Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
PETITIONER:
UNION OF INDIA
Vs.
RESPONDENT:
JAI NARAIN MISRA
DATE OF JUDGMENT:
31/10/1968
BENCH:
BACHAWAT, R.S.
BENCH:
BACHAWAT, R.S.
SIKRI, S.M.
CITATION:
1970 AIR 753
ACT:
Arbitration-Award when vague and uncertain--Part of
award based on mistake may be struck out if separable.
HEADNOTE:
The respondent, a building contractor, entered into a
contract with the Government of India for the construction
of certain flats. On disputes arising, they were referred
to an arbitrator. the arbitrator made an award and
directed certain sums to be paid by the Union of India to
tile respondent. Rupees twenty-two thousand two hundred and
ninety two, annas five were to be paid as the amount due to
the respondent ’as calculated by the Union of India. Rupees
six thousand were to be paid as the amount of security
deposit made by the respondent with the Union of India. The
third item was mentioned as Rupees seventy nine thousand
three hundred and thirty nine. The. total amount payable
was mentioned as Rupees one lakh seven thousand six hundred
and thirty one, annas five. The respondent made an
application for modifying the award and for remitting it to
the arbitrator for reconsideration. The Second Civil Judge,
Kanpur dismissed the objections and pronounced judgment
according to the award. The appellant filed an appeal
against the order under s. 39 of the Arbitration Act, 1940.
The High Court allowed’ the appeal and set aside the award
on the ground that it was vague and uncertain. According to
the High Court it was not clear why the arbitrator awarded
the first item of Rs. 22,292/5/-and the third item of Rs.
79,339/- separately. Since the arbitrator found only the
fir.st item of Rs. 22,922/5/to be due to the respondent, the
High Court did not find it clear whether he intended also to
award the 3rd item of Rs. 79,339/- to the respondent. As the
dispute related to 29 items of claims and counter-claims the
arbitrator, according to High Court, should have made an
award in respect of all the items separately or in
combination or should have made a lump sum award in respect
of nil the items. Against the order of the High Court the
Union of India appealed to this Court with certificate.
HELD: The reasoning of the. High Court could not be
accepted.
(i) The award on the face of it professed to be of and
concerning all matters submitted for arbitration. In
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
respect of all such matters the arbitrator awarded a sum of
Rs. 1,07,631/6/- to the respondent. This amount was made of
three sums separately mentioned in the award. On the record
there was nothing to show that the award was not
intelligible to the parties. [590 G]
The court leans towards the construction that the award
is certain. the evidence item No. 1 represented the sum
admitted the sum due to respondent and item No. 3
represented the additional sum found by the arbitrator to be
due to him. [590 H]
(ii) The arbitrator is not bound to give an award on
each point. He can give his award on the whole case. An
’arbitrator may award one sum generally in respect of all
money claims submitted to him. unless the submission
requires him to award separately on some one or more of
them.
589
The arbitrator can lawfully make an award of a sum admitted
to be due and a lump sum in respect of the remaining claim.
As the final award in favour of the respondent professed
to be made of and concerning all the matters referred to
him, it must be presumed that in making it the arbitrator
had taken into consideration ’all the claims and counter
claims. The award must be held to be a final and certain
determination of all the disputes referred. [591 C, D]
(iii) The mention of the second item of Rupees six
thousand in the award was a mistake. This part of the award
being clearly separable must be struck out. The award of the
sum of Rupees six thousand was to the advantage of the
respondent and the court could not set aside an award at the
instance of a party who had not suffered any injury. [591 F]
Mays and Anr. v. Cannel 24- Law Journal Q.B. 41, 45;
Ghulam Khan v. Mohammad Hassan I.L.R. 29 Cal. 167, 186
(P.C.); Whiteworth v. Hulse (1866) L.R. 1 Ex. 251;
Harrison v. Creswick (1853) 13 C.B. 399, Jewell v. Christie
(1867) 2 C.B. 296 and Narsingh Narain Singh v. Ajodhya
Prasad Singh, (1912) 15 C.L.J. 110, 113, referred to.
JUDGMENT:
APPELLATE JURISDICTION: Civil Appeal No. 31 of 1966.
Appeal from the judgment gad decree dated December 5,
1962 of the Allahabad High Court in First Appeal from Order
No. 260 of 1952.
R.M. Mehta and S.P. Nayar, for the .appellant.
A.K. Sen, S.V. Gupte and S.S. Shukla, for the respondent.
The Judgment of the Court was delivered by
Bachawat, J. The respondent Jai Narain Misra is a building
contractor. On September 2, 1944, he entered into a contract
(No. ES. 2944) with the Government of India represented by
the Chief Engineer, Central Command, for the construction of
additional quarters at T.P. 2 Kanpur. The contract contained
an arbitration clause. Disputes between the parties relating
to the contract were referred to Col. H.T. Faithful. The
arbitrator made his award on May 19, 1947. On November 15,
1947 the respondent made an application for modifying the
award and for remitting it to the arbitrator for re-
consideration. On January 5, 1948, he filed additional
objections. By his order dated May 26, 1952 the Second
Civil Judge, Kanpur, dismissed the objections and
pronounced judgment according to the award. The appellant
filed an appeal against the order under s. 39 of the
Arbitration Act, 1940. By an order dated December 5, 1962,
the High Court allowed the appeal and set aside the award on
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
the ground that it was vague and uncertain. The present
appeal has been filed by the Union of India on the strength
of a certificate granted by the High Court.
It appears that the respondent submitted 23 items of
claim to the arbitrator. By his letter dated May 6, 1947 he’
added 6 more items of claim. The Union of India made a
counter-claim. The
4Sup. C.I./69-5
590
arbitrator was thus required to decide 29 disputed items of
claim and the counter claim. The award recited that certain
differences between the parties in respect of contract No.
ES. 2944 of 1944 had been referred to the arbitrator for his
decision and that a final award was being made of and
concerning the matters referred to him. The relevant part of
the award was as follows :--
"I award and direct that the following
sums be paid by the respondent to the
claimant.
Rupees twenty two thousand two hundred
and ninety two annas five being the amount due
to the claimant as calculated by the
respondent.
(2) Rupees six thousand being the amount
of security deposit paid by the claimant and
now in possession of the respondent.
(3) Rupees seventy nine thousand three
hundred and thirty nine.
The total amount to be paid by the
respondent to the claimant is therefore one
lakh seven thousand six hundred and thirty one
annas five.
Each party to the dispute shall bear its
own-costs, including the cost of the stamp
duty on this award."
The High Court held that the award suffered from a
patent ambiguity for the following reasons: It was not
clear why the arbitrator awarded the first item of Rs.
22,292/5 and the 3rd item of Rs. 79,339 separately. The
arbitrator found only the first item of Rs. 22,292/5 to be
due to the respondent, it was not clear whether he intended
also to award the 3rd item of Rs. 79,339 to the respondent.
As the dispute consisted of 29 items of claims and a
counter-claim, the arbitrator should have made an award in
respect of all the items separately or in combination or
should have made a lump award in respect of all the items.
We are unable to accept this line of reasoning.
The award on the face of it professes to be of and
concerning all matters submitted to the arbitrator. In
respect of all such matters the arbitrator awarded ’a sum cf
Rs. 1,07,631/5 to the respondent. This amount was made up
of three sums separately mentioned in the award. It was not
the case of the respondent in the Trial Court that the
award was uncertain or not intelligible. The objection was
taken for the first time before the High Court. On the
record there is nothing to show that the award was not
intelligible to the parties.
The Court leans towards the construction that the award
is certain. Prima facie the award is good, and it is for the
defendant
591
10 show that it is uncertain. Per Jervis, C.J. in Mays &
Anr. v. Cannel(1). There is no ambiguity about the first
and the third items of the award. The uncontradicted
evidence of S. Choudhry, the witness for the Government is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
"Item no. 1 of the award is that which was calculated by us
in the government bill. Item no. 3 is in respect of the
remaining claim of the plaintiff." Item no. 1 thus
represents the sum admitted by the government to be due to
the respondent, and item no. 3 represents the additional
sum found by the arbitrator to be due to him.
The arbitrator is not bound to give an award on each
point. He can make his award on the whole case, see Ghulam
Khan v. Mohammad Hassan (1). An arbitrator may award one
sum generally in respect of all money claims submitted to
him, unless the submission requires him to award separately
on some one or more of them, see Whiteworth v. Hulse(3).
The arbitrator can lawfully make an award of a sum admitted
to be due and a lump sum in respect of the remaining claim.
As the final award favour of the respondent professes to
be made of and concerning all the matters referred to him,
it must be presumed that in making it the arbitrator has
taken into consideration all the claims and counter claims,
see Harrison v. Creswick (4), Jewell v. Christie (5). We
hold that the award is a final and certain determination of
all the disputes referred.
The arbitrator made an award in respect of the second
item under some misapprehension. The security deposit of
Rs. 6,000 had been returned to the respondent and there was
no dispute about it before the arbitrator. In the
circumstances, the arbitrator had no authority to award Rs.
6,000 to the respondent on account of the security
deposit. This part of the award is clearly separable and
may be struck out. Moreover, the award of Rs. 6,000 is
to the advantage of the respondent; and the Court usually
declines to set aside an award at the instance of a party
who has not suffered any injury by the error, see Narsingh
Narain Singh v.Ajodhya Prasad Singh(6). We find also that
the award of Rs. 6,000 is now of no consequence. After the
award was made, the respondent received a sum of Rs.
1,00,594/7 in full settlement of the award, presumably
after giving the government credit for the sum of Rs. 6,000
already received by him.
We therefore hold that there is no ground for setting
aside the award. The award is not vague and/or uncertain
and does not suffer from any other infirmity.
(1) 24 Law Journal, Q.B. 41,45. (2) I.L.R. 29 Cal. 167, 186
(P.C.).
(3) (1866) L,R. I Ex. 251. (4) (1853) 13 C.B. 399.
(15) (1867) 2 C.B. 296. (6) (1912) 15 C.L.J. 110,
113.
592
Mr. Mehta also contended that (1) the appeal before
the High Court was not maintainable under ss. 17 and 39 of
the Arbitration Act, 1940 and (2) the respondent having
received payment in full settlement of the award was
estopped from challenging it. We do not find it necessary
to decide these points in view of our conclusion that the
award is not liable to be set aside.
The appeal is allowed with costs in this Court, and the
High Court. The order of the High Court is set aside and
the order and decree passed by the Second Civil Judge,
Kanpur, is restored.
G.C. Appeal allowed.
593