Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 10
CASE NO.:
Appeal (civil) 2801 of 2006
PETITIONER:
State Bank of India & Anr.
RESPONDENT:
Mula Sahakari Sakhar Karkhana Ltd.
DATE OF JUDGMENT: 06/07/2006
BENCH:
S.B. Sinha & P.K. Balasubramanyan
JUDGMENT:
J U D G M E N T
S.B. SINHA, J.
(Arising out of SLP (C) No. 22576 of 2005)
Leave granted.
BACKGROUND FACTS
The Respondent is a cooperative society. It has a sugar factory. It
entered into a contract for installation of a paper plant at village Sonai on
turnkey basis so as to enable it to utilize the left over material called
"bagasse" of the sugarcane with M/s. Pentagon Engineering Pvt. Ltd. (for
short "Pentagaon"). The total value of the contract was Rs. 3,40,00,000/-.
Pentagon furnished a performance guarantee in regard to the machinery
supplied by it. The said contract contained a clause for retention of 10% of
the contract price by the cooperative society in the following terms:
"15.2.4 5% of the contract price shall be
payable after satisfactory commissioning and
working of the plant for three months that is three
months from the achievement of the performance
guarantee as stipulated in clause no. 8 and 9 above,
by a separate letter of credit.
15.2.5 5% of the contract price shall be paid
after six months after satisfactory commissioning
of the plant and continuous successful working of
the plant during the period i.e. six months working
of the plant as per clause 8 and 9 above, by a
separate letter of credit."
Pentagon, however, by a letter dated 6th April, 1985 suggested for a
modification as regards the said payment clause regulating the cooperative
society to waive its rights to retain the said 10% of the contract price, and in
its turn proposed to have a letter of credit so that they can furnish
appropriate bank guarantee; to which the cooperative society accepted
stating:
"You have also to submit the performance
guarantee at 10% of the contract price, if the same
guarantee is not received the karkhana is entitled to
recover it from the balance payment and
accordingly we have deducted it for want of
performance guarantee."
Pentagon in response thereto by its letter dated 16th April, 1985 agreed
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 10
to the said proposal stating:
"\005As per agreement you have to open separate
L/C for 10% retention which is still not done by
you. As soon as you open L/C, we will give you
Bank Guarantee for the retention money within 10
to 15 days thereafter."
The Bank Guarantee/Indemnity was thereafter furnished by the
Appellant herein on or about 7th September, 1985; the relevant clauses
whereof read as under:
"Please find enclosed herewith the bank guarantee
bearing No. 85/17 dated 4th September, 1985
issued by State Bank of India, Dombivli Industrial
Estate Branch, Dombivli.
The guarantee is issued in pursuance of our
agreement for paper project dated 25.9.1983. The
guarantee covers 10% retention amount of Rs. 34
lacs.
An amount of Rs. 13,76,285/- is retained
from the Proforma Invoices of the material reached
at site.
Kindly release the amount of Rs.
13,76,285/- to be retained by you immediately on
receipt of this guarantee and oblige."
THE DISPUTE
Disputes and differences arose by and between the cooperative society
and Pentagon. The contract of Pentagon was terminated by the cooperative
society by a notice dated 17th July, 1987. A claim of Rs.3,23,28,209.10 was
also raised. Pentagon not only denied and disputed its liability to pay the
said sum but also, on the other hand, asserted that an amount of
Rs.4,66,73,300/- was due and owing to it by a letter dated 18th July, 1987.
The Bank Guarantee was thereafter invoked by the cooperative
society. The demand of the cooperative society invoking the said Bank
Guarantee met resistance from the Appellant stating that it had executed an
agreement of indemnity pursuant whereto or in terms whereof only losses,
claims, damages, actions and costs which might have been suffered by it,
were covered and the transaction in question does not constitute Bank
Guarantee. It was, therefore, contended that unless the cooperative society
proved any loss or damage for design, performance, workmanship or supply
of any defective material through a competent court or authority, the
Appellants were not liable to pay the said amount.
PROCEEDINGS
Cooperative society thereafter filed a suit in the Court of Civil Judge,
Senior Division, Ahmednagar which was numbered as Special Civil Suit No.
310 of 1987. An application was filed by the cooperative society in the said
suit for a direction upon the Appellant to deposit the amount of
Rs.34,00,000/-.
ORDER OF THE COURT
The matter relating to passing of an interim order went upto the High
Court. The High Court by an order dated 23rd February, 1988 directed that
the said amount be retained by the Appellant subject to the condition that in
the event, the suit is decreed the said amount would be paid with interest @
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 10
12% per annum. The suit was dismissed. An appeal was preferred
thereagainst by the cooperative society before the High Court. The High
Court construing the said agreement dated 25.9.1983 to be a Bank Guarantee
decreed the suit directing Appellant to pay the said sum of Rs.34,00,000/-
with interest @ 14% per annum.
The Appellant is, thus, before us.
SUBMISSIONS
Mr. G.E. Vahanvati, learned Solicitor General appearing on behalf of
the Appellants submitted that:
(i) On a true construction of the document dated 4th September, 1985,
it would be seen that the same is a contract of indemnity and not a
Bank Guarantee.
(ii) The High Court committed a manifest error in considering the oral
evidence adduced by the parties in construing the said document
dated 4th September, 1985.
(iii) Interest awarded @ 14% per annum is contrary to and inconsistent
with the directions of the High Court as contained in its order dated
23rd February, 1988.
Mr. Naphade, learned Senior Counsel appearing on behalf of the
cooperative society, on the other hand, submitted that:
(i) the substance of the matter must be considered in the backdrop of
events in which the Bank Guarantee was furnished by the
Appellant and for that purpose surrounding circumstances were
relevant. As the terms of contract need not necessarily be gathered
from one document, the relevant circumstances could also be
considered, they being:-
(a) The document in question is by way of a letter. It refers to
the original agreement dated 29.5.1983 in terms whereof
the cooperative society agreed to purchase from Pentagon
the paper plant on turnkey basis. The said agreement
stipulates that final payment should be made to the supplier
on his furnishing a Bank Guarantee to the cooperative
society for design, performance, workmanship or against
defective materials or equipment supplied.
(b) Pantagon was a client of the Appellant and it had
approached it for furnishing the Bank Guarantee.
Strong reliance in this behalf has been placed on S. Chattanatha
Karayalar v. The Central Bank of India and Others [1965 (3) SCR 318] and
P.L. Bapuswami v. N. Pattay Gounder [1966 (2) SCR 918].
BANK GUARANTEE
The Operative portion of the Bank Guarantee dated 7th September,
1985 reads, thus:
"NOW THEREFORE THIS BANK
GUARANTEE is made in favour of Mula Sahakari
Sakhar Karkhana Ltd. by State Bank of India
(Dombivli Industrial Estate Branch) agreed
security the State Bank of India (Dombivli
Industrial Estate Branch) hereby agrees and
undertake subject to the terms and conditions set
forth in this agreement to indemnify and keep
indemnified Mula Sakhari Sakhar Karkhana Ltd.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 10
against all losses, claims, damages actions and cost
in respect of such sums which the supplier shall
become liable to pay as the terms of the said
order."
In addition to the aforementioned, the Appellant agreed to the other
terms and conditions referred to therein, stating :
"NOTWITHSTANDING anything hereinbefore
contained, our maximum liability under this
guarantee is restricted to Rs. 34,00,000/- (Rupees
Thirty four Lacs only). This guarantee shall
remain in force upto 3rd September 1987 unless a
suit or action to enforce claim under this guarantee
is filed against us on or before the 3rd September,
1987 all right under this guarantee shall be
forfeited and we shall be relieved and discharged
from all liabilities hereunder."
The High Court, however, despite noticing the said document in
extenso, committed a manifest error in opining:
"\005The recital in the preamble in question itself
cannot be the foundation to interpret the document
in question as a document of indemnity\005"
Although it was opined that the same was intended to be a contract of
indemnity, the High Court wrongly observed:
"\005There was no objection of any kind referred to
or placed on the record by the appellants. The
Officer of the Bank stated before the Court that the
document in question was intended to be a contract
of guarantee and not a contract of indemnity. The
written document (Exhibit-46) as quoted above
lays emphasis on the preamble as under\005"
Yet again, in the said paragraph, the operative portion of the
document was erroneously described as a preamble stating:
"\005The preamble of the document in question
creates an impression that the said document is a
contract of indemnity and not a contract of
guarantee."
The High Court, furthermore, inserted some words in the said
document which in fact were not there, as for example, in paragraph 31 of
the impugned judgment it added the term "unequivocal condition" which
term did not find place in the document in question. Similarly, in paragraph
34, it was stated:
"\005The appellants are entitled to their claimed
money without any delay or demur. The nature
and need of such commercial contracts and
documents need to be respected by the parties
concerned\005"
Yet again, it was stated:
"If the terms and conditions of the Bank Guarantee
are unconditional and absolute, the respondents
have no choice but to honour the same\005"
(Emphasis added)
No such terms were used in the said document. The approach of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 10
High Court on construction of the said document was, thus, patently wrong.
The High Court committed a manifest error in terming the operative
portion of the document as a preamble. It had inserted terms and
expressions which did not find place in the document in question.
The High Court furthermore considered the oral evidence adduced by
the parties despite the bar contained in Sections 91 and 92 of the Indian
Evidence Act holding:
(i) "\005The testimony of these witnesses, in no
way, derogates the document in question.
On the contrary, the evidence supports the
purpose and object of the execution of the
Bank Guarantee in question. It also supports
that the parties, specially the appellants are
the creditors-beneficiaries, the respondents \026
Bank are the guarantors \026 the surety and the
supplier is M/s Pentagon \026 the principal
debtor. As we have noted and as
contemplated under Section 124 of the
Contract Act, such Bank Guarantee should
have three ingredients, i.e., creditor,
guarantor and principal debtor. On a bare
reading of this document, it is nothing but a
tripartite agreement between the parties.
M/s. Pentagon submitted the said Bank
Guarantee by its letter dated 7th September,
1985 to the appellants. The appellants, as
noted above, without any demur or
objection, accepted this document as a Bank
Guarantee and based upon the same, the
amount was released. There is no evidence
to support that in absence of this bank
guarantee, the amount would not have been
released by the appellants."
(ii) "\005Therefore, according to us, the express
terms of the written agreement in question,
supported by the testimony of the
respondent \026 Bank’s Officer itself, apart
from the appellants, some statements in the
cross-examination or raising doubts about
the nature of the agreement by one of the
Bank witness, that itself would not affect the
written agreement in question\005"
(iii) "\005In this background, we cannot overlook
the circumstances under which the particular
words were used and/ or misused\005"
A document, as is well known, must primarily be construed on the
basis of the terms and conditions contained therein. It is also trite that while
construing a document the court shall not supply any words which the author
thereof did not use.
The document in question is a commercial document. It does not on
its face contain any ambiguity. The High Court itself said that ex facie the
document appears to be a contract of indemnity. Surrounding circumstances
are relevant for construction of a document only if any ambiguity exists
therein and not otherwise.
The said document, in our opinion, constitutes a document of
indemnity and not a document of guarantee as is clear from the fact that by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 10
reason thereof the Appellant was to indemnify the cooperative society
against all losses, claims, damages, actions and costs which may be suffered
by it. The document does not contain the usual words found in a bank
guarantee furnished by a Bank as, for example, "unequivocal condition",
"the cooperative society would be entitled to claim the damages without any
delay or demur" or the guarantee was "unconditional and absolute" as was
held by the High Court.
The High Court, thus, misread and misinterpreted the document as on
scrutiny thereof, it had opined that it was a contract of guarantee and not a
contract of indemnity.
The document was executed by the Bank in favour of the cooperative
society. The said document indisputably was executed at the instance of
Pentagon.
We have hereinbefore noticed the surrounding circumstances as
pointed out by Mr. Naphade as contained in Clauses 15.2.4 and 15.2.5 of the
contract vis-‘-vis the letters exchanged between the parties dated 6.4.1985,
11.4.1985, 16.4.1985 leading to execution of the document dated 07.09.1985
by the First Appellant in favour of the cooperative society.
We are, however, unable to accept the submissions of the learned
Senior Counsel that the bank guarantee must be construed in the light of
other purported contemporaneous documents. A contract indisputably may
be contained in more than one document. Such a document, however, must
be a subject matter of contract by and between the parties. The
correspondences referred to hereinbefore were between the cooperative
society and Pentagon. The said correspondences were not exchanged
between the parties hereto as a part of the same transaction. The Appellant
understood that it would stand as a surety and not as a guarantor.
The decision of this Court in S. Chattanatha Karayalar (supra) on
which reliance was placed by Mr. Naphade is not applicable to the fact of
the present case. Therein, the construction of a promissory note executed in
favour of a Bank was in question. The said promissory note was construed
in the context of the letters and the hypothecation agreement executed by the
borrower on the basis whereof it was held that the status of the Appellant
therein with regard to the overdraft amount was that of a surety and not that
of a co-applicant. In the said decision itself, Ramaswami, J. opined:
"\005The provisions of Section 92 of the Evidence
Act do not apply in the present case, because
Defendant 3 is not attempting to furnish evidence
of any oral agreement in derogation of the
promissory note but relying on the existence of a
collateral agreement in writing \027 Exs. A & G
which form parts of the same transaction as the
promissory note \027 Ex. B\005"
The High Court proceeded on the basis that Section 92 of the
Evidence Act would be attracted in the instant case but despite the same it
referred to the oral evidence so as to find out the purported circumstances
surrounding the transaction, which in our view, was not correct.
In P.L. Bapuswami (supra), relied upon by Mr. Naphade, this Court
was concerned with a question as to whether Ex. B-1 therein was a
transaction of mortgage by conditional sale or a sale with a condition of re-
transfer in the light of Section 58(c) of the Transfer of Property Act. We are
not concerned with such a case here.
It is one thing to say that the nature of a transaction would be judged
by the terms and conditions together with the surrounding and/or attending
circumstances in a case where the document suffers from some ambiguities
but it is another thing to say that the court will take recourse to such a
course, although no such ambiguity exists.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 10
[See Bishwanath Prasad Singh v. Rajendra Prasad and Anr. [(2006)
2 SCALE 699]
It is beyond any cavil that a bank guarantee must be construed on its
own terms. It is considered to be a separate transaction.
If a construction, as was suggested by Mr. Naphade, is to be accepted,
it would also be open to a banker to put forward a case that absolute and
unequivocal bank guarantee should be read as a conditional one having
regard to circumstances attending thereto. It is, to our mind, impermissible
in law.
In New India Assurance Company Ltd. v. Kusumanchi Kameshwara
Rao and Another [(1997) 9 SCC 179], it is stated:
"\005It is obvious that when such guarantee bonds
are reduced to writing the express terms of this
writing containing the guarantee bond would be
the repository of the obligations of the guarantor
flowing from the surety bond. As per Sections 91
and 92 of the Indian Evidence Act, 1872 no
evidence dehors the terms of the agreement,
whether documentary or oral, can be led by the
parties to get out of the express terms thereof.
Whether the express terms of the guarantee bond
give rise to the contract of guarantee sought to be
enforced will be the only limited enquiry which
could be gone into by the courts while deciding the
rights and obligations flowing from such contract
of guarantee which is a tripartite contract between
the creditor, principal debtor and the surety. Once
such suretyship agreement is established on the
clear terms of the bond then as laid down by the
aforesaid decisions of this Court no latitude can be
given to the contracting party, namely, the surety
or even the principal debtor to enable them to get
out of the obligations of the suretyship agreement
flowing from such contract, except in exceptional
circumstances as indicated in these decisions."
In Hindustan Construction Co. Ltd. v. State of Bihar and Others
[(1999) 8 SCC 436], the guarantee in question was in the following terms:
"\005We, State Bank of India, incorporated under
the State Bank of India Act, 1955, and having one
of our branches at Nyayamurti C.N. Vaidya Marg,
Fort, Bombay-400 023 (hereinafter referred to as
’the said Bank’), as instructed by the contractor,
agree unconditionally and irrevocably to guarantee
as primary obligator and not as surety merely, the
payment of the Executive Engineer, Kharkai Dam
Division II, Icha, Chaliama, Post Kesargarhia,
District Singhbhum, Bihar, on his first demand
without whatsoever right of objection on our part
and without his first claim to the contractor, in the
amount not exceeding Rs.10,00,000 (Rupees ten
lakhs only) in the event that the obligations
expressed in the said clause of the above-
mentioned contract have not been fulfilled by the
contractor giving the right of claim to the employer
for recovery of the whole or part of the advance
mobilisation loan from the contractor under the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 10
contract\005"
Despite such conditions, holding that the guarantee in question was a
performance guarantee, this Court opined:
"The Bank, in the above guarantee, no doubt,
has used the expression "agree unconditionally and
irrevocably" to guarantee payment to the
Executive Engineer on his first demand without
any right of objection, but these expressions are
immediately qualified by following:
"... in the event that the obligations
expressed in the said clause of the above-
mentioned contract have not been
fulfilled by the contractor giving the right
of claim to the employer for recovery of
the whole or part of the advance
mobilisation loan from the contractor
under the contract."
This condition clearly refers to the original
contract between HCCL and the defendants and
postulates that if the obligations, expressed in the
contract, are not fulfilled by HCCL giving to the
defendants the right to claim recovery of the whole
or part of the "advance mobilisation loan", then the
Bank would pay the amount due under the
guarantee to the Executive Engineer. By referring
specifically to clause 9, the Bank has qualified its
liability to pay the amount covered by the
guarantee relating to "advance mobilisation loan"
to the Executive Engineer only if the obligations
under the contract were not fulfilled by HCCL or
HCCL has misappropriated any portion of the
"advance mobilisation loan". It is in these
circumstances that the aforesaid clause would
operate and the whole of the amount covered by
the "mobilisation advance" would become payable
on demand. The bank guarantee thus could be
invoked only in the circumstances referred to in
clause 9 whereunder the amount would become
payable only if the obligations are not fulfilled or
there is misappropriation. That being so, the bank
guarantee could not be said to be unconditional or
unequivocal in terms so that the defendants could
be said to have had an unfettered right to invoke
that guarantee and demand immediate payment
thereof from the Bank."
It was clearly held therein that the bank guarantee constitutes a
separate, distinct and independent contract between the bank and the
defendants.
In this case, the document in question does not specifically refer to
any particular clause of the contract. In fact the contract does not contain
any clause requiring Pentagon to furnish any Bank Guarantee.
We may now consider the decision in Daewoo Motors India Ltd. v.
Union of India and Others [(2003) 4 SCC 690]. The bank guarantee
involved therein inter alia read as under:
"We, Times Bank Ltd., PTI Building, Parliament
Street, New Delhi, 110 001 further agree that the
demand made by the President of India any money
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 10
so demanded notwithstanding any dispute raised
by M/s Daewoo Motors India Ltd. in any
proceeding before any court or tribunal;
We, Times Bank Ltd., PTI Building, Parliament
Street, New Delhi 110 001 further agree that the
demand made by the President of India shall be
conclusive as regards the amount due and payable
by us under these presents as out of liability under
these presents are absolute and unequivocal;"
Construing the terms thereof, this Court held:
"From a perusal of the above clauses, it is
abundantly clear that the bank guarantee furnished
by the Bank is an unconditional and absolute bank
guarantee. The Bank has rendered itself liable to
pay the cash on demand by the President of India
"notwithstanding any dispute raised by M/s
Daewoo Motors India Limited in any proceeding
before any court or tribunal". It is worth noticing
that the clause in the bank guarantee specifically
provides that the demand made by the President of
India shall be conclusive as regards the amount
due and payable by the Bank under this guarantee
and the liability under the guarantee is absolute
and unequivocal. In the face of the clear
averments, it is trite to contend that the bank
guarantee is a conditional bank guarantee.
Therefore, the Bank has no case to resist the
encashment of the bank guarantee. Inasmuch as we
have held that the bank guarantee is an
unconditional bank guarantee, the case of
Hindustan Construction Co. Ltd. v. State of Bihar
is of no avail to the appellant."
The said decision, in the facts and circumstances of the case, cannot
be said to have any application here.
We are not oblivious of the decisions of this Court where, save and
except the cases of fraud or irretrievable evil, the Bank has been held liable
to pay the guaranteed amount without any demur whatsoever. In an
instructive judgment, M. Jagannadha Rao, J. in Federal Bank Ltd. v. V.M.
Jog Engineering Ltd. and Others [(2001) 1 SCC 663] referring to Uniform
Commercial Practice of Documentary Credits and a catena of decisions of
this Court as also the English Courts, dealt with a case where a fraud was
alleged and observed:
"Thus, not only must "fraud" be clearly proved but
so far as the bank is concerned, it must prove that
it had knowledge of the fraud. In United Trading
Corpn. S.A. v. Allied Arab Bank it was stated that
there must be proof of knowledge of fraud on the
part of the bank at any time before payment. It was
also observed that it
"would be sufficient if the corroborated evidence
of the plaintiff usually in the form of contemporary
documents and the unexplained failure of a
beneficiary to respond to the attack, lead to the
conclusion that the only realistic inference to draw
was ’fraud’."
[See also Dwarikesh Sugar Industries Ltd. v. Prem Heavy Engineering
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 10
Works (P) Ltd. and Another, (1997) 6 SCC 450] and M/s. BSES Ltd. (Now
Reliance Energy Ltd.) v. M/s. Fenner India Ltd. & Anr. JT 2006 (2) SC 192]
However, in this case, we have no doubt in our mind that the
document in question constitutes a contract of indemnity and not an absolute
or unconditional bank guarantee. The High Court, therefore, erred in
construing the same to be an unconditional and absolute bank guarantee.
RATE OF INTEREST
Contention of Mr. Vahanvati as regards the rate of interest is also
incontrovertible. The order dated 23rd February, 1988 clearly states that the
amount would be repaid with an interest @ 12% and in that view of the
matter, the High Court could not have directed payment of interest @ 14%.
For the reasons aforementioned, the impugned judgment cannot be
sustained which is set aside accordingly. The decree of the trial court is
restored. The appeal is allowed with costs. Counsel’s fee assessed at Rs.
5000/-.