STATE OF HARYANA vs. M/S. SHIV SHANKAR CONSTRUCTION CO.

Case Type: Civil Appeal

Date of Judgment: 14-12-2021

Preview image for STATE OF HARYANA vs. M/S. SHIV SHANKAR CONSTRUCTION CO.

Full Judgment Text


REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NOS.7379­7380 OF 2021
State of Haryana            ..Appellant (S)
VERSUS
M/s. Shiv Shankar Construction Co. & Anr.    ..Respondent (S)
J U D G M E N T 
M. R. Shah, J.
1. Feeling   aggrieved   and   dissatisfied   with   the   impugned
judgment and order dated 03.11.2015 passed by the High
Court  of   Punjab   and   Haryana  at  Chandigarh  in  FAO  No.
4482 of 2011 (O&M), by which the High Court has dismissed
Signature Not Verified
the appeal preferred by the appellant herein under Section
Digitally signed by R
Natarajan
Date: 2021.12.14
16:41:24 IST
Reason:
1

37 of the Arbitration and Conciliation Act, 1996, the State of
Haryana has preferred the present appeals. 
2. At the outset it is required to be noted that while issuing
notice   in   the   present   appeals,   this   Court   has   stayed   the
award   exceeding   Rs.1,03,50,263/­   insofar   as   claim   Nos.1
and 8 are concerned.  
3. The facts leading to the present appeals in a nutshell are as
under:­
3.1 That the appellant herein awarded the contract to respondent
No.1 herein – contractor for strengthening, up­gradation and
maintenance of road from Palwal to Hasanpur, Haryana for a
length of 31.17 kilometres on certain terms and conditions as
per   the   contract   entered   into   between   the   parties.   The
contract was for Rs.5,26,59,688/­. That as per the design
calculation   data,   the   specifications   as   prepared   by   the
appellant department were meant for 3364 traffic intensity
PCU   (Passenger   Car   Unit)/day.   The   contract   was   up   to
31.05.2010. That on 05.03.2005 due to the closing of the
Palwal Aligarh Road on account of the construction of the
railway bridge, the entire traffic was diverted from Palwal
2

Aligarh Road to the present road. That due to this diversion
of traffic from Palwal Aligarh Road, heavy traffic of 24418
PCUS per day was plying on the road as against the design of
3364 PCUS per day, which damaged the road. That according
to the contractor – respondent No.1 herein, he was required
to   do   heavy   repair   by   incurring   additional   expenditure.
Disputes arose between the parties. A legal notice was served
upon the appellant making the claims. Disputes were not
resolved and therefore respondent No.1 – contractor invoked
the   arbitration   clause   as   per   clauses   24   &   25   and
approached the High Court for appointment of an arbitrator
in exercise of power conferred under Section 11 (6) of the
Arbitration and Conciliation Act, 1996. 
3.2 Vide order dated 23.04.2007, the High Court appointed Shri
R.S.   Jindal,   retired   Chief   Engineer,   Delhi   Development
Authority as the sole Arbitrator to adjudicate upon all the
disputes between the parties. That the contractor submitted
various claims including claim Nos. 1 and 8. For the purpose
of   deciding   the   present   appeals,   claim   Nos.1   and   8   are
relevant.   The   sole   Arbitrator   awarded   a   total   sum   of
Rs.1,51,95,400/­ with respect to claim Nos.1 and 8.  
3

4. Feeling aggrieved and dissatisfied with the award declared by
the learned Arbitrator, the appellant preferred an application
before the Court under Section 34 of the  Arbitration and
Conciliation Act, 1996, which came to be dismissed against
which   the   appellant   –   State   preferred   an   appeal   under
Section   37   of   the   Arbitration   and   Conciliation   Act,   1996
before the High Court. By the impugned judgment and order
the High Court has dismissed the said appeal. Hence, the
State of Haryana has preferred the present appeals.  
5. Shri Shyam Divan, learned Senior Advocate has appeared on
behalf   of   the   State   –   appellant   and   Shri   Ranjit   Kumar,
learned   Senior   Advocate   has   appeared   on   behalf   of   the
respondent No.1 – contractor. 
5.1 Shri  Shyam   Divan,   learned   Senior   Advocate   appearing  on
behalf   of   the   appellant   submitted   that   the   appellant   has
already paid to respondent No.1 – contractor an amount of
Rs.1,03,50,263/­   pursuant   to   the   interim   order   dated
26.08.2016 passed by this Court.
4

5.2 Shri  Shyam   Divan,   learned   Senior   Advocate   appearing  on
behalf of the appellant has submitted that the arbitral award
is liable to be set aside on the following grounds:­
(i) The award is in excess of claim;
(ii) The Arbitrator exceeded the scope of reference;
(iii) The Arbitrator has rewritten the contract with respect to
the amount payable which was specified in the contract.
5.3 Now, so far as ground No.1 that the award is in excess of
claim,   it   is   vehemently   submitted   by   Shri   Shyam   Divan,
learned Senior Advocate appearing on behalf of the appellant
that the contractor in its statement of claim had claimed an
amount of Rs. 1,03,50,263/­ only under the claim Nos.1 and
8. It is submitted that despite the above the Arbitrator has
awarded a total sum of Rs.1,51,95,400/­, which is in far
excess of amount claimed. It is submitted that the statement
of claim was never modified by the contractor and therefore,
the Arbitrator ought not to have awarded the sum/amount in
excess of the amount claimed.
5

5.3.1 It   is   submitted   that   the   differential   amount   of
Rs.48,45,137/­ is in excess of claim and to that extent the
arbitral award is invalid and liable to be set aside. Reliance
is placed on the decision of this Court in the case of  ONGC
(2011) 14 SCC 147
Ltd. v. Off­Shore Enterprises Inc.,  
(para 16). 
5.3.2 It is submitted that as held by this Court in the cases of
Associate   Builders   v.   Delhi   Development   Authority ,
(2015)   3   SCC   49   (para   36)   and   J.C.   Budhraja   v.
Chairman, Orissa Mining Corpn. Ltd. & Anr.,   (2008) 2
SCC 444 (para 31­32), making an award in excess of claim
is clear cut an act exceeding the jurisdiction and amounts
to a misconduct of the Arbitrator.
5.4 Now,   so   far   as   ground   No.2   namely,   that   the   Arbitrator
exceeded   the   scope   of   reference,   it   is   contended   that   the
Arbitrator cannot exceed the scope of reference.
5.4.1 It is submitted that the contractor invoked the arbitration
clause on 06.03.2006. The High Court appointed the sole
6

Arbitrator on 23.04.2007 and the Arbitrator entered upon
reference on 19.05.2007. It is urged that by allowing the
claims   for   a   period   beyond   19.05.2007,   the   Arbitrator
exceeded the scope of reference. 
5.4.2 It is submitted that an amount of Rs.57,96,000/­ (approx.)
has been awarded for claims arising between 19.05.2007 to
31.07.2008 (calculated as amount for maintenance of road
@   Rs.   45,000/­   per   kilometre   (km)   per   month).   It   is
submitted that it was not permissible for the Arbitrator to
exceed the scope of the reference beyond the date upon
entering reference and as a consequence the award is liable
to be set aside. 
5.4.3 Learned   senior   counsel   appearing   on   behalf   of   the
appellant has relied upon the decisions of this Court in the
cases of  Indian Aluminium Cables Ltd. v. Haryana State
 1996 (5) SCALE 708 (para 2) and 
Electricity Board, MSK
Projects India (JV) Ltd. v. State of Rajasthan & Anr.
(2011)   10   SCC   573   (para   15),   in   support   of   his   above
submissions that as the Arbitrator exceeded the scope of
reference and hence the award is liable to be set aside.
7

5.5 In   so   far   as   the   ground   No.3   is   concerned   namely,   the
Arbitrator   has   rewritten   the   contract   with   respect   to   the
amount payable which was specified in the contract, it is
submitted that the Arbitrator has rewritten the terms of the
contract by directing the appellant to pay the compensation
to respondent No.1 – contractor at the rate of Rs.45,000/­
per km per month instead of mutually agreed contractual
rate of Rs.1,000/­ per km per month. It is contended that it
was not open to the Arbitrator to rewrite the terms of the
contract and award the contractor a higher rate for the work
than the rate which was already fixed in the contract. It is
submitted that such an exercise is beyond the competence
and authority of the Arbitrator. Reliance is placed on the
decision   of   this   Court   in   the   case   of   Satyanarayana
Construction   Company   v.   Union   of   India   and   Others
(2011) 15 SCC 101 (para 11). 
5.6 It   is   further   contended   by   Shri   Divan,   learned   Senior
Advocate   appearing   on   behalf   of   the   appellant   that   even
otherwise,   the   amount   awarded   by   the   Arbitrator   at
8

Rs.45,000/­ per km per month beyond the time period of
additional traffic i.e. from 31.07.2008 to 31.05.2010 i.e. till
the end of contract is wholly impermissible. It is submitted
that diversion of traffic on 9.2 km stretch of the road which
gave rise to the cause of action ceased to exist w.e.f. January
2008.   It   is   submitted   that   however,   the   Arbitrator   has
directed the appellant to make payment at Rs. 45,000/­ per
km   per   month  even   beyond  the   time   period  of   additional
traffic.   It   is   contended   that   the   aforesaid   is   wholly
impermissible. 
6. Making   the   above   submissions,   it   is   prayed   to   allow   the
present appeals. 
7. Shri Ranjit Kumar, learned  Senior Advocate   appearing  on
behalf   of   respondent   No.1   –   contractor,   has   vehemently
contended that the award passed by the Arbitrator cannot be
said to be (i) in excess of claim; (ii) exceeding the scope of
reference and (iii) rewriting the contract with respect to the
amount   payable   which   was   specified   in   the   contract,   as
submitted on behalf of the appellant. It is submitted that in
the statement of claim the contractor specifically stated that
9

the amount has been worked out up to the month of May,
2007 and the details of expenditure beyond May, 2007 will be
submitted   during   the   course   of   hearing.   It   is   therefore
submitted that it cannot be said that claim Nos.1 and 8 were

restricted   to   Rs. 1,03,50,263/­   only.   It   is   urged   that   on
appreciation   of   the   evidence   on   record   the   Arbitrator   has
awarded Rs. 1,51,95,400/­  for claim Nos.1 and 8, which in
any case cannot be said to be beyond the amount claimed in
the statement of claim. 
7.1 It is  next  contended  that it also cannot be  said  that the
award   passed   by   the   Arbitrator   was   beyond   the   scope   of
reference. It is submitted that as such cause of action to
claim the additional amount arose due to over­expenditure
owing to maintenance of road due to diversion of traffic from
Palwal Aligarh  Road to the  present  road which continued
even beyond 06.03.2006 and/or 23.04.2007 and 19.05.2007.
It is submitted that the amount awarded by the Arbitrator
under claim Nos.1 and 8 cannot be said to be exceeding the
scope of reference.
10

7.2 It is further submitted that even the award passed by the
Arbitrator   to   make   payment   at   Rs.45,000/­   per   km   per
month cannot be said to be rewriting of the contract with
respect to the amount payable which was specified in the
contract. It is urged that at the time when the contract was
written/entered into between the parties the contract rate of
Rs.1,000/­ per km per month was agreed against the design
of   3364   PCUS   per   day.   However,   after   the   contract   was
entered into and the contractor acted as per the contract
there was diversion of traffic from Palwal Aligarh Road to the
present road and the heavy traffic of 24418 PCUS per day
was plying on the road as against the design of 3364 PCUS
per day and therefore the contractor was required to incur
additional expenditure at Rs.45,000/­ per km per month. It
is submitted that the amount awarded by the Arbitrator at
Rs.45,000/­ per km per month cannot be said to be rewriting
the contract with respect to the amount payable than what
was   specified   in   the   contract   i.e.   Rs.1,000/­   per   km   per
month. 
7.3 However,   Shri   Ranjit   Kumar,   learned   Senior   Advocate
appearing on behalf of the contractor is not in a position to
11

justify the award by which the Arbitrator has awarded the
payment at Rs.45,000/­ per km per month even beyond the
time period of additional traffic i.e. up to 31.05.2010 i.e. till
the end of the contract. 
8. We   have   heard   the   learned   senior   counsel   appearing   on
behalf   of   the   respective   parties   at   length   and   given   our
thoughtful consideration.
9. That   the   contractor   was   awarded   the   contract   for
maintenance,   etc.   The   contract   amount   was   for
Rs.5,26,59,688/­. The rate of maintenance of the road as
accepted was Rs.12,000/­ per km per annum or Rs.1,000/­
per km per month. The maintenance contract was valid up to
31.07.2010.   When   the   contract   was   entered   into,   the
contract was meant for only 3364 PCUS per day. However,
due to diversion of traffic from Palwal Aligarh Road to the
present road, the contractor was required to incur additional
expenditure on the maintenance due to increase in the traffic
and plying the additional commercial vehicles. Therefore the
contractor   claimed   the   amount   towards   additional
expenditure for maintenance which was due to increase in
12

the   traffic   and   plying   more   commercial   vehicles.   On
appreciation of evidence the Arbitrator has determined the
loss at Rs.45,000/­ per km per month (claim Nos.1 and 8). 
9.1 The case on behalf of the appellant that as in the statement
of   claim,   the   claimant   claimed   an   amount   of
Rs.1,03,50,263/­   under   the   claim   Nos.   1   and   8   and   the
Arbitrator has awarded Rs.1,51,95,400/­, the same is in far
excess   of   amount   claimed   and   therefore   the   award   is   in
excess   of   amount   claimed   has   no   substance.   When   the
statement of claim submitted by the contractor is seen, it is
specifically   stated   by   the   claimant   that   the   amount   of
Rs.1,03,50,263/­ has been worked out up to May, 2007 and
the   details   of   expenditure   beyond   May,   2007   will   be
submitted   during   the   course   of   hearing.   It   is   specifically
stated that expenditure incurred up to May, 2007 works out
to Rs.1,03,50,263/­. Therefore, the amount awarded by the
Arbitrator cannot be said to be in excess of the claim. 
9.2 Now so far as the submission on behalf of the appellant that
the Arbitrator exceeded the scope of reference while awarding
an amount beyond 19.05.2007 – the date on which the High
13

Court appointed the sole Arbitrator is concerned, the same
has no substance. The case on behalf of the appellant that
the Arbitrator ought to have restricted the claim either up to
06.03.2006 – the date on which the contractor invoked the
arbitration clause or 23.04.2007, the date on which the High
Court   appointed   the   sole   Arbitrator   or   at   least   up   to
19.05.2007 – the date on which the Arbitrator entered into
reference, is concerned, it is required to be noted that the
claim made by the Arbitrator was till the traffic was diverted
which was up to January, 2008. Therefore, the Arbitrator
was justified in awarding the amount beyond the aforesaid
periods and till the additional traffic was diverted due to the
closure of Palwal Aligarh Road.
9.3 Now the submission on behalf of the appellant is that by
awarding Rs.45,000/­ per km per month the Arbitrator has
rewritten the contract with respect to the amount payable
than  what  was  specified  in  the   contract.  It  is   urged  that
under   the   contract   mutually   agreed   contractual   rate   was
Rs.1,000/­   per   km   per   month   and   therefore   any   amount
higher   than  Rs.1,000/­  per   km  per   month  is   beyond   the
terms   and   conditions   of   the   contract,   is   also   without
14

substance. It is noted that at the time when the contract was
entered   into   the   mutually   agreed,   the   rate   fixed   was
Rs.1,000/­ per km per month and the estimated traffic was
3364 PCUS per day. The cause of action arose subsequently
due   to   diversion   of   traffic   from   Palwal   Aligarh   Road   and
plying of more heavy vehicles due to which the contractor
was required to incur additional expenditure for maintenance
of the road. Therefore, the contractor was entitled to the loss
on   account   of   the   additional   expenditure   incurred   for
maintenance   of   the   road   due   to   increase   in   the   traffic
because   of   the   closure   of   the   Palwal   Aligarh   Road   and
diversion of the traffic to the present road. Therefore, by no
stretch of imagination it can be said that there was rewriting
the   terms   of   the   contract   as   submitted   on   behalf   of   the
appellant. 
9.4 In view of the above findings, none of the decisions of this
Court relied upon by the learned senior counsel appearing on
behalf of the appellant are applicable to the facts of the case
on   hand   as   the   same   are   not   of   any   assistance   to   the
appellant. 
15

9.5 However,   at   the   same   time   Shri   Divan,   learned   Senior
Advocate, appearing on behalf of the appellant is justified in
submitting that the Arbitrator ought not to have awarded an
amount of Rs.45,000/­ per km per month beyond the time
period of additional traffic. The Arbitrator has awarded the
loss/amount   at   Rs.45,000/­   per   km   per   month   up   to
31.05.2010 i.e. till the end of the contract which is wholly
impermissible   diversion   of   the   additional   traffic   ceased   to
exist w.e.f. January, 2008. Therefore, the Arbitrator ought
not   to   have   awarded   any   amount   beyond   the   above   time
period   beyond   January,   2008.   To   that   extent   the   award
passed by the Arbitrator can be said to be perverse and to
that extent the present appeals are required to be allowed.
10. In view of the above and for the reasons stated above, the
present appeals are allowed in part. The award passed by the
Arbitrator   awarding   the   amount/compensation   at
Rs.45,000/­ per km per month up to January, 2008 under
claim Nos.1 and 8 is hereby confirmed. The award passed by
the   Arbitrator   awarding   the   amount/compensation   at
Rs.45,000/­   per   km   per   month   from   February,   2008   to
31.05.2010 i.e. till the end of the contract is hereby quashed
16

and set aside. The amount due and payable has to be worked
out accordingly. The present appeals are partly allowed to the
aforesaid extent. In the facts and circumstances of the case
there shall be no order as to costs.        
…………………………………J.
  (M. R. SHAH)
…………………………………J.
 (B.V. NAGARATHNA)
New Delhi, 
December  14, 2021.
17