Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
CASE NO.:
Appeal (civil) 4841 of 2007
PETITIONER:
M/s. Paras Ship Breakers Ltd
RESPONDENT:
Commissioner of Central Excise
DATE OF JUDGMENT: 12/10/2007
BENCH:
S.B. Sinha & Harjit Singh Bedi
JUDGMENT:
J U D G M E N T
[Arising out of SLP (Civil) No. 10073 of 2005]
S.B. SINHA, J :
1. Leave granted.
2. This appeal is directed against a judgment and order dated 11.02.2005
passed by a Division Bench of the Gujarat High Court in Tax Appeal No.
427 of 2004 whereby and whereunder the appeal preferred by the appellant
herein from a judgment and order of the Customs, Excise and Gold Control
Appellate Tribunal dated 22nd May, 2003 as well as Miscellaneous order
dated 6th February, 2004, was dismissed.
3. The issue involved in this appeal is as to how the deemed annual
production in terms of Section 3A of the Central Excise Act, 1944 which
was brought into force with effect from 14.05.1987 should be determined.
Appellant herein installed an induction furnace, the capacity whereof was 8
M.Ts. It had asked the Gujarat State Electricity Board (Board) for supply of
3000 KVA of electrical energy. The Board agreed to supply only 1900
KVA input of power. The said furnace was manufactured by Inductotherm
(India) Ltd. Keeping in view the fact that the appellant could not obtain
supply the requisite quantity of electrical energy, it thought of reducing the
capacity of the said induction furnace. According to it, the capacity was
brought down to 4 = M.Ts from 8 M.Ts. Appellant contends that the
Department was informed thereabout. Allegedly, an inspection was carried
out and the capacity of the said induction furnace was also noticed by the
inspecting team. Despite the same, a show cause notice was issued as to
why the deemed annual production should not be determined on the basis
that the capacity of the said furnace was 8 M.Ts. A finding of fact was
arrived at by the concerned authorities that the capacity of the said furnace
was 8 M.Ts, and not 4 = M.Ts.
4. Mr. Gourab Banerjee, learned senior counsel appearing on behalf of
the appellant, would submit that the appellant had obtained a certificate from
M/s. Furcon Consultancy Services to show that the possible capacity of the
furnace was 4.5 M.Ts. for melting steel and in view of the fact that the
Board was not in a position to supply 3000 KVA at 11 KV to the Unit, the
appellant had no other option but to reduce the capacity of the said furnace.
In this connection, our attention has been drawn to the following letter dated
16.07.1997 issued by the Board:
\023In connection to your letter cited above regarding
increase in power requirement from 2400 KVA to
3000 KVA at 11 KV to your unit to Khakhariya, it
is informed you that your total power requirement
of 3000 KVA cannot be catered at 11 KV as per
feasibility received from our field office.
Please note that as per recent amendment
condition No. 28 power requirement of 2500 KVA
and above requirement to be catered at 66 KV or
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
above voltage as per condition of supply. We are
accordingly advising our E.E. (Const.) Amreli to
send feasibility report.\024
5. A certificate dated 4.09.1997 was issued by a Chartered Engineer
wherein the following observation was made:
\023c. Crucibles are converted to 4500 Kg.
capacity due to lack of power supply.\024
6. Our attention has also been drawn to a letter dated 7.04.2000 issued
by the Customs and Central Excise, Commissionerate, Rajkot addressed to
the Deputy Commissioner wherein it was stated:
\023Parameters which are crucial for the
determination capacity of production of the
Induction furnace were measured in presence of
the authorized person of the unit (Drawing of the
measurement is enclosed herewith). As shown in
the drawing the heating coils which wrapped
around the Crucible Furnace are only upto \023Metal
Level\024. Hence, only upto that level scrap can be
melted. Weighment of Iron ingots, duly
manufactured in during the visit were made. In
each batch, number of ingots manufactured on an
average taken from three batches comes to 42 nos.
per batch. And the weight of five nos. of ingots
from different batches was taken and the average
weight of one ingot came to 98 kgs. Hence,
average production on the basis of this calculation
comes to 4.1 tones per batch. Moreover, one heat
(batch) time required is about 1 hours and 30
minutes.\024
7. Despite the same, Mr. Banerjee would submit that a show cause
notice was issued purported to be only on the premise that the appellant had
not intimated any proposed change in the induction furnace to the
Commissionerate which is contrary to the fact as such an intimation had
been given to the authorities, as would appear from the show cause filed by
the appellant therein on 6.02.2001 wherein it was stated:
\023\005We have found out from our records that on the
date of carrying out modifications i.e. on
14.5.1997 we had addressed a letter dated
14.5.1997 to the Superintendent of Central Excise,
AR-Sihor, intimating that we were carrying out
changes in the capacity of our crucible through
M/s Furcon Consultancy Services. We have given
detailed reasons necessitating such modification.
A copy of the said letter dated 14.5.1997, duly
received in the office of the said Superintendent, is
enclosed for your perusal. After completion of the
changes, we again informed the said
Superintendent vide our letter dated 16.5.1997, a
receipted copy of which is also enclosed for
perusal. Even though at that time the compounded
levy was not in force, still we kept the Department
informed of the changes carried out by us. It is,
therefore, not correct to allege that the department
was not informed about the changes.\024
It was urged that the said statement having not been factually
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
disputed, what arose for consideration was the legal interpretation of the
rules.
The said contention of the appellant, however, was rejected by the
respondent on the ground that modification of the capacity of induction
furnace was irrelevant; the only relevant criterion therefor being the installed
capacity.
Mr. Banerjee would submit that such a finding on the part of the
respondent was eminently unreasonable as the said conclusion could not
have been arrived at in view of the extant rules.
8. Submission of Mr. Gopal Subramanium, learned Additional Solicitor
General appearing on behalf of the respondent, on the other hand, is that the
Tribunal having arrived at a finding of fact, no question of law arose for
consideration before the High Court.
9. Section 3A(2) of the Central Excise Act reads as under:
\023(2) Where a notification is issued under sub-
section (1), the Central Government may, by rules,
provide for determination of the annual capacity of
production, or such factor or factors relevant to the
annual capacity of production of the factory in
which such goods are produced, by the
Commissioner of Central Excise and such annual
capacity of production shall be deemed to be the
annual production of such goods by such factory:
Provided that where a factory producing notified
goods is in operation only during a part of the year,
the production thereof shall be calculated on
proportionate basis of the annual capacity of
production.\024
10. The show cause notice dated 19.06.2000 was issued to the appellant
by the respondent on the premise that the capacity of the induction furnace is
in excess of 4.5 MTs. The question as to whether in effect and substance the
appellant had reduced the capacity of the said induction furnace or not is
essentially a question of fact. The Tribunal has passed a very detailed order.
It took into consideration all the contentions raised by the appellant herein.
It is evident that on representation having been made by the appellant that
the capacity of the furnace stood reduced, a Deputy Commissioner was
deputed by the Department for the purpose of measurement and verification
of the parameters of furnace on 8.03.2000. The officers of the Department
had actually seen the melting capacity of the furnace and the average
production. They took into consideration the actual production recorded in
RG I registers. On verification of the relevant registers, it was found that the
actual production recorded was nearer to the level of 8 M.Ts. The rule no
doubt provides for determining the annual capacity in case where
manufacturer proposes to increase or decrease the capacity of the induction
furnace but before the said authorities even Shri Deepak Shah, Chartered
Engineer was examined. In his statement, he admitted that he had certified
the capacity of the furnace on the basis of the documents produced and
information made available to him by the appellant. It was, therefore,
evident that he had not carried out any physical verification of the furnace.
According to the said witness, the actual production may vary from 10% to
20% of the capacity shown in the joint verification report. Even the officer
of M/s. Furcon Consultancy Services, Shri B.K. Shukla stated that the
modification had been carried out in one of the crucible only but a certificate
was issued in respect of both the crucibles. The Tribunal, therefore, arrived
at the finding that in fact no modification was carried out in the crucible of
the said induction furnace. Various other circumstances which were relevant
for determination of the issue, viz., the conduct of the parties, had also been
taken into consideration.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
11. The Tribunal in its order dated 22.05.2003 held:
\0234. The learned Advocate, further, contended that
the Commissioner seems to have laboured under a
misconception of the scope of ACD Rules as he
had observed that change in the working capacity
did not lead to change in the installed capacity of
the furnace; that the ACD Rules do not talk of
\021installed capacity\022 as the Rules require capacity of
the furnace installed in the factory to be
determined; that the Rules even provide for
increase and reduction of the capacity of the
furnace even where a particular capacity has
already been determined; that, therefore, where
any change is effected before or after the
introduction of compounded levy scheme, such
increased or reduced capacity has to be given due
weight and regard. He relied upon the decision in
Shreeje Concast Ltd. Vs. Commissioner of Central
Excise & C, Rajkot, 2002 (139) ELT 131(T)
wherein it has been held by the Tribunal that \023The
Rules do not at any point speak of capacity of a
furnace when it is first manufactured. They refer
to only capacity and the specified parameter on
which the capacity is to be based. One of the
parameters is the total capacity of the furnace
installed in the site. Such capacity is evidently the
capacity that is present. The capacity of the
furnace after would be the quantity of bunch that it
can produce in one operation (illegible) bunch the
annual capacity would be based upon it. That this
is so (illegible) from the provisions of Rule 4.
This Rule provides for determining the annual
capacity in case where a manufacturer proposes to
increases or (illegible) the capacity of the
induction furnace. \023No doubt the Rules does
(illegible) \023installed capacity\024. In the context of
the other Rule it is clear that (illegible) too the
capacity of a furnace, not when it was initially
constructed, but (illegible) the increase or decrease
referred to in that Rules, newly determined
(illegible) capacity\024. He emphasized that since
Rule 4 provides for change (illegible) capacity in a
case where the capacity is already fixed at the
commencement of the scheme, the change which
has already taken place before (illegible)
commencement of the scheme, is required to be
given due weightage (illegible) consideration; that
the last sentence of Rule 4 of ACD Rules makes
(illegible) obligatory on the part of Commissioner
to determine the date from which the change in the
installed capacity has taken place.\024
12. In its judgment, the Tribunal has noticed:
\023\005These evidences, according to Revenue are (i)
measurement of Crucible volume of the furnace
(specific gravity x volume) which works out to be
7.97 MTs (ii) the weight of MS Ingots including
runners and riser produced in a single heat during
spot visit was 5.86 MTs (iii) Increase in power
consumption and (iv) scrutiny of daily production.
We find substantial force in the finding of the
commissioner which are contained in the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
impugned order\005\024
13. Upon consideration of all relevant facts, as a finding of fact had been
arrived at by the Tribunal, in our opinion, the High Court cannot be said to
have committed any error in passing the impugned judgment.
14. Relevant portion of Section 35G of the Central Excise Act reads as
under:
\02335G. Appeal to High Court
(1) An appeal shall lie to the High Court from
every order passed in appeal by the Appellate
Tribunal on or after the 1st day of July, 2003 (not
being an order relating, among other things, to the
determination of any question having a relation to
the rate of duty of excise or to the value of goods
for the purposes of assessment), if the High Court
is satisfied that the case involves a substantial
question of law\005\024
18. In terms of Section 35G of the Central Excise Act, the High Court,
thus, could entertain an appeal only if a question of law arose. No question
of law having, thus, arisen for consideration before the High Court, we are
of the opinion that the impugned judgment does not suffer from any legal
infirmity.
19. For the reasons aforementioned, there is no merit in this appeal which
is dismissed accordingly. No costs.