Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 26
PETITIONER:
I.T.C. LIMITED
Vs.
RESPONDENT:
GEORGE JOSEPH FERNANDES & ANR.
DATE OF JUDGMENT06/02/1989
BENCH:
SAIKIA, K.N. (J)
BENCH:
SAIKIA, K.N. (J)
OZA, G.L. (J)
CITATION:
1989 AIR 839 1989 SCR (1) 469
1989 SCC (2) 1 JT 1989 (1) 552
1989 SCALE (1)283
ACT:
Arbitration Act, 1940: Sections 32, 33, 34.
Stay of Legal proceedings--Whether court has jurisdic-
tion to decide validity of contract containing Arbitration
clause--Existence of a valid agreement--Whether condition
precedent.
Jurisdiction of court to decide on--Validity and legali-
ty of contract--Whether to be decided on affidavits and
documents or on evidence.
Constitution of India 1950, Article 136.
Interference by Supreme Court--With discretion of courts
under Section 34 of Arbitration Act, 1940--When called for.
Contract Act, 1872: Section 20.
Mistake of fact--Nature of--An erroneous opinion as to
the value of the contracted thing--Not a mistake of
fact--Common mistake of both parties must be about the same
vital fact--Common mistake and Mutual Mistake--Distinction
between.
Fishing trawlers--Refrigeration
system--Deficiency--Required temperature Minus 20 Degree
F--Attained temperature Minus 10 Degree F--Whether mutual
mistake.
Words & Phrases: Naturali ratione inunitilis.
Ex turpi causa non oritur actio---Meaning of.
HEADNOTE:
Under an import licence dated 3rd March, 1971 issued by
the Chief Controller of Imports and Exports the respondent
imported two fishing trawlers with the financial assistance
of the second respondent Canara Bank. The respondent con-
ducted negotiations with the appellant for a charter-party
agreement in respect of the said trawlers. On 21st March,
1977, an agreement between the parties was executed
470
under which the appellant agreed to take on charter hire the
said two trawlers for the purpose of deep sea fishing for a
period of two years with an option to continue the hire for
a further period of three years. Under the terms of the
agreement the respondent was to deliver the said trawlers to
the appellant at Vishakhapatnam within seven days of the
receipt of approval from the Chief Controller of Imports and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 26
Exports or no objection certificate from the Canara Bank,
for making the said trawlers fully operational and to ascer-
tain the cost of such repairs. The appellant charterer was
then to conduct fishing trials to ascertain actual condi-
tions and thereafter the charter hiring was to commence from
the date the fishing trials were ended.
On 18th August, 1977, the Chief Controller of Imports
and Exports granted permission to the respondent to charter
the said trawlers to the appellant on the conditions that
the charter rent would be Rs.50,000 per month per trawler
and that the charter would be for a period of three years.
On 30th September, 1977, the respondent delivered the said
two trawlers for repairs to the appellant.
On 2nd February, 1978, the parties modified the agree-
ment revising the rate of charter hire and the date of
commencement of hire, to the extent that the charter hire
would commence from 15th January, 1978 and the revised rate
of hire would be Rs.6,25,000 per trawler per year.
The appellant charterer raised objections alleging that
the trawlers suffered from inherent and latent defects in
the refrigeration system which was an essential part of such
trawlers and as such the trawlers were not fully operational
because even after carrying out extensive repairs the re-
frigeration system could not be brought to the required
standard of minus 20 degree F but attained only minus 10
degree F.
On 29.9.1978, the appellant instituted a suit in the
original side of the Calcutta High Court claiming (i) a
decree for a sum of Rs.39,64,341 towards cost, charges,
damages and compensation incurred on the said trawlers and,
(ii) a declaration that the agreement was contrary to the
terms of the permission granted by the Chief Controller of
Imports and Exports and consequently illegal and against
public policy and void; (iii) that the Parties had entered
into the agreement on the basic fundamental assumption that
by effecting necessary repairs the trawlers would be made
fully operational but the assumption was subsequently dis-
covered to be mistaken because of the deficiency in the
refrigeration system and it rendered the agreement void.
471
The respondent filed an application under Section 34 of
the Arbitration Act, 1940 praying that the suit instituted
by the appellant, and all proceedings therein be stayed
because the disputes were wholly covered by the arbitration
clause as contained in the modified agreement dated 2nd
February, 1978 which was binding between the parties.
The Single Judge held that there was no invalidity for
non-compliance of the conditions of the licence granted
because necessary permission was obtained in respect of the
agreement from the Chief Controller of Imports and Exports
and the modifications of the agreement did not impair its
validity; though in a particular case if there was any doubt
about facts, the matter had to be decided by trial on evi-
dence but in the instant case, having regard to the admitted
facts and conduct of the parties it was not necessary to set
down the matter for trial on evidence; there was no illegal-
ity or mutual mistake; that the alleged fundamental breach
was wholly covered by the arbitration clause; that the
arbitration clause was valid and binding between the par-
ties; and that all the conditions of Section 34 were satis-
fied. Accordingly, the Single Judge granted stay of the suit
and directed the parties to take immediate steps for initia-
tion of reference under the arbitration agreement.
The judgment and order of the Single Judge was confirmed
by the Division Bench by dismissing the appeal.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 26
In this appeal by special leave it was contended on
behalf of the appellants that (i) the subject-matter of the
suit, namely, the question whether the agreement was void ab
initio for mutual mistake was not arbitrable; and the courts
below erred in holding so; (ii) assuming that the subject-
matter was arbitrable, the court should not have exercised
its jurisdiction on the application under Section 34 because
it involved complicated questions of fact and in exercising
such jurisdiction the courts acted without jurisdiction;
(iii) the court should have decided only after taking oral
and documentary evidence and not merely on affidavits; (iv)
the agreement was void being violative of the conditions of
the permission granted by the Chief Controller of Imports
and Exports; (v) the agreement itself having been void ab
initio due to mutual mistake, the arbitration clause per-
ished with it and the courts below erred in holding that the
disputes were arbitrable.
Dismissing the appeal, the Court,
HELD: 1. Section 34 deals with the staying of a suit where
there
472
is an arbitration agreement concerning the subject-matter of
the suit and between the same parties. For the Court to have
power to exercise the discretion conferred upon it by this
section, there must have been a valid agreement to submit to
arbitration. Where the objection is that the arbitration is
a nullity, it amounts to an objection of want of jurisdic-
tion. The term "arbitration agreement" includes "agreement
to refer", and "submission" to Arbitrator. A submission
forming part of a void contract is itself void and cannot be
enforced. [484B-C]
1.1 Whether a particular dispute arising out of a par-
ticular contract is referable to arbitration or not, must
necessarily depend on the intention of the parties as em-
bodied in the arbitration clause. If the dispute is squarely
covered by the arbitration clause, the relevant provisions
of the Act will be attracted. The question whether the
dispute in the suit fails within the arbitration clause
really pre-supposes that there is such agreement and in-
volves consideration of two matters, that is (i) what is the
dispute in the suit, and (ii) what dispute the arbitration
clause covers. It is incumbent upon the court to decide
whether there is a binding contract for arbitration between
the parties. If it is found that the dispute in the suit is
not covered by the arbitration clause the application for
stay may be dismissed. [488H; 489A]
2. Where in an application under Section 34 of the Act
an issue is raised as to the validity or existence of the
contract containing the arbitration clause, the court has to
decide first of all whether there is a binding arbitration
agreement, even though it may involve incidentally a deci-
sion as to the validity or existence of the parent contract.
If the arbitration clause is so wide as to have included the
very validity or otherwise of the contract on the grounds of
fraud, mis-representations, mutual mistake or any valid
reason the arbitrator will surely have jurisdiction to
decide even that dispute. The proper approach would be to
examine the issue raised in the suit and to ascertain wheth-
er it squarely falls within the compass of the arbitration
clause and take a decision before granting the stay of the
suit. If an issue is raised as to the formation, existence
or validity of the contract containing the arbitration
clause, the court has to exercise discretion to decide or
not to decide the issue of validity or otherwise of the
arbitration agreement even though it may involve incidental-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 26
ly a decision as to validity or existence of the challenged
contract. Should the Court find the parent contract to be
void ab initio or illegal or non-existent, it will be with-
out jurisdiction to grant stay. If the challenged contract
is found to be valid and binding and the dispute raised in
the suit covered by the arbitration clause, stay of the suit
may be justified. [491F-G; 492A-B, D-F]
473
2.1 In the instant case, considering the issues raised,
the arbitration clause and the surrounding circumstances and
the part played by the parties pursuant to the charter party
since execution to the modification and thereafter till
objection raised by the appellant-plaintiff. it must be held
that the trial court did not err in proceeding to decide the
issue of validity or legality of the parent contract.
[492F-G]
3. Where the validity, existence or legality of the
contract is challenged in suit on grounds de hors, independ-
ent of, or external to the terms or stipulations of the
contract, the court in an application under Section 34 of
the Act shall have no jurisdiction to go into the question,
and that in a large majority of cases it would be applica-
ble, in appropriate cases, having regard to the nature of
the dispute raised in the pleadings of the suit, the compass
and scope of the arbitration clause in the contract, the
surrounding facts and circumstances of the case having a
bearing on the question of genuine grievance failing outside
or inside the arbitration agreement and the objects and
spirit of the Arbitration Act, the Court may be justified in
deciding the validity, existence or legality of the chal-
lenged contract containing the arbitration agreement.
[488A-C]
3.1 In the instant case, the arbitration clause formed
part of the agreement. The arbitration agreement is not the
same as the contract in the charter party. It cannot, there-
fore, be said that the validity or otherwise of the charter
party was covered by the arbitration clause. [489D-E]
Jee Lae v. Lord Dalmeny, [1927] 1 Ch. 300; Heyman v.
Darwins, [1942] A.C. 356; Monro v. Bognor Urban District
Council, [1915] 3 K.B. 167; Jawaharlal Burman v. Union of
India, [1962] 3 S.C.R. 769: Waverly Jute Mills Co. Ltd. v.
Raymon & Co. (India) Pvt. Ltd.,3 S.C.R. 209; A.I.R. 1963
S.C. 90; Khardah Co. Ltd. v. Raymon & Co. India Ltd., [1963]
3 S.C.R. 183; Renusagar Co. v. General Electric Co., [1985]
1 S.C.R. 432; Anderson Wright Ltd. v. Moran and Company,
[1955] 1 S.C.R. 862; Damodar Valley Corporation v.K.K. Kar,
[1974] 2 S.C.R. 240; Hirji Mulji v. Cheong Yue Steamship
Co., [1926] A.C. 497; applied.
Banwari Lal v. Hindu College, A.I.R. 1949 East Punjab 165;
Johurmull Parasram v. Louis Dreyfus Co. Ltd. 52 C.W.N.
(1947-48) 137 A.I.R. 1949 Cal 179; Pramada Prasad v. Sagar
Mal Aggarwal, A.I.R. 1952 Patna 352; Narsingh Prasad v.
Dhanraj Mills. I.L.R. 21 Patna 544; A.I.R. 1943 Patna 53;
Birla Jute Manufacturing Co. Ltd. v. Dulichand. A.I.R. 1953
Calcutta 450; W.F. Ducat & Co. Pvt. Ltd. v.
474
Hiralal Pannalal, A.I.R. 1976 Calcutta 126; General Enter-
prises v. Jardine Handerson Ltd., A.I.R. 1978 Calcutta 407;
Khusiram v. Hanutmal, [1948] 53 C.W.N. 505, approved.
4. In the instant case, facts were admitted. [493B-C]
All the relevant documents and affidavits were before
the Court and were considered by it. Therefore no illegality
was committed by the trial court in not setting down the
matter for trial on evidence and deciding the validity and
legality of the matter without taking oral evidence. [49211;
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 26
493B]
4.1 Even if it appears that the discretion could have
also been exercised to decide the issue of invalidity in a
trial on evidence adduced, this court would not substitute
its view for that of the trial court, unless the ends of
justice required it to be done. This Court would not lightly
interfere under Article 136 of the Constitution with the
concurrent exercise of discretion of the courts below under
Section 34 of the Arbitration Act. Before it can justly do
so, the appellant must satisfy the Court, on the relevant
facts referred to by the Courts below, that they exercised
their discretion in a manifestly unreasonable or perverse
way which was likely to defeat the ends of justice. The
appellant has failed to do so in the instant case. [493C,
E-F]
Ormarod v. Todmordon, [1882] 8 Q.B.D. 664; Charles
Osenton and Co. v. Johnston, [1942] A.C. 130; Gardner v.
Jay, [1885] 29 Ch. D. 50; Printers (Mysore) Pvt. Ltd. v.
Pothan Joseph, [1960] 3 S.C.R. 713, applied.
5. Where the parties make mutual mistake misunderstand-
ing each other and are at cross purposes, there is no real
correspondence of offer and acceptance and the parties are
not really consensus ad idem. There is thus no agreement at
all; and the contract is void. Section 20 is concerned with
common mistake of fact and not mutual mistake. A common
mistake is there where both parties are mistaken about the
same vital fact although both parties are ad idem, e.g., the
subject matter of the contract has already perished. A con-
tract in such a case is void. Where each party is mistaken
as to the other’s intention, though neither realises that
the respective promises have been misunderstood, there is
mutual mistake. 1493H; 494A-B]
6. A mistake will not affect assent unless it is the
mistake of both parties, and is as to the existence of some
quality which makes the thing
475
without the quality essentially different from the thing as
it was believed to be. Neither party can rely upon his own
mistake to say that it was a nullity from the beginning, no
matter that it was a mistake which to his mind was fundamen-
tal, and no matter that the other party knew that he was
under a mistake. A fortiori, if the other party did not know
of the mistake but shared it. The question is not what the
parties had in their minds, but what reasonable third par-
ties would infer from their words or conduct. The court has
to ascertain the "sense of the promises". [496E; 495G-H]
7. The application of the doctrine of mutual mistake
depends upon the true construction of the contract made
between the parties. A mutual misunderstanding will not
nullify a contract but only if the terms of contract con-
strued in the light of the nature of the contract and of the
circumstances believed to exist at the time it was done show
that it was never intended to apply to the situation which
in reality existed at that time, will the contract be held
void. Thus a mistake as to an essential and integral element
in the subject matter of the contract will avoid the con-
tract. A mistake as to the quality of the article contracted
for may not always avoid the contract. A distinction, there-
fore, should be drawn between a mistake as to the substance
of the thing contracted for, which will avoid the contract
and mistake as to its quality which will be without effect.
According to circumstances even a mistake as to the sub-
stance of the thing contracted for may not necessarily
render a contract void. Thus there must be a difference so
complete that, if the contract were enforced in the actual
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 26
circumstances which have unexpectedly emerged, this would
involve an obligation fundamentally different from that
which the parties believed they were undertaking. [496A-H]
8. From the series of steps taken for repairs and the
stipulations in the charter party including the modifica-
tions thereof, it is not possible to hold that it was a case
of mutual mistake as to a quality which made the trawlers
transferred essentially different from the trawlers that the
parties in their minds agreed to transfer. Therefore, there
was no mutual mistake and the contract would not be avoided
on this ground. [498C-D]
Cooper v. Phibbs, [1867] L.R. 2 H.L. 149; Ear/Beauchamp
v. Winn., [1873] 6 H.L. 223; Hudders field Banking Co. v.
Henry Lister & Sons, [1895] 2 Ch. 273; Bell v. Laver Brs.
Ltd., [1932] A.C. 161; Kannedy v. Panama Royal Mail Co.,
[1867] L.R. 2 Q.B. 580; Smith v. Hughes, [1871] L.R. 6 Q.B.
597; Solle v. Butcher, [1950] 1 K.B. 671:
476
Fraderick E. Rose (London) Ltd. v. William H. Pim Junior &
Co. Ltd. [1953] 2 Q.B. 450; Sheikh Brothers LId. v. Arnold,
[1957] A.C. 136; referred to.
U.P. Government v. Nanhoo Mal, A.I.R. 1960 All. 420,
approved.
9. It is settled law that where the subject matter of a
reference is illegal, no award can be of any binding effect.
If the contract itself was illegal, the controversy as to
whether it was illegal or not would not be a dispute arising
out of the contract as also would be the question whether
the contract was void ab initio. When, however, it is found
that a binding contract was made which was not illegal what
follows from such a contract would be covered by the expres-
sion "dispute arising out of contract". To stay a suit under
Section 34 the Court has to see whether there was a valid
agreement to have the dispute settled by arbitration and
that the proceedings are in respect of a dispute so agreed
to be referred. [498E, (;-H; 499A]
10. Public policy imposes certain limitations on the
freedom of contract by forbidding the making of certain
contracts. In such cases though all other requisites for
formation of the contract are complied with, parties to such
forbidden contracts are not allowed to enforce any rights
under them. In clear cases the law strikes at the agreement
itself by making the contract illegal. However, the effect
and nature of illegality are by no means uniform and will
depend upon the facts and circumstances of each case. Where
a statute makes a contract illegal or where a certain type
of contract is expressly prohibited there can be no doubt
that such a contract will not be enforcible. [499B-D]
11. A contract which was not illegal from the beginning
may be rendered illegal later by the method of performance
which did not comply with the statutory requirements. The
appellant’s burden was to show that the charter party was
illegal to take it out of the arbitration clause for if the
contract is illegal and not binding on the parties the
arbitration clause would also be not binding. Once it is
shown to have been illegal it would be unenforcible as ex
turpi causa non oritur actio. [499G-H]
12. One who knowingly enters into a contract with im-
proper object cannot enforce his rights thereunder. The
appellant in the instant case was also a party to the agree-
ment of charter party in respect of the two imported trawl-
ers. Though it purported to be actual user’s licence
477
there was no violation of this condition in view of the
express permission granted by the Controller of Imports and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 26
Exports allowing the chartering of the two imported trawl-
ers. The modifications to the contract did not make any
alteration so as to make the agreement contrary to the terms
and conditions of the permission inasmuch as the permission
was for a period of three years. The option to continue hire
of the trawlers for a further period of three years did not
ipso facto violate the permission. There was also no viola-
tion as to the duration of the charter party. [499H; 500C-E]
Taylor v. Barnett, [1953] 1 W.L.R. 562; Anderson Wright
Ltd. v. Moran and Company, [1955] 1 S.C.R. 862; In Re arbi-
tration between Mahmoud and Isphani, [1921] 2 K.B. 176;
applied.
13. The Courts below were right in holding that the
matters were arbitrable apart from the question of illegali-
ty, invalidity of the contract. The question of invalidity
of the contract due to the alleged mutual mistake would be
de hors and independent of the contract and as such would
not be referable under the arbitration clause. In so far as
the question of illegality of the charter party is concerned
as the appellant has not established that the charter party
was illegal or void as initio, the question whether the
modification as alleged had rendered the contract illegal
would be covered by the arbitration clause. [500F-G]
14. In the instant case, the reliefs claimed in the suit
other than the question of ab initio invalidity or illegali-
ty of the contract would be referable. However, it will be
within the jurisdiction of the arbitrator to decide the
scope of his jurisdiction. The Court cannot make a contract
between the parties and its power ends with the interpreta-
tion of the contract between them. The same principle also
applies to the arbitration agreement unless the parties to
the arbitration agreement authorises the court to make and
modify the agreement. The arbitrator shall proceed in ac-
cordance with law to decide the questions including that of
jurisdiction, if raised. [501C-1). E]
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 1795 of
1982.
From the Judgment and Order dated 3.2. 1982 of the High
Court of Calcutta in Appeal No. 75 of 1981.
Shanti Bhushan, Ms. Lira Goswami, S. Ganesh, R. Narain
and D.N. Mishra for the Appellant.
478
C.S. Vaidyanathan, S.R. Setia, K.V- Mohan and K.V.
Viswanathan for the Respondents.
The Judgment of the Court was delivered by
K.N. SAIKIA, J. This appeal by special leave is from the
appellate judgment of the Calcutta High Court in Appeal No.
75 of 1981 dismissing the appeal and upholding the judgment
of the learned Single Judge granting stay of the appellant’s
suit on the respondent’s application under section 34 of the
Arbitration Act, 1940.
The appellant as plaintiff has instituted suit No. 736
of 1978 on 29.9.1978 in the original side of the
Calcutta High Court against the respondent as first de-
fendant and Canara Bank as second defendant stating in the
plaint, inter alia, that the first defendant, was the sole
and absolute owner of two fishing trawlers, Ave Maria-I and
Ave maria-II, registered under No. 1567 dated 30th January,
1974 and No. 1568 dated 30th January, 1974 with the Regis-
trar of Indian Ships, Cochin that the said trawlers were
imported by the first defendant with financial assistance of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 26
the second defendant, Canara Bank, under Import Licence No.
P/CC/2062299 dated 3rd March, 1971 issued by or on behalf of
the Chief Controller of Imports & Exports, Ministry of
Commerce, Government of India, New Delhi, that in or about
March, 1977 the first defendant as owner agreed to charter
and the plaintiff as charterer agreed to take on charter for
the purpose of deep sea fishing, the said two trawlers on
the terms and conditions contained in a "Bare Boat Charter
Party" dated the 21st March, 1977, hereinafter called, the
agreement, executed at Calcutta, subject to the owner first
defendant obtaining the requisite permission in writing from
the Chief Controller of Imports & Exports and the No Objec-
tion Certificate of the second defendant for chartering the
said trawlers; that within seven days of receipt of the
approval of the Chief Controller of Imports & Exports or no
objection certificate from the Canara Bank the first defend-
ant owner will deliver the said trawlers to the plaintiff
charterer at the Port of Vishakapatnam for carrying out the
inspection of the said trawlers by its authorised agents to
ascertain repairs to be carried out to the trawlers for
making them fully operational without any defect whatsoever
and also to ascertain the cost of such repairs and thereaf-
ter the Chatterer will undertake the repairs at the cost of
the owner and bring them to fully operational condition
without any defect including all aspects of refrigeration
equipment; that the charterer will then conduct fishing
trials to ascertain actual condition of the trawlers and in
case the condition is fully satisfied according to the
Charterer, and the
479
owner furnishes to the Charterer all documents certifying
sea-worthiness and also supplies proof of compliance of
pre-condtions, the Charter hiring shall commence on or from
the date fishing trials are ended; that the charterer shall
pay to the owner Rs.50,000 per trawler per month payable in
advance every month and shall continue to pay up to and
including the date of redelivery of each trawler to the
owner at Vishakapatnam (unless lost-sunk); that he shall
keep a deposit of Rupees one lakh per trawler with the owner
during the period of the agreement to be adjusted without
interest towards the charter hire against the last two
months of charter period; that by a Letter No.
CG/N-2-143-70-71 dated 18th August, 1977 the Chief Control-
ler of Imports & Exports granted permission to the first
defendant to charter the said trawlers to the plaintiff on a
charter rental of Rs.50,000 per month per trawler for a
period of three years; that the owner delivered the said two
trawlers for repairs to the plaintiff at Vishakapatnam on or
about 30th September, 1977 and thereafter on or about 2nd
February, 1978 the parties agreed to modify the agreement in
the manner stated in a subsequent written agreement dated
2nd February, 1978 executed at Calcutta; and that according
to the agreement after modification, the charter hire com-
menced from 15.1.1978 and the charter hire revised to
Rs.6,25,000 per trawler per year.
The plaintiff’s main averments in the plaint are that
the permission dated 18th August, 1977 granted by the Chief
Controller of Imports & Exports to the first defendant for
chartering the said trawlers to the plaintiff was given
under the said Import Licence to the first defendant and the
permission was given subject to two conditions, namely, that
the charter rental would be Rs.50,000 per month and that the
charter would be for a period of three years but the agree-
ment dated 21st March, 1977 was, in fact, for a period of
two years with an option to the plaintiff to continue the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 26
hire for a further period of three years and as such the
agreement was in contravention of and contrary to the terms
of the said permission and consequently to the said Import
Licence, and hence, illegal, against public policy and void;
that the plaintiff and the first defendant entered into the
agreement and its modification dated 2nd February, 1978 on
the basic, essential and fundamental assumption that the
trawlers would be made fully operational and free from all
defects by effecting repairs as contemplated thereby but the
assumption was mistaken and not true and was subsequently
discovered to be so mistaken that it rendered the agreement
with its modifications void; that pursuant to the agreement
the plaintiff paid to the first defendant through the second
defendant the initial deposit of Rupees two lakhs in respect
of the said two trawlers of the
480
charter rent as agreed up to and for the month of July 1978,
but in or about early September 1978 the plaintiff having
discovered the agreement to have been void and illegal
called upon the first defendant to take back or obtain
permission of the said trawlers lying at Vishakapatnam at
the risk and cost of the first defendant but he failed and
neglected to do so; and that the first defendant is bound to
pay or make compensation for all the advantages which he had
received under the agreement and its modifications and the
costs, charges and expenses which the plaintiff has incurred
on the said trawlers, being assessed at Rs. 39,64,34 1 as
per Schedule ’D’ to the plaint. In the alternative it has
been averred that in supplying the said trawlers the first
defendant committed a fundamental breach of the agreement
and its modifications which went to the root and affected
the very substance of the same and which made its perform-
ance impossible and such a breach on the part of the first
defendant has produced a situation fundamentally different
from anything which the parties could as reasonable persons
have contemplated when the agreement was entered into, and
as the plaintiff has not been able to use or obtain any
benefit out of the said trawlers, the plaintiff never was
nor is bound by the obligation under the agreement and the
modification thereof and was entitled to and had duly re-
scinded the same and the plaintiff had in the premises
suffered loss and damages which the first defendant is bound
to compensate and such loss and damage is assessed reasona-
bly at Rs.39,64 341 particulars whereof have been given in
Schedule ’D’ thereof; and that the plaintiff is entitled to
recover the said sum of Rs.39,64,34 1 as money paid to and
or on account of the first defendant and expenses so in-
curred without any consideration and or for consideration
which has totally failed and/or to the use of the first
defendant.
The plaintiff accordingly claimed, inter-alia, a decla-
ration that the agreement dated 2 Ist March, 1977 and the
modifications thereof dated 2nd February, 1978 were, and are
illegal, against public policy and void; a decree for
Rs.39,64,341 against the first defendant; alternatively an
enquiry into the amount due to the plaintiff from the first
defendant and decree for a sum found due on such enquiry; in
the alternative decree for the same amount as compensation
for loss and damage and or as money paid to or expenses
incurred without any consideration or for consideration
which has totally failed or to the use of the first defend-
ant; and further and other reliefs.
In the matter of the aforesaid Suit No. 736 of 1978,
hereinafter referred to as ’the suit’, the first defendant
after receiving summons
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 26
481
and entering appearance moved on 25th April, 1979 and appli-
cation under section 34 of the Arbitration Act, 1940, here-
inafter referred to as ’the Act’, impleading the plaintiff
(instant appellant) as first respondent and Canara Bank
second defendant as second respondent stating, inter-alia,
that the agreement as modified on 2nd February, 1978 con-
tained an arbitration clause; that the agreement has been
and is perfectly binding and not violative of the conditions
of the permission granted by the Controller of Imports &
Exports; that the defects in the refrigeration system as
alleged are factually wrong; that the plaintiff, his serv-
ants and agents have themselves materially deteriorated the
machines and hence no amount was payable to the plaintiff as
claimed in the plaint; and that all the disputes, conten-
tions alleged to have arisen between the plaintiff and the
defendant were wholly covered by the said arbitration clause
contained in the agreement which was binding between the
parties. Accordingly, it was prayed that the suit and all
proceedings therein be stayed and interim orders, costs and
other reliefs be granted. The plaintiffs filed affidavit in
opposition to the application and the applicant first de-
fendant filed affidavit in reply.
The learned Single Judge in his judgment dated 11.2.
1981 held, inter alia, that there was no question of inva-
lidity for non-compliance of the conditions of the licence
granted to the first defendant-applicant as necessary per-
mission was obtained in respect of the agreement from the
Chief Controller of Imports and Exports vide his letter
dated 18th August, 1977 and the modification of the agree-
ment on 2nd February, 1978 could not and did not materially
alter its terms to impair its validity and there was sub-
stantial compliance with the obtained permission; that
though in a particular case if there was any doubt about
facts, the matter had to be decided by trial on evidence, in
this case, having regard to the admitted facts and conduct
of the parties, it was not necessary to set down the matter
for trial on evidence to determine the facts as the same
could not be disputed; that having regard to the conduct of
the parties in admitted documents, being the licence of the
petitioner granted by the Chief Controller of Import &
Export in respect of the said two trawlers and the provi-
sions of the Import and Export Control Act, 1947, and Appen-
dix 31 of the Import & Export Trade Control Hand Book for
Rules and Procedures, 1979, the correspondence between the
parties before the alleged discovery of purported mistake
and illegality by the respondent (plaintiff) and particular-
ly the letter dated 18th July, 1978 from the respondent No.
1 (plaintiff) to the applicant 1(first defendant) and the
Balance Sheet of the plaintiff (Respondent No. 1) I.T.C.
Ltd, for the year 1978, there is no question of any illegal-
ity or any mutual mistake; that the alleged
482
fundamental breach is wholly covered by the arbitration
clause as it
wide enough to include the same; that the arbitration clause
is valid and binding between the parties; that the allega-
tion of breach of contract and the claims made are within
the jurisdiction of the arbitrator; and that all the condi-
tions under section 34 of the Act have been satisfied in
this case. Accordingly the learned Judge granted stay of the
suit and directed the parties to take immediate steps for
initiation of reference under the arbitration agreement.
On appeal, the learned Division Bench by an elaborate
and erudite judgment dismissed the appeal holding, inter-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 26
alia, that in the facts and circumstances of the case it
could not be held that the trial court erred in exercising
its discretion to decide the controversy, namely, whether
the contract being void the arbitration clause also was
void, in the application without evidence and on the basis
of pleadings only, nor was the discretion exercised improp-
erly; that the learned Judge was not wrong in coming to the
conclusion that the mistake as pleaded as to quality of the
goods was not a mistake of such nature as to make the thing
contracted for something different, and in holding that
there was no case of mutual mistake of such a type as to
quality of the thing contracted for which could have avoided
the parent contract which contained the arbitration clause;
and that the learned Single Judge was right in so far as he
held that the matters were arbitrable apart from the ques-
tion of illegality of the contract. It was further held that
there was no breach of conditions of the permission or the
provisions of the Import & Export Control Act to render the
contract illegal or void; and that the Court having held
that all the contentions and allegations were arbitrable,
the granting stay in the suit was reasonable and proper.
Mr. Shanti Bhushan, the learned counsel for the appel-
lant submits, inter-alia, that the subject matter of the
suit, namely, the question whether the agreement was void
ab-initio for mutual mistake was not arbitrable at all and
the learned Courts below erred in holding so; that even
assuming but not admitting that the subject matter was
arbitrable, it having involved complicated questions of
facts the court ought not to have exercised jurisdiction on
the application under section 34 and in doing so it acted
without jurisdiction and, assuming that the court had juris-
diction, it should have decided only after taking oral and
documentary evidence and not merely on affidavits; that the
agreement itself having been void ab initio due to mutual
mistake the arbitration clause, namely, clause 18 of the
charter party, also perished with it and there was no scope
for arbitration at all and the learned
483
courts below erred in holding that all the contentions
raised and allegations made in the suit were arbitrable
under the arbitration clause; and that the agreement was
void being violative of the conditions of the permission and
for that matter the import licence and the provisions of the
Import and Export Control Act.
Mr. C.S. Vaidyanathan, the learned counsel for the
respondent refuting submits that there having been no mutual
mistake so as to invalidate the agreement, the arbitration
clause remains binding and the subject matter of the suit
has rightly been held to be arbitrable; that the court
rightly exercised jurisdiction on the application under
section 34 of the Arbitration Act on the basis of the affi-
davits and at no stage before argument the appellant as
respondent No. 1 applied to the court for permission to
adduce oral evidence, and stay of the suit was granted in
accordance with law on the basis of the evidence on record;
that the agreement as modified was not void on the ground of
violation of the permission or of the import licence or of
the provisions of the Import & Export Control Act; and that
the direction to proceed to arbitration is just and proper
and the respondent has no objection to a Retired Supreme
Court Judge being appointed arbitrator.
The first question to be decided in this appeal, there-
fore, is whether in an application under section 34 of the
Indian Arbitration Act the court has jurisdiction to decide
the validity of the Contract containing the arbitration
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 26
clause, and if so, whether it has to be decided on affida-
vits or on evidence.
To decide the question we may conveniently refer to the
provisions of section 34 of the Arbitration Act;
Section 34: Power to stay legal proceedings
where there is an arbitration agreement. Where
any party to an arbitration agreement or any
person claiming under him commences any legal
proceedings against any other party to the
agreement or any person claiming under him in
respect of any matter agreed to be referred,
any party to such legal proceedings may, at
any time before filing a written statement or
taking any other steps in the proceedings,
apply to the judicial authority before which
the proceedings are pending to stay proceed-
ings; and if satisfied that there is no suffi-
cient reason why the matter should not be
referred in accordance with the arbitration
agreement and that the applicant was, at the
time, when the proceedings were commenced, and
484
still remains, ready and willing to do all
things necessary to the proper conduct of the
arbitration, such authority may make an order
staying the proceedings.
This section deals with the staying of a suit where
there is an arbitration agreement concerning the subject-
matter of the suit and between the same parties, for the
Court to have power to exercise the discretion conferred
upon it by this section, there must have been a valid agree-
ment to submit to arbitration. Where the objection is that
the arbitration is a nullity, it amounts to an objection of
want of jurisdiction. The term "arbitration agreement"
includes "agreement to refer", and "submission" to arbitra-
tor. A submission forming part of a void contract is itself
void and cannot be enforced. Where a firm of bookmakers had
engaged in betting transactions with the defendants on the
terms that any dispute which might arise should be referred
to arbitration, it was held that the whole contract was void
and unenforceable and that the defendants could not be
compelled to submit to arbitration: Joe Lee v. Lord Dalneny,
[1927] 1 Ch. 300. Where there is no valid arbitration agree-
ment on the subject matter of the suit, there is no justifi-
cation for staying a suit for that will deprive the plain-
tiff of his fight to sue on that subject matter.
In Heyman v. Darwins, [1942] A.C. 356, Lord Macmillan
pointed out at Pages 370-371:
"If it appears that the dispute is whether
there has ever been a binding contract between
the parties, such a dispute cannot be covered
by an arbitration clause in the challenged
contract. If there has never been a contract
at all, there has never been as part of it an
agreement to arbitrate. The greater includes
the less. Further, a claim to set aside a
contract on such grounds as fraud, duress or
essential error cannot be the subject matter
of a reference under an arbitration clause in
the contract sought to be set aside. Again, an
admittedly binding contract containing a
general arbitration clause may stipulate that
in certain events the contract shall come to
an end. If a question arises where the con-
tract has for any such reason come to an end I
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 26
can see no reason why the arbitrator should
not decide that question. It is clear, too,
that the parties to a contract may agree to
bring it to an end to all intents and purposes
and to treat it as if it had never existed. In
such a case, if there be an arbitration clause
in the contract, it perishes with the con-
485
tract. If the parties substitute a new con-
tract for the contract which they have abro-
gated the arbitration clause in the abrogated
contract cannot be invoked for the determina-
tion of questions under the new agreement. All
this is more or less elementary."
Earlier in Monro v. Bognor Urban District Council,
[1915] 3 K.B. 167; where a building contract had been en-
tered into between the plaintiff and the defendants for a
construction of sewerage works contained an arbitration
clause which provided that if at any time any question,
dispute or difference should arise between the parties upon
or in relation to or in connection with the contract, the
matter should be referred to arbitration and during the
progress of the works disputes arose between the parties
mainly as to the nature of the site upon which the works had
to be carried out, which the plaintiff alleged was different
from that which he had been led to believe by the specifica-
tions. The plaintiff having brought an action against the
defendants claiming, inter alia, damages for fraudulent
misrepresentation whereby he was induced to enter into the
contract, the defendants took out a summons asking that all
proceedings in the action be stayed and the matter be re-
ferred to arbitration. It was held that the action, being
based on fraud, referred to matters wholly outside the
powers of the arbitrator, with which he could not possibly
deal, and so could not be said to be a question, dispute or
difference upon or in relation to or in connection with the
contract and as such referable to arbitration under the
arbitration clause.
In Jawaharlal Burman v. Union of India, [1962] 3 S.C.R.
769 it was held that section 32 of the Act creates a bar
against the institution of suits with regard to an arbitra-
tion agreement or award on any ground whatsoever. Thus if a
party affirms the existence of an arbitration agreement or
its validity it is not open to the party to file a suit for
the purpose of obtaining a declaration about the existence
of the said agreement or its validity. The bar to the suit
thus created by section 32 of the Act inevitably raises the
question as to what remedy is open to a party to adopt in
order to obtain an appropriate declaration about the exist-
ence or validity of an arbitration agreement. 1t was held
that having regard to the scheme of sections 31, 32 and 33
of the Act in matters which fail within the bar created by
section 32, if a suit cannot be filed it is not necessarily
intended that an application can be made under the Court’s
powers provided for by section 31 and impliedly recognised
by section 32 of the Act. In the later part of section 33 an
application can be made to have the effect or purport of the
agreement
486
determined but not its existence. That means that an appli-
cation to have the effect of the agreement can be made
provided the existence of the agreement is not in dispute,
and that a party affirming the existence of an arbitration
agreement cannot apply under section 3 for obtaining a
decision that the agreement in question exists.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 26
In Waverly Jute Mills Co. Ltd. v. Raymon & Co. (India)
Pvt. Ltd., [1963] 3 S.C.R. 209; A.I.R. 1963 S.C. 90 the
Constitution Bench reiterated the decision in Khardah Co.
Ltd. v. Raymon & Co. India Ltd., [1963] 3 S.C.R. 183 where
it was held that if a contract is illegal and void, the
arbitration clause which is one of the terms of the contract
thereof must also perish along with it and that a dispute
relating to the validity of the contract is in such a case
for the court and not for the arbitration to decide. Where
the arbitration clause is a term of the particular contract
whose validity is in question it has no existence apart from
the impugned contract and must perish with it.
In Renusagar Co. v. General Electric Co., [1985] 1
S.C.R. 432 at page 507 it has been reiterated that though
section 34 of the Arbitration Act, 1940 confers a discretion
upon the Court in the matter of granting stay of legal
proceedings where there is an arbitration agreement, it
cannot be disputed that before granting the stay the Court
has to satisfy itself that arbitration agreement exists
factually and legally and that the disputes between the
parties are in regard to the matters agreed to be referred
to arbitration and that decided cases have taken the view
that the Court must satisfy itself about these matters
before the stay order is issued. In other words, Court under
section 34 must finally decide those issues before granting
stay.
Among High Court decisions reference may be made to
Banwari Lal v. Hindu College, Delhi, A.I.R. 1949 East Punjab
165 wherein it has been held at paragraph 33 that the Arbi-
tration Act has been enacted merely with the object of
consolidating the law relating to arbitrations, and the
question of the existence or validity of the contract con-
taining an arbitration agreement being not a matter falling
within the purview of the Act, it cannot be said, with any
show of reason, that section 32 takes away the jurisdiction
of the courts to give appropriate relief in suit brought
either to contest or to establish, the existence or validity
of the contract. In Johurmull Parasram v. Louis Dreyfus Cx.
Ltd., 52 C.W.N. (1947-48) 137; A.I.R. 1949 Cal. 179 it was
held at para 14 that the court must consider a suit as it is
pleaded and framed. If it comes to a conclusion that a suit
as pleaded in a suit on the contract or arising out of the
contract containing the arbitration clause
487
then the suit should be stayed. But on the other hand if the
suit is pleaded as a suit independent of the contract then
the Court has no power to stay the suit although it is
satisfied that the frame of the suit is merely a means of
avoiding the consequences of alleging the true nature of the
claim. In considering the question of stay of the suit the
Court is not entitled to go into the question as to what is
substantially the nature of the claim. So also in Pramada
Prasad v. Sagar Mal Aggarwal, A.I.R. 1952 Patna 352 it was
observed that from the language of the Section 34 it is
clear that party can apply to stay a legal proceeding only
when the repudiation is of the right or obligation in re-
spect of any matter agreed to be referred, and not when the
very existence of the agreement is repudiated. The court
relied on the decision in Monro v. Bognor Urban District
Coun, [1915] 3 K.B. 167. In Narsingh Prasad v. Dhanraj
Mills, I.L.R. 21 Patna 544; A.I.R. 1943 Pat 53 Harries, C.J.
held that where an agreement is impeached on the ground of
fraud and the dispute is as to the factum or validity of
contract, such a dispute does not fail under the arbitration
clause and should be decided by the Court. Similarly in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 26
Birla Jute Manufacturing Co. Ltd. v. Dulichand, AIR 1953
Calcutta 450 it was held at paragraph 15 that a dispute as
to the validity of the contract cannot be held to be within
an arbitration agreement contained in the contract itself
and such a dispute cannot be referred to arbitrators or
dealt with by them under such an agreement, unless the
parties agreed to include it in the arbitration clause.
Otherwise where the contract itself is repudiated in the
sense that its original existence or its binding force is
challenged, for example, where it is said that the parties
were never ’ad idem’ or where it is said that the contract
is voidable ad initio on the ground of fraud, misrepresenta-
tion or mistake and it has been avoided, the parties are not
bound by any contract and escape the obligation to perform
any of its terms, including the arbitration clause, unless
the provisions of that clause are wide enough to include the
question of jurisdiction as well. In W.F. Ducat & Co. Pvt.
Ltd. v. Hiralal Pannalal, A.I.R. 1976 Calcutta 126, Salil K.
Roy Choudhary, J. held at paragraph 8 that where in a suit
the plaintiff alleges that the contract containing the
arbitration clause is void and illegal and prima facie it
appears that there are sufficient grounds on which the
legality of the said contract has been challenged for non-
compliance of the statutory requirement, the court should
decline to exercise discretion in favour of the stay of the
suit. Similarly in General Enterprises v. Jardine Handerson
Ltd., A.I.R. 1978 Calcutta 407, Sabyasachi Mukharji, J., as
his Lordship then was, held that if the contract containing
the arbitration clause was obtained by fraud the stay of the
suit could not be granted under Section 34 of the Act. Thus,
while there is not doubt
488
about the law as enunciated in the above English and Indian
decisions, namely, where the validity, existence or legality
of the contract is challenged in the suit on grounds de
hors, independent of, or external to the terms or stipula-
tions of the contract, the court in an application under
Section 34 of the Act shall have no jurisdiction to go into
the question, and that in large majority of cases it would
be applicable, in appropriate cases, having regard to the
nature of the dispute raised in the pleadings of the suit,
the compass and scope of the arbitration clause in the
contract, the surrounding facts and circumstances of the
case having a bearing on the question of genuine grievance
falling outside or inside the arbitration agreement and the
objects and spirit of the Arbitration Act, the court may be
justified in deciding the validity, existence or legality of
the challenged contract containing the arbitration agree-
ment. In Heyman v. Darwins, (supra) Viscount Simon, L.C.
stated thus:
"if the dispute is whether the contract which
contains the clause has ever been entered into
at all that issue cannot go to arbitration
under the clause, for the party who denies
that he has ever entered into the contract is
thereby denying that he had ever joined in the
submission. Similarly, if one party to the
alleged contract is contending that it is void
ab initio (Because for example, the making of
such a contract is illegal), the arbitration
clause cannot operate for on this view the
clause itself also is void. But, in a situa-
tion where the parties are at one in asserting
that they entered into a binding contract, but
a difference has arisen between them whether
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 26
there has been a breach by one side or the
other, or whether circumstances have arisen
which have discharged one or both parties from
further performance, such differences should
be regarded as difference which have arisen
’in respect of’ or ’with regard to’ or ’under’
the contract, and an arbitration clause which
uses these, or similar, expressions should be
construed accordingly."
Section 34 of the Arbitration Act, deals with the staying of
a suit where reference concerning the subject matter of the
suit and between the same parties is pending. This section
corresponds to Section 4 of the English Arbitration Act.
Whether a particular dispute arising out of a particular
contract is referable to arbitration or not must necessarily
depend on the intention of the parties as embodied in the
arbitration clause. If the dispute is squarely covered by
the arbitration clause the
489
relevant provisions of the Act will be attracted. Section 32
puts a bar to suits contesting arbitration agreement or
award by providing that notwithstanding any law for the time
being in force, no suit shall lie on any ground whatsoever
for a decision upon the existence, effect or validity of an
arbitration agreement or award, nor shall any arbitration
agreement or award be enforced, set aside, amended modified
or in any way affected or otherwise than as provided in the
Act. Section 33 of the Act provides that any party to an
arbitration or any person claiming under him desiring to
challenge the existence or validity of an arbitration agree-
ment or an award to have the effect of either determined
shall apply to the Court and the Court shall decide the
question on affidavits: Provided that where the Court deems
it just and expedient it may set down the application for
hearing on other evidence also, and it may pass such orders
for discovery and particulars as it may do in a suit.
It may be noted that section 32, 33 and 34 speak of an
arbitration agreement as defied in section 2(a) of the Act
which means a written agreement to submit present or future
differences to arbitration, whether an arbitrator is named
therein or not. In the instant case the arbitration clause
forms a part of the agreement, namely, the charter party.
The question is whether the validity or otherwise of the
charter party itself can be said to have been covered within
the arbitration clause. On scrutiny of clause 18 we find
that any dispute or difference in respect of the construc-
tion, meaning or effect or as to the rights and liabilities
of the parties thereunder or any other matter arising out of
this agreement shall be referred to arbitration. Can the
validity of the contract itself as embodied in the charter
party be said to have arisen out of the contract or can the
validity or otherwise of the contract in the charter party
itself be said to be construction, meaning or effect or
rights and liabilities of the party thereunder? In our
opinion, the answer is in the negative. The arbitration
agreement is not the same as the contract in the charter
party. It cannot, therefore, be said that the validity or
otherwise of the chartery party was covered by clause 18. In
Khardah Company Ltd. v. Raymon & Co. (India) Pvt. Ltd.,
[1963] 3 S.C.R. 183 the appellant company entered into a
contract on September 7, 1955 for the purchase of certain
goods and clause 14 thereto provided that all disputes
arising out of or concerning the contract should be referred
to the arbitration of the Bengal Chamber of Commerce. The
respondents having failed to deliver the goods as agreed the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 26
appellants applied to the Bengal Chamber of Commerce for
arbitration and an award made in favour of the appellant.
Thereupon the respondent filed an application in the High
Court of Calcutta under
490
section 33 of the Arbitration Act, 1940 challenging the
validity of the award on the ground that the contract dated
September 7, 1955 itself was illegal as it was in contraven-
tion of the notification of the Central Government dated
October 29, 1953. It was held that the dispute as to the
validity of the contract dated September 7, 1955, was not
one which the arbitrators were competent to decide under
clause 14 and that in consequences the respondents were
entitled to maintain the application under section 33 of the
Act and that where an agreement is invalid every part of it
including clause as to arbitration contained therein must
also be invalid. In Anderson Wright Ltd. v. Moran and Compa-
ny, [1955] 1 S.C.R. 862 it has been laid down that in order
that a stay may be granted under section 34 of the Act, it
is necessary, among others, that the legal proceeding which
is sought to be stayed must be in respect of a matter agreed
to be referred and the Court must be satisfied that there is
no sufficient reason why the matter should not be referred
to an arbitrator in accordance with the arbitration agree-
ment. The question whether the dispute in the suit falls
within the arbitration clause really pre-supposes that there
is such agreement and involves consideration of two matters,
i.e. (i) what is the dispute in the suit and (ii) what
dispute the arbitration clause covers. It is incumbent upon
the Court to decide whether there is a binding contract for
arbitration between the parties. If it is found that the
dispute in the suit is not covered by the arbitration clause
the application for stay may be dismissed. In Damodar Valley
Corporation v.K.K. Kar, [1974] 2 S.C.R. 240 it has been held
that as the contract is an outcome of the agreement between
the parties it is equally open to the parties thereto and to
Court to bring to an end or to treat it as if it never
existed. It may also be open to the parties to terminate
previous contract and substitute in the place a new contract
or alter the original contract in such a way that it cannot
subsist. In all these cases since the entire contract is put
to an end to, the arbitration clause, which is a part of it,
also perishes along with it. Where, therefore, the dispute
between the parties is that the contract itself does not
subsist either as a result of its being substituted by a new
contract or by rescission on alteration, that dispute cannot
be referred to the arbitration as the arbitration clause
itself would perish if the averment was found to be valid.
As the very jurisdiction of the arbitrator is dependent upon
the existence of the arbitration clause under which he is
appointed, the parties have no right to invoke a clause
which perished with the contract. In case of rescission it
would put an end to the rights of the parties to the con-
tract in future but it may permit claiming of damages either
for previous breaches or for the breach which constitute the
termination. The contract being consensual, the question
whether the
491
arbitration clause survives or perishes would depend on the
nature of the controversy and its effect upon the existence
of survival of the contract itself. A dispute as to the
binding nature of the contract cannot be determined by
resort to arbitration because the arbitration clause itself
stands or falls according to the determination of the ques-
tion in dispute. As was held in Hirji Mulji v. Cheong Yue
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 26
Steamship Co., [1926] A.C. 497, "a contract that has deter-
mined is in the same position as one that has never been
concluded at all". In Heyman v. Darwins, (supra) Lord Porter
pointed out "that it is not in every instance in which it is
claimed that the arbitrator has no jurisdiction the Court,
will refuse to stay an action. If this were the case such a
claim would always defeat an agreement to submit disputes to
arbitration, at any rate, until the question of jurisdiction
had been decided. The Court to which an application for stay
is made is put in possession of the facts and arguments and
must in such a case make up its mind whether the arbitrator
has jurisdiction or not as best it can on the evidence
before it. Indeed, the application for stay gives an oppor-
tunity for putting these and other considerations before the
court that it may determine whether the action shall be
stayed or not." These observations were accepted by S.R.
Das, J in the case of Khusiram v. Hanutmal, [1948] 53 C.W.N.
505,518 wherein it was held that where on an application
made under section 34 of the Arbitration Act for stay of a
suit, an issue is raised as to the formation, existence or
validity of the contract containing the arbitration clause,
the Court is not bound to refuse a stay but may in its
discretion, on the application for stay, decide the issue as
to the existence or validity of the arbitration agreement
even though it may involve incidentally a decision as to the
validity or existence of the present contract (Emphasis
supplied). Their Lordships in Anderson Wright Ltd. v. Moran
and Company, (supra) reiterating the above passage observed:
"We are in entire agreement with the view enunciated above."
Thus, where in an application under section 34 of the Act an
issue is raised as to the validity or existence of the
contract containing the arbitration clause, the court has to
decide first of all whether there is a binding arbitration
agreement, even though it may involve incidentally a deci-
sion as to the validity or existence of the parent contract.
The court has to bear in mind that a contract is an agree-
ment enforcible at law and that it is for the parties to
make their own contract and not for the court to make one
for them. Court is only to interpret the contract. The
stipulations in the contract have, therefore, to be examined
in the light of the dispute raised in the pleadings of the
suit. If it is found that the dispute raised in the suit
outside or independent of the contract it follows that the
arbitration clause will not encompass that dispute. However,
as the parties were
492
free to make their own contract they were also free to have
agreed as to what matters would be referred to arbitration.
If the arbitration clause is so wide as to have included the
very validity or otherwise of the contract on the grounds of
fraud, misrepresentations, mutual mistake or any valid
reason the arbitrator will surely have jurisdiction to
decide even that dispute. Two extreme cases have to be
avoided, namely, if simply because there is an arbitration
clause all suits including one questioning the validity or
existence or binding nature of the parent contract is to be
referred to arbitrator irrespective of whether the arbitra-
tion clause covered it or not, then in all cases of con-
tracts containing arbitration clause the parties shall be
deprived of the right of a civil suit. On the other hand if
despite the arbitration clause having included or covered ex
facie even a dispute as to the existence, validity or bind-
ing nature of the parent contract, to allow the suit to
proceed and to deprive the arbitrator of his jurisdiction to
decide the question will go contrary to the policy and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 26
objects of the Arbitration Act as embodied in Sections 32,
33 and 34 of the Act. Both the extremes have, therefore, to
be avoided. The proper approach would be to examine the
issues raised in the suit and to ascertain whether it
squarely fails within the compass of the arbitration clause
and take a decision before granting the stay of the suit. If
an issue is raised as to the formation existence or validity
of the contract containing the arbitration clause, the court
has to exercise discretion to decide or not to decide the
issue of validity or otherwise of the arbitration agreement
even though it may involve incidentally a decision as to
validity or existence of the challenged contract. Should the
court find the present contract to be void ab initio or
illegal or non-existent, it will be without jurisdiction to
grant stay. If the challenged contract is found to be valid
and binding and the dispute raised in the suit covered by
the arbitration clause, stay of the suit may be justified.
In the instant case considering the issues raised, the
arbitration clause and surrounding circumstances and the
part played by the parties pursuant to the charter party
since execution to the modification and thereafter till
objection raised by the appellant plaintiff, we are of the
view that the learned trial court did not err in proceeding
to decide the issue of validity or legality of the parent
contract.
The question whether the validity and legality of the
parent contract could be decided without taking oral evi-
dence need not detain us long. All the relevant documents
and affidavits were before the court and were considered.
Mr. Shanti Bhushan submits that in deep sea fishing, use of
trawlers, requirement and standard of refrigeration system
in the trawlers so as to maintain 20F temperature in their
fish-
493
holds are highly technical matters and given the opportunity
the appellant plaintiff could have produced expert evidence
in the matter. Counsel, however, states, that at no stage of
the proceedings before argument any written or even oral
application was made seeking permission to adduce oral
evidence. Admittedly, it was only during agreement that oral
prayer was made. We are, therefore, of the view that no
illegality was committed by the trial court in this regard
considering the facts and circumstances of the case. The
learned judge rightly observed that if there was any doubt
about facts, the matter had to be decided by trial on evi-
dence, in this case the admitted facts could not be disput-
ed. The learned courts have also exercised discretion to
grant stay. Even if it appears that the discretion could
have also been exercised to decide the issue of invalidity
in a trial on evidence adduced, this court would not substi-
tute its view for that of the trial court, unless the ends
of justice required it to be done. Since it was said by the
Court of Appeal in Ormerod v. Todmordon, [1882] 8 Q.B.D. 664
that while it had jurisdiction to review the descreation of
the judge it would not do so except in a case in which it
clearly though that the judge had wrongly exercised his
discretion and that an injustice had thereby been done by
his order. This was approved in Charles Osenton & Co. v.
Johnston, [1942] A.C. 130 holding that a legitimate exercise
of the jurisdiction would not be disturbed in appeal but a
wrongful exercise of the discretion will be corrected by the
House of Lords. Referring to Gardner v. Jay, [1885] 29 Ch.
D. it was ruled in the Printers (Mysore) Pvt. Ltd. v. Pothan
Joseph, [1960] 3 S.C.R. 713 that this court would not light-
ly interfere under Article 136 of the Constitution with the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 20 of 26
concurrent exercise of discretion of the Courts below under
Section 34 of the Act. Before it can justly do so, the
appellant must satisfy the court, on the relevant facts
referred by the courts below, that they exercised their
discretion in a manifestly unreasonable or perverse way,
which was likely to defeat the ends of justice. The appel-
lant has failed to do so in this case.
The next question is whether the learned courts below
were correct in holding that there was no mutual mistake so
as to render the agreement void ab initio under section 20
of the Contract Act.
Section 20 of the Indian Contract Act, 1872 provides
that where both the parties to an agreement are under a
mistake as to a matter of fact essential to the agreement,
the agreement is void. The explanation to the section says
that an erroneous opinion as to the value of the thing which
forms subject-matter of the agreement is not to be deemed a
mistake as to a matter of fact. Where the parties make
mutual mis-
494
take misunderstanding each other and are at cross purposes,
there is no real correspondence of offer and acceptance and
the parties are not really consensus ad idem. There is thus
no agreement at all; and the contract is also void. A common
mistake is there where both parties are mistaken about the
same vital fact although both parties are ad idem, e.g. the
subject-matter of the contract has already perished. The
contract in such a case is void as the illustrations to the
section make clear. In U.P. Government v. Nanhoo Mal, A.I.R.
1960 Allahabad 420 it has been observed that section 20 is
concerned with common mistake of fact and not mutual mis-
take. A common mistake is made or shared alike by both while
mutual means made or entertained by each of the persons
towards or with regard to each other. In Cooper v. Phibbs,
[1867] L.R. 2 H.L. 149, A agreed to take a lease of a fish-
ery from B, though contrary to the belief of both parties at
the time, A was tenant for life of the fishery and B had no
title at all. Lord Westbury applied the principle that if
parties contract under a mutual mistake and misapprehension
as to their relative and respective rights, the result is
that the agreement is liable to be set aside as having
proceeded upon a common mistake. The transfer of ownership
being impossible, the stipulation was naturali ratione
inunitilis. This principle of Cooper v. Phibbs has been
followed in Earl Beauchamp v. Winn [1873] 6 H.L. 223 and
Hudders field Banking Co. v. Henry Lister & Sons, [1895] 2
Ch. 273. However, Lord Atkin in Bell v. Lever Bros Ltd.,
[1932] A.C. 161; (1931) All E.R. Rep. 1, 27 followed in
Kennedy v. Panama Royal Mail Co., [1867] L.R. 2 Q.B. 580 and
Smith v. Hughes, [1871] L.R. 6 Q.B. 597 described the state-
ment of Westbury too wide and said that the correct view was
that there was a contract which the vender was either inca-
pable of performing or had committed breach of a stipulation
as to title; the contract was unenforceable but not void. In
Bell v. Lever Bros Ltd., (supra) an agreement of service
between the company and two of the directors of its subsidi-
ary company was terminated on payment of compensation. The
parties proceeded on the assumption that the service agree-
ment was not liable to immediate termination by reason of
misconduct of the directors which assumption proved to be
mistaken. Fraud was however negatived. In an action by the
company for recession of contract and repayment of moneys
paid the agreement was set aside on the ground of mutual
mistake as to the quality of the service contract. The
accepted proposition was that whenever it is to be inferred
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 21 of 26
from the terms of the contract or its surrounding circum-
stances that the consensus has been reached upon the basis
of a particular contractual assumption, and that assumption
is not true, the contract is avoided; i.e. it is void ab
initio if the assumption is of present fact and it ceases to
bind if the assumption is of future
495
fact. The assumption must have been fundamental to the
continued validity of the contract or a foundation essential
to its existence. Lord Atkin observed that the common stand-
ard for mutual mistake and implied conditions as to the
existing or as to future fact is: Does the state of new
facts destroy the identity of the subject-matter as it was
in the original state of facts? In the words of Lord Than-
kerton the error must be such that it either appeared on the
face of the contract that the matter as to which the mistake
existed was an essential and integral element of the sub-
ject-matter of the contract or was an inevitable inference
from the nature of the contract that all parties so regarded
it. Where each party is mistaken as to the other’s inten-
tion, though neither realises that the respective promises
have been misunderstood, there is mutual mistake. The illus-
tration in Cheshire and Fifoots Law of Contract is, if B
were to offer to sell his Ford Comina Car to A and A were to
accept in the belief that the offer related to a Ford Zeph-
yr. In such a case, no doubt, if the minds of the parties
could be probed, genuine consent would be found wanting. But
the question is not what the parties had in their minds, but
what reasonable third parties would infer from their words
or conduct. The court has to ascertain "the sense of the
promises". In other words, it decides whether a sensible
third party would take the agreement to mean what A under-
stood it to mean or what B understood it to mean, or whether
indeed any meaning can be attributed to it at all. Blackman
J in Smith v. Hughes, [1871] L.R. 6 Q.B. 597,607 said "if
whatever a man’s real intention may be he so conducts him-
self what a reasonable man would believe that he was assent-
ing to the terms proposed by the other party, and that other
party upon that belief enters into the contract with him,
the man thus conducting himself would be equally bound as if
he had intended to agree the other party’s terms".
This case establishes that a contract is void at law
only if some term can be implied in both offer and accept-
ance which prevents the contract from coming into operation.
In Solle v. Butcher, [1950] 1 K.B. 671 (691) Lord Denning
said that once a contract has been made, that is to say,
once the parties, whatever their in most states of mind,
have to all outward appearances agreed with sufficient
certainty in the same terms on the subject-matter, then the
contract is good unless and until it is set aside for fail-
ure of some condition on which the existence of the contract
depends, or for fraud, or on some equitable ground. Neither
party can rely upon his own mistake to say that it was a
nullity from the beginning, no matter that it was a mistake
which to his mind was fundamental, and no matter that the
other party knew that he was under a mistake. A fortiori, if
the other party did not know of the
496
mistake but shared it. There is no doubt that the applica-
tion of the doctrine of mutual mistake depends upon the true
construction of the contract made between the parties. A
mutual misunderstanding will not nullify a contract but only
if terms of the contract construed in the light of the
nature of the contract and of the circumstances believed to
exist at the time it was done show that it was never intend-
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 22 of 26
ed to apply to the situation which in reality existed at
that time, will the contract be held void. Mistake as to the
quality of the article contracted for may not always avoid
the contract. As Lord Atkin said in Bell v. Lever Bros Ltd.
(supra) mistake as to the quality of the thing contracted
for raises more difficult questions. In such a case a mis-
take will not affect assent unless it is the mistake of both
parties, and is as to the existence of some quality which
makes the thing without the quality essentially different
from the thing as it was believed to be. A distinction has,
therefore, to be made between a mistake as to substance or
essence on the one hand, and a mistake as to quality or
attributes on the other. A mistake of the former type, will
avoid the contract whereas a mistake of the latter type will
not. Such a distinction was made in Kennedy v. Panama, Royal
Mail Co. Ltd., (supra). It may be said that if there be
misapprehension as to the substance of the thing there is no
contract; but if it be a difference in some quality or
accident, even though the misapprehension may have been the
actuating motive to the purchaser, yet the contract remains
binding. Thus a mistake as to an essential and integral
element in the subject-matter of the contract will avoid the
contract. A mistake will not affect assent unless it is the
mistake of both parties, and is as to the existence of some
quality which makes the thing without the quality essential-
ly different from the thing as it was believed to be. A
distinction, therefore, should be drawn between a mistake as
to the substance of the thing contracted for, which will
avoid the contract and mistake as to its quality which will
be without effect. According to circumstances even a mistake
as to the substance of the thing contracted for may not
necessarily render a contract void as was observed in Solle
v. Butcher (supra). Similarly in Frederick E. Rose (London)
Ltd. v. William H. Pim Junior & Co. Ltd., [1953] 2 Q.B. 450
where both parties entered into a contract for the sale of
horse-beans, which were quite different from the feveroles
which they each believed them to be, yet the contract was
held not to be void. Thus there must be a difference so
complete that, if the contract were enforced in the actual
circumstances which have unexpectedly emerged, this would
involve an obligation fundamentally different from that
which the parties believed they were undertaking. In Sheikh.
Brothers Ltd. v. Arnold, [1957] A.C. 136; Belly. Lever Bros
(supra) was applied.
497
Applying the above principles of law to the facts of the
instant case, we find that the two fishing trawlers Ave
Maria-I and Ave Mariall were imported by the respondent on
30.1.1974 and were operated by him based at Vishakapatnam.
At the time of negotiations survey report relating to the
trawlers dated 20.2. 1977 of ABS Worldwide & Technical
Services India Pvt. Ltd. was handed over by the respondent
to the appellant and thereafter the agreement was executed
on 21.3.1977. Delivery of the trawlers was to be made seven
days after receipt of the approval or no objection certifi-
cate for carrying out inspection to ascertain repairs to be
carried out for making the trawlers fully operational and to
ascertain the cost of such repairs. On 10.7. 1977 trawlers
were delivered to the charterer for inspection and repairs.
On 12.11.1977 the charterer wrote to the owner asking for
payment of hire charges from 1.10.1977 and pointing out
delays in repairs. The owner also requested the charterer to
pay port charges with effect from 1.10.1977. On 2.2.1978 the
charter party was modified to the extent that charter hire
would commence from 15.1.1978 and that as the charterer had
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 23 of 26
incurred substantial charges on repairs the owner shall bear
only Rs. 1.5 lakhs per trawler for repairs carried out up to
the commencement of the charter hire. The charter hire was
revised to Rs.6,25,000 per trawler per year and an amount of
Rs.6,70,000 paid towards deposit and charter hire from
15.1.1978 to May 1978. In the first week of March, 1978 the
charterer paid Rs. 1,04,000 towards charter hire for June
1978. On 18.7.1978 the charterer wrote to the owner setting
out payments made and claiming adjustment of Rs.90,000
towards repair charges and transferring Rs.14,000 towards
charter hire. It was only on 14.9.1978 that the charterer
for the first time raised some complaints and objections on
the trawlers and questioned the very validity of the agree-
ment. On 14.9. 1978 the trawlers were inspected by Kamath &
D’Abrie Marine Surveyors who submitted their report on 26.9.
1978 and the suit was filed on 29.9. 1978.
The appellant-plaintiff’s averment, as we have already
mentioned, is that the trawlers suffered from inherent and
latent defects in the refrigeration system which was an
essential part of such trawlers and which were not discover-
able by ordinary diligence at the time of entering into the
agreement on 21st March 1977 and as such they were not fully
operational. It is not their grievance that there was no
refrigeration system at all in the trawlers but that only it
was not of a particular standard, namely that even after
extensive repairs it could not be brought to the standard of
minus 20 degree F but attained only minus 10 degree F. The
learned counsel for the appellant submits that
498
for deep sea fishing the temperature in the trawler’s fish-
hold has to be minus 20 degree F and minus 10 degree F would
not be adequate and as a result the trawlers cannot be used
for deep sea fishing. The grievance has been made that no
opportunity to lead expert evidence on this question was
available to the appellant. The question, therefore, arises
under the facts and circumstances of the case, namely,
whether the deficiency in the refrigeration systems to the
extent of minus 10 degree F made the trawlers essentially
different from trawlers with a refrigeration system of minus
20 degree F. The other question is whether this standard of
the refrigeration system was in the minds of the parties at
the time of entering into the contract and there was a
mutual mistake regarding this, and the contracting minds
were, therefore, not ad idem. From the series of steps taken
for repairs and the stipulations in the charter party in-
cluding the modifications thereof we are unable to hold that
it was a case of mutual mistake as to a quality which made
the trawlers transferred essentially different from the
trawlers that the parties in their minds agreed to transfer.
This being the position we have to agree with the learned
courts below that there was no mutual mistake and the con-
tract would not be avoided on this ground.
The next question is that of illegality or otherwise of
the agreement. The learned trial court exercised its discre-
tion to go into the question and arrived at the finding that
there was no illegality on the ground of violation of the
permission or the condition of licence granted by the Chief
Controller of Exports and Imports. The learned lower appel-
late court upheld that finding. It is settled law that where
the subject matter of a reference is illegal no award can be
of any binding effect. In Taylor v. Barnett, [1953] W.L.R.
562; the plaintiff had agreed to purchase goods from the
defendants. The defendants had agreed to deliver. The goods
were subject to the price control, sales at price in excess
of the control price being forbidden by regulations at the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 24 of 26
time of making the contract (though not at the time of the
delivery). The control price was less than the agreed price.
The umpire awarded the plaintiffs damages and the award was
good on the face of it, but it was held that the award
should be set aside for illegality. If the contract itself
was illegal, the controversy as to whether it was illegal or
not would not be a dispute arising out of the contract as
also would be the question whether the contract was void ab
initio. When, however, it is found that a binding contract
was made which was not illegal what follows from such a
contract would be covered by the expression "dispute arising
out of the contract". To stay a suit under section 34 of the
Act the Court has to see, inter-alia, whether there was a
valid agreement to have the dispute concerned settled by
arbitration and that the
499
proceedings are in respect of a dispute so agreed to be
referred. In Taylor v. Barnett, (supra) Singleton J; ex-
pressed the opinion that an arbitrator is guilty of miscon-
duct if he knows or recognises that a contract is illegal
and thereafter proceeds to make award upon dispute arising
under that contract. The illegality of a contract can be an
issue in deciding want of jurisdiction. The first and essen-
tial pre-requisite to making an order of stay under section
34 of the Act, as was ruled in Anderson Wright Ltd. (supra)
is that there is a binding arbitration agreement between the
parties to the suit which is sought to be stayed. Public
policy imposes certain limitations on the freedom of con-
tract by forbidding the making of certain contracts. In such
cases though all other requisites for formation of the
contract are complied with, parties to such forbidden con-
tracts are not allowed to enforce any rights under them. In
clear cases the law strikes at the agreement itself by
making the contract illegal. However, the effect and nature
of illegality will depend upon on the facts and circum-
stances of each case. Thus, the effects of illegality are by
no means uniform. In other words, the effect of illegality
is not the same in all cases. Where a statute makes a con-
tract illegal or where a certain type of contract is ex-
pressly prohibited there can be no doubt that such a con-
tract will not be enforcible. In Rearbitration between
Mahmoud and Isphani, [1921] 2 K.B. 716 by a war time statu-
tory order it was forbidden to buy or sell linseed oil
without a licence from the Food Controller. The plaintiff
had a licence to sell to other licenced dealers. He agreed
to sell and deliver to the defendant a quantity of linseed
oil, and before the contract was made, asked the defendant
whether he possessed a licence, the defendant falsely as-
sured him that he did. Subsequently; however, the defendant
refused to accept the oil on the ground that he had no
licence. The plaintiff having brought an action for damages
for nonacceptance, the Court of Appeal refused to entertain
the action even if the plaintiff-was ignorant, at the time
the contract was made, of the facts which brought it within
the statutory prohibition observing that it was a clear and
unequivocal declaration by the legislature in the public
interest that this particular kind of contract shall not be
entered into. A contract which was not illegal from the
beginning may be rendered illegal later by the method of
performance which did not comply with the statutory require-
ments. The appellant’s burden was to show that the charter
party was illegal to take it out of the arbitration clause
for if the contract is illegal and not binding on the par-
ties the arbitration clause would also be not binding. Once
it is shown to have been illegal it would be unenforcible as
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 25 of 26
ex turpi causa non oritur actio. Again it is a settled
principle that one who knowingly enters into a contract with
improper object cannot enforce his rights thereunder. The
learned
500
counsel for the appellant submitted that the import of
trawlers was subject to the conditions of the import li-
cence, and one of the conditions was that the goods imported
under it will be utilised in the licence holder’s factories
and that no portion thereof will be sold or will be permit-
ted to be utilised by any other party or placed with any
financier other than the banks authorised to deal in the
foreign exchange and State Financial Corporation, provided
that particulars of goods to be pledged are reported by the
licence to the licencing authorities. We are of the view
that this was a proforma condition in the licence No.
P/CC/206299 dated3.3.1971 and could not appropriately be
applied to the two imported trawlers. Needless to observe
that the appellant plaintiff was also a party to the agree-
ment of charter party in respect of the two imported trawl-
ers. We are also of the view that though it purported to be
actual user’s licence there was no violation of this condi-
tion in view of the express permission granted by the Con-
troller vide his Memo No. GG.IV/28/143/70/71/374 dated
17.8.1977 with specific reference to the licence
No.P/CC/2062299 dated 3.3.1971 allowing the chartering of
the two imported trawlers to be delivered to plaintiff M/s.
I.T.C. India Ltd. We also agree with the learned courts
below that the modifications dated 2.2.1978 did not make any
alteration so as to make the agreement contrary to the terms
and conditions of the permission inasmuch as the permission
was for a period of three years. The option to continue hire
of the trawler for a further period of three years did not
ipso facto violate the permission. There was also no viola-
tion as to the duration of the charter party.
The next question is whether the dispute under the
charter party raised in the suit are arbitrable. The divi-
sion bench held that the learned Single Judge was right in
so far as he held that the matters were arbitrable apart
from the question of illegality, invalidity of the contract.
We agree with this view inasmuch as it is obvious that the
question of invalidity of the contract due to the alleged
mutual mistake would be de hors and independent of the
contract and as such would not be referable under the arbi-
tration clause, In so far as the question of illegality of
the charter party is concerned as the appellant plaintiff
has not established that the charter party was illegal or
void ab initio the question whether the modification as
alleged had rendered the contract illegal would be covered
by arbitration clause which reads:
"Any dispute or difference at any time arising
between the parties hereto in respect of the
construction meaning or effect or as to the
rights and liabilities of the parties afore-
said hereunder or any other matter arising out
of this
501
agreement, shall be referred to arbitration in
accordance with the subject to the provision
of the Indian Arbitration Act, 1940 or any
statutory modification or re-enactment thereto
or thereof for the time being in force and the
venue of Arbitration shall be Madras or Cal-
cutta, and not elsewhere and the Award or
Awards in such arbitration shall be made a
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 26 of 26
rule of court of competent jurisdiction at the
instance of either party".
We agree that under the above clause the reliefs claimed
in the suit other than the question of ab initio invalidity
or illegality of the contract would be referable. However,
it will be within the jurisdiction of the arbitrator to
decide the scope of his jurisdiction as we have said earlier
that the court cannot make a contract between the parties
and its power ends with interpretation of the contract
between them. The same principle also applies to the arbi-
tration agreement unless of course, the parties to the
arbitration agreement authorises the court to make and
modify the agreement for themselves.
Mr. C.S. Vaidyanathan for the respondents states that
the respondent shall have no objection to a retired Judge of
the Supreme Court being appointed as Arbitrator and the
respondents shall not raise the question of limitation as
indicated by Mr. Shanti Bhushan learned counsel for the
appellant. We have no doubt that the Arbitrator so appointed
shall proceed in accordance with law to decide the questions
including that of the jurisdiction, if raised.
In the result, we find no merit in this appeal and hence
it is dismissed leaving the parties to bear their own costs.
T.N.A. Appeal dis-
missed.
502