STATE OF HARYANA vs. M/S. SHIV SHANKAR CONSTRUCTION CO.

Case Type: Civil Appeal

Date of Judgment: 14-12-2021

Preview image for STATE OF HARYANA vs. M/S. SHIV SHANKAR CONSTRUCTION CO.

Full Judgment Text

REPORTABLE IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION CIVIL APPEAL NOS.7379­7380 OF 2021 State of Haryana            ..Appellant (S) VERSUS M/s. Shiv Shankar Construction Co. & Anr.    ..Respondent (S) J U D G M E N T  M. R. Shah, J. 1. Feeling   aggrieved   and   dissatisfied   with   the   impugned judgment and order dated 03.11.2015 passed by the High Court  of   Punjab   and   Haryana  at  Chandigarh  in  FAO  No. 4482 of 2011 (O&M), by which the High Court has dismissed Signature Not Verified the appeal preferred by the appellant herein under Section Digitally signed by R Natarajan Date: 2021.12.14 16:41:24 IST Reason: 1 37 of the Arbitration and Conciliation Act, 1996, the State of Haryana has preferred the present appeals.  2. At the outset it is required to be noted that while issuing notice   in   the   present   appeals,   this   Court   has   stayed   the award   exceeding   Rs.1,03,50,263/­   insofar   as   claim   Nos.1 and 8 are concerned.   3. The facts leading to the present appeals in a nutshell are as under:­ 3.1 That the appellant herein awarded the contract to respondent No.1 herein – contractor for strengthening, up­gradation and maintenance of road from Palwal to Hasanpur, Haryana for a length of 31.17 kilometres on certain terms and conditions as per   the   contract   entered   into   between   the   parties.   The contract was for Rs.5,26,59,688/­. That as per the design calculation   data,   the   specifications   as   prepared   by   the appellant department were meant for 3364 traffic intensity PCU   (Passenger   Car   Unit)/day.   The   contract   was   up   to 31.05.2010. That on 05.03.2005 due to the closing of the Palwal Aligarh Road on account of the construction of the railway bridge, the entire traffic was diverted from Palwal 2 Aligarh Road to the present road. That due to this diversion of traffic from Palwal Aligarh Road, heavy traffic of 24418 PCUS per day was plying on the road as against the design of 3364 PCUS per day, which damaged the road. That according to the contractor – respondent No.1 herein, he was required to   do   heavy   repair   by   incurring   additional   expenditure. Disputes arose between the parties. A legal notice was served upon the appellant making the claims. Disputes were not resolved and therefore respondent No.1 – contractor invoked the   arbitration   clause   as   per   clauses   24   &   25   and approached the High Court for appointment of an arbitrator in exercise of power conferred under Section 11 (6) of the Arbitration and Conciliation Act, 1996.  3.2 Vide order dated 23.04.2007, the High Court appointed Shri R.S.   Jindal,   retired   Chief   Engineer,   Delhi   Development Authority as the sole Arbitrator to adjudicate upon all the disputes between the parties. That the contractor submitted various claims including claim Nos. 1 and 8. For the purpose of   deciding   the   present   appeals,   claim   Nos.1   and   8   are relevant.   The   sole   Arbitrator   awarded   a   total   sum   of Rs.1,51,95,400/­ with respect to claim Nos.1 and 8.   3 4. Feeling aggrieved and dissatisfied with the award declared by the learned Arbitrator, the appellant preferred an application before the Court under Section 34 of the  Arbitration and Conciliation Act, 1996, which came to be dismissed against which   the   appellant   –   State   preferred   an   appeal   under Section   37   of   the   Arbitration   and   Conciliation   Act,   1996 before the High Court. By the impugned judgment and order the High Court has dismissed the said appeal. Hence, the State of Haryana has preferred the present appeals.   5. Shri Shyam Divan, learned Senior Advocate has appeared on behalf   of   the   State   –   appellant   and   Shri   Ranjit   Kumar, learned   Senior   Advocate   has   appeared   on   behalf   of   the respondent No.1 – contractor.  5.1 Shri  Shyam   Divan,   learned   Senior   Advocate   appearing  on behalf   of   the   appellant   submitted   that   the   appellant   has already paid to respondent No.1 – contractor an amount of Rs.1,03,50,263/­   pursuant   to   the   interim   order   dated 26.08.2016 passed by this Court. 4 5.2 Shri  Shyam   Divan,   learned   Senior   Advocate   appearing  on behalf of the appellant has submitted that the arbitral award is liable to be set aside on the following grounds:­ (i) The award is in excess of claim; (ii) The Arbitrator exceeded the scope of reference; (iii) The Arbitrator has rewritten the contract with respect to the amount payable which was specified in the contract. 5.3 Now, so far as ground No.1 that the award is in excess of claim,   it   is   vehemently   submitted   by   Shri   Shyam   Divan, learned Senior Advocate appearing on behalf of the appellant that the contractor in its statement of claim had claimed an amount of Rs. 1,03,50,263/­ only under the claim Nos.1 and 8. It is submitted that despite the above the Arbitrator has awarded a total sum of Rs.1,51,95,400/­, which is in far excess of amount claimed. It is submitted that the statement of claim was never modified by the contractor and therefore, the Arbitrator ought not to have awarded the sum/amount in excess of the amount claimed. 5 5.3.1 It   is   submitted   that   the   differential   amount   of Rs.48,45,137/­ is in excess of claim and to that extent the arbitral award is invalid and liable to be set aside. Reliance is placed on the decision of this Court in the case of  ONGC (2011) 14 SCC 147 Ltd. v. Off­Shore Enterprises Inc.,   (para 16).  5.3.2 It is submitted that as held by this Court in the cases of Associate   Builders   v.   Delhi   Development   Authority , (2015)   3   SCC   49   (para   36)   and   J.C.   Budhraja   v. Chairman, Orissa Mining Corpn. Ltd. & Anr.,   (2008) 2 SCC 444 (para 31­32), making an award in excess of claim is clear cut an act exceeding the jurisdiction and amounts to a misconduct of the Arbitrator. 5.4 Now,   so   far   as   ground   No.2   namely,   that   the   Arbitrator exceeded   the   scope   of   reference,   it   is   contended   that   the Arbitrator cannot exceed the scope of reference. 5.4.1 It is submitted that the contractor invoked the arbitration clause on 06.03.2006. The High Court appointed the sole 6 Arbitrator on 23.04.2007 and the Arbitrator entered upon reference on 19.05.2007. It is urged that by allowing the claims   for   a   period   beyond   19.05.2007,   the   Arbitrator exceeded the scope of reference.  5.4.2 It is submitted that an amount of Rs.57,96,000/­ (approx.) has been awarded for claims arising between 19.05.2007 to 31.07.2008 (calculated as amount for maintenance of road @   Rs.   45,000/­   per   kilometre   (km)   per   month).   It   is submitted that it was not permissible for the Arbitrator to exceed the scope of the reference beyond the date upon entering reference and as a consequence the award is liable to be set aside.  5.4.3 Learned   senior   counsel   appearing   on   behalf   of   the appellant has relied upon the decisions of this Court in the cases of  Indian Aluminium Cables Ltd. v. Haryana State  1996 (5) SCALE 708 (para 2) and  Electricity Board, MSK Projects India (JV) Ltd. v. State of Rajasthan & Anr. (2011)   10   SCC   573   (para   15),   in   support   of   his   above submissions that as the Arbitrator exceeded the scope of reference and hence the award is liable to be set aside. 7 5.5 In   so   far   as   the   ground   No.3   is   concerned   namely,   the Arbitrator   has   rewritten   the   contract   with   respect   to   the amount payable which was specified in the contract, it is submitted that the Arbitrator has rewritten the terms of the contract by directing the appellant to pay the compensation to respondent No.1 – contractor at the rate of Rs.45,000/­ per km per month instead of mutually agreed contractual rate of Rs.1,000/­ per km per month. It is contended that it was not open to the Arbitrator to rewrite the terms of the contract and award the contractor a higher rate for the work than the rate which was already fixed in the contract. It is submitted that such an exercise is beyond the competence and authority of the Arbitrator. Reliance is placed on the decision   of   this   Court   in   the   case   of   Satyanarayana Construction   Company   v.   Union   of   India   and   Others (2011) 15 SCC 101 (para 11).  5.6 It   is   further   contended   by   Shri   Divan,   learned   Senior Advocate   appearing   on   behalf   of   the   appellant   that   even otherwise,   the   amount   awarded   by   the   Arbitrator   at 8 Rs.45,000/­ per km per month beyond the time period of additional traffic i.e. from 31.07.2008 to 31.05.2010 i.e. till the end of contract is wholly impermissible. It is submitted that diversion of traffic on 9.2 km stretch of the road which gave rise to the cause of action ceased to exist w.e.f. January 2008.   It   is   submitted   that   however,   the   Arbitrator   has directed the appellant to make payment at Rs. 45,000/­ per km   per   month  even   beyond  the   time   period  of   additional traffic.   It   is   contended   that   the   aforesaid   is   wholly impermissible.  6. Making   the   above   submissions,   it   is   prayed   to   allow   the present appeals.  7. Shri Ranjit Kumar, learned  Senior Advocate   appearing  on behalf   of   respondent   No.1   –   contractor,   has   vehemently contended that the award passed by the Arbitrator cannot be said to be (i) in excess of claim; (ii) exceeding the scope of reference and (iii) rewriting the contract with respect to the amount   payable   which   was   specified   in   the   contract,   as submitted on behalf of the appellant. It is submitted that in the statement of claim the contractor specifically stated that 9 the amount has been worked out up to the month of May, 2007 and the details of expenditure beyond May, 2007 will be submitted   during   the   course   of   hearing.   It   is   therefore submitted that it cannot be said that claim Nos.1 and 8 were restricted   to   Rs. 1,03,50,263/­   only.   It   is   urged   that   on appreciation   of   the   evidence   on   record   the   Arbitrator   has awarded Rs. 1,51,95,400/­  for claim Nos.1 and 8, which in any case cannot be said to be beyond the amount claimed in the statement of claim.  7.1 It is  next  contended  that it also cannot be  said  that the award   passed   by   the   Arbitrator   was   beyond   the   scope   of reference. It is submitted that as such cause of action to claim the additional amount arose due to over­expenditure owing to maintenance of road due to diversion of traffic from Palwal Aligarh  Road to the  present  road which continued even beyond 06.03.2006 and/or 23.04.2007 and 19.05.2007. It is submitted that the amount awarded by the Arbitrator under claim Nos.1 and 8 cannot be said to be exceeding the scope of reference. 10 7.2 It is further submitted that even the award passed by the Arbitrator   to   make   payment   at   Rs.45,000/­   per   km   per month cannot be said to be rewriting of the contract with respect to the amount payable which was specified in the contract. It is urged that at the time when the contract was written/entered into between the parties the contract rate of Rs.1,000/­ per km per month was agreed against the design of   3364   PCUS   per   day.   However,   after   the   contract   was entered into and the contractor acted as per the contract there was diversion of traffic from Palwal Aligarh Road to the present road and the heavy traffic of 24418 PCUS per day was plying on the road as against the design of 3364 PCUS per day and therefore the contractor was required to incur additional expenditure at Rs.45,000/­ per km per month. It is submitted that the amount awarded by the Arbitrator at Rs.45,000/­ per km per month cannot be said to be rewriting the contract with respect to the amount payable than what was   specified   in   the   contract   i.e.   Rs.1,000/­   per   km   per month.  7.3 However,   Shri   Ranjit   Kumar,   learned   Senior   Advocate appearing on behalf of the contractor is not in a position to 11 justify the award by which the Arbitrator has awarded the payment at Rs.45,000/­ per km per month even beyond the time period of additional traffic i.e. up to 31.05.2010 i.e. till the end of the contract.  8. We   have   heard   the   learned   senior   counsel   appearing   on behalf   of   the   respective   parties   at   length   and   given   our thoughtful consideration. 9. That   the   contractor   was   awarded   the   contract   for maintenance,   etc.   The   contract   amount   was   for Rs.5,26,59,688/­. The rate of maintenance of the road as accepted was Rs.12,000/­ per km per annum or Rs.1,000/­ per km per month. The maintenance contract was valid up to 31.07.2010.   When   the   contract   was   entered   into,   the contract was meant for only 3364 PCUS per day. However, due to diversion of traffic from Palwal Aligarh Road to the present road, the contractor was required to incur additional expenditure on the maintenance due to increase in the traffic and plying the additional commercial vehicles. Therefore the contractor   claimed   the   amount   towards   additional expenditure for maintenance which was due to increase in 12 the   traffic   and   plying   more   commercial   vehicles.   On appreciation of evidence the Arbitrator has determined the loss at Rs.45,000/­ per km per month (claim Nos.1 and 8).  9.1 The case on behalf of the appellant that as in the statement of   claim,   the   claimant   claimed   an   amount   of Rs.1,03,50,263/­   under   the   claim   Nos.   1   and   8   and   the Arbitrator has awarded Rs.1,51,95,400/­, the same is in far excess   of   amount   claimed   and   therefore   the   award   is   in excess   of   amount   claimed   has   no   substance.   When   the statement of claim submitted by the contractor is seen, it is specifically   stated   by   the   claimant   that   the   amount   of Rs.1,03,50,263/­ has been worked out up to May, 2007 and the   details   of   expenditure   beyond   May,   2007   will   be submitted   during   the   course   of   hearing.   It   is   specifically stated that expenditure incurred up to May, 2007 works out to Rs.1,03,50,263/­. Therefore, the amount awarded by the Arbitrator cannot be said to be in excess of the claim.  9.2 Now so far as the submission on behalf of the appellant that the Arbitrator exceeded the scope of reference while awarding an amount beyond 19.05.2007 – the date on which the High 13 Court appointed the sole Arbitrator is concerned, the same has no substance. The case on behalf of the appellant that the Arbitrator ought to have restricted the claim either up to 06.03.2006 – the date on which the contractor invoked the arbitration clause or 23.04.2007, the date on which the High Court   appointed   the   sole   Arbitrator   or   at   least   up   to 19.05.2007 – the date on which the Arbitrator entered into reference, is concerned, it is required to be noted that the claim made by the Arbitrator was till the traffic was diverted which was up to January, 2008. Therefore, the Arbitrator was justified in awarding the amount beyond the aforesaid periods and till the additional traffic was diverted due to the closure of Palwal Aligarh Road. 9.3 Now the submission on behalf of the appellant is that by awarding Rs.45,000/­ per km per month the Arbitrator has rewritten the contract with respect to the amount payable than  what  was  specified  in  the   contract.  It  is   urged  that under   the   contract   mutually   agreed   contractual   rate   was Rs.1,000/­   per   km   per   month   and   therefore   any   amount higher   than  Rs.1,000/­  per   km  per   month  is   beyond   the terms   and   conditions   of   the   contract,   is   also   without 14 substance. It is noted that at the time when the contract was entered   into   the   mutually   agreed,   the   rate   fixed   was Rs.1,000/­ per km per month and the estimated traffic was 3364 PCUS per day. The cause of action arose subsequently due   to   diversion   of   traffic   from   Palwal   Aligarh   Road   and plying of more heavy vehicles due to which the contractor was required to incur additional expenditure for maintenance of the road. Therefore, the contractor was entitled to the loss on   account   of   the   additional   expenditure   incurred   for maintenance   of   the   road   due   to   increase   in   the   traffic because   of   the   closure   of   the   Palwal   Aligarh   Road   and diversion of the traffic to the present road. Therefore, by no stretch of imagination it can be said that there was rewriting the   terms   of   the   contract   as   submitted   on   behalf   of   the appellant.  9.4 In view of the above findings, none of the decisions of this Court relied upon by the learned senior counsel appearing on behalf of the appellant are applicable to the facts of the case on   hand   as   the   same   are   not   of   any   assistance   to   the appellant.  15 9.5 However,   at   the   same   time   Shri   Divan,   learned   Senior Advocate, appearing on behalf of the appellant is justified in submitting that the Arbitrator ought not to have awarded an amount of Rs.45,000/­ per km per month beyond the time period of additional traffic. The Arbitrator has awarded the loss/amount   at   Rs.45,000/­   per   km   per   month   up   to 31.05.2010 i.e. till the end of the contract which is wholly impermissible   diversion   of   the   additional   traffic   ceased   to exist w.e.f. January, 2008. Therefore, the Arbitrator ought not   to   have   awarded   any   amount   beyond   the   above   time period   beyond   January,   2008.   To   that   extent   the   award passed by the Arbitrator can be said to be perverse and to that extent the present appeals are required to be allowed. 10. In view of the above and for the reasons stated above, the present appeals are allowed in part. The award passed by the Arbitrator   awarding   the   amount/compensation   at Rs.45,000/­ per km per month up to January, 2008 under claim Nos.1 and 8 is hereby confirmed. The award passed by the   Arbitrator   awarding   the   amount/compensation   at Rs.45,000/­   per   km   per   month   from   February,   2008   to 31.05.2010 i.e. till the end of the contract is hereby quashed 16 and set aside. The amount due and payable has to be worked out accordingly. The present appeals are partly allowed to the aforesaid extent. In the facts and circumstances of the case there shall be no order as to costs.         …………………………………J.   (M. R. SHAH) …………………………………J.  (B.V. NAGARATHNA) New Delhi,  December  14, 2021. 17