Full Judgment Text
NON-REPORTABLE
IN THE SUPREME COURT OF INDIA
| PEAL NO | S. 2970-29 |
Maniben Devraj Shah … Appellant(s)
Versus
Municipal Corporation of Brihan Mumbai … Respondent
J U D G M E N T
G. S. Singhvi, J.
1. Whether the cause shown by Municipal Corporation of Brihan
Mumbai (for short, ‘the Corporation’) for condonation of 7 years and 108
JUDGMENT
days delay in filing appeals against judgments and decrees dated 2.5.2003
passed by the City Civil Court (hereinafter referred to as ‘the trial Court’) in
L.C. Suit Nos. 2726, 2727, 2728 of 1999 was sufficient cause within the
meaning of Section 5 of the Limitation Act and the learned Single Judge of
the Bombay High Court was justified in condoning the delay is the question
which arises for consideration in these appeals.
Page 1
2
2. At the outset, it deserves to be mentioned that the respondent had
withdrawn one of the three appeals filed before the High Court and, as such,
the impugned order makes a reference to the two appeals only.
| uits for gr | ant of a de |
|---|
by the Corporation under Section 314 of the Mumbai Municipal Corporation
Act, 1888 (for short, ‘the Act’) for demolition of the properties specified in
the plaints are illegal and not binding on them. They pleaded that the action
taken by the Corporation is discriminatory and liable to be annulled because
some persons whose structures were taken for road widening were allowed
to construct mezzanine floor in the remaining portions of their respective
properties and were also allotted alternative accommodation in the new
building but they were not given similar benefit. The appellants further
pleaded that they had entered into development agreements with Shamji D.
JUDGMENT
Shah and Popatbhai Baghbhai Bharwad for developing the property and they
will construct market for and on behalf of the Corporation. They prayed for
issue of a direction to the respondent to provide shops in the market
proposed to be constructed on C.T.S. No.997, Near Purnapragya High
School, Bharucha Marg, Dahisar (E), Bombay.
Page 2
3
4. In the written statement filed on behalf of the Corporation, an
objection was taken to the maintainability of the suit on the ground that
notice under Section 527 of the Act had not been given by the appellants. On
| at the app | ellants ha |
|---|
portion of the road and it had become necessary to demolish the same for
widening the existing road.
5. On the pleadings of the parties the trial Court framed identical issues
in all the suits. For the sake of reference, the issues framed in LC Suit No.
2726 of 1999 titled Smt. Maniben Devraj Shah v. The Municipal
Corporation of Greater Bombay are reproduced below:
“ ISSUES FINDINGS
1. Does the plaintiff prove that
notice issued u/s. 314 of BMC
Act is illegal, bad in law,
malafides and inexcitable?
In the affirmative
JUDGMENT
2. Does the plaintiff prove that she is
entitled for alternate
accommodation in lieu of
structure affected by road
widening?
In the affirmative
3. Does the plaintiff prove that suit
is maintainable for the want of
notice u/s. 527 of BMC Act?
In the affirmative
4. Whether the plaintiff is entitled As per final order
Page 3
4
for any relief?
5. What order? As per final order”
| pleadings | of the par |
|---|
by them, the trial Court decreed the suits by separate but identical judgments
dated 2.5.2003.
7. The Corporation did not challenge the judgments of the trial Court
within the prescribed period of limitation and filed appeals sometime in
September, 2010 along with the applications for condonation of 7 years and
108 days delay. In support of its prayer for condonation of delay the
Corporation also filed the affidavits of Shri Ranindra Y. Sirsikar, Junior Law
Officer. For the sake of reference, paragraph 3 of the application for
condonation of delay and paragraphs 2, 3 and 5 of the affidavit of Shri
JUDGMENT
Ranindra Y. Sirsikar filed in First Appeal No. 3691 of 2010 titled Municipal
Corporation of Brihan Mumbai v. Smt. Maniben Devraj Shah are
reproduced below:
APPLICATION FOR CONDONATION OF DELAY
“3) The applicants herein have filed the present first appeal
against the order dated 2.5.2003 and applied for certified copy
of judgment on 23.8.2010 and same was made available on
6.9.2010 and collected on 6.9.2010. The applicant corporation
Page 4
5
| ppeared in<br>ction to cr | the above<br>iminal sec |
|---|
JUDGMENT
AFFIDAVIT OF SHRI RANINDRA Y. SIRSIKAR
“2. I say that the present suits bearing No. (1) 2726 of 1999,
2727 of 1999 and 2728 of 1999 was decreed on 02.05.2003 by
Hon’ble City Civil Court. I say that I was on leave from
30.4.2003 till 11.5.2003. I resumed my office by 12.5.2003. A
copy of leave application is annexed herewith and marked as
Exhibit-A. I say that as per the office procedure, the necessary
intimation was also forwarded to the concerned department and
informed them about the court orders dated 2.5.2003. A copy of
dispatch extract regarding intimation to the concerned ward on
Page 5
6
| n transferre<br>5.6.2004 | d from M<br>. A copy |
|---|
3. I say that in the instant case, the Local Councillor Shri
Prakash Karkar wrote a letter on 20.7.2010 to the concerned
Additional Municipal Commissioner requesting for joint
meeting regarding widening of road and expediting the
development and construction of Municipal Market, i.e.,
property under reference. A copy of letter dt. 20.7.2010 of
Local Councillor Shri Prakash Karkar is annexed herewith and
marked as Exhibit – F. I say that accordingly joint meeting was
held in the Chamber of Addl. M.C. on 2.8.2010, when all
concerned officers along with Jt. Law Officer (City Civil Court
Section) of Legal Department of the appellant was also present
in the said meeting. In the course of said meeting, it came to the
notice that the respondents are claiming the right of alternative
accommodation pursuant to impugned order in view of that
matter, respective Addl. Municipal Commissioner directed Jt.
Law Officer (City Civil Court Section) of Legal Department to
study entire matters and also ascertain above appeal and its
stage against the judgment and order dated 2.5.2003 passed by
City Civil Court. A copy of minutes dated 2.8.2010 is annexed
herewith and marked as Exhibit – G.
JUDGMENT
5. I say that though papers were misplaced and not traceable, I
personally inquired with the staff of High Court (Appellate Side
Page 6
7
| 9.8.2010 to<br>nd order d | file an ap<br>ated 2.5.2 |
|---|
8. The appellants contested the prayer made by the Corporation for
condonation of delay by asserting that the story of misplacement of the
papers is unbelievable and is liable to be discarded because the applications
for condonation of delay do not mention as to when the misplaced papers
were traced out by the concerned department. They also pleaded that the
transfer of Shri Ranindra Y. Sirsikar from one section to the other has no
JUDGMENT
bearing on the issue of condonation of delay because the Corporation has
employed several advocates and no explanation whatsoever has been offered
for not filing the applications for certified copies of the judgment of the trial
Court till 23.8.2010.
9. The learned Single Judge of the High Court referred to the judgments
of this Court in Collector, Land Acquisition, Anantnag v. Mst.Katiji (1987)
Page 7
8
2 SCC 107 and State of Nagaland v. Lipok AO (2005) 3 SCC 752 and
condoned the delay by recording the following observations:
| the Corpor<br>sufficient | ation for c<br>and the d |
|---|
Taking the law laid down by the Supreme Court in view and
considering over all facts and circumstances of the case, so also
the fact that if the delay is not condoned the meritorious appeal
is likely to be thrown at the very threshold, I am inclined to
condone the delay in filing these appeals. Hence, the Civil
Application Nos. 3625 of 2010 and 3691 of 2010 are allowed in
terms of prayer clause (a).”
10. Shri A.S. Bhasme, learned counsel for the appellants argued that the
reasons assigned by the learned Single Judge for condoning more than 7
JUDGMENT
years and 3 months delay in filing the appeals are legally unsustainable and
the impugned order is liable to be set aside because the explanation given by
the Corporation lacked bonafides and was wholly unsatisfactory. Learned
counsel emphasized that in the absence of any denial by the Corporation that
it has a battery of advocates to deal with the litigation, the transfer of Shri
Ranindra Y. Sirsikar in January, 2004 to Miscellaneous Court and,
thereafter, to other Courts has no bearing on the issue of delay because the
Page 8
9
suits filed by the appellants had been decided in May, 2003 and no
explanation has been given as to why applications for certified copies could
not be filed for 7 years and 5 months. Shri Bhasme submitted that even if
| was transfe | rred from |
|---|
another, nothing prevented the Corporation from taking steps to apply for
certified copies of the judgment. Shri Bhasme further submitted that the
story of misplacement of papers was concocted by the Corporation and the
same ought to have been rejected by the High Court because the assertion
made in that regard was vague to the core and no indication was given as to
when the papers were traced and by whom. In support of his argument, Shri
Bhasme relied upon the judgments of this Court in Oriental Aroma
Chemical Industries Limited v. Gujarat Industrial Development Corporation
(2010) 5 SCC 459.
JUDGMENT
11. Shri Pallav Shishodia, learned senior counsel appearing for the
Corporation argued that the discretion exercised by the learned Single Judge
of the High Court to condone the delay does not suffer from any legal
infirmity and the mere possibility that this Court may, on a fresh analysis of
the pleadings of the parties, form a different opinion does not furnish a valid
ground for exercise of power under Article 136 of the Constitution. Shri
Shishodia submitted that in last more than two decades the Courts have time
Page 9
10
and again emphasized that while considering the question of condonation of
delay, the pleadings of the parties should be construed liberally and the
genuine cause of a party should not be defeated by refusing to condone the
| ument, Shr | i Shishodi |
|---|
judgments in Collector, Land Acquisition, Anantnag v. Mst. Katiji (supra)
and State of Nagaland v. Lipok AO (supra). Shri Shishodia also pointed out
that the appellants had raised illegal construction and if the challenge to the
decrees passed by the trial Court was aborted by the High Court by refusing
to condone the delay, serious injury would have been caused to the public
interest.
12. We have considered the respective arguments / submissions and
carefully scrutinized the record. The law of limitation is founded on public
policy. The Limitation Act, 1963 has not been enacted with the object of
JUDGMENT
destroying the rights of the parties but to ensure that they approach the Court
for vindication of their rights without unreasonable delay. The idea
underlying the concept of limitation is that every remedy should remain
alive only till the expiry of the period fixed by the Legislature. At the same
time, the Courts are empowered to condone the delay provided that
sufficient cause is shown by the applicant for not availing the remedy within
the prescribed period of limitation. The expression ‘sufficient cause’ used in
Page 10
11
Section 5 of the Limitation Act, 1963 and other statutes is elastic enough to
enable the Courts to apply the law in a meaningful manner which serve the
ends of justice. No hard and fast rule has been or can be laid down for
| or condona | tion of de |
|---|
Court has advocated that a liberal approach should be adopted in such
matters so that substantive rights of the parties are not defeated merely
because of delay.
13. In Ramlal v. Rewa Coalfields Ltd. AIR 1962 SC 361, this Court
while interpreting Section 5 of the Limitation Act, laid down the following
proposition:
“In construing Section 5 (of the Limitation Act), it is relevant to
bear in mind two important considerations. The first
consideration is that the expiration of the period of limitation
prescribed for making an appeal gives rise to a right in favour
of the decree-holder to treat the decree as binding between the
parties. In other words, when the period of limitation prescribed
has expired, the decree-holder has obtained a benefit under the
law of limitation to treat the decree as beyond challenge, and
this legal right which has accrued to the decree-holder by lapse
of time should not be light-heartedly disturbed. The other
consideration which cannot be ignored is that if sufficient cause
for excusing delay is shown, discretion is given to the court to
condone delay and admit the appeal. This discretion has been
deliberately conferred on the court in order that judicial power
and discretion in that behalf should be exercised to advance
substantial justice.”
JUDGMENT
Page 11
12
14. In Collector, Land Acquisition, Anantnag v. Mst. Katiji (supra), this
Court made a significant departure from the earlier judgments and observed:
| the Indian<br>to do su | Limitation<br>bstantial |
|---|
1. Ordinarily a litigant does not stand to benefit by lodging
an appeal late.
2. Refusing to condone delay can result in a meritorious
matter being thrown out at the very threshold and cause of
justice being defeated. As against this when delay is
condoned the highest that can happen is that a cause would
be decided on merits after hearing the parties.
JUDGMENT
3. “Every day's delay must be explained” does not mean
that a pedantic approach should be made. Why not every
hour's delay, every second's delay? The doctrine must be
applied in a rational common sense pragmatic manner.
4. When substantial justice and technical considerations are
pitted against each other, cause of substantial justice
deserves to be preferred for the other side cannot claim to
have vested right in injustice being done because of a non-
deliberate delay.
5. There is no presumption that delay is occasioned
deliberately, or on account of culpable negligence, or on
Page 12
13
account of mala fides. A litigant does not stand to benefit by
resorting to delay. In fact he runs a serious risk.
| o. |
|---|
JUDGMENT
15. In N. Balakrishnan v. M. Krishnamurthy, (1998) 7 SCC 123, the
Court went a step further and made the following observations:
“It is axiomatic that condonation of delay is a matter of
discretion of the court. Section 5 of the Limitation Act does not
Page 13
14
| e the cou<br>sult of pos | rt accepts<br>itive exerc |
|---|
Rules of limitation are not meant to destroy the rights of parties.
They are meant to see that parties do not resort to dilatory
tactics, but seek their remedy promptly. The object of providing
a legal remedy is to repair the damage caused by reason of legal
injury. The law of limitation fixes a lifespan for such legal
remedy for the redress of the legal injury so suffered. Time is
precious and wasted time would never revisit. During the efflux
of time, newer causes would sprout up necessitating newer
persons to seek legal remedy by approaching the courts. So a
lifespan must be fixed for each remedy. Unending period for
launching the remedy may lead to unending uncertainty and
consequential anarchy. The law of limitation is thus founded on
public policy. It is enshrined in the maxim interest reipublicae
up sit finis litium (it is for the general welfare that a period be
put to litigation). Rules of limitation are not meant to destroy
the rights of the parties. They are meant to see that parties do
not resort to dilatory tactics but seek their remedy promptly.
The idea is that every legal remedy must be kept alive for a
legislatively fixed period of time.
JUDGMENT
It must be remembered that in every case of delay, there can be
some lapse on the part of the litigant concerned. That alone is
not enough to turn down his plea and to shut the door against
Page 14
15
| et the oppo<br>is a loser | site party<br>and he too |
|---|
16. In P.K. Ramachandran v. State of Kerala, (1997) 7 SCC 556, this
Court while reversing the order passed by the High Court which had
condoned 565 days delay in filing an appeal by the State against the decree
of the Sub-Court in an arbitration application, observed that the law of
limitation may harshly affect a particular party but it has to be applied with
all its rigour when the statute so prescribes and the Courts have no power to
extend the period of limitation on equitable grounds. In Vedabai v.
JUDGMENT
Shantaram Baburao Patil, (2001) 9 SCC 106, the Court observed that a
distinction must be made between a case where the delay is inordinate and a
case where the delay is of few days and whereas in the former case the
consideration of prejudice to the other side will be a relevant factor, in the
latter case no such consideration arises.
Page 15
16
17. In State of Nagaland v. Lipok AO (supra), the Court referred to
several precedents on the subject and observed that the proof of sufficient
cause is a condition precedent for exercise of discretion vested in the Court.
| gth of the | delay but t |
|---|
and shortness of the delay is one of the circumstances to be taken into
account in using the discretion. The Court also took cognizance of the usual
bureaucratic delays which takes place in the functioning of the State and its
agencies/instrumentalities and observed:
“Experience shows that on account of an impersonal machinery
(no one in charge of the matter is directly hit or hurt by the
judgment sought to be subjected to appeal) and the inherited
bureaucratic methodology imbued with the note-making, file-
pushing, and passing-on-the-buck ethos, delay on its part is less
difficult to understand though more difficult to approve. The
State which represents collective cause of the community, does
not deserve a litigant-non-grata status. The courts, therefore,
have to be informed with the spirit and philosophy of the
provision in the course of the interpretation of the expression of
sufficient cause. Merit is preferred to scuttle a decision on
merits in turning down the case on technicalities of delay in
presenting the appeal.”
JUDGMENT
18. What needs to be emphasised is that even though a liberal and justice
oriented approach is required to be adopted in the exercise of power under
Section 5 of the Limitation Act and other similar statutes, the Courts can
neither become oblivious of the fact that the successful litigant has acquired
certain rights on the basis of the judgment under challenge and a lot of time
Page 16
17
is consumed at various stages of litigation apart from the cost. What colour
the expression ‘sufficient cause’ would get in the factual matrix of a given
case would largely depend on bona fide nature of the explanation. If the
| en no negl | igence on |
|---|
the cause shown for the delay does not lack bona fides, then it may condone
the delay. If, on the other hand, the explanation given by the applicant is
found to be concocted or he is thoroughly negligent in prosecuting his cause,
then it would be a legitimate exercise of discretion not to condone the delay.
In cases involving the State and its agencies/instrumentalities, the Court can
take note of the fact that sufficient time is taken in the decision making
process but no premium can be given for total lethargy or utter negligence
on the part of the officers of the State and / or its agencies / instrumentalities
and the applications filed by them for condonation of delay cannot be
JUDGMENT
allowed as a matter of course by accepting the plea that dismissal of the
matter on the ground of bar of limitation will cause injury to the public
interest.
19. In the light of the above, it is to be seen whether the explanation given
by the respondent for condonation of more than 7 years and 3 months delay
was satisfactory and whether the learned Single Judge of the High Court had
Page 17
18
correctly applied the principles laid down by this Court for the exercise of
power under Section 5 of the Limitation Act.
| f the applic | ations file |
|---|
affidavit of Shri Ranindra Y. Sirsikar:
1.
As per the office procedure, Shri Ranindra Y. Sirsikar had given
intimation to the concerned department about the trial Court’s
judgment dated 2.5.2003. This statement is supported by copy of
the despatch extract dated 12.5.2003 (Ext. B) filed with his
affidavit.
2. According to the Corporation, the papers required for filing the
first appeals were misplaced and not traceable in spite of good
JUDGMENT
efforts. In this context, Shri Sirsikar has made the following
statement:
“I say that thereafter, from the record it seems that the
concerned department misplaced the papers and were not
traceable. So nobody followed up on the matter”
3.
As per the averments contained in the application, Shri Sirsikar
was transferred from Civil Section to Criminal Section in June,
2004 and, therefore, lost tract of the matter and the first appeals
Page 18
19
remained to be filed due to oversight and heavy work load. As
against this, Shri Sirsikar states that he was transferred to
Miscellaneous Court on 2.1.2004 and from Miscellaneous Court to
| n 5.6.2004 | , where h |
|---|
Thereafter, he was transferred to High Court on original side and
was working there on the date of filing the affidavit.
4.
As per the averments contained in the application, the advocate
came to know that appellant fraudulently obtained alternative
accommodation under the judgment of the trial Court even though
she was given permission for constructing mezzanine floor to the
extent of structure affected by road widening. In this context, Shri
Sirsikar has disclosed that the issue relating to the claim made by
the appellant for alternative accommodation was considered in the
JUDGMENT
meeting held on 2.8.2010 in the chamber of Additional Municipal
Commissioner and, on the basis of discussion held in that meeting,
direction was given by him to the Managing Clerk on 19.8.2010 to
file application for certified copy of the judgment. According to
Shri Sirsikar, the application was made on 23.8.2010 and the
certified copy was made available on 6.9.2010.
Page 19
20
21. The applications filed for condonation of delay and the affidavits of
Shri Sirsikar are conspicuously silent on the following important points:
| ot been dis | closed. |
|---|
(b) The date, month and year when the papers required for filing
the first appeals are said to have been misplaced have not
been disclosed.
(c) The date on which the papers were traced out or recovered
and name of the person who found the same have not been
disclosed.
(d) No explanation whatsoever has been given as to why the
applications for certified copies of the judgments of the trial
JUDGMENT
Court were not filed till 23.8.2010 despite the fact that Shri
Sirsikar had given intimation on 12.5.2003 about the
judgments of the trial Court.
(e)
Even though the Corporation has engaged battery of lawyers
to conduct cases on its behalf, nothing has been said as to
how the transfer of Shri Ranindra Y. Sirsikar operated as an
Page 20
21
impediment in the making of applications for certified
copies of the judgments sought to be appealed against.
| in the story | concocte |
|---|
misplacement of the papers and total absence of any explanation as to why
nobody even bothered to file applications for issue of certified copies of
judgment for more than 7 years. In our considered view, the cause shown by
the Corporation for delayed filing of the appeals was, to say the least, wholly
unsatisfactory and the reasons assigned by the learned Single Judge for
condoning more than 7 years delay cannot but be treated as poor apology for
the exercise of discretion by the Court under Section 5 of the Limitation Act.
23. In the result, the appeals are allowed. The impugned order is set aside
and the appeals filed by the respondent against the judgments of the trial
JUDGMENT
Court are dismissed. The parties are left to bear their own costs.
……………..…..……..…..………………..J.
[G.S. SINGHVI]
……………..…..……..…..………………..J.
[ SUDHANSU JYOTI MUKHOPADHAYA]
New Delhi
April 09, 2012.
Page 21