Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
PETITIONER:
PURAN LAL SAH
Vs.
RESPONDENT:
STATE OF U.P.
DATE OF JUDGMENT21/01/1971
BENCH:
REDDY, P. JAGANMOHAN
BENCH:
REDDY, P. JAGANMOHAN
DUA, I.D.
CITATION:
1971 AIR 712 1971 SCR (3) 469
1971 SCC (1) 424
ACT:
Contract-Claim on basis of quantum meruit-When sustainable.
HEADNOTE:
The Public Works Department of the respondent-State had
issued a tender notice for the construction of a road. The
appellant inspected the site, went to the place where stone
for the construction was said to be available, and after
satisfying himself submitted a tender below the estimates in
the tender notice. It was accepted and a contract was
signed. The estimates in the tender notice were prepared by
the P.W.D. on the basis that stone was available at a
distance of 26 chains from the work spot. In fact, stone
was available at that distance in the Cantonment area but
for its removal permission of the Cantonment authorities had
to be taken. The appellant was not able to obtain the
necessary permission and so, he bad to get the stone from a
Much longer distance. He requested for a higher rate but
his request was rejected. Thereafter, he commenced work,
and after the work was completed the Executive Engineer
recommended his case for a higher rate.
By a subsidiary contract the appellant undertook to execute
some additional work for the department. The quantity of
work which the appellant actually performed was far in
excess of what was mentioned in the contract. He claimed a
higher ’rate of payment for such extra work also.
Since he did not get the higher rates he claimed, be filed a
suit which. was dismissed by the High Court in appeal.
In appeal to this Court,
HELD : (1) (a) In- none of the clauses of the tender notice
or conditions of contract or in any other document was there
any assurance that if stone was not available at the
distance of 26 chains the appellant would ’be paid higher
rates. It was for the appellant to have satisfied himself
before entering into the contract that the Cantonment
authorities would permit him to take the stone. Since be
commenced work after his request for higher rate was
rejected, it could not be said that the appellant was in any
way induced by any assurance. The Executive Engineer’s
letter was only recommendatory and did not establish any
right to obtain a higher rate. [472 G-H; 473 G-H; 475 C.]
(b) It could not be said that once stone was not available
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
at a distance, of 26 chains, the contract was at an end and
that because the appellant had done the work, he should be
paid on the basis of quantum meruit. That remedy would be
available only when the original contract had been
discharged by the defendant in such a way as to entitle the
plaintiff to regard himself as discharged from any further
performance, and be elects to do so; but, where work is done
under a contract persuant to its terms no amount can be
claimed by way of quantum meruit. [475 G-H; 476 C-D]
Adopi Parshad & Sons. Ltd. v. Union of India, [1960] 2
S.C.R. 793, followed.
(2) On the second item also the appellant could not
succeed, because of cl. 12 of the contract. Under the
clause the appellant was bound to perform all additional
work which was required of him on the same terms and
conditions in which be undertook to do the main work.
Further,
470
paragraph 5 of the special instructions which formed part
and parcel of the original contract provided that unless he
gave notice that he was not prepared to do any extra work in
excess of the quantity of the wort: mentioned in the
contract plus 30 per cent of that quantity of work, and
settled fresh rates for such extra work over 30 per cent,
the appellant could not claim anything other than the rates
mentioned in the contract. [476 E-H]
JUDGMENT:
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1687 of
1966.
Appeal from the judgment and decree dated March 8, 1965 of
the Allahabad High Court in First Appeal No. 84 of 1954.
G. N. Dixit and 0. P. Rana, for the respondent.
The Judgment of the Court was delivered by
P. Jaganmohan Reddy, J. This appeal is by a certificate
under Art. 133(1) (a) of the Constitution against the
judgment and decree of the Allahabad High Court dated 8th
March 1965 setting aside the decree of the Trial Court and
dismissing the suit of the ,plaintiff-appellant.
The appellant had submitted a tender to construct mile 3 of
Nainital-Bhowali Road at 13 per cent below the rates given
in Schedule B to the notice issued by the Government of the
United Provinces on the 30th September, 1946. This tender
was accepted and a contract was signed on 20th November
1946. It is alleged by the appellant that the rates given
in Schedule B were based ,on the calculation that stone
required for the road construction work would be available
at a distance of 26 chains while as a matter of fact no
stone was available within that distance. The appellant had
in fact to get stone from Gadhera and Bhumadar from ;a
distance of 79 and 110 chains respectively. It is his
contention that by reason of the non-availability of the
stone and the definite understanding and assurance given by
the local authorities of the P.W.D. that higher rates would
be given for the extra work done ,over and above the work
provided in the contract he carried on the work. It was
also alleged that during the construction work,on the road
very hard shale rock came in the way mot originally provided
for in the contract, as such he was entitled to get the
costs for the work so done at the current rates from the
P.W.D. which was not paid to him. In respect of these items
of work done as also due to his having done the work by
bringing stone from a longer distance than was given in the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
estimates the appellant claimed Rs. 48,840-0-0 due as
balance together with interest by way of damages at 12%
amounting to Rs. 17,582-0-0, making a total of Rs. 66,422-0-
0. When this claim was rejected the appellant gave notice
under Section 80 of the C.P.C. and thereafter filed a suit
for the above amount.
471
The defendant respondent resisted the suit and pleaded that
no assurance was given to the appellant by officers of- the
PWD as alleged; that the quantity of very hard shale shown
in the plaint was incorrect and at any rate the contractor,
under paragraph 5 of the special instructions must be
prepared to execute the work at the original tender rate in
excess of the given quantities of work upto 30% and if an
increase in excess of 30% is ordered over the work. the
contractor must intimate, to the Engineer-in-Charge in
writing his willingness or refusal to do extra work at the
original tendered rates. If he refuses to carry on at the
original rates he is required to settle fresh rate for
increased work over 30% before doing the work.
On these averments the trial court held issues 1, 2, 6 and 7
in favour of the appellant while issues 3, 4 and 5 were
decided against him. In the result a decree for a sum of
Rs. 20,495/for extra lead plus Rs. 1,663-14-0 for extra work
done under the item very hard shale and Rs. 4,155/- interest by way of da
mages, on Rs. 22,158-14-0 making a total of Rs.
26,313-14-0 was passed with interest at 3 % per annum. In
appeal the High Court reversed the decree holding that (I)
the employment of the figure 26 chains in the estimate was
for no other purpose. than that of calculation. . and if
knowing that the same was available within 26 chains it
(PWD) worked out its estimates on that basis, it could not
be held’ to have extended any assurance, much less guarantee
to the contractors that they would get stone within that
distance; (2) the plaintiff appellant performed the work
required of him without exercising his right under paragraph
5 of the special instructions which gives the option to do
the extra work in excess of 30% but if he refuses to do the
extra work at the originally tendered rates he should settle
fresh rates for increased work over 30% before doing the
work which he failed to do. In view of these findings
against the appellant the appeal of the respondent was
allowed and the suit dismissed but in the special
circumstances of the case left the parties to bear their
respective costs in both the Courts.
The two main questions in this appeal are: (1) Whether the
estimate of the PWD formed part of the contract so as to be
binding on both parties and whether any assurances were
given to the, appellant that he would be given higher rates
for bringing the stone from places situated at 79 chains and
1 1 0 chains respectively; (2) Whether clause 5 of the
special conditions of the contract was applicable to the
extra item of work contained in Ex. B3 and whether he was
entitled on the assurances given by the local officers to
higher rate for the extra work done. Shri Bindra, learned
Advocate for-the appellant has referred us to clauses 8, 11
and 14 of the notice calling for the tender as also to
certain letters and passages in the evidence to substantiate
his contention that the estimates of
472
the PWD were part of the contract and that in any case
assurances were given to the appellant that when he could
not get stone from distance of 26 chains, to bring from
chains 79 and 1 1 0 for which higher rates would be paid.
It may be stated that the PWD of the United Provinces, as it
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
then was, had issued a tender notice consisting of 16
paragraphs and the appellant was required to sign this
tender notice in token of his having received it because
ultimately under clause 34 of the conditions of the contract
all papers signed by the parties to the contract and bond
will be deemed to be part of the contract bond and have to
be read as conditions to the contract. Clause 8, 11 and 14
of the notice to which reference was made are as follows :
8. All tenders should be on percentage rates
above or below the rates given in the Schedule
’B’.
11. Items not provided in the Schedule B will be paid at
current schedule of rate plus or minus the percent, age
above or below as tendered by the contractor whose tender is
accepted for this work.
14. Contractors are advised to see the estimate, plans,
specifications, special conditions prescribed and site of
work before tendering.
It is obvious, from these clauses that the rates are given
in Schedule B on the basis of certain plans and
specifications. The person intending to tender for the work
was required to examine this material and also inspect the
site before tendering. These instructions were designed to
make all those who were desirous of obtaining the contract
responsible for their acts so that it cannot be said that
any mis-represeneation was made or. they were misguided in
any way. The contention of the learned Advocate for the
appellant is that it was definitely stated in the estimates
that stone was available at 26 chains which representation
was binding ,on the respondents and if no stone was
available within that distance he was entitled to claim
higher rates if he had to get stone from places farther
away. In fact the appellant alleges that the Engineers
assured him that he would be paid higher rates.
We may here observe that in none of the clauses of the
notice or conditions of contract or in any other document is
there any specific mention that stone will be available at
26 chains nor is there any assurance that if stone was not
available within that distance the contractor will be paid
higher rates. The mere fact that the estimates were
prepared by the PWD on the basis of the stone being
available at 26 chains which respondents admitted as stated
in the judgmen it of Civil Judge, Nainital, does not mean
that there was any assurance or undertaking given that stone
would be avail-
473
able at that place. In fact it is not denied that stone was
available within the distance of 26 Chaim but it was in the.
area belonging to the Cantonment, for the removal of which
permission of the Cantonment authorities had to be taken.
Evidently the contractor was not able to obtain that
permission. In our view it was upto the contractor to have
satisfied himself before entering into the contract that the
Cantonment authorities would permit him to take stone from
its jurisdiction just in the same way as permission Will
have to be taken from any private individual in whose land
stone required for road building is found. If the
contractor has failed successfully to negotiate with the,
owners of land from which he could bring stone it cannot be
said that the estimate prepared by the PWD on the basis that
the stone was available at 26 Chains was a statement which
amounted to an assurance or constituted a condition of the
contract.
The appellant as P.W. I stated in his evidence : "Before
giving offer I saw the estimates and plan. In the estimate
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
it was written that the stone would be found within 26
Chains. On this basis estimate was prepared through the
PWD, I enquired this be available within 26 Chains. On
this basis I prepared the estimate..............In the
beginning of the year 1947 1 started work attempted to take
out stone from within 26 Chains.’, The moment I started to
take out stones, the Cantonment authorities checked me. For
this act I was challanged, but I was acquitted. The entire
area within 26 Chains was of the Cantonment." Further on he
says "I have seen the tender notice and I had gone through
it; after that I signed it. Schedule B was attached to the
notice. I signed it after going through it. I submitted
tender 13% less than the Scheduled rate...... before giving
the tender I went to that place and found that the stones
were available within 26 Chins, when I wanted to take them
out, I learnt that this was within the Cantonment boundary.
I sought permission to take out stones from the Cantonment
authorities, but, it was disallowed."
It is clear from this evidence that the appellant before
giving the tender inspected the site, went to the place
where stone was said to be available and after satisfying
himself that the stone was available he gave the tender. A
perusal of the documentary evidence would also show that he
actually commenced work after his request to allow him
higher rate was rejected which was long after the time when
under the contract he was required to start the work. In
fact just before the date fixed for the completion of the
work, he had under Ex. B4 dated the 12th June 1947 made the
following representation :
"That as agreed upon the contract deed of my contract
Nainital Bhowali Motor Road Mile 3 the lead of stones for
masonary
474
work is given only about half a mile. On inspecting the
place I find it very difficult to get a quarry there as
there is no stone at all. I am getting the stones from near
the K. E. Sanitorium which falls at a distance of two and a
half miles from may place, as has already been brought to
your and the C.E.’s kind notice. Therefore, you are
requested kindly to allow me a lead of two and a half miles
distance." On this the concerned authorities seem to have
made the endorsement: "As lead and royalty is provided in
the schedule B of the tender, the request cannot be acceded
to. Draft reply is put up". Accordingly by letter dated
the 21st June 1947 he was informed as follows :,
"Reference your application dated 12th June 1947.
Please refer to item Nos. 6, 7, 8 and 9 of Schedule B
attached with your tender and on which basis you tendered
your rate in this connection. As the rates noted therein
provides all lead and royalty and there is no mention there
that the rate contains a lead for I ’a mile, your request
cannot be acceded to".
This correspondence shows that the appellant’s claim to have
extra lead was definitely rejected as untenable even before
he started the work under the contract, as is apparent from
Ex. B2 dated the 19th July ’47. In that letter the
appellant was being informed as follows:-
"Please note that since you have signed the contract for
the, above work, the work must be started now in con-
sultation with the Overseer-in-charge, Nainital Section.
The date of start and completion will be as follows
Date of start-20 November 1946
Date of completion-19 July 1947".
It cannot therefore be said that the appellant was in any
way induced by any assurances given by the PWD authorities
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
that they would give a. higher rate for the extra lead
before he commenced work. The case of the appellant in
these letters was that no stone was available within half a
mile while in his,deposition he gave a contrary version
altogether. Subsequently he seems to have become hopeful
because in the letter of the Assistant Engineer dated 28th
December 1948 it is stated
"In the estimate lead for 26 Chains was provided on the
assumption that stone Will be available within the distance
from the quarries in Cantonment areas. Later on when the
work was in progress the Cantonment authorities objected to
quarrying stones from Cantonment, land ........"
475
No doubt the Executive Engineer in his letter dated 15th
June. 1950, Ex. 22 has recommended the case of the appellant
for a higher rate as he says "When the stones were not
available from the Cantonment area it seems that the
contractor naturally was forced to bring them from quarries
situated outside the Cantonment area" and he further says
"If these quarries are the places from. where stones were
actually obtained then naturally the contractor is entitled
to get the lead for the, full quantity of stones brought by
him to complete different items requiring the use of
stones".
This letter seems to be a recommendatory letter by a subor-
dinate to the high officer but it does not in any way
establish the right of the appellant to obtain a higher
rate, nor does the evidence justify this conclusion. In our
view neither the terms and conditions of the contract nor
the oral or documentary evidence justify the conclusion that
the appellant was entitled to any extra lead.
Another argument was put forward by the learned Advocatefor
the appellant which is also based on the same, assumption
that the availability of the stone at 26 Chains was a
condition of the contract namely that once stone was not
available at 26 Chains the contract was at an end and that
because the appellant had done the work he should be paid on
the basis of quantum meruit. This in our view is a far
fetched argument and has no relation to the facts and
circumstances of the case. Even assuming that the stand
taken by the appellant that the availability of stone at 26
chains was a condition of the contract was justified, he had
notwithstanding the rejection of his claim even before he
started the work, acquiesced in the stand taken by the
respondents that he is not entitled to any higher rates,
carried on and completed the contract as if there was no
such condition. We therefore cannot understand the
contention of the appellant’s Advocate as to how the
contract came to an end and who put an end to it. Even if
at that stage the contract had been put an end to by the
respondents which is no one’s case, as the appellant had not
started the work no question of quantum meruit would arise.
The principle of quantum meruit is rooted in English law
under which there were certain procedural advantages in
framing an action for compensation for work done. In order
to avail of the remedy under quantum meruit, the original
contract must have been discharged by the defendant in such
a way as to entitled the plaintiff to regard himself as dis-
charged from any further performance and he must have
elected’ to do so. The remedy it may be noticed is however,
not available to the party who breaks the contract even
though he may have partially performed part of his
obligation. This remedy by way of quantum meruit is
restitutory that is it is a recompense for the value of the
work done by the plaintiff in order to restore him
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
476
to the position which he would have been,in if the contract
had never been entered into. In this regard it is different
to a claim for damages which is a compensatory remedy aimed
at placing the injured party, as near as may be in the
position which he would have been in, had the other party
performed the contract. This Court had in M/s. Alopi
Parshad & Sons Ltd. v. The Union of India(1) observed at
page 809 :
"Compensation quantum meruit is awarded for work done or
services rendered when the price thereof is not fixed by a
contract. For work done or services rendered persuant to
the terms of a contract compensation quantum meruit cannot
be awarded where the contract provides for consideration
payable in that behalf".
Though in that case the basis of the principle was not
explained, it nonetheless lays down that where work is done
under a contract pursuant to the terms thereof no amount can
be claimed by way of quantum meruit. In the view we have
taken on the facts of the case we do not propose to examine
the decisions cited at the Bar in this behalf. The claim of
the appellant for higher rates which in fact was by way of
damages has been rightly disallowed by the High Court.
On the second question also the appellant cannot succeed be-
cause under clause 12 of the contract Ex. B1. the,
plaintiff was bound to perform additional work which was
required of him on the same terms and conditions on which he
undertook to do the work for which he tendered. It appears
that by a subsidiary contract entered into between the
appellant and the P.W.D. Ex. B3 on the 12th April, 1946,
the appellant undertook to execute some additional work for
the Department. The quantity of work which appellant
actually performed was far in excess of what was mentioned
in Ex. B.3. The appellant therefore claimed payment for the
work done by him in excess of the quantity mentioned in the
contract plus 30% at the current rate as against the
stipulated rates. It was submitted on behalf of the State
of U.P. before the High Court that under clause 1 2 of the
contract Ex. B I and paragraph 5 of the special
instructions the plaintiff was not entitled to any amount in
excess of what he had already been paid. This contention
was accepted because under the, aforesaid clause 1.2 the
contractor was bound to perform all additional work Which
was required of him on the same terms and conditions in
which he undertook to do the main work. Paragraph 5 of the
special instructions further provides as follows :
"Contractors must be prepared to do. at their original
tender rate work in excess of the given quantities
(1) [1960] 2 S.C.R. 793.
477
of work upto 30% if an increase in excess of 30% is ordered
over the work the contractor must intimate to the Engineer
Incharge in writing his willingness or refusal to do extra
work at the originally tendered rates. In the latter case
he should settle fresh rate for increased work over 30%
before doing the work".
These instructions being part and parcel of the original
contract Ex. B1 would govern the parties. As such the
appellant unless he gave notice under that paragraph that he
is not prepared to do the extra work over the 30% at normal
rates, he cannot claim anything other than at the rates
mentioned in the contract, unless he had settled fresh rates
for that extra work. There is no evidence nor is it claimed
by the appellant that he had given any notice as required
under paragraph 5 of the special instructions and since he
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
did the work without fulfilling these requirements he is not
entitled to claim, any amounts at a higher rate for the
extra work done. As neither of the contentions have force
the appeal is dismissed but in the circumstances without
costs.
V.P.S. Appeal,
dismissed.
478