Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 4
PETITIONER:
NEELAKANTAN & BROS. CONSTRUCTION
Vs.
RESPONDENT:
SUPERINTENDING ENGINEER, NATIONAL HIGHWAYS,SALEM & ORS.
DATE OF JUDGMENT16/08/1988
BENCH:
MUKHARJI, SABYASACHI (J)
BENCH:
MUKHARJI, SABYASACHI (J)
RANGNATHAN, S.
CITATION:
1988 AIR 2045 1988 SCR Supl. (2) 462
1988 SCC (4) 462 JT 1988 (3) 743
1988 SCALE (2)586
ACT:
Arbitration Act, 1940: Sections 2, 20, 30 and 33-
Arbitration- Statements of parties filed-Evidence adduced-
Change of Arbitrator -Parties did not protest and
participate in proceedings before successor-Whether amounts
to acquiescence-Appointment of successor-Whether can be
challenged as invalidating proceedings_Award-Unreasoned-No
legal proposition made-Whether can be interfered with.
HEADNOTE:
The petitioner-Construction firm entered into agreements
with respondent No. 3, Superintending Engineer of a Circle
for execution of certain civil works. Respondent No. 1-
Superintending Engineer of another Circle entered into a
reference for arbitration and parties filed statements and
adduced evidence. Before the adjudication was completed,
respondent No. 1 was transferred and his successor-in-office
entered into the task of adjudication with the knowledge,
consent and active participation of the petitioner in the
proceeding. Since the arbitrator could not complete the
award within time, be sought extension of time by a letter
to the petitioner and the petitioner agreed to such
extension by a letter. The petitioner did not ask for any
further or fresh opportunity for adducing any evidence.
Thereafter, the arbitrator made his award.
The petitioner challenged the award under ss. 30 and 33
of the Arbitration Act, 1940 before the District Judge on
the ground that the previous arbitrator having entered into
reference, his successor-in-office had no jurisdiction to
conclude it and the award was violative of principles of
natural justice.
The District Judge held that the successor-in-office to
the original arbitrator was competent to pass the award.
Upholding this, the High Court rejected the challenge to the
award. Hence the petitioner filed the Special Leave Petition
in this Court contending that once an arbitrator had entered
into a reference, the next incumbent could not conclude the
said arbitration proceedings without a fresh agreement, that
there was violation of principles of natural justice and
PG NO 462
PG NO 463
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 4
that the award was bad.
Dismissing the Special Leave Petition,
HELD: 1. If the parties to the reference either agree
before,hand to the method of appointment, or afterwards
acquiesce in the appointment made, with full knowledge of
all the circumstances, they will be precluded from objecting
to such. appointment as invalidating subsequent proceedings.
Attending and taking part in the proceedings with full
knowledge of the relevant fact will amount to such
acquiescence [465G ]
N. Challappan v. Secretary, Kerala State Electricity
Board and another, [1975] 1 S.C.C. 289 relied on.
Chowdhury Murtaza Hossein v. Mussumat Bibi Bechunnissa,
3 I.A. 209 and Prasun Roy v. The Calcutta Metropolitan
Development Authority and another, [1982] 2 Scale 125,
referred to.
Russell on Arbitration, 18th Edition/20th Edition, pages
105/432-435, referred to.
In the instant case, the petitioner had full knowledge
of the change of the incumbent and did not protest and
proceedings went on before the new incumbent. Thus, the
petitioner had knowledge of the alleged defect and had
acquiesced in the proceedings before the successor. There
was, therefore, no violation of principles of natural
justice. [465C, F]
2. Unless there was a patent mistake of law and gross
misstatement of facts resulting in miscarriage of justice or
of equity, the award remains unassailable. [466C]
Champsey Bhara & Company v. Jivraj Ballo Spinning and
Weaving Company Ltd., 50 I.A. 324 and Firm Madanlal
Roshanlal Mahajan v. Hukumchand Mills Ltd., lndore, [1967j 1
S.C.R. 105, referred to.
In the instant case, the arbitrator gave no reason for
the award. There is no legal proposition which is the basis
of the award, far less any legal proposition which is
erroneous. There is no appeal from the verdict of the
arbitrator. The Court cannot review, in such
circumstances,the award and correct any mistake in the
adjudication by the arbitrator. [466D]
PG NO 464
3. In the facts and circumstances of the case, the award
is unassailable. The High Court was right in upholding the
District Judge’s dismissal of the challenge to the award.
[466F]
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Special Leave Petition
[Civil) Nos. 1 l(i50-58 of 1987.
From the Judgment and Order dated 3 1.7. 1987 of the
Madras High Court in Appeal against Order Nos. 54 1 to 544
and 558 to 562 of 1981.
A.K. Sen, V. Krishnamurthy and V. Balachandran for the
Petitioner.
A. V. Rangam for the Respondents.
The Judgment of the Court was delivered by
SABYASACHI MUKHARJI, J. These are petitions under
Article 136 of the Constitution seeking leave to appeal
against the judgment and order of the High Court of Madras
dated 31st July, 1987. The petitioner company undertook the
work of widening and strengthening pavements in Nation
Highway No. 7, Madurai-Kanya-kumari Road from Reaches 37.6
k.m. to ’1’, k.m. on the Madurai-Kanyakumari Road and the
work was divided into fourteen Reaches and 14 separate
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 4
agreements were entered into between the petitioner and the
Superintending Engineer, National Highways, Tirunelveli.
respondent No. 3 to the present petitions. There is not much
dispute on this point. At the relevant time, according to,
the petitioner, the Superintending Engineer. National
Highways, Salem was one Thiru Mohan. He entered into
reference. He took up the matter for arbitration and called
for statements from the parties. Statements were filed
before him and evidence were also adduced before him. But
before he could complete the adjudication he was transferred
and was succeeded by one Thiru J.R. Cornelius,
Superintending Engineer. The contention of the petitioner in
this case was that he had no Jurisdiction to, proceed and
complete the arbitration. It appears however, that he
entered into the task of adjudication with the knowledge and
consent of the petitioner and the petitioner had
participated actively in the proceeding before him. From the
notices served by Thiru Mohan previously and subsequently by
Thiru Cornelius. it is apparent that the petitioner had
knowledge of the change of the incumbent of the
Superintending Engineer who was to arbitrate in the matter.
This is evident from the documents appearing at pages 164
PG NO 465
and 165 of the present paper book and both the parties had
notice of the succession in office. The arbitrator could not
complete the award within time and there was need for
extension of time. He wrote a letter to the petitioner on
lst May 1977 stating "extension of time was necessary to
pass orders on reference and hearing has been concluded". In
reply to that fetter on 11th May, 1977 the petitioner agreed
to such extension. The petitioner was content with that
situation and never asked for any further or fresh
opportunity either to make any submission or to adduce any
evidence. In that light the arbitrator has made the award.
This was challenged before the learned District Judge by
means of a suit under sections 30 and 33 of the Arbitration
Act, 1940 that the previous arbitrator Thiru Mohan having
entered into reference and Thiru Cornelius had-no
jurisdiction to conclude. It was violative of the principles
of natural justice, it was submitted. But as mentioned
hereinbefore, the petitioner had knowledge of the change of
the incumbent. He did not protest and the proceedings went
on before Thiru Cornelius. It is apparent from the terms of
the agreement between the parties that the Superintending
Engineer of the Circle for the time being was the named
arbitrator. The learned District Judge held that Thiru
Cornelius was competent to pass the award. The High Court
also upheld that and rejected the challenge to the award on
this ground made by the petitioner.
Shri A.K. Sen, learned counsel for the petitioners,
urged before us that once an arbitrator had entered into
reference, the next incumbent could not conclude the said
arbitration proceeding without a fresh agreement. In the
facts of this case, as the petitioner had knowledge of the
alleged defect and had acquiesced in the proceedings before
the successor, namely, Thiru Cornelius; we are of the
c,pinion, that this contention of Shri Sen cannot be
entertained. It was contended that there was violation of
the principles of natural justice. This objection cannot be
entertained. If the parties to the reference either agree
beforehand to the method of appointment, or afterwards
acquiescence in the appointment made with full knowledge of
all the circumstances. they will be precluded from
objection˜ to such appointment as invalidating subsequent
proceedings. Attending and taking part in the proceedings
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 4
with full knowledge of the relevant fact will amount to such
acquiescence, explains Russell on Arbitration. 18th Edition
at page 105. This was stated by the Judicial Committee long
ago in Chowdhury Murtaza Hossein v. Mussumat Bibi
Bechunnissa, 3 I.A. 209. See also the observations of P.B.
Mukherji, J. in the decision of the Calcutta High Court
PG NO 466
Calcutta, A.I.R. 1456 Calcutta 470 at 472. This Court held
in N. Challappan v. Secretary, Kerala State Electricity
Board and another, [1975] 1 S.C.C. 289 that acquiescence
defeated the right of the appellant at a latter stage. See
also the observations of this Court in Prasun Roy v. The
Calcutta Metropolitan Development Authority and another,
[1982] 2 Scale 125. See Russell on Arbitration, 20th
Edition, pages 432-435. Shri Sen contended that no notice
was issued after the appointment of the new arbitrator. This
was factually incorrect, as mentioned before. Then, it was
said that the award was bad as it did not consider all the
claims. This also cannot be entertained. It must be assumed
that the arbitrator had considered all the evidence adduced
before him. There was no disregard of any principle of law.
There was nothing to indicate that the arbitrator had not
considered all the evidence. Unless there was a patent
mistake of law and gross misstatement of facts resulting in
miscarriage of justice or of equity, the award remains
unassailable. In this case the arbitrator gave no reason for
the award. There is no legal proposition which is the basis
of the award, far less any legal proposition which is
erroneous. There is no appeal from the verdict of the
arbitrator. The Court cannot review, in such circumstances,
the award and correct any mistake in the adjudication by the
arbitrator-See Champsey Bhara B Company v. Jivray Ballo
Spinning and Weaving Company Ltd., 50 I.A. 324 and the
observations of Bachawat, J. in Firm Madanlal Roshanlal
Mahajan v. Hukumchand Mills Ltd., Indore, [ l967] 1 S. C. R.
105 of this Court.
In the facts and circumstances of the case, in our
opinion, this award is not assailable. The High Court was,
therefore, right in upholding the learned District judge’s
dismissal of the challenge to the award. These petitions,
therefore, fail and are dismissed accordingly ,without any
order as to costs.
N.P.V. Petitions dismissed.