Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CRIMINAL APPELLATE JURISDICTION
CRIMINAL APPEAL NO. OF 2009
[Arising out of SLP (Crl.) No. 4130 of 2006]
State of Madhya Pradesh …Appellant
Versus
Sheetla Sahai & Ors. …Respondents
J U D G M E N T
S.B. SINHA, J :
1. Leave granted.
2. Appellant is before us being aggrieved by and dissatisfied with a
judgment and order dated 12.01.2006 passed by a learned Single Judge of
the Madhya Pradesh High Court allowing the criminal revision applications
filed by the respondents herein arising out of the orders dated 21.12.1998
2
and 13.05.1997 passed by the Special Judge, Bhopal in Special Case No. 6
of 1997.
3. The respondents herein were proceeded against for commission of
offences under Section 13(1)(d)(2)(ii-iii) read with Section 13(2) of the
Prevention of Corruption Act, 1988 (for short “the Act”) and Section 120B
of the Indian Penal Code, 1860.
4. Before proceeding further, we may notice the positions held by the
respondents herein. Respondent No. 1 Sheetla Sahai was Minister for Water
Resources of the State of Madhya Pradesh. Respondent No. 2 D.V.S.R.
Sarma and the respondent No. 7 S.W. Mohgoankar were the Secretary to the
Government of Madhya Pradesh. Respondent No. 3 P.V. Srinivasaiyah was
the Engineer-in-Chief and the respondent No. 4 A.S. Laxminarsimhaiya was
the Deputy Secretary in the Government of Madhya Pradesh. Respondent
No. 5 V.R.B. Gopal and the respondent No. 6 M.N. Nadkarni were the Chief
Engineers, Hasdeo Bango Project. Respondent No. 11 R.P. Khare was the
Secretary, Control Board for Major Projects.
3
5. Appellant under the aegies of the World Bank undertook construction
of the Hasdeo Bango Masonry dam project. For the aforementioned
purpose, the respondent Nos. 8, 9 and 10 herein, viz.,M/s Progressive
Constructions Pvt. Ltd., M/s Prasad & Company, M/s SEW Construction
Co. (hereinafter referred to as “the contractors”) were awarded contracts in
terms whereof they were required to excavate stones etc. from Therma Pahar
Quarry, which was situate at only 12 kms. away from the site, for use of the
stone to be extracted therefrom for construction of masonry spillway.
6. One of the terms of the said contract is as under:
“…The tenderer should satisfy himself regarding
availability of the required quality and quantity of
the materials, if any quarry is changed for any
reason whatsoever, no claim shall be entertained
on this account.”
In addition to the guidelines, a plan was also supplied to the
contractors containing the following note:
“the contractor shall extract materials from
the approved sources and quarry areas to be
designated by the engineer-in-charge for their
particular contract group. They shall have no
claim for any material collected elsewhere without
4
having obtained the prior approval in writing of the
engineer in charge. Such material shall become
the property of the department unless approval to
use the same is subsequently accorded by the
engineer-in-charge, in which case, however, the
contractor shall not be entitled for any extra rate or
lead.”
7. However, on the premise that whereas eight lakh cubic meters of
stones of the requisite specification were required for masonry work, only
one lakh cubic meter stone was available from the Therma Pahar Quarry,
permission was sought for by the contractors to excavate stones, rubbles and
other materials from a quarry known as Katghora Quarry which was situated
at a distance of 22 kms. from the dam.
8. The question was considered by the concerned engineers. The
District Mining Officer and the Additional Collector Korba, having regard to
the fact that the mining leases in respect of the said quarries were to be
granted, asked them not to do so as the stones in the hillocks of villages
Katghora, Hunkra and Maheshpur were found to be suitable for the masonry
work of the dam, as would appear from a letter dated 14.07.1983 issued by
the Executive Engineer to the Additional Collector, Korba.
5
9. The Superintending Engineer, respondent No. 7 herein also by his
letter dated 28.07.1983 addressed to Shri R.C. Gupta, the then Executive
Engineer stated:
“I am informed that Rampura quarry near
Katghora on Kathora Ambikapur road, may also
yield good masonary stones. You may also
explore this possibility and let me know if the
stones were got tested. If not, the samples from
this quarry may also be tested. Case could also be
moved to obtain lease for this quarry.”
10. A request was also made to the Mining Officer of Bilaspur to the
same effect by Shri R.C. Gupta, the then Executive Engineer by a letter
dated 16.10.1983, stating:
“…Adequate quantity of rubble is not available
from Therma quarries of Forest Department
acquired for this purpose and Geologist,
Geological Survey of India had intimated that
about one lakh cum. of rubble can only be
extracted from Therma quarries. For completion
of this major dam about ten lakh cum. rubble &
metal are needed. Out of which 1 lakh cum. can
be extracted from Therma quarry, about three lakh
cum. can be used out of the stone received from
excavation of foundation of dam, remaining 6 (six)
lakh cum. is required from adjacent stone quarries
like Katghora, Hukra & Maheshpur. Hence, I have
requested in my letter cited above (copy enclosed)
6
to additional Collector, Korba, to reserve rubble
quarries in the surroundings of the above villages
so that rubble from these quarries can be extracted
for completion of the Bango Dam in time.
Now I understand that you have proposed
the above quarries for auction on 20th & 21st
Oct.’83. I request to delete the rubble quarries
situated in the surrounding of Katghora, Hukra &
Maheshpur from the purview of auction and
transfer to Irrigation Department. Depending upon
the quantity of rubble required by each agency
executed masonry works at Bango Dam, allotment
of individual quarries will be made by us after the
agencies deposit the royalty charges which will be
refundable to them after awarding the certificate of
utilizing the material in bonafide Government
works.
Till the formalities are over for transfer of
the above quarries to Irrigation Department, I
request to delete the following quarries from the
purview of auction.
| S.No. | Name of<br>Village | PC No. | Name of<br>material | Khasra No. | Area |
|---|---|---|---|---|---|
| 1. | Hukra | 47 | Stone | 347/1 | 17.396<br>Hec. |
| 2. | Maheshpur | 31-A | Stone | 1/1-K | 30.425<br>Hec.” |
11. The Additional Collector (Mining Section), Korba in response thereto
by a letter dated 22.11.1983 addressed to the Executive Engineer reserved
7
the aforementioned quarries for extraction of stones departmentally, subject
to the conditions mentioned therein.
12. Yet again, the Executive Engineer by a letter dated 05.12.1984
addressed to the Superintending Engineer brought to his notice that
alternative sites for quarrying operations for extraction of stones were
necessary, inter alia, stating:
“2. The quarrying operations for extraction of
stones was started in the real sense during 82-83
working season, i.e., prior to the area was ready for
starting the masonry. The contractors after the
start of quarry operations, repeatedly wrote,
regarding the non availability of sufficient stones
of requisite quality. They had also brought out that
the yield of even this small quantity of stone was
very much less. In consultations with the
department and the resident geologist, they have
opened more number of quarry faces, but this did
not result yields. This office has also carried out
case studies which has established the yield of
useful stone to be very much less. The details
enclosed at Annexure A. Even the quantum of
stone available is less, when compared to the
requirement.
3. It was reported that the quantum of useful
rubble available in the entire Therma Pahad Hills
is to the tune of one lakh cum. against the total
requirement of 8 lakh cum. for the entire dam.
This was based on the detailed investigations and
8
report of the Resident Geologist. Even this
quantity can be extracted with much difficulty.
Therma Pahad Quarry on the visual appearance
and the random bore holes, initially appeared to be
good. As such this was declared as quarry for
masonry stone and accordingly estimates prepared
and designated as the specified quarry in the
quarry map enclosed along with the agreements.
The contractors naturally could not have
investigated the quarry by actual opening/
operation, and have inspected the quarry with the
data available to them. Therefore neither
department nor the contractor could have foreseen
the non availability of useful stone in the required
quantity from the designated quarry.”
It was requested:
“It is therefore requested that the sanction may be
obtained for payment of additional leads and
communicated. However, the payment towards
additional wasteful expenditure incurred in therma
quarries as claimed by contractors is recommended
for rejection.”
13. The Superintending Engineer brought the same to the notice of the
Chief Engineer by a letter dated 18.12.1984 stating that there had always
been a controversy regarding the use of those stones as rubble in masonry
dam. A question was also raised as to whether the department would permit
additional payment due to change in the quarry. If such a step is not taken,
9
the contractor may put an end to the contract and, thus, inter alia requested
that payment of additional leads from Katghora quarry may be allowed.
14. It appears that even the Central Water Commission of the Government
of India by a letter dated 04.05.1984 informed the Chief Engineer of the
project to the following effect:
“Please refer to your letter on the above mentioned
subject. You have proposed to use stone from
Therma Pahar quarry for the construction of the
dam. Though the stone from this quarry has been
approved as Granite, the Compressive strength of
the stone from this quarry varies from 289 kg/cm
to 373 kg/cm, which is very low. It is necessary
that the reasons for such low strength for the
Granite are investigated before deciding to use the
same for the construction of the dam.”
15. By a letter dated 7.06.1983, the Executive Engineer of the Quality
Control Division brought the following to the notice of the Superintending
Engineer of the Quality Control Department:
“Thus, it is noticed the mica existing in the rocks
under question varies from 7% to 11%. No
mention of the permissible percentage of mica is
given in IS codes or other books. Only Hand book
on civil engineering by PN Khanna, reveals that
10
2% of mica is permissible. In view of the above it
is submitted that the pigmetite band stones are not
fit for use in masonry dam from quality control
unit Machadoli’s point of view. This is, however,
continuously used in masonry on dam blocks 16,
17, 18, 19, 25, 26, 27, 28, 29, 35, 37 in which work
continuously in progress. If the higher authority
deems it fit, that use of pigmetite is to be continued
by overruling the opinion of the undersigned clear
written instructions may kindly be issued to this
office for guiding the A.R.Os. Quality Control
deployed on Quality control work of masonry dam.
Early reply is solicited.”
16. In view of the aforementioned development, the Chief Engineer of the
Project brought the same to the notice of the Secretary of the Major,
Medium and Minor Irrigation Department, Bhopal by a letter dated
11.01.1985 inter alia making the following recommendations:
“(i) Permitting the Chief Engineer for declaring
Katghora quarry as an additional quarry for
balance quantity of rubble quarry for rubble for
masonry dam other than one lakh cubic meter of
rubble, as assessed by the geologist to be extracted
by the contractors from Therma Pahad quarry as
far as possible in the contracts mentioned in this
letter.
(ii) To allow payment of additional leads from
Katghora quarry for cum of masonry at the rates
detailed in table at para 5.3 above.”
11
Along with the said letter, various other documents were enclosed as
specified therein including a letter dated 4.05.1990, wherein it was inter alia
stated:
“10. In view of the above, the Chief Engineer
submitted proposals on 4.07.85 for Government
Orders. According to the above proposals sanction
to pay extra lead amounting to Rs. 1,23,23,767/-
has been sought. This amount is about 3% of the
total amount of contract of Rs. 41.77 crores. The
Chief Engineer had also sought the opinion of the
World Bank, and the World Bank gave a
suggestion to deal the issue with in the contractual
provisions. Similar problem has been raised by the
contractors in Bansagar Project also, and the
Executive Committee had recommended approval
of lead payment.
11. According to the Chief Engineer’s report,
the Executive Engineers had reported that only
30% to 35% useful stones can be extracted which
was not economical. This project is under
construction with the World Bank assistance, will
have to be completed on time, to supply water to
the National Thermal Power Corporation, and also
to the M.P.E.B. Power Station. In view of this
stones have been brought from Katghora quarry
situated at 22 Km. where sufficient quality of
stones are available.
In case, due to above reasons had the Agreements
drawn been cancelled and new tenders recalled the
cost would have been more. Further, precious time
would have been lost in this process which would
have affected the works and it would not be
12
possible to supply water to N.T.P.C. and
M.P.E.B.”
17. In a letter dated 14.02.1985 addressed to the Chief Engineer, the
World Bank stated:
“We note you have referred the matter to the
Secretary, Irrigation Department, Bhopal for
decision. We suggest that the matter be resolved
within contractual limits.”
18. Pursuant thereto and in furtherance thereof, even the Progress Review
Committee observed in its note dated 14.05.1985 as follows:
“27. Chief Engineer (HBP) explained his proposal
submitted through his memo No. 1916/HB/84
dated 29/3/85. He gave the background of the
change of quarry, in view of unexpectedly low
yield of useful stone from the Therma Pahad
quarry, approved in the technically sanctioned,
sanctioned estimate and also on which basis
tenders had been invited and contractors’ rates
accepted. He informed the Committee that the
total extra commitment for the various contracts
worked out to Rs. 1.23 crores – approximately 3%
of the total contract value.
28. Financial Adviser observed that he had no
offered any comments on the merit of the case, as
13
then appeared to him essentially a claim case.
PRC does not deal such claim cases.
29. The Committee observed that the World
Bank too vide their letter of 14/2/85 had suggested
that the matter be resolved within contractual
limits.
30. In view of the above, the Committee did not
examine the proposal of Chief Engineer and
refrained from giving any comments in the matter
at this stage.”
19. However, the contractors invoked the arbitration agreement contained
in the said contract in the year 1987 and an ad hoc settlement was proposed.
20. The matter was placed before the Financial Adviser. The Financial
Adviser in his note dated 4.01.1991 to the Secretary, while stating that the
Financial Adviser functions as a consultant offering comments on cases
referred to him in the light of his background, experience and expertise and
going by the facts placed before him which may not be treated as a substitute
for vetting by the Finance Department wherever such vetting is required
under the rules of governmental business, inter alia made the following
comments:
14
“…However, since the whole contract action was
based on the presumption that the required
quantity of material of required specification
would be available from a quarry with in 12 KM of
the work site, it can be reasonable assumed that the
contractors have quoted their rates on this
assumption. The departmental estimates were also
based on this assumption. Since, later on, this
assumption was found to be invalid and majority
of the material had to be obtained from a quarry
with an average lead of 22 KM from the work site
as against 12 KM in respect of the contemplated
quarry, the contractors have a reasonable case for
additional payment on account of extra lead of the
material brought by them from this second quarry.
Thus, their claim is based on consideration of
equity rather than there of law.”
In regard thereto, the Financial Adviser opined:
“4. Since the proposed settlement will amount
to extra-contractual payment, it has to be ensured
that the proposed settlement is acceptable to the
contractors concerned. In other words, the
settlement has to be a negotiated settlement and
should not leave room for further disputes with the
various contractors. Since the purpose of the
whole exercise is to avoid arbitration it could even
be ascertained if there are any other disputed issues
in these contracts. If an overall settlement of all
the disputes could be attempted and a sort of
package deal is evolved in respect of each contract
so that the contracts are finalized once for all
leaving no scope for arbitration on the other hand
15
if the contractors intend to take resort to arbitration
for other issues, this issue could also go in for
arbitration. A package approach would allow
negotiation in a spirit or give and take for an over-
all settlement of all disputes.”
21. The then Secretary (Irrigation) Shri M.S. Billore constituted a
committee comprising of the Engineer-in-Chief P.V. Srinivasaiyah, the
Chief Engineer, the Financial Adviser, Secretary (Control Board) and the
Deputy Secretary, some of whom are Accused Nos. 3, 4,5 and 11.
22. The said Committee submitted a report in respect whereof the
Secretary made a note that the same be critically examined.
The Officer on Special Duty noticed the recommendations of the
Committee, which are as under:
“(i) As the quarry has been changed by the
Department due to Technical reasons the
contractors cannot be held responsible.
(ii) When the Department itself did not know
about the quarry’s unsuitability it will be unfair to
expect the contractors to bring stones from the
changed quarry at the same rates.
(iii) Payment to the extent of actual quantity
brought from the quarries be made.”
16
The proposals of the Chief Engineer, the quantities under each
agreement, the rate and the amount were also noticed. It was proposed:
“Therefore, it is proposed to approve payment for
actual quantity and the Chief Engineer may be
informed to take undertakings from the contractors
before making the payment.”
The Financial Adviser was asked to examine the said proposal in
details. Some discussions apparently were held and it was found necessary
to obtain the following information before taking decision at the government
level:
“1. After the inspection of the Geologists how
much quantity has been brought from Therma
Pahad by each contractor.
2. How much quantity has been brought from
Katghora quarry.
3. How the records are kept by the Department
about the quantity of stones brought from different
quarries.”
A draft letter was also prepared.
17
23. On or about 6.04.1991, one Shri Uday Shinde in his note stated that
the Chief Engineer had not sent any detail in regard to Block 31-38 as in the
agreement only Therma Pahar quarry had been shown for the balance work
and as the original file was sent to the Hon’ble Minister, it was not possible
to deal with the case. The file was re-submitted and the amount payable to
the contractor for additional lead was again put up for administrative
approval. Yet again, the Engineering in-Chief Committee was asked to
examine the matter.
24. In a note to the Secretary dated 27.04.1991, the salient features in
respect of the aforementioned matter were placed again to which Shri M.S.
Billore by his note dated 1.05.1991 opined :
“Since government decision has already been
informed to the Chief Engineer, Hasdeo Bango
Project through government letter No:
9/CP/B/31/89/319, Bhopal dated 28.2.89. Hence,
any action at government level is not pending in
this case and Chief Engineer to take action in this
case as per government order.”
18
25. Allegedly, the respondent No. 1 who was Minister at the relevant
point of time sat over the file for a period of about six months. He on
4.11.1991 noted:
“I have studied the case. Whenever any opinion
has been sought by the Secretary, from whichever
authority, they gave their opinion as per their
wisdom. Every time the Secretary has been
seeking the opinion from one after another officer.
In this process he spent a period of one year
between 3.5.90 to 1.5.91. In accepting the opinion
or recommending any action, it was expected from
the Secretary to take into consideration the fact
that the opinions had been given as per their
wisdom. Therefore, question does not arise to take
any action against the subordinate officers.
No basis appears for the Secretary to take a totally
different view than the unanimous opinions.
Therefore, it is necessary to investigate the basis
on which the Secretary Shri Billore had rendered
his opinion.
The new Secretary to study the case and give
opinion.”
26. Pursuant thereto or in furtherance thereof, the respondent No. 2 Shri
D.V.S.R. Sarma submitted a report upon constitution of a Committee,
stating:
19
“(i) Due to technical reasons, the department has
changed the quarry. Therefore, its liability should
not be upon the contractors.
(ii) When the Department had not any
knowledge about the quarry, and to expect this that
even under the changed quarry the contractor
should fetch/ transport the stones at the same rate,
is also not proper.
(iii) Where & Where (sic) and for that much of
the quantities, the materials have been brought
from a quarry at more distance, it is proper to
make payment for that much excess distance.”
27. The respondent No.1 approved the said note of the respondent No. 2
on or about 20.01.1992 whereupon the amount in question was sanctioned.
28. Thereafter, the accounts were audited and one Shri G.K. Shukla,
Deputy Accountant General reported:
“a) The clause of the agreement noted above
and the quarry chart clearly bring out that in the
event of change of quarry on whatever reasons no
claim will be entertained and contractor should
before quoting rates, visit the quarry site and
satisfy himself regarding quantity and quality of
the material available. Thus, the sanction appears
a negotiated settlement beyond the contractual
provisions, for which concurrence of Finance
Department ought to have been obtained.
20
b) The PRC considered this as a claim case
which was to be decided by Arbitrator under M.P.
Adhikaran Adhiniyan, 1983.
c) The Member, World Bank suggested to
resolve the matter within the contractual limits.
d) The Secretary Irrigation had earlier rejected
the case as it was not admissible.
e) The rates quoted by the contractors were
inclusive of all lead and lift, being item rate
tender.”
The Auditor General of India also took note of the said report, stating:
“Therefore, in spite of the report of the Geologist
that the good quality of stone was available in
sufficient quantities in the upper portion of the
quarry situated in the hill mentioned in the
agreement and in spite of there being specific
provision in the agreements that no additional
payment would be acceptable in the event of
change in leads or change in quarry, the payments
made to the contractors were irregular and
resultantly made additional gains of Rs. 102.46
lacs to them.”
29. Pursuant thereto or in furtherance thereof, a complaint was lodged.
The matter was investigated by the Special Police Establishment. They
collected all the materials and filed a chargesheet in the Court of learned
21
Special Judge on 27.03.1997. The case was registered as Special Case No. 6
of 1997.
30. By an order dated 13.05.1997, the learned Special Judge took
cognizance of the case, opining:
(i)
As none of the accused is a public servant, no sanction was
required to be obtained in terms of Section 19 of the Act.
(ii) Criminal misconduct relating to corrupt practice under Section
13(1)(d)(ii-iii) of the Act has nothing to do with normal activity
and work under government duty of any public servant at any time.
31. In the year 1997, the respondent Nos. 1 and 2 had filed a revision
application before the High Court.
32. The Special Judge framed charges against the respondents on or about
29.07.1999; a sample copy whereof reads as under:
“You were working as Minister In-charge,
Ministry of Water Resources, Government of
Madhya Pradesh from June 1990 to September
22
1992. On the recommendatory note of Shri
D.V.S.R. Sharma ignoring the letter dated 14.02.85
of the Finance Branch of World Bank and earlier
decision dated 18.02.85 according to which the
case of extra lead was to be decided within the
ambit of the contract in respect of payment of extra
lead to the concerned Tender Contractors for
transportation of stones used in construction work
of masonry non-flow dam upstream in Hasdeo
Bango Project. You in conspiracy with the
employees and Tender Contractors accorded
administrative sanction and payment of one crore
two lac forty six thousand two hundred rupees was
made to the Contractors towards extra lead.
Hence, you while holding the post of public
servant misusing the position of the post provided
financial benefit to the Tender Contractors without
public interest.
Your above act being offence under Section
13(1)(D)(ii-iii), the Prevention of Corruption Act,
1988 is punishable under Section 13(2) the
Prevention of Corruption Act, 1988. In the
alternative, you in criminal conspiracy with Shri
D.V.S.R. Sharma, Secretary, working in the
Ministry of Water Resources, Government of
Madhya Pradesh and other employees and
contractors acted as mentioned above, which is
punishable under Section 13(1)(D)(ii and iii) read
with Section 120B IPC, which is within the
jurisdiction of this Court.
Hence, I hereby direct that you will be tried
for the offence mentioned above by this Court.”
23
33. Aggrieved by and dissatisfied therewith, the respondents filed revision
applications before the High Court, which by reason of the impugned order
have been allowed. The State is, thus, before us.
34. Mr. K.T.S. Tulsi, learned senior counsel appearing on behalf of the
appellant, in support of the appeal, inter alia would submit:
(i) The High Court committed a serious error in opining that an order
of sanction in terms of Section 197 of the Code of Criminal
Procedure was required to be obtained despite the fact that the
respondent Nos. 1 to 7 were no longer holders of public office(s).
(ii) While exercising its revisional jurisdiction, the High Court could
not enter into the question of appreciation of evidence as also the
probative value of the materials brought on record, contrary to the
tests laid down by this Court in Soma Chakravarty v. State
Through CBI [(2007) 5 SCC 403] as the tests for framing of charge
are different from the tests for recording a judgment of acquittal
against an accused insofar as whereas in the former, strong
suspicion would be sufficient, in the latter proof beyond any
reasonable doubt is necessary.
24
(iii) The prosecution agency being a special agency constituted under
the Madhya Pradesh Special Police Establishment Act, which
functions under the jurisdiction of the Lokayukata, only because all
materials have been made part of the chargesheet, the same could
not have been relied upon by the High Court as the only materials
upon which the prosecution would rely upon for proving its case
would be the terms of the contract, the note sheets, the letters dated
4.08.1983, 11.08.1983, 16.08.1983, 17.08.1983, 10.07.1984,
14.11.1984 and 2.03.1988, in terms whereof the contractors were
categorically informed that they would not be entitled to any extra
amount towards additional lead or otherwise.
(iv) The World Bank having opined that stones from alternative
sources may be obtained within the budgeted amount, the extra
amount could not have been sanctioned by the respondents.
(v) By reason of the acts of the respondents, the State has suffered a
loss to the extent of Rs. 1.02 crores and in that view of the matter,
the High Court should not have passed the impugned order.
(vi) As none of the accused is a public servant, the question of
obtaining sanction in terms of Section 19 of the Act did not arise.
25
(vii) Criminal misconduct relating to corrupt practices under Section
13(1)(d)(ii-iii) of the Act cannot be mingled with the normal
activity and duties of the public servant at any time, and, thus, no
order of sanction was required to be obtained even under Section
197 of the Code of Criminal Procedure, 1973.
(viii) The Indian Institute of Technology having tested the rocks
excavated from Therma Pahar Quarry and having opined that they
can safely be used for rubble masonry as well as for coarse and
fine aggregate, any opinion rendered contrary thereto or
inconsistent therewith should have been ignored.
35. Mr. U.U. Lalit and Mr. Vivek Tankha, learned senior counsel
appearing on behalf of the respondents, on the other hand, urged :
(i) The court at the stage of framing of charge and consequently the
High Court in exercise of its jurisdiction under Sections 397 and
401 of the Code of Criminal Procedure were entitled to consider
the entire materials on record for the purpose of arriving at a
finding as to whether the contents thereof, even if taken to be
26
correct in their entirety, constituted a prima facie case against the
accused or not.
(ii) It would not be correct to contend that although all the documents
collected during investigation form part of the final report
submitted by the Special Police Establishment in terms of Sub-
section (5) of Section 173 of the Code of Criminal Procedure, for
the purpose of framing of charge or otherwise the prosecution can
rely only on a few of them so as to make a distinction between the
documents which are in favour of the prosecution and those which
are in favour of the accused.
(iii) The materials brought on record clearly show that the concerned
authorities found it necessary to explore the possibility of
procuring stones of requisite quality from other sources as they had
proceeded on a wrong premise that stone of requisite quality to the
extent of 8 lakh cubic meters would be available in the quarry in
question.
(iv)
Although the contract could be considered to show that no claim
for any material collected elsewhere, without obtaining the prior
approval of the Engineer Incharge, as was contended by the
prosecution, was admissible, on a close reading of the terms of the
27
contract it would appear that a contingency of this nature, viz., that
the parties entered into a contract on a mistaken fact was not
contemplated as the contractors cannot be asked to take upon
themselves the financial burden in respect of matter for which they
were not responsible.
(v)
A decision having been taken by the highest authority not only
upon taking into consideration the opinion of all concerned, viz.,
from Executive Engineer to the Minister concerned but also in
view of the opinion of the Government of India and on the basis of
two reports of the Committee, viz., reports by respondent No. 2
D.V.S.R. Sarma Committee and respondent No. 3 P.V.
Srinivasaiyah Committee, no interference with the impugned
judgment is warranted.
(vi) The documents relied upon by the prosecution, even if given face
value and taken to be correct in their entirety, do not disclose
commission of any offence under the Prevention of Corruption Act
as no allegation had been made as regards misuse or abuse of
office.
(vii) The State having acted within its jurisdiction in taking a decision
in regard to making of extra payment by way of novation of the
28
original contract, no exception thereto can be taken as the situation
was unforeseen. Even the arbitral tribunal having passed an award
in favour of the contractor which is in consonance with a decision
of this Court in K.N. Sathyapalan (Dead) by LRs. v. State of
Kerala & Anr. [(2006) 12 SCALE 654], the respondents cannot be
said to have committed any offence.
(viii)
In any view of the matter, no evidence has been brought on record
to show that any conspiracy was entered into by the respondents
inter se.
(ix) Assuming that the respondents have arrived at a wrong conclusion,
the same would only constitute an error of judgment and not a
criminal misconduct.
(x) The malafide attitude on the part of the State would be evident
from the fact that the respondents herein who were members of the
Committee have also been roped in although they had made fair,
proper and impartial recommendations which could have been
accepted or rejected. Even the respondent No. 1 in his note dated
4.11.1991 did not issue any direction to make payment but merely
asked the respondent No. 2 to have a re-look at the entire matter as
prior to the purported opinion of Mr. Billore, as contained in his
29
note dated 1.05.1991 he had opined otherwise, viz., not in the tune
of the recommendations made by the Quality Control Department,
i.e., in favour of the contractors.
(xi) There is nothing on record to show that the respondent Nos. 1 to 7
herein have done any act which was beyond their official duty and
hence, the impugned judgment is unassailable.
36. The question raised before us is required to be determined on the
backdrop of factual matrix involved herein. We have taken into
consideration in details the background materials only with a view to
consider as to whether the High Court was right in opining that no case for
framing of charges against the respondents was made out.
The fact that the State entered into contracts with the respondent Nos.
8, 9 and 10 is not in dispute. The basic terms of the contract, which we have
taken note of, are also not in dispute. What is in dispute is the interpretation
and application thereof.
37. The contract contained an arbitration clause. The respondents herein
invoked the said arbitration agreement, as noticed hereinbefore, as far back
30
in the year 1987. Indisputably, an award had been made in their favour on
the basis of a settlement arrived at by and between the parties. Such a
settlement was arrived at on the basis of the stand taken by the authorities of
the State of Madhya Pradesh upon entering into detailed deliberations.
38. The learned counsel for the parties took us through the entire
agreement to raise rival contentions as to whether despite the apparent
rigours contained therein, the contractors could have been paid any
additional amount towards extra lead.
39. We think a construction of the terms of contract in the light of the
factual matrix of the matter to which we have adverted to heretobefore, as
has been argued by the respondents, is possible. It is, however, not
necessary for us to delve deep into the matter inasmuch as we are concerned
only with the question as to whether the materials brought on record form
sufficient basis for framing of charges under Section 13(1)(d)(ii-iii) of the
Act read with Section 13(2) thereof read with Section 120B of the Indian
Penal Code or not.
31
40. At the outset, however, we must place on record that construction of
the dam over river Hasdeo Bango became necessary for the purpose of
supply of water to the National Thermal Power Corporation. It was a World
Bank project. The project was required to be completed within a time frame.
Stones required to be used for the construction of the dam, as of necessity,
were required to be of sufficient strength. The opinion of the Indian Institute
of Technology, referred to by Mr. Tulsi, is not on record. Correspondences
as also the opinion of the Central Water Commission, Government of India,
however, point out that stones of requisite strength were not available at
Therma Pahar Quarry. The quantum of stone required was eight lakh cubic
meters and only one lakh cubic metres was available thereat. The balance
seven lakh cubic meters of stone was, thus, required to be obtained from the
quarries situated at villages villages Katghora, Hunkra and Maheshpur.
41. Stone is a minor mineral within the meaning of the provisions of the
Mines and Minerals (Regulation and Development) Act, 1957 and the Minor
Mineral Concession Rules framed by the State. Lease and/ or licence for
extraction thereof is to be granted by the Collector. Although the Mines
Department of the State intended to grant ‘Quarry lease’ in favour of others
32
having regard to the requirements of the State, the said quarries were
reserved, subject to certain conditions.
42. The respondent Nos. 8 to 10, in view of the provisions of the Mines
and Mineral (Regulation and Development) Act, 1957 and the Madhya
Pradesh Minor Mineral Concession Rules could not have on their own
undertaken mining operation for the purpose of extracting the said minor
mineral. They could have done so only on a licence granted in their favour
by the Collector/State. However, as the hillocks of the villages in question
were reserved for departmental use, only by reason thereof the contractors
could carry on mining operation thereat and not otherwise. It was, therefore,
a conscious decision on the part of the competent authorities of the State.
43. The contract itself suggests that there was a possibility of dispute in
regard to allocation of the parts of the quarries. A dispute resolution
mechanism by creating a forum viz. the Office of the Superintending
Engineer was created.
44. The intra-departmental and inter-departmental correspondences and
notesheets to which we have adverted to heretobefore clearly go to show that
33
the authorities incharge of construction of the dam were aware of the
difficulties which were being faced by the contractors. Their apprehension
was that in the event the contractors were not permitted to mine stones from
Katghora Quarry and other Quarries, they may leave the job as a result
whereof the entire project might come to a stand-still.
45. The representations made by the contractors for the aforementioned
purpose, even if to be ignored, the intra-departmental and inter-departmental
correspondences cannot be. They clearly point out a clear picture as regards
necessity for explaining the possibilities of extracting stones from some
other mines for being used in the construction of dam.
46. We would proceed on the basis that two divergent opinions on the
construction of the contract in the light of the stand taken by the World Bank
as also the earlier decision taken by the State was possible. That, however,
would not mean that a fresh decision could not have been taken keeping in
view the exigencies of the situation. A decision to that effect was not taken
only by one officer or one authority. Each one of the authorities was ad
idem in their view in the decision making process. Even the Financial
Adviser who was an independent person and who had nothing to do with the
34
implementation of the project made recommendations in favour of the
contractors stating that if not in law but in equity they were entitled to the
additional amount.
47. From the materials available on record, it is crystal clear that the
decision taken was a collective one. The decision was required to be taken
in the exigency of the situation. It may be an error of judgment but then no
material has been brought on record to show that they did so for causing any
wrongful gain to themselves or to a third party or for causing wrongful loss
to the State
48. Section 13 of the Act provides for criminal misconduct by a public
servant. Such an offence of criminal misconduct by a public servant can be
said to have been committed if in terms of Section 13(1)(d)(ii-iii) a public
servant abuses its position and obtains for himself or for any other person
any valuable thing or pecuniary advantage; or while holding office as a
public servant, obtains for any person any valuable thing or pecuniary
advantage without any public interest. Sub-section (2) of Section 13
provides that any public servant who commits criminal misconduct shall be
35
punishable with imprisonment for a term which shall be not less than one
year but which may extend to seven years and shall also be liable to fine.
49. Criminal conspiracy has been defined in Section 120A of the Indian
Penal Code, 1860 to mean:
“When two or more persons agree to do, or cause
to be done,--
(1) an illegal act, or
(2) an act which is not illegal by illegal means,
such an agreement is designated a criminal
conspiracy:
Provided that no agreement except an agreement to
commit an offence shall amount to a criminal
conspiracy unless some act besides the agreement
is done by one or more parties to such agreement
in pursuance thereof.
Explanation.--It is immaterial whether the illegal
act is the ultimate object of such agreement, or is
merely incidental to that object.”
Section 120B of the Indian Penal Code provides for punishment for
criminal conspiracy.
36
50. Criminal conspiracy is an independent offence. It is punishable
separately. Prosecution, therefore, for the purpose of bringing the charge of
criminal conspiracy read with the aforementioned provisions of the
Prevention of Corruption Act was required to establish the offence by
applying the same legal principles which are otherwise applicable for the
purpose of bringing a criminal misconduct on the part of an accused.
51. A criminal conspiracy must be put to action inasmuch as so long a
crime is generated in the mind of an accused, it does not become punishable.
What is necessary is not thoughts, which may even be criminal in character,
often involuntary, but offence would be said to have been committed
thereunder only when that take concrete shape of an agreement to do or
cause to be done an illegal act or an act which although not illegal by illegal
means and then if nothing further is done the agreement would give rise to a
criminal conspiracy.
Its ingredients are
(i) an agreement between two or more persons;
37
(ii) an agreement must relate to doing or causing to be done either (a)
an illegal act; (b) an act which is not illegal in itself but is done by
illegal means.
What is, therefore, necessary is to show meeting of minds of two or
more persons for doing or causing to be done an illegal act or an act by
illegal means.
52. While saying so, we are not oblivious of the fact that often conspiracy
is hatched in secrecy and for proving the said offence substantial direct
evidence may not be possible to be obtained. An offence of criminal
conspiracy can also be proved by circumstantial evidence.
In Kehar Singh and Ors. v. State (Delhi Administration), [1988 (3)
SCC 609 at 731], this Court has quoted the following passage from Russell
th
on Crimes (12 Edn. Vol 1):
“The gist of the offence of conspiracy then lies, not
in doing the act, or effecting the purpose for which
the conspiracy is formed, nor in attempting to do
them, nor in inciting others to do them, but in the
forming of the scheme or agreement between the
parties. Agreement is essential. Mere knowledge,
38
or even discussion, of the plan is not, per se
enough”
In State (NCT) of Delhi v. Navjot Sandhu @ Afsan Guru [(2005) 11
SCC 600], this Court stated the law, thus:
“101. One more principle which deserves notice is
that the cumulative effect of the proved
circumstances should be taken into account in
determining the guilt of the accused rather than
adopting an isolated approach to each of the
circumstances. Of course, each one of the
circumstances should be proved beyond reasonable
doubt. Lastly, in regard to the appreciation of
evidence relating to the conspiracy, the Court must
take care to see that the acts or conduct of the
parties must be conscious and clear enough to infer
their concurrence as to the common design and its
execution.”
We may also notice that in Ram Narayan Popli v. CBI [(2003) 3 SCC
641], it was held:
“…Law making conspiracy a crime is designed to
curb immoderate power to do mischief which is
gained by a combination of the means. The
encouragement and support which co-conspirators
give to one another rendering enterprises possible
which, if left to individual effort, would have been
impossible, furnish the ground for visiting
39
conspirators and abettors with condign
punishment…”
In Yogesh @ Sachin Jagdish Joshi v. State of Maharashtra [(2008) 6
SCALE 469], this Court opined:
“23. Thus, it is manifest that the meeting of minds
of two or more persons for doing an illegal act or
an act by illegal means is sine qua non of the
criminal conspiracy but it may not be possible to
prove the agreement between them by direct proof.
Nevertheless, existence of the conspiracy and its
objective can be inferred from the surrounding
circumstances and the conduct of the accused. But
the incriminating circumstances must form a chain
of events from which a conclusion about the guilt
of the accused could be drawn. It is well settled
that an offence of conspiracy is a substantive
offence and renders the mere agreement to commit
an offence punishable even if an offence does not
take place pursuant to the illegal agreement.”
Ex facie, there is no material to show that a conspiracy had been
hatched by the respondents.
53. Mr. Tulsi would suggest that the very fact that the respondent No. 1
being a Minister kept the file with him for a period of six months so as to see
that the then Secretary Mr. M.S. Billore retires so as to enable him to obtain
40
opinion of another officer would prima facie establish that he intended to
cause pecuniary gain to the respondent Nos. 8, 9 and 10.
We have noticed hereinbefore that the Minister in his note dated
4.11.1991 did not make any recommendation. He merely lamented the
manner in which the former Secretary Mr. M.S. Billore acted as prior
thereto, the said authority himself for all intent and purport had accepted the
recommendations of the authorities incharge of construction of the dam
including the Chief Engineer. He constituted a committee. He obtained the
opinion of the Financial Adviser. If upon consideration of the entire
materials on record, independent opinion had been rendered and
recommendations were made, it is difficult to comprehend as to how that by
itself would constitute a criminal misconduct or leads to the conclusion of
hatching any criminal conspiracy. Recommendations made by the
Committee or the opinion rendered by an independent officer like Financial
Adviser need not be acted upon. It was for the State to take a decision.
Such a decision was required to be taken on the basis of the materials
available.
41
In Inspector Prem Chand v. Govt. of N.C.T. of Delhi & Ors. [2007
AIR SCW 2532], this Court observed:
“In State of Punjab and Ors. vs. Ram Singh Ex.
Constable [1992 (4) SCC 54], it was stated:
“Misconduct has been defined in Black's
Law Dictionary, Sixth Edition at page 999, thus:
'A transgression of some established and
definite rule of action, a forbidden act, a
dereliction from duty, unlawful behaviour, wilful
in character, improper or wrong behaviour, its
synonyms are misdemeanor, misdeed,
misbehavior, delinquency, impropriety,
mismanagement, offense, but not negligence or
carelessness.'
Misconduct in office has been defined as:
“Any unlawful behaviour by a public officer
in relation to the duties of his office, willful in
character. Term embraces acts which the officer
holder had no right to perform, acts performed
improperly, and failure to act in the face of an
affirmative duty to act.”
rd
In P. Ramanatha Aiyar's Law Lexicon, 3
edition, at page 3027, the term 'misconduct' has
been defined as under:
“The term ‘misconduct’ implies, a wrongful
intention, and not a mere error of judgment.
Misconduct is not necessarily the same thing
as conduct involving moral turpitude.
42
The word ‘misconduct’ is a relative term,
and has to be construed with reference to the
subject matter and the context wherein the term
occurs, having regard to the scope of the Act or
statute which is being construed. Misconduct
literally means wrong conduct or improper
conduct.”
[See also Bharat Petroleum Corpn. Ltd. vs. T.K.
Raju, [2006 (3) SCC 143].”
54. Even under the Act, an offence cannot be said to have been committed
only because the public servant has obtained either for himself or for any
other person any pecuniary advantage. He must do so by abusing his
position as public servant or holding office as a public servant. In the latter
category of cases, absence of any public interest is a sine qua non. The
materials brought on record do not suggest in any manner whatsoever that
the respondent Nos. 1 to 7 either had abused their position or had obtained
pecuniary advantage for the respondent Nos. 8, 9 and 10, which was without
any public interest.
55. Whether, on the one hand, the dam should be constructed within a
time frame fixed by the World Bank is a public interest or whether sticking
to the terms of the contract which may lead to abandonment of work by the
contractors would be a public interest is a matter over which a decision was
43
required to be taken, particularly when the authorities proceeded on the basis
that they had made advertisements and called for the tender on a wrong
premise, viz., the stones available in the quarry in question for supply of
requisite quality of stone was not in requisite quantity.
56. It is also interesting to notice that the prosecution had proceeded
against the officials in a pick and choose manner. We may notice the
following statements made in the counter-affidavit which had not been
denied or disputed to show that not only those accused who were in office
for a very short time but also those who had retired long back before the file
was moved for the purpose of obtaining clearance for payment of additional
amount from the government, viz., M.N. Nadkarni who worked as Chief
Engineer till 24.03.1987 and S.W. Mohogaonkar, Superintending Engineer
who worked till 19.06.1989 have been made accused but, on the other hand,
those who were one way or the other connected with the decision, viz., Shri
J.R. Malhotra and Mr. R.D. Nanhoria have not been proceeded at all. We
fail to understand on what basis such a discrimination was made.
57. In Soma Chakravarty (supra), whereupon strong reliance has been
placed by Mr. Tulsi, this Court opined:
44
“23. In a case of this nature, the learned Special
Judge also should have considered the question
having regard to the “doctrine of parity” in mind.
An accused similarly situated has not been
proceeded against only because, the departmental
proceedings ended in his favour. Whether an
accused before him although stands on a similar
footing despite he having not been departmentally
proceeded against or had not been completely
exonerated also required to be considered. If
exoneration in a departmental proceeding is the
basis for not framing a charge against an accused
person who is said to be similarly situated, the
question which requires a further consideration
was as to whether the applicant before it was
similarly situated or not and/or whether the
exonerated officer in the departmental proceeding
also faced same charges including the charge of
being a party to the larger conspiracy.”
58. There cannot be any doubt whatsoever that the tests for the purpose of
framing of charge and the one for recording a judgment of conviction are
different.
A distinction must be borne in mind that whereas at the time of
framing of the charge, the court may take into consideration the fact as to
whether the accused might have committed the offence or not; at the time of
45
recording a judgment of conviction, the prosecution is required to prove
beyond reasonable doubt that the accused has committed the offence.
59. In this case, the probative value of the materials on record has not
been gone into. The materials brought on record have been accepted as true
at this stage. It is true that at this stage even a defence of an accused cannot
be considered. But, we are unable to persuade ourselves to agree with the
submission of Mr. Tulsi that where the entire materials collected during
investigation have been placed before the court as part of the chargesheet,
the court at the time of framing of the charge could only look to those
materials whereupon the prosecution intended to rely upon and ignore the
others which are in favour of the accused. The question as to whether the
court should proceed on the basis as to whether the materials brought on
record even if given face value and taken to be correct in their entirety
disclose commission of an offence or not must be determined having regard
to the entirety of materials brought on record by the prosecution and not on a
part of it. If such a construction is made, Sub-section (5) of Section 173 of
the Code of Criminal Procedure shall become meaningless.
46
The prosecution, having regard to the right of an accused to have a
fair investigation, fair inquiry and fair trial as adumbrated under Article 21
of the Constitution of India, cannot at any stage be deprived of taking
advantage of the materials which the prosecution itself has placed on record.
If upon perusal of the entire materials on record, the court arrives at an
opinion that two views are possible, charges can be framed, but if only one
and one view is possible to be taken, the court shall not put the accused to
harassment by asking him to face a trial.
{See State of Maharashtra and Others v. Som Nath Thapa and Others
[(1996) 4 SCC 659]}.
60. This leaves us with the question as to whether an order of sanction
was required to be obtained. There exists a distinction between a sanction
for prosecution under Section 19 of the Act and Section 197 of the Code of
Criminal Procedure. Whereas in terms of Section 19, it would not be
necessary to obtain sanction in respect of those who had ceased to be a
public servant, Section 197 of the Code of Criminal Procedure requires
sanction both for those who were or are public servants.
47
61. Strong reliance has been placed by Mr. Tulsi on a judgment of this
Court in Centre for Public Interest Litigation and Another v. Union of India
and Another [(2005) 8 SCC 202]. In that case, it was held:
“9. The protection given under Section 197 is to
protect responsible public servants against the
institution of possibly vexatious criminal
proceedings for offences alleged to have been
committed by them while they are acting or
purporting to act as public servants. The policy of
the legislature is to afford adequate protection to
public servants to ensure that they are not
prosecuted for anything done by them in the
discharge of their official duties without
reasonable cause, and if sanction is granted, to
confer on the Government, if they choose to
exercise it, complete control of the prosecution.
This protection has certain limits and is available
only when the alleged act done by the public
servant is reasonably connected with the discharge
of his official duty and is not merely a cloak for
doing the objectionable act. If in doing his official
duty, he acted in excess of his duty, but there is a
reasonable connection between the act and the
performance of the official duty, the excess will
not be a sufficient ground to deprive the public
servant from the protection. The question is not as
to the nature of the offence such as whether the
alleged offence contained an element necessarily
dependent upon the offender being a public
servant, but whether it was committed by a public
servant acting or purporting to act as such in the
discharge of his official capacity. Before Section
197 can be invoked, it must be shown that the
official concerned was accused of an offence
alleged to have been committed by him while
48
acting or purporting to act in the discharge of his
official duties. It is not the duty which requires
examination so much as the act, because the
official act can be performed both in the discharge
of the official duty as well as in dereliction of it.
The act must fall within the scope and range of the
official duties of the public servant concerned. It is
the quality of the act which is important and the
protection of this section is available if the act falls
within the scope and range of his official duty.
There cannot be any universal rule to determine
whether there is a reasonable connection between
the act done and the official duty, nor is it possible
to lay down any such rule. One safe and sure test
in this regard would be to consider if the omission
or neglect on the part of the public servant to
commit the act complained of could have made
him answerable for a charge of dereliction of his
official duty. If the answer to this question is in the
affirmative, it may be said that such act was
committed by the public servant while acting in the
discharge of his official duty and there was every
connection with the act complained of and the
official duty of the public servant. This aspect
makes it clear that the concept of Section 197 does
not get immediately attracted on institution of the
complaint case.
10. Use of the expression “official duty” implies
that the act or omission must have been done by
the public servant in the course of his service and
that it should have been in discharge of his duty.
The section does not extend its protective cover to
every act or omission done by a public servant in
service but restricts its scope of operation to only
those acts or omissions which are done by a public
servant in discharge of official duty.
49
11. If on facts, therefore, it is prima facie found
that the act or omission for which the accused was
charged had reasonable connection with discharge
of his duty then it must be held to be official to
which applicability of Section 197 of the Code
cannot be disputed.”
62. Were the respondent Nos. 1 to 7 required to act in the matter as a part
of official duty?
Indisputably, they were required to do so. Be he an Executive
Engineer, Superintending Engineer, Chief Engineer, Engineer-in-Chief,
Secretary or Deputy Secretary, matters were placed before them by their
subordinate officers. They were required to take action thereupon. They
were required to apply their own mind. A decision on their part was
required to be taken so as to enable them to oversee supervision and
completion of a government project. The Minister having regard to the
provisions of the Rules of Executive Business was required to take a
decision for and on behalf of the State. Some of the respondents, as noticed
hereinbefore, were required to render their individual opinion required by
their superiors. They were members of the Committee constituted by the
authorities, viz., the Minister or the Secretary. At that stage, it was not
possible for them to refuse to be a Member of the Committee and/ or not to
50
render any opinion at all when they were asked to perform their duties.
They were required to do the same and, thus, there cannot be any doubt
whatsoever that each one of the respondent Nos. 1 to 7 was performing his
official duties.
63. For the purpose of attracting the provisions of Section 197 of the Code
of Criminal Procedure, it is not necessary that they must act in their official
capacity but even where a public servant purports to act in their official
capacity, the same would attract the provisions of Section 197 of the Code of
Criminal Procedure. It was so held by this Court in Sankaran Moitra v.
Sadhna Das and Another [(2006) 4 SCC 584].
The question came up for consideration before this Court in Matajog
Dobey v. H.C. Bhari [AIR 1956 SC 44 : 1955 (2) SCR 925] wherein it was
held:
“17. Slightly differing tests have been laid down in
the decided cases to ascertain the scope and the
meaning of the relevant words occurring in Section
197 of the Code; “any offence alleged to have been
committed by him while acting or purporting to act
in the discharge of his official duty”. But the
difference is only in language and not in substance.
The offence alleged to have been committed must
51
have something to do, or must be related in some
manner with the discharge of official duty. No
question of sanction can arise under Section 197,
unless the act complained of is an offence; the only
point to determine is whether it was committed in
the discharge of official duty. There must be a
reasonable connection between the act and the
official duty. It does not matter even if the act
exceeds what is strictly necessary for the discharge
of the duty, as this question will arise only at a
later stage when the trial proceeds on the merits.
What we must find out is whether the act and the
official duty are so inter-related that one can
postulate reasonably that it was done by the
accused in the performance of the official duty,
though possibly in excess of the needs and
requirements of the situation. In Hori Barn Singh
v. Crown Sulaiman, J. observes:
“The section cannot be confined to only such acts
as are done by a public servant directly in
pursuance of his public office, though in excess of
the duty or under a mistaken belief as to the
existence of such duty. Nor is it necessary to go to
the length of saying that the act constituting the
offence should be so inseparably connected with
the official duty as to form part and parcel of the
same transaction.”
The interpretation that found favour with
Varadachariar, J. in the same case is stated by him
in these terms at p. 187: “There must be something
in the nature of the act complained of that attaches
it to the official character of the person doing it.”
In affirming this view, the Judicial Committee of
the Privy Council observe in Gill case: “A public
servant can only be said to act or purport to act in
the discharge of his official duty, if his act is such
as to lie within the scope of his official duty …
The test may well be whether the public servant, if
challenged, can reasonably claim that, what he
52
does, he does in virtue of his office.” Hori Ram
case is referred to with approval in the later case of
Lieutenant Hector Thomas Huntley v. King-
Emperor but the test laid down that it must be
established that the act complained of was an
official act appears to us unduly to narrow down
the scope of the protection afforded by Section 197
of the Criminal Procedure Code as defined and
understood in the earlier case. The decision in
Meads v. King does not carry us any further; it
adopts the reasoning in Gill’s case.”
The said principle has been reiterated by this Court in B. Saha v. M.S.
Kochar [(1979) 4 SCC 177] in the following terms:
“17. The words “any offence alleged to have been
committed by him while acting or purporting to act
in the discharge of his official duty” employed in
Section 197(1) of the Code, are capable of a
narrow as well as a wide interpretation. If these
words are construed too narrowly, the section will
be rendered altogether sterile, for, “it is no part of
an official duty to commit an offence, and never
can be”. In the wider sense, these words will take
under their umbrella every act constituting an
offence, committed in the course of the same
transaction in which the official duty is performed
or purports to be performed. The right approach to
the import of these words lies between these two
extremes. While on the one hand, it is not every
offence committed by a public servant while
engaged in the performance of his official duty,
which is entitled to the protection of Section
197(1), an act constituting an offence, directly and
reasonably connected with his official duty will
53
require sanction for prosecution under the said
provision. As pointed out by Ramaswami, J., in
Baijnath v. State of M.P., “it is the quality of the
act that is important, and if it falls within the scope
and range of his official duties, the protection
contemplated by Section 197 of the Criminal
Procedure Code will be attracted”.
18. In sum, the sine qua non for the applicability of
this section is that the offence charged, be it one of
commission or omission, must be one which has
been committed by the public servant either in his
official capacity or under colour of the office held
by him.”
[See also R. Balakrishna Pillai v. State of Kerala and Another [(1996)
1 SCC 478]
In Rakesh Kumar Mishra v. State of Bihar and Others [(2006) 1 SCC
557], this Court held:
“12. It has been widened further by extending
protection to even those acts or omissions which
are done in purported exercise of official duty; that
is under the colour of office. Official duty,
therefore, implies that the act or omission must
have been done by the public servant in the course
of his service and such act or omission must have
been performed as part of duty which further must
have been official in nature. The section has, thus,
to be construed strictly, while determining its
applicability to any act or omission in the course of
service. Its operation has to be limited to those
duties which are discharged in the course of duty.
But once any act or omission has been found to
54
have been committed by a public servant in the
discharge of his duty then it must be given liberal
and wide construction so far its official nature is
concerned. For instance a public servant is not
entitled to indulge in criminal activities. To that
extent the section has to be construed narrowly and
in a restricted manner. But once it is established
that an act or omission was done by the public
servant while discharging his duty then the scope
of its being official should be construed so as to
advance the objective of the section in favour of
the public servant. Otherwise the entire purpose of
affording protection to a public servant without
sanction shall stand frustrated. For instance a
police officer in the discharge of duty may have to
use force which may be an offence for the
prosecution of which the sanction may be
necessary. But if the same officer commits an act
in the course of service but not in the discharge of
his duty and without any justification therefor then
the bar under Section 197 of the Code is not
attracted…”
64. Reliance has been placed by Mr. Tulsi on Parkash Singh Badal v.
State of Punjab and Others [(2007) 1 SCC 1] wherein this Court held:
“38. The question relating to the need of sanction
under Section 197 of the Code is not necessarily to
be considered as soon as the complaint is lodged
and on the allegations contained therein. This
question may arise at any stage of the proceeding.
The question whether sanction is necessary or not
may have to be determined from stage to stage.”
55
In that case, the appellant therein was charged for commission of an
offence of cheating under Section 420 and Sections 467, 468, 471 and 120B
of the Indian Penal Code.
In the factual matrix involved therein, it was held:
“29. The effect of sub-sections (3) and (4) of
Section 19 of the Act are of considerable
significance. In sub-section (3) the stress is on
“failure of justice” and that too “in the opinion of
the court”. In sub-section (4), the stress is on
raising the plea at the appropriate time.
Significantly, the “failure of justice” is relatable to
error, omission or irregularity in the sanction.
Therefore, mere error, omission or irregularity in
sanction is (sic not) considered fatal unless it has
resulted in failure of justice or has been occasioned
thereby. Section 19(1) is a matter of procedure and
does not go to the root of jurisdiction as observed
in para 95 of Narasimha Rao case. Sub-section
(3)(c) of Section 19 reduces the rigour of
prohibition. In Section 6(2) of the old Act [Section
19(2) of the Act] question relates to doubt about
authority to grant sanction and not whether
sanction is necessary.”
65. In State of Karantaka v. Ameerjan [(2007) 11 SCC 273], it was held
that an order of sanction is required to be passed on due application of mind.
56
66. Thus, in this case, sanction for prosecution in terms of Section 197 of
the Code of Criminal Procedure was required to be obtained.
67. For the reasons aforementioned, there is no merit in this appeal which
is dismissed accordingly.
………………………….J.
[S.B. Sinha]
..…………………………J.
[Cyriac Joseph]
New Delhi;
August 04, 2009