Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 2
CASE NO.:
Appeal (civil) 8115 of 2001
PETITIONER:
STATE OF RAJASTHAN AND ANR.
RESPONDENT:
NAV BHARAT CONSTRUCTION CO.
DATE OF JUDGMENT: 27/11/2001
BENCH:
M.B. SHAH & B.N. AGRAWAL
JUDGMENT:
JUDGMENT
2001 Supp(5) SCR 350
The Judgment of the Court was delivered by SHAH, J. C.A. No. 8115 of 2001
@; S.L.P. (C) No. 7192 of 2001. Leave granted.
Learned Senior Counsel Mr. Ashwani Kumar appearing for the appellant
contended that the judgment and decree passed by the High Court confirming
the award made by the arbitrator is on the face of it illegal because \007:
(a) Arbitrator has failed to consider counter-claim.
(b) second reference to arbitrator was not maintainable under Order 2
Rule 2 CPC, and
(c) the arbitrator has awarded interest despite the contrary condition
in the agreement.
As against this, Mr. G.L. Sanghi learned senior counsel for the respond-ent
as well as the respondent who is appearing in person submitted that in the
written statement, counter-claim or set off was neither pleaded nor proved
by the appellant before the arbitrator. He also contended that in case of
claims raised by the respondent after preparation of final bill, there is
no question of application of Order 2 Rule 2 CPC as rightly held by the
arbitrator and the Courts below. For the contention based on clause 23 of
the Agreement, it is submitted that the appellant never contended before
the arbitrator that clause 23 provides for non-payment of interest in such
cases. It is pointed out that neither before the arbitrator nor before die
courts below, it was contended that arbitrator had no authority to grant
interest in view of clause 23. Only conten-tion which was raised with
regard to grant of interest pendente lite for which reliance was placed on
various decisions of this Court;
We would state that the respondent who is appearing in person has in the
alternative referred to the decision rendered by this Court in State of
U.P. v. Harish Chandra & Co., [1999] 1 SCC 63 and submitted that similar
clause is interpreted by this Court and it is held that there is no such
prohibition on granting interest. He further pointed out that if such plea
was raised, he would have produced the necessary documentary evidence or
the letters written by the concerned officers and proved that interest was
payable for wrongfully with1 holding the amount due and payable.
In our view, it has been rightly pointed out that in the written statement,
appellants have not claimed any set off or title counter claim for the
alleged amount due and payable by the contractor on the alleged ground that
Account-ant General’s Office has raised objection for payment of labour
charges at accelerated rate. In our view as no such set off or claim nor
any counter claim was filed by the appellant, arbitrator has rightly not
considered the same which was sought to be raised after lapse of 4 years of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 2
reference. Further the High Court has noted that the learned Additional
Advocate General was unable to point out any legal basis to support the
contention that arbitrator was required to go into the counter-claim in the
circumstances of the present case.
There is also no substance in the contention raised by Mr. Ashwani Kumar,
learned senior counsel for the appellant that the second reference was
barred by Order 2 Rule 2 CPC As such the contention was not raised before
the High Court. In any case, the dispute with regard to the subsequent
claims arose after the first reference, that is, after the final bill was
prepared and this aspect is rightly dealt with by the Additional District
Judge,
Lastly, in the present case, the award passed by the arbitrator is reasoned
one. The contention raised by the learned counsel for the appellant that
under Clause 23 of the Agreement between the parties, contractor was not
entitled to recover any interest on delayed payment was neither raised
before the arbitrator, the District Court or before the High Court. This
question depends Upon the evidence Which may be led by the parties as well
as interpretation of clause 23 by the parties and the arbitrator. The
parties have understood that there is no bar on granting interest on
delayed payments. It appears that no such contention was raised on behalf
on behalf of the State of Rajasthan. In this view of the matter, it cannot
be held that arbitrator has committed any error apparent on the face of the
record or has misconducted himself in passing the impugned award. It is
settled law that scope for setting aside the award is limited to the
grounds available under the Arbitration Act which have been well defined by
long line of decided cases. In this view of the manner, it is not necessary
for us to consider the contention of the contractor that similar clause is
interpreted by this Court in Harsish Chandra and Company’s case (supra) and
it is held that there is no bar on granting interest. In our view as the
contention was not raised before the arbitrator or at any stage thereafter,
it is not necessary for us to deal with or decide the same in this appeal.
However, considering the dispute involved and overall circumstances of the
case, we modify the award qua the rate of interest and reduce the same at
the rate of 6% per annum. The arbitrator in paragraph 21.8.1 .of the award
has granted interest on the principal amount of claims no 1 to 8 from
1.7.1990 to 30.4.1998 and 10 to 18 from 29.4.1991 to 30.4,1998 at the rate
of 18% and the District Court has awarded interest at the rate of 15% from
the date of decree. That part of the award and decree is modified and it is
held that respondent-claimant is entitled to recover the said amount with
interest at the rate of 6% only. The appeal is disposed of accordingly.
Parties to bear their own cost of litigation all throughout.
S.LP. (C) No. 6172 of 2001
In view of the aforesaid order, the S.L.P. filed by the contractor for
enhancement of interest rate from 15% to 18% would riot survive and is
dismissed.