Full Judgment Text
$~J-1
* IN THE HIGH COURT OF DELHI AT NEW DELHI
Judgment reserved on: 30.05.2023
% Judgment pronounced on: 03.07.2023
+ ARB.P. 1048/2022
MS GOYALA INFRA PROJECTS PVT LTD ..... Petitioner
` Through: Mr. Kushagra Bansal, Adv.
versus
THE ENGINEER IN CHIEF, MILITARY ENGINEERING
SERVICE ..... Respondent
Through: Mr. Bhagvan Swarup Shukla,
CGSC alongwith Mr. Sarvan
Kumar (GP) and Mr. Sakasham
Sethi, Adv.
CORAM:
HON'BLE MR. JUSTICE SACHIN DATTA
JUDGMENT
SACHIN DATTA, J.
1. The present petition under Section 11 of the Arbitration and
Conciliation Act 1996, (the “A & C Act”) seeks appointment of an
independent sole arbitrator to adjudicate the dispute between the parties.
2. At the outset, learned standing counsel for the respondent, relying
upon of the judgment of the Constitution Bench of the Supreme Court in
N.N. Global Mercantile (P) Ltd. v. Indo Unique Flame Ltd ., 2023 SCC
OnLine SC 495, contends that the contract agreement in the present case is
Signature Not Verified
ARB.P. 1048/2022 Page 1 of 8
Digitally Signed
By:RADHA BISHT
Signing Date:03.07.2023
17:35:27
liable to be impounded since the same is un-stamped. Learned counsel for
the petitioner has relied on proviso (1) to Section 3 of the Indian Stamp Act,
1899 to contend that there is an exemption from stamping of the contract
agreement in the present case since the same has been awarded to the
petitioner “for and on behalf of the President of India”.
3. The fact that the contract was awarded to the petitioner “for and on
behalf of the President of India” is not disputed by the respondent.
4. The proviso (1) to Section 3 of the Indian Stamp Act reads as under:
“3. Instruments chargeable with duty —
xx xx xx
Provided that no duty shall be chargeable in respect of—
(1) any instrument executed by, or on behalf of, or in favour of, the
Government incases where, but for this exemption, the Government would
be liable to pay the duty chargeable in respect of such instrument.‖
5. Ex-facie , the contract agreement in the present is not chargeable to the
payment of stamp duty and is exempted under proviso (1) to Section 3 of the
Indian Stamp Act.
6. The disputes between the parties have arisen in the context of a tender
process initiated by the respondent for ―Provision of Deficient Married
Accommodation for Coast Guard Officers At Sector-52 Noida‖; pursuant to
which vide letter dated 28.05.2013 the said work was awarded in favour of
the petitioner. The stipulated date for completion of the said work was
18.12.2014. The petitioner submits that the work came to be completed
beyond the scheduled date of completion since there was lapse on the part of
the respondent on various counts including continuous amendments and
deviations in the scope of work, delay in approvals etc. Consequently,
Signature Not Verified
ARB.P. 1048/2022 Page 2 of 8
Digitally Signed
By:RADHA BISHT
Signing Date:03.07.2023
17:35:27
certain disputes have arisen between the parties and certain claims are raised
by the petitioner.
7. The General Conditions of the Contract (GCC) applicable to the
aforesaid contract agreement contains an arbitration agreement in the
following terms:
―70. Arbitration – All disputes between the parties to the Contract
(other than those for which the decision of the C.W.E. or any other
person is by the Contract expressed to be final and binding) shall,
after written notice by either party to the Contract to the other of
them, be referred to the sole arbitration of an Engineer Officer to be
appointed by the authority mentioned in the tender documents.
Unless both parties agree in writing such reference shall not take
place until after the completion or alleged completion of the Work or
termination or determination of the Contract under Condition Nos.
55. 56 and 57 hereof.
Provided that in the event of abandonment of the Works or
cancellation of the Contract under Condition Nos. 52, 53 or 54 hereof,
such reference shall not take place until alternative arrangements
have been finalized by the Government to get the Works completed by
or through any other Contractor or Contractors or Agency or
Agencies.
Provided always that commencement or continuance of any
arbitration proceeding hereunder or otherwise shall not in any
manner militate against the Government's right of recovery from the
contractor as provided in Condition 67 hereof.
If the Arbitrator so appointed resigns his appointment or vacates his
office or is unable or unwilling to act due to any reason whatsoever,
the authority appointing him may appoint a new Arbitrator to act in
his place.
The Arbitrator shall be deemed to have entered on the reference on
the date he issues notice to both the parties, asking them to submit to
him their statement of the case and pleadings in defence.
The Arbitrator may proceed with the the arbitration, exparte, if either
party, inspite of a notice from the Arbitrator fails to take part in the
proceedings.
Signature Not Verified
ARB.P. 1048/2022 Page 3 of 8
Digitally Signed
By:RADHA BISHT
Signing Date:03.07.2023
17:35:27
The Arbitrator may, from time to time with the consent of the parties,
enlarge, the time upto but not exceeding one year from the date of his
entering on the reference, for making and publishing the award.
The Arbitrator shall give his award within a period of six months from
the date of his entering on the reference or within the extended time as
the case may be on all matters referred to him and shall indicate his
findings, along with sums awarded, separately on each individual item
of dispute.
The venue of Arbitration shall be such place or places as may be fixed
by the Arbitrator in his sole discretion.
The award of the Arbitrator shall be final and binding on both parties
to the Contract.‖
8. The petitioner invoked the aforesaid arbitration agreement vide letter
dated 1 4.03 . 202 2, whereby the petitioner requested the respondent to
mutually appoint a sole arbitrator to adjudicate the disputes between the
parties, since in view of the judgment of Supreme Court in Perkins Eastman
Architects DPC v. HSCC (India) Ltd., (2020) 20 SCC 760, it is
impermissible for the respondent to unilaterally appoint an arbitrator. No
reply thereto is stated to have been sent by the respondent.
9. The claims that are sought to be referred to the arbitration vide the
above communication, are as under:
| CLAIMS | AMOUNT (RUPEES) |
|---|---|
| Claim No.1<br>Payment/Release of arbitrarily withheld<br>amount from Final bill | 14,72,40,177/- |
| Claim No.2<br>On account of extra expenditure incurred<br>by M/s Goyala Infra on account of risk<br>and cost for sunken floor and other<br>defects | 11,50,000/- |
| Claim No.3<br>Loss of income for not providing<br>completion Certificate in March, 2017 | 10,00,000/- |
Signature Not Verified
ARB.P. 1048/2022 Page 4 of 8
Digitally Signed
By:RADHA BISHT
Signing Date:03.07.2023
17:35:27
| Claim No.4<br>Loss of income for idle labour charges<br>from March, 2017 till June, 2017 | 5,00,000/- |
|---|---|
| Claim No.5<br>Interest @ 18% on part of payment of Rs.<br>62,50,000/- from the date of submission<br>of final bill till date of payment | To be calculated |
| Claim No.6<br>Interest @ 18% P.A. on delayed payment<br>till the date of realization. | As per actual |
| Claim No.7<br>Refund of Security Deposit as per Clause<br>68 of General Conditions of Contract for<br>Lump-sum Contracts (I.A.F.W. -2249) | 25,00,000/- |
| Claim No.8<br>Arbitration Cost and Legal Expenses | 15,00,000/- |
10. Learned standing counsel for the respondent does not dispute the
existence of the arbitration agreement between the parties and applicability
of the judgment in Perkins (supra). However, he submits that the petitioner
has claimed non-contractual amounts in final bill such as escalation, etc.
which were outside the scope of the contract agreement and the same has
been disallowed by the respondent. He further submits that no hindrances
have been created by the respondent during the currency of work and the
delay in completion in work is not on account of the respondent. He also
submits that in terms of Clause 11(c) of the GCC, it was agreed between the
parties that no compensation claims of any kind can be made on account of
delays in completing the work, even if the respondent granted extensions of
time. He further submits that there was no delay on part of the respondent in
providing the petitioner with completion certificate and the same was issued
to the petitioner after the actual completion of the work. It is further
submitted that no extra amount for repair of sunken floor and other defects
Signature Not Verified
ARB.P. 1048/2022 Page 5 of 8
Digitally Signed
By:RADHA BISHT
Signing Date:03.07.2023
17:35:27
can be claimed by the petitioner since the same has been done as per the
condition of contract agreement.
11. In response to the aforesaid contentions of Shri Shukla, learned
standing counsel, the learned counsel for the petitioner relies upon the
judgment of K.N. Sathyapalan v. State of Kerala , (2007) 13 SCC 43,
wherein it has been held as under:
― 31. The question which we are called upon to answer in the instant
appeal is whether in the absence of any price escalation clause in the
original agreement and a specific prohibition to the contrary in the
supplemental agreement, the appellant could have made any claim on
account of escalation of costs and whether the arbitrator exceeded his
jurisdiction in allowing such claims as had been found by the High Court.
32. Ordinarily, the parties would be bound by the terms agreed upon in
the contract, but in the event one of the parties to the contract is unable to
fulfil its obligations under the contract which has a direct bearing on the
work to be executed by the other party, the arbitrator is vested with the
authority to compensate the second party for the extra costs incurred by
him as a result of the failure of the first party to live up to its obligations.
That is the distinguishing feature of cases of this nature and Alopi
Parshad case [(1960) 2 SCR 793 : AIR 1960 SC 588] and also Patel
Engg. case [(2004) 10 SCC 566] . As was pointed out by Mr Dave, the
said principle was recognised by this Court in P.M. Paul [1989 Supp (1)
SCC 368] where a reference was made to a retired Judge of this Court to
fix responsibility for the delay in construction of the building and the
repercussions of such delay. Based on the findings of the learned Judge,
this Court gave its approval to the excess amount awarded by the
arbitrator on account of increase in price of materials and costs of labour
and transport during the extended period of the contract, even in the
absence of any escalation clause. The said principle was reiterated by this
Court in T.P. George case [(2001) 2 SCC 758]‖
12. Having perused the record and having heard learned counsel for the
parties, there is no controversy about existence of the arbitration agreement
and consequently, there is no impediment in appointing an independent
arbitrator to adjudicate the disputes(s) between the parties. The objections
Signature Not Verified
ARB.P. 1048/2022 Page 6 of 8
Digitally Signed
By:RADHA BISHT
Signing Date:03.07.2023
17:35:27
raised by the respondent pertain mainly to the merits/maintainability of the
disputes, which shall be decided by the arbitrator in accordance with law.
13. The Supreme Court in NTPC Ltd. v. SPML Infra Ltd., 2023 SCC
OnLine SC 389, has held as under:
―26 . As a general rule and a principle, the arbitral tribunal is the preferred
first authority to determine and decide all questions of non-arbitrability. As
an exception to the rule, and rarely as a demurrer, the referral court may
reject claims which are manifestly and exfacie non-arbitrable. Explaining
this position, flowing from the principles laid down in Vidya Drolia (supra),
this Court in a subsequent decision in Nortel Networks (supra) held:
―45.1 ...While exercising jurisdiction under Section 11 as
the judicial forum, the court may exercise the prima facie test to
screen and knockdown ex facie meritless, frivolous, and dishonest
litigation. Limited jurisdiction of the courts would ensure
expeditious and efficient disposal at the referral stage. At the
referral stage, the Court can interfere ―only‖ when it is
―manifest‖ that the claims are ex facie time-barred and dead, or
there is no subsisting dispute...‖
27. The standard of scrutiny to examine the non-arbitrability of a claim is
only prima facie. Referral courts must not undertake a full review of the
contested facts; they must only be confined to a primary first review and let
facts speak for themselves. This also requires the courts to examine whether
the assertion on arbitrability is bona fide or not. The prima facie scrutiny of
the facts must lead to a clear conclusion that there is not even a vestige of
doubt that the claim is non-arbitrable. On the other hand, even if there is
the slightest doubt, the rule is to refer the dispute to arbitration‖
14. In the present case, prima facie, the claims raised by the petitioner
cannot be said to be not manifestly and ex-facie non-arbitrable or deadwood.
Whether or not the claims sought to be raised are within the scope of, and/or
permissible under the contract, requires a detailed factual analysis, for which
the “preferred first authority” is the arbitral tribunal. It shall be open for the
respondent to take suitable preliminary objection(s) with regard thereto,
which shall be duly considered and pronounced upon by the arbitrator.
Signature Not Verified
ARB.P. 1048/2022 Page 7 of 8
Digitally Signed
By:RADHA BISHT
Signing Date:03.07.2023
17:35:27
15. Accordingly, Mr. Justice (Retd.) Talwant Singh, Former Judge, Delhi
High Court (Mobile No. 9910384653) is appointed as the Sole Arbitrator to
adjudicate the disputes between the parties.
16. As mentioned hereinabove, the respondent shall be entitled to raise
preliminary objections as regards arbitrability/maintainability of the claims
which shall be decided by the arbitrator, in accordance with law.
17. The learned Sole Arbitrator may proceed with the arbitration
proceedings subject to furnishing to the parties requisite disclosures as
required under section 12 of the A&C Act; and in the event there is any
impediment to the appointment on that count, the parties are given liberty to
file an appropriate application in this court.
18. The learned Sole Arbitrator shall be entitled to fee in accordance with
Fourth Schedule to the A&C Act; or as may otherwise be agreed to between
the parties and the learned Sole Arbitrator.
19. Parties shall share the arbitrator’s fee and arbitral costs, equally.
20. All rights and contentions of the parties in relation to the
claims/counter-claims are kept open, to be decided by the learned Arbitrator
on their merits, in accordance with law.
21. Needless to say, nothing in this order shall be construed as an
expression of this court on the merits of the case.
22. The present petition stands disposed of in the above terms.
SACHIN DATTA, J
JULY 03, 2023/hg
Signature Not Verified
ARB.P. 1048/2022 Page 8 of 8
Digitally Signed
By:RADHA BISHT
Signing Date:03.07.2023
17:35:27