Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 9
CASE NO.:
Appeal (civil) 8261 of 2001
PETITIONER:
WEST BENGAL STATE ELECTRICITY BOARD
Vs.
RESPONDENT:
CALCUTTA ELECTRIC SUPPLY CORPN. LTD.
DATE OF JUDGMENT: 04/12/2001
BENCH:
G.B. Pattanaik & Ruma Pal
JUDGMENT:
PATTANAIK, J.
Leave Granted.
The West Bengal State Electricity Board is in appeal
against the Judgment of the Division Bench of Calcutta High
Court. The respondent is the licensee. The licensee, on 27th
of December, 1989 submitted an application to the Board for
getting its consent for establishment of new Thermal
Generating Station at Budge Budge and a Project Report was
enclosed with the said application. Under Section 44 of the
Electricity (Supply) Act, 1948, [hereinafter referred to as the
Supply Act], no licensee can establish a new generating
station without the previous consent in writing of the Board.
Under Sub-section 2A of Section 44, the Board before
giving consent to a licensee for establishing a new generating
station, shall consult the Authority. The expression
Authority has been defined in Section 2(1) of the Supply
Act to mean the Central Electricity Authority constituted
under Section 3 of the Act. On 23.2.1990, the Board
accorded sanction under Section 44 of the Supply Act for
setting up a new generating station in Budge Budge with an
installed capacity of 2 x 250 M.W. Units, operating on
pulverised fuel fired boilers. The Board forwarded the
Project Report to the CEA, requesting the authority to
consider the proposal in the light of likely gap in system
demand that would exist in the year 1995, after taking into
account the plans of the Board to set up the Sagardighi
Thermal Project, which was at that point of time awaiting
techno-economic clearance from CEA. The C.E.A.
replied to the Board that issues may be resolved through
Government of West Bengal and intimated that the techno-
economic examination of the proposal was being withheld by
CEA till the final views on the matter is conveyed by the
Board. The Board in its letter dated 23rd of April, 1990,
informed the CEA that the issues raised had been resolved
and the consent already given may be treated as final and,
therefore, CEA may take up the techno-economic
examination. On 29th of January, 1991, CEA communicated
its in principle clearance to the Budge Budge Project,
subject to certain conditions mentioned therein. It also
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 9
informed that any clearance required under Section 44 of the
Supply Act would be made after the Department of Power,
Ministry of Energy, Govt. of India, clears the project.
Finally on 11th of November, 1991, CEA intimated its
clearance of the Budge Budge Project under Section 44 of the
Act at a total cost of Rs. 1285.70 crores, subject to the
conditions mentioned in the letter. The licensee informed the
CEA by its letter dated 23rd April, 1992, indicating that there
has been an enhancement of Project cost which stands
revised to Rs. 2220 crores and requested the CEA to convey
its approval, after examining the estimates and other required
particulars. On 24th of April, 1992, a revised breakup of the
Project cost was furnished to the CEA. The Government of
India, Ministry of Power by its letter dated 21st October, 1992
intimated its approval of the revised financial plan for the
project at Rs. 1638 crores, with certain conditions mentioned
in the said letter. The CEA then wrote a letter to the
Government of West Bengal on 26th of September, 1996
regarding escalation of the Budge Budge Project cost to
Rs.2220 crores and it was stated therein that the CEA has not
received any revised cost estimates from the Board though
the same was required under Section 44 of the Supply Act.
The Board then called upon the licensee by its letter dated 4th
of December, 1996 to furnish the detailed break-up of the
cost estimates as well as the revised cost of the Project which
was then at Rs. 2220 crores. The Government of West
Bengal, through its Power Department also made
correspondence with the licensee, seeking information as to
whether the licensee has submitted the detailed proposal for
revision of the Project cost, as required under Section 44 of
the Supply Act and also further requested that the copies of
the Project cost be furnished to the Government. On 17th of
January, 1997, the licensee wrote to the petitioner Board,
giving groupwise break-up of the escalated project cost as in
July, 1996, amounting to Rs. 2220 crores and also intimated
that the cost is being revised by the Financial Institution
I.C.I.C.I. The licensee then informed the Board by letter
dated 24 of February, 1997 that the revised cost which has
been approved by the financial institution in January, 1997
work out at Rs. 2308 crores. On 30th of July, 1997, the
Board sought for clarification, details and reasonings from
the licensee, regarding the revised cost and those
clarifications were duly communicated by the licensee to the
Board. Unit I of the Project was commissioned on 15th of
September, 1997 and on 20th of February, 1998, the licensee
requested the Board to give its consent to the revised project
cost at Rs. 2460 crores, as in the interregnum, the project cost
had further got escalated. The Board then constituted a
Committee for determining the quantum as to what would be
the reasonable cost of the Budge Budge Project and the said
Committee arrived at a figure at Rs.1853 crores. On 22nd of
May, 1998, West Bengal State Electricity Board approved
the revised cost by Resolution at Rs. 1853 crores and the
same was intimated to the licensee. Along with the
Resolution, the Committees Report also had been appended.
On 4th of June, 1998, the Government of West Bengal,
Department of Power, directed the Board to communicate the
decision of the Board, approving the revised project cost
under Section 44 of the Supply Act to the licensee. Finally
on 11th of June, 1998, the Board intimated the licensee with
regard to its approval of the revised project cost of Budge
Budge Project at Rs. 1853 crores under Section 44 of the
Supply Act and along with it forwarded the copy of the
Report of the Committee and the Minutes of the Boards
Resolution. Since entire project cost furnished by the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 9
licensee had not been approved by the Board, as stated
earlier, the licensee wrote a letter to the CEA, requesting him
to refer the dispute to the Arbitration under Section 44(3) of
the Supply Act. Before the CEA, the licensee also filed his
Statement of claims on 16th of December, 1998. The Board,
on the other hand, filed an application under Section 16(2)
and 16(3) of the Arbitration & Conciliation Act, 1996 against
the appointment of CEA as arbitrator, contending inter alia
that the approval of the revised project cost was not
contemplated under Section 44 of the Supply Act and,
therefore, CEA had no authority to arbitrate on the dispute, if
any. Board then filed an application under Section 13(2) of
the Arbitration & Conciliation Act, 1996, challenging the
appointment of the Arbitral Tribunal. The arbitrator passed
an Award on 13th of July, 1999, dismissing the applications
filed by the Board under Section 13 and Section 16 of the
Act. The Board then filed a writ petition in Delhi High
Court, but that was withdrawn with liberty to file in the
appropriate forum. Arbitrator then passed an award,
determining the revised project cost at Rs.2295.57 crores on
12th of January, 2000. Against the Award, an objection was
filed by the Board, which was heard by a learned Single
Judge of the Calcutta High Court. The objection was
essentially on the ground that the dispute regarding escalated
project cost would not be a dispute under Section 44 of the
Supply Act and, therefore, provisions contained in Section
44(3) will not apply and consequently, the Award is without
jurisdiction and a nullity. The licensee, on the other hand
reiterated before the Single Judge that the project cost as well
as the revised project cost would be a matter coming under
Section 44 of the Supply Act and, therefore, any dispute in
relation to the same would be arbitrable under Section
44(3). It was also contended that all the parties namely the
licensee, the Board, the State Government, as well as the
Electricity Authority have understood that the project cost
was the matter covered under Section 44 and, therefore, it
would not be open for the Board to take a stand that such
project cost is outside the purview of Section 44 and as such
is not arbitrable under Sub-section (3) of Section 44 of the
Supply Act. The learned Single Judge on an analysis of
Section 44 of the Supply Act, was persuaded to accept the
contention of the Board and held that the subject matter of
arbitration was beyond the scope of the statutory provision
under Sub-section (3) of Section 44 and as such the award
passed by the Electricity Authority is without jurisdiction and
is liable to be set aside. The licensee being aggrieved by
the aforesaid order of the learned Single Judge, filed an
appeal before the Division Bench and the Division Bench of
Calcutta High Court by the impugned judgment, having
allowed the appeal, on setting aside the conclusions and
finding of the Single Judge, the present appeal by grant of
special leave has been filed in this Court by the Board.
Mr. V.R. Reddy, the learned senior counsel, appearing
for the appellant-Board, contended that on a plain reading of
Section 44 of the Supply Act, it is difficult to comprehend
that the approval of the project cost comes within the
purview of the said Act and as such any dispute relating to
the project cost, will not be a dispute arising out of the
provisions contained in Section 44 and as such is not
arbitrable under Sub-section (3) of Section 44 of the Supply
Act. Mr. Reddy further contended that it is true that the
Board itself has approved and given its consent to the revised
cost to the tune of Rs. 1853 crores, but that was under the
pressure from the State Government and such decision of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 9
Board cannot be construed to bring within the sweep of
Section 44 of the Act, any dispute on the project cost. Mr.
Reddy also urged that Section 44 of the Supply Act, confers
power on the Board to give consent in writing for
establishment of a new generating station or to extend or
replace any major unit of plant or works pertaining to the
generation of electricity in a generating station and under the
proviso to Sub-section (1) of Section 44, such a consent can
be withheld within three months from the date of receipt of
an application only under two contingencies, as provided in
Clauses (a)(i) & (ii). According to Mr. Reddy, on a fair
reading of the provisions contained in Section 44 of the
Supply Act, the question of approval of the project cost of a
generating station, would not come within the ambit of
Section 44 and as such, the Division Bench of Calcutta High
Court committed serious error in holding that the dispute
relating to the project cost is an arbitrable dispute under
Section 44(3) of the said Act.
Mr. Shanti Bhushan, the learned senior counsel,
appearing for the licensee-respondent, on the other hand
contended that all the parties namely the CEA, the
Government of West Bengal and the Board have all along
understood that the project cost comes within the purview of
Section 44 of the Act and various documents would establish
the aforesaid understanding of the provisions of the Act.
That being the position and parties having acted on the said
understanding and the Board itself having approved the
project cost on 22.5.1998 at Rs. 1853 crores, and thereby
having exercised power under Section 44, is not entitled to
raise the question that the cost of the project would not come
within the purview of Section 44 and, therefore, the dispute
in relation to the project cost, cannot be an arbitrable dispute
under Section 44(3) and consequently, challenging the
jurisdiction of the arbitrator. Mr. Shanti Bhushan also
contended that Boards power to withhold consent in the
event the Board can show to the applicant that the electricity
required by him could be more economically obtained within
a reasonable time from another appropriate source, as
provided in Section 44(1) proviso (b)(ii) indicate that the
Board must know the project cost of the applicant or else it
will not be possible for the Board to find out whether the
required electricity could be economically obtained from any
other appropriate source. That being the position, the project
cost would be a matter within the ambit of Section 44 and
consequently, any dispute relating to the project cost will be
an arbitrable dispute under Section 44(3). Mr. Shanti
Bhushan further urged that the cost of the project being an
essential particular, required to be furnished in every
application filed under sub-section (1) of Section 44, on the
basis of which, the Board has given a consent, any escalated
revised cost will be a material variation to the said particular
for which a further consent of the Board would be necessary
under sub-section (2) of Section 44. In the case in hand, the
Board in fact has given its further consent to the revised cost
of Rs. 1853 crores, and thus the dispute arises between the
Board and the licensee with regard to the said revised cost in
respect of which, further consent has been given by the Board
and in this view of the matter, the Division Bench of the
Calcutta High Court was fully justified in holding that the
dispute is in relation to the provisions contained in Section 44
and as such arbitrable and the Award cannot be held to be
without jurisdiction.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 9
In view of the rival submissions, the sole question that
arises for consideration is whether a dispute relating to
escalated project cost of a generating station would come
within the purview of sub-section (3) of Section 44 of the
Supply Act? The Ministry of Power, Government of India
is primarily responsible for development of electrical energy
in the country. It is concerned with perspective planning,
policy formulation, processing of projects for investment
decisions, monitoring of the projects, training and manpower
development and the administration and enactment of
legislation with regard to power generation, transmission
and distribution. It is also responsible for the administration
of the Supply Act as well as the Indian Electricity Act, 1910.
Government of India, under the Ministry of Power,
constituted the Investment Promotion Cell as a nodal agency
to provide information and assistance to prospective
entrepreneurs in the electricity sector. Setting up of the
aforesaid Cell provided initiative to involve the private
sector in power generation in a much bigger way. It provides
information on the policy regarding private sector
participation and provides guidance on the clearances to be
obtained and the modalities for obtaining these. Under
Section 3 of the Supply Act, 1948, a statutory body has been
constituted, called the Central Electricity Authority [for short
CEA]. This authority is charged with the responsibilities
to develop a sound, adequate and uniform National Policy in
relation to the control and utilization of national power
resources. The said authority also conducts the techno-
economic appraisal of the Project reports in respect of setting
up of generating stations in the country. Under the aforesaid
Supply Act of 1948, the Board is constituted by the State
Government and the main functions of the Board are to
generate, transmit and distribute electricity in coordination
with the generating companies, if any, operating in the State
and with the Central Government or any other Board or
agency having control over a power system; transmission
and distribution of electricity within the State; and exercise
of control in relation to generation, distribution and
utilization of electricity within the State. A Licensee is one,
who has been granted a license by the State Government, in
consultation with the State Electricity Board to supply energy
in any specified area, under Section 3 of the Indian
Electricity Act, 1910 as well as Supply Act of 1948.
Generating company is set-up under Section 15A of the
Supply Act. The Parliament has enacted the Electricity
Regulatory Commissions Act of 1998, under which the
Central Electricity Regulatory Commission has been set up,
the main functions of which are to regulate the tariff of
generating companies owned or controlled by the Central
Government, to regulate the tariff of generating companies
other than those owned or controlled by the Central
Government and to regulate the inter-State transmission of
energy including tariff of the transmission utilities. Besides,
it regulates inter-State bulk sale of power and to aid and
advise the Central Government in formulation of tariff
policy. This Regulatory Commission has been constituted
since 24th of July, 1998. Under Section 17(1) of the
Regulatory Commissions Act of 1998, even the State
Electricity Regulatory Commission is envisaged. In the case
in hand, we are not concerned with the Regulatory
Commission or its role. The respondent, admittedly is the
licensee. Under the Electricity (Supply) Act, 1948, Chapter
V deals with the preparation and sanctioning of scheme.
Ordinarily, the Board or a generating company may prepare a
scheme relating to the establishment or acquisition of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 9
generating stations, sub-stations or transmission lines and
such scheme estimated to involve a capital expenditure
exceeding such sum, as may be fixed by the Central
Government by notification in the official Gazette, must get
the concurrence of the authority. Section 29 occurring in
Chapter V, provides the procedure to be adopted and Section
30 deals with the matters required to be considered by the
authority before concurring to a scheme, submitted to it
under sub-section (1) of Section 29. Apart from the Board
or a generating company being the author for production of
power, any licensee also has a right to establish new
generating stations, as provided in Section 44 of the Supply
Act. The provision contained in Section 44 is an
independent one and has nothing to do with the general
scheme, contemplated in Chapter V and the provisions of
Section 44 start with a non obstante clause. Under Sub-
section (1) of Section 44, it shall not be lawful for a licensee,
except with the previous consent in writing of the Board to
establish or acquire a new generating station, but such a
consent being sought for, the Board has a limited right within
the prescribed period to withhold the consent, if the Board
gives an undertaking to the licensee that it is competent to,
and will, within twenty four months from the said date,
afford to the licensee, a supply of electricity sufficient for his
requirements, pursuant to his application or if the Board
shows to the applicant that the electricity required, could be
more economically obtained within a reasonable time from
another appropriate source, then it can withhold the consent,
required under Section 44(1), but that again has to be done
within three months from the date of receipt of the
application. It would thus appear that the Board can
withhold the consent under two clauses of Section 44(1)
proviso (a), but that has to be within three months from the
receipt of the application. Section 44(2) of the Supply Act is
materials for our purpose and the same may be extracted
hereinbelow in extenso:
Sec. 44(2). There shall be stated in every
application under this section such particulars as
the Board may reasonably require of the station
plant or works, as the case may be, in respect of
which it is made, and where consent is given
thereto, in acting in pursuance of such consent,
the applicant shall not, without the further consent
of the Board, make any material variation in the
particulars as stated.
A plain reading of the aforesaid sub-section would indicate
that an applicant is bound to furnish all such particulars
which the Board may reasonably require to enable the Board
to give its consent and where a consent is given, then while
acting in pursuance of that consent, the applicant shall not
without further consent of the Board, make any material
variation in the particulars, so stated. If the project cost is
one of the particulars required to be given by an applicant,
while making an application under sub-section (1) of Section
44, then in the event, Board gives the consent and while
acting in pursuance of that consent, the project cost varies,
then for such variation, further consent of the Board would be
necessary, as provided under sub-section(2) of Section 44.
Since the Board could withheld the consent, if it shows to the
applicant that the electricity required by him could be more
economically obtained within a reasonable time from another
appropriate source, to arrive at such conclusion, it would be
reasonable to infer that the applicant must indicate the project
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 9
cost in its application for consent. If the project cost is not
indicated in the application for consent, then the Board will
not be in a position to find out whether the electricity
required by the applicant could be more economically
obtained from another appropriate source within a reasonable
time and, therefore, in our view it is necessary for every
applicant while invoking power of the Board under sub-
section (1) of Section 44 to obtain the previous consent in
writing for establishment of a generating station to indicate
the cost of the project. This being the position, where
consent is received on the basis of the project cost indicated
in the application, while acting in pursuance of such consent,
if the project cost varies, then it would be a material variation
of an important particular and consequently, a further consent
of the Board would be necessary under sub-section (2) of
Section 44. In the case in hand, the original consent of the
Board had been obtained and while acting in pursuance of
such consent, it was found that the project cost has got
escalated and application for further consent was made to the
Board and the Board also did accord its further consent at Rs.
1853 crores, which was communicated to the applicant-
licensee. While the applicant-licensee had indicated the
revised project cost at a much higher figure but the Board
approved the revised cost at Rs.1853 crores and this further
consent on the basis of revised cost can only be under sub-
section (2) of Section 44 and in fact the Board also
communicated the same in the purported exercise of power
under sub-section (2) of Section 44. The further consent in
respect of the revised project cost having been given under
sub-section (2) of Section 44, a dispute did arise within the
ambit of sub-section (3) of Section 44 and, therefore, the
authority concerned contemplated under sub-section (3) of
Section 44, gets jurisdiction to arbitrate upon the dispute
between the parties and in the case in hand, the said authority
ultimately passed an award. In view of our analysis, as
stated above, it is difficult for us to sustain the argument of
Mr. Reddy, appearing for the Board that the so-called dispute
regarding the project cost, cannot be a dispute arising out of
the provision of Section 44 and as such would not be
arbitrable under sub-section (3) of the said Section. We,
therefore, are in agreement with the conclusion of the
Division Bench of Calcutta High Court and hold that the
dispute in question did come within the purview of sub-
section (2) of Section 44 and as such was arbitrable under
sub-section (3) thereof and the award cannot be held to be
without jurisdiction, as contended by the Board.
There is yet another facet in the case in hand, namely
how the Board itself as well as the authority have themselves
understood the provisions of the Act. The concerned
authority, who was the statutory arbitrator under sub-section
(3) of Section 44, while deciding the question of jurisdiction,
unequivocally came to the conclusion that Section
44(1)(a)(ii) brings within its sweep the cost aspect of the
project which is important for taking decision regarding
establishment or acquisition of a generating station and the
revision of cost is also being done under said section 44.
With this conclusion it rejected the prayer of the Board,
challenging the jurisdiction of the arbitrator. When the
question of revision of project cost cropped up, the Chief
Engineer of the Board by its letter dated 4.12.1996 called
upon the licensee to furnish the detailed break up of the cost
estimate, while it furnished the application originally in the
year 1991 and the revised cost claimed by the licensee to the
tune of Rs.2220 crores. On 18th of December, 1996, the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 9
Joint Secretary to the Government of West Bengal also called
upon the licensee to submit a detailed proposal for revision of
the project cost, as required under Section 44 of the Supply
Act. Again on 4th June, 1998, the Government wrote to the
Board, requiring the approval of the Board to the revised
project cost under Section 44 of the Act. On the very same
date, that is on 4th June, 1998, the Government also wrote to
the licensee that under the provisions of the Electricity
Supply Act , the revised cost of the project of the licensee has
to be worked out and approved by the State Electricity Board
under Section 44 of the said Act and in the event the licensee
is not satisfied with the decision of the Board, then the relief
is available in the Supply Act itself, obviously referring to an
arbitrator under sub-section (3) of Section 44. On 11th June,
1998, the Board wrote to the licensee that after careful and
detailed examination of all data and records furnished by the
licensee, the Board in its 505th meeting held on 22nd May,
1998, resolved that the reasonable project cost would be Rs.
1853 crores and as such the Board approves the revised
project cost at Rs. 1853 crores under Section 44 of the
Electricity (Supply) Act. The Board, therefore not only
understood that the project cost is required to be approved
under Section 44, but did take a decision, approving the
reasonable revised project cost at a particular figure in
exercise of its power under Section 44. The Board having
exercised power under Section 44 and having approved the
revised cost at a particular figure, cannot take a stand when
the dispute regarding the project cost was referred to the
authority for arbitration that the project cost does not come
within the purview of Section 44. Thus, apart from our
conclusion on interpreting the provisions of Section 44 of the
Electricity (Supply) Act, the conduct of the Board itself
disentitles it to take a stand that the revised project cost
would not come within the ambit of Section 44 of the Supply
Act. In the aforesaid premises, we do not find any merits in
the contention of Mr. Reddy, challenging the jurisdiction of
the arbitrator to entertain the dispute regarding the
reasonability of the revised project cost. In our considered
opinion, the dispute is one, which comes within the ambit of
Section 44 and as such arbitrable under sub-section (3) of
Section 44 and the Award cannot be held to be without
jurisdiction. The conclusion of the Division Bench of the
Calcutta High Court on this score remains unassailable.
Mr. Reddy, then contended that the High Court was not
justified in making any observations with regard to the
impact of the revised project cost on the tariff, as the same
was not a subject matter and the only question that had been
raised before the High Court was whether the arbitrator had
the jurisdiction or not. We find sufficient force in the
aforesaid contention of Mr. Reddy and Mr. Shanti Bhushan,
the learned senior counsel, appearing for the licensee also
fairly stated that it was not necessary for the High Court to
make any observation as to what would be the effect of the
reasonable project cost on the tariff structure. While,
therefore, upholding the Division Bench Judgment of the
Calcutta High Court, we further observe that it was not at all
necessary for the High Court to go into the question of
impact of the project cost upon the tariff structure and any
observations made in respect of the same are set aside.
This appeal is accordingly dismissed with the aforesaid
observations. There will be no order as to costs.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 9
..........................................J.
(G.B. PATTANAIK)
..........................................J.
(RUMA PAL)
December 04, 2001.