took the view that the tender of Respondent No.5 is at a
lower rate and hence, acceptable and set aside the order of the learned
Single Judge directing fresh negotiations with the parties. The Division
Bench directed that supply of material by the appellant be stopped
forthwith and balance material be taken from Respondent No.5 at the
rate furnished by him. Hence, these appeals against the order of the
High Court.
This Court is normally reluctant to intervene in matters of entering
into contracts by the Government, but if the same is found to be
unreasonable, arbitrary, mala fide or is in disregard of mandatory
procedures it will not hesitate to nullify or rectify such actions.
It is settled law that when an essential condition of tender is not
complied with, it is open to the person inviting tender to reject the same.
Whether a condition is essential or collateral could be ascertained by
reference to consequence of non-compliance thereto. If non-fulfilment of
the requirement results in rejection of the tender, then it would be
essential part of the tender otherwise it is only a collateral term. This
legal position has been well explained in G.J.Fernandez vs. State of
Karnataka & Ors., 1990(2) SCC 488.
In the present case, the short question that falls for consideration
is whether the tender offered by the appellant with the rebate could have
been accepted and whether such acceptance would affect the interests of
any other party.
The letter dated 27.2.2001 accompanying the tender made by the
appellant after setting out rate offered by him also set out certain
circumstances with a note in the following terms :-
"Note :- I would like to offer if the tender is finalised in my favour :
(a) 5% reduction in rate within 45 days;
(b) 3% reduction in rate within 60 days;
(c) 2% reduction in rate within 75 days;
(d) to make use of the machinery at the quickest possible
time."
Bureaucratic delay is a notorious fact and delay in finalising tenders will
cause hardship to the tenderer. In such circumstances, if a hardened
businessman makes an attractive offer of concessional rates if tender is
finalized within a shorter period, it cannot be said that the rates offered
are subject to conditions. The rates offered are clear and the time within
which they are to be accepted is also clear. As long as such offer does
not militate against the terms and conditions of inviting tender it cannot
be said that such offer is not within its scope. All that is required is that
offer made is to be kept open for a minimum period of 90 days. Offer in
compliance of that term has been made by the appellant. The concession
or rebate given is an additional inducement to accept the offer
expeditiously to have a proper return on the investment made by the
tenderer in the equipment and not keeping the labour idle for long
periods which is part of commercial prudence. The commercial aspect of
each one of the offers made by the parties will have to be ascertained
and, thereafter a decision taken to accept or reject a tender.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 3
The Division Bench of the High Court proceeded on the basis that
the offer of concession is contrary to the terms of tender but we have
demonstrated to the contrary.
Now the appellant made his offer of concessional rates along with
the tender while Respondent No.5 made such offer after opening of the
tenders. It is difficult to conceive that the Respondent No.5 who is a
prudent businessman would not be aware of commercial practice of
giving rebate or concession in the event of quick finalization of a
transaction. What the appellant offered was part of the tender itself
while the Respondent No.5 made such offer separately and much later.
There was nothing illegal or arbitrary on the part of Railway
Administration in accepting the offer of the appellant, which was made at
the time of submitting the tender itself.
In the result, we allow these appeals by setting aside the orders
made by the High Court both by the Division Bench and the learned
Single Judge and dismiss the writ petition. No costs.