Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
PETITIONER:
(WITH C.A.NOS.1934, 1938, 1940-43 OF 1989,C.A.NO.8956/96
Vs.
RESPONDENT:
DATE OF JUDGMENT: 27/05/1996
BENCH:
B.L. HANSARIA
ACT:
HEADNOTE:
JUDGMENT:
[With C.A. Nos.1934, 1938, 1940-43 of 1989, C.A.Nos of 1996
(arising out of SLP (C) Nos.11085, 10377, 11907, 9282, 9184,
8644, 7164, 9646, 9534, 9430, 11605, 10408, 10246, 10255,
10257, 10285, 10329, 15187, 14467, 11949, 11948, 10085,
11951, 9538, 9419, 9142, 9288 and 9259 of 1989, 17538,
17522, 17521, 17520, 17519, 17529, 17528, 17543, 17525,
17524, 17523, 17542, 17541, 17540-40A, 17539, 17536, 17535,
17534, 17533, 17532, 17531, 17530, 17527, 17526 of 1993, CC
Nos.1269, 1084 and 1055 of 1989]
Bihar State Electricity
Board and others
V.
Parmeshwar Kumar Agarwala etc.etc.
J U D G M E N T
HANSARIA,J.
Theft of electricity has become so chronic a disease
that there can be no doubt that all efforts must be made to
curb the same; not only to make the State Electricity Boards
viable, but also to ensure regular supply of electricity to
the lawful consumers at reasonable tariff.
2. The facet of theft of electricity with which these
appeals are concerned relates to the mischief of consumers
to tamper with the meters, first to slow it down and then to
make the same defective. The basic idea behind this is that
the general terms and conditions governing the agreement
between Electricity Boards and the consumers require that in
such a case reading of the meter shall be based on the
average reading cf previous three months, in which the meter
ran correctly and reading was duly recorded. Section 26 of
the Indian Electricity Act, 1910, hereinafter the 1910 Act,
is on the subject of "Meters" and sub-section (1) of this
section requires that the amount of energy applied to the
consumer shall be ascertained by means of a correct meter.
Sub-section (6) has provided that where any difference or
dispute arises as to whether any meter is or is not correct,
the matter shall be decided, upon the application of either
party, by an Electrical Inspector. Further steps are
required to be taken as per the opinion cd such Inspector.
3. Confronted with the aforesaid position, the Bihar State
Electricity Board (for short, the Board) found itself
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
suffering heavy financial loss to the tune of several
crores. It, therefore, arranged a meeting of the General
Managers - cum - Chief Engineers on 12.6.1982 and decided,
inter alia, that the assessment of the aforesaid type of
consumers, should be made, in the case of low tension
industrial consumers at 30% load factor and in case of high
tension industrial consumers at 45% load factor, during the
period their meters remained defective.
4. On the aforesaid decision put to implementation, some
consumers approached the High Court of Judicature at Patna
by filing a writ petition (CWJC No.2250 of 1984) in which it
was held that the decision dated 12.6.1982 having far
reaching consequences and having not been taken by the Board
itself, could not be sustained. It was also pointed out that
the power to amend tariff lay with the Board in exercise of
powers under sections 46 and 49 of the Electricity (Supply)
Act, 1948 to be referred hereinafter as the 1948 Act. The
High Court, therefore, quashed the decision dated 12.6.1982.
5. The Board thereafter issued a Notification on 16.2.1987
invoking its power under sections 46 and 49 of 1948 Act and
decided to bill industrial consumers in the line of the
decision taken earlier. The Notification reads as below :
"In view of the observations
of the Hon’ble High Court in its
order dated 25.8.86 passed in
C.W.J.C.No.2250/84 filed by Sri
Vishnu Re-Rolling Mills against the
Bihar State Electricity Board and
others, the B.S.E.Board, in its
resolution No.5873 taken in the
388th meeting of the Board held on
23.1.1987, after taking into
consideration all the aspects of
the matter, has decided and
resolved to bill L.T.I.S. (meaning,
Law Tension Industrial Sector?)
consumers at 30% load factor, H.T.
(meaning, High Tension) consumers
at 45% load factor, for the period
the meter remained defective or
non-working, with effect from
12.6.92.
Accordingly, it is hereby
notified that by virtue of the
power conferred under sec.46 and 49
of the Electric Supply Act, 1948,
the Bihar State Electricity Board,
has decided to bill LTIS consumers
at 30% load factors, H.T. consumers
at 45% load factors and commercial
consumers at 30% load factors for
the period meter remained defective
or non-working with effect from
12.6.82."
6. This notification came to be challenged by a number of
consumers and the judgments impugned in these appeals relate
to the view taken by the High Court qua this notification.
The High Court has quashed the notification, not only the
retrospective part of it, but the whole of it, being of the
view that the Board had no power to issue the same. In these
appeals by special leave, the Board has challenged the
legality of the view taken by the High Court.
7. Shri Sibal, appearing for the appellant-Board, made a
submission, when the appeals were taken for hearing, that he
was not in a position to find fault with that part of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
judgment of the High Court by which retrospective operation
of the notification has been set aside. He, however,
strenuously contended that the notification could not have
been quashed in its entirety by regarding the same as ultra
vires. We would, therefore, address ourselves to this stand
only of Shri Sibal.
8. The notification having been issued in exercise of
powers under sections 46 and 49 of the 1948 Act the learned
counsel first referred us to section 49 of this Act, which
is on the subject of "Effect of other lass". Tn sub-section
(1) of this section, it has been stated that no provision of
the Indian Electricity Act, 1910 or of any rules made
thereunder, shall have any effect, so far as it is
inconsistent with any of the provisions of 1948 Act. It was,
therefore, urged that in case of conflict between the two
statutes, namely, 1910 and 1948 Acts, the provision
contained in the latter shall prevail. This legal position
cannot assist the Board, as what has been provided in
section 70 cannot protect the notification, because the same
is not a part of the provision of the 1948 Act, but has been
issued with the and of the provision of this Act.
9. It is because of this that the learned counsel referred
us to section 49 of the 1948 Act and we were addressed on
the width of the power given to the Board by various sub-
sections of this section. The one which was specifically
mentioned is sub-section (3), which has laid down that
nothing in the foregoing provisions of the section shall
derogate from the power of the Board to fix different
tariffs for the supply of electricity to any person not
being a licensee, having regard to some objects mentioned in
the sub-section and "any other relevant factors".
10. Shri Sibal referred us to certain decisions of this
Court in which the width of the power of the Board conferred
by section 49 had come to be examined. These decisions are:
(1) New Central Jute Mills Co. Ltd. v. U.P. State
Electricity Board, 1993 (Supp) SCC 581; and (2) Ferro Alloys
Corporation Ltd. v. A.P. State Electricity Board, 1993(Supp)
4 SCC 136. In the first of these decision the view taken by
a two-Judge Bench of this Court was that the expression "any
other relevant factors" appearing in section 49(3) was not
to be construed ejusdem generis; and that the combined
effect of section 49 and the terms and conditions of supply
was that having regard to the nature of supply and other
relevant factors, the Board had the power to enhance the
tariff rates. What had happened in New Central Jute Mills’s
case was that the U.P. Electricity Board had levied a
surcharge of 5.5 paise per unit of electricity drawn in
excess of the permissible 70% authorised by the State
Government. As the State Government had imposed a ban on
drawing electricity in excess of 70% in exercise of powers
under section 22-B of the 1910 Act, it was contended that
the Board had no legal authority to levy the surcharge. This
contention was not accepted by pointing out the agreement
with the Board being silent on this aspect, the Board was
justified in invoking its power under section 49(3).
11. In the second of the aforesaid decision, this Court,
while upholding the validity of section 49, approved the
condition imposed by the regulations framed by the Board,
which required a consumer to make security deposit, as under
clause VI of the Schedule to the 1948 Act, supply of energy
by the Board is to be made after a written contract is
executed with sufficient security. Another provision of the
Act noted by the Court also permitted Board to require any
consumer to deposit security for payment of the monthly
energy bills. The non-payment of interest by the Board on
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
the deposit made was approved as none of the concerned
statutes created such an obligation.
12. Thus, these two decisions do not advance the case of the
Board qua the validity of the notification (except that
different tariffs could have been charged from different
industrial concerns, which, as per the High Court, however,
could not have been done) because in those cases the Board
had done nothing against the terms and conditions on which
it had agreed to supply energy, which the Board is said to
be doing hereby force of the notification.
13. This takes us to the main objection of the High Court to
the notification which is that it is inconsistent with the
terms and conditions of the agreement entered into between
the Board and the consumers. The submission of Shri Sibal on
this facet of the case was that clause 11 of the agreement,
read with clause 14, permits the Board to vary the
conditions which find place in clauses 3(c) and 6, which are
the two clauses said to have been violated by the
notification.
14. To appreciate this submission, let the aforesaid four
cclauses be noted. These read as below:
"3.(a) *
(b) *
(c) Subject to clause 6 appearing
hereinafter in the agreement, in
the event of any meter ceasing to
register or found to be defective
or the Board’s employee having been
unable to read meter. the reading
during the period of each cessation
or defective registration or non-
reading shall be based on the
average reading of the previous
three months, in which the meter
ran correctly and reading was duly
recorded. In taking such average
due regard shall be given to the
conditions of working month under
dispute and during the previous
three months. In case of failure to
take reading by the Board’s
employee, proper adjustment shall
be made when actual reading is
taken next.
6. Should the consumer dispute the
accuracy of any meter not being his
own property, the consumer may upon
giving notice and paying the
prescribed fee have the meter
officially tested by the Electric
Inspector, Government of Bihar, in
accordance with sub-section (6) of
Section 26 of the Indian
Electricity Act, 1910. In the event
of the meter being tested by the
Electric Inspector, Government of
Bihar, and found to be beyond the
limits of accuracy as prescribed in
the Indian Electricity Rules, 1956,
or any other statutory modification
thereof as may be in force from
time to time the testing fee will
be refunded and the amount in
respect of the meter readings of
three months prior to the month in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
which the dispute has arisen or of
three months as provided in clause
3(c) above, as the case may be,
will be adjusted in accordance with
the result of the test taken, due
regard being paid to the conditions
of working during the month under
dispute and during the previous
three months.
11. This agreement shall be read
and construed as subject in all
respects to the provisions of the
Indian Electricity Act, 1910, rules
framed thereunder and the
Electricity (Supply) Act, 1948
together with rules, regulations
(if any) tariffs and terms and
conditions for supply cf
electricity framed and issued
thereunder and for the time being
in force as far as the same may
respectively be applicable and all
such provisions shall prevail in
case of any conflict or
inconsistency between them and the
terms and conditions of this
agreement.
14. The Board shall be at liberty
at any time to alter the demand
charges, energy charges including
fuel-surcharge and minimum
guarantee charges as set out in the
Schedule appended hereto and this
Schedule shall be deemed as having
been automatically revised with
effect from the date the Board
enforces new tariff for the
consumer."
15. Shri Ganguli, who addressed us on behalf some of the
respondents, urged orally, as well as in A submissions, that
the aforesaid clauses have to be read and construed
harmoniously. To this, it was added by Shri Sanyal,
appearing for other respondents, that clause 11 has not
mentioned about any "notification".
16. Before we advert to the effect produced by a combined
reading of the four clauses, it deserves to be pointed out
that the terms and conditions have sacrosanctity, in that
Rule 27 of the Indian Electricity Rules, 1956, framed by the
Central Electricity Board in exercise of power under section
37 of 1910 Act has, read with Annexure VI thereof, provided
the model conditions of supply which are required to be
adopted by the State Boards. It is on the basis of this
statutorily prescribed model, with suitable variations, that
energy had been supplied by the Board to the consumers. The
model conditions can be said to be akin to the model
Standing Orders prescribed by Industrial Employment
(Standing Orders) Act, 1946, which, when certified, become
part of the statutory terms and conditions of service
between the employer and employees and they govern the
relationship between the parties, as held in Workmen v.
Firestone Tyle & Rubber Co.Ltd., 1973 (1) SCC 813(832). We
are inclined to think that similar is the effect of terms
and conditions, on which a State Board supplies energy to
the consumers.
17. We may now see what clause 11 has provided. It has
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
stated that the provisions 1910 and 1948 Acts together with
the rules and regulations, if any, shall prevail, in case of
any conflict or inconsistency between them and the terms and
condition of the agreement. Nothing has been mentioned in
this clause about any notification issued by the Board; and
the agreements at hand being earlier in point of time to the
impugned notification, we are of the view that the
stipulation made in the notification cannot override the
terms and conditions mentioned in clauses 3(c) and 6.
18. Clause 14 deals with alteration of various energy
charges and states that on the charges being altered, the
tariff shall become realisable accordingly. This clause has
dealt with : (1) demand charges: (2) energy charges; and (3)
minimum guarantee charges. The expression ’demand charges’
means minimum consumption guarantee charges. (See para 5 of
Ashok Soap Factory v. Municipal Corporation of Delhi, 1993
(2) SCC 37). A perusal of this para also shows that for big
consumers of electricity, there is two-part tariff system,
i.e. it is comprised of two charges : (1) minimum
consumption guarantee charges (called demand charges); and
(2) energy charges for actual amount of energy consumed. In
the Schedule to this present agreement a so, para 5(a) deals
with demand charge and 5(b) with energy charge. Rates of
each has also been mentioned. Clause 14 has empowered the
Board to alter rates of these charges.
19. In Ashok Soap Factory case, this Court dealt with the
power of the Board to alter the rate of demand charges
(which had been enhanced from Rs.40/- per KVA to Rs.340/-)
and the same was sustained, because valid reasons existed
for the enhancement (theft of electricity and defective
meters recording extremely low consumption causing loss of
huge revenue) and the particular clause in the agreement
(quoted in para 15) permitted increase in the rates.
20. Though in the case at hand, the motivating factor for
the issuance of the notification is similar to the one as
was in the aforementioned case, we don’t think if clause 14
can be pressed into service to sustain the notification, as
present is not a case of alteration of charges mentioned in
the clause; it really seeks to introduce an unknown mode of
charging for energy, which is not visualised by the
agreement entered into between the parties. This apart, a
harmonious reading of clauses 3(c), 6 and 14 would not
permit us to say that clause 14 has overridden what has been
provided in clauses 3(c) and 6.
21. This is not all, as it has been held by this Court in
M.P. Electricity Board vs. Bassantibai, 1988 (1) SCC 23,
that section 26(6) of the 1910 Act does not authorise the
Electricity Boards to issue any supplementary bill in
respect of the energy consumed during the pendency of the
dispute with an Electrical Inspector. We have mentioned
about this decision because pursuant to the notification,
the Board did submit supplementary bills to the respondent-
consumers. It seems to us that this action was really in
conflict with the statutory provision contained in section
26(6) of 1910 Act, as interpreted by this Court in
Basantibai’s case.
22. The only other point urged by Shri Sibal, which needs to
be dealt with, is relatable to the power of the Board under
section 26 of the 1948 Act. We do not think the provisions
of this section can assist the appellant Board in any way to
sustain the notification, as that section has only provided
that the Board shall have, in respect of the whole of any
State, all the powers and obligations of a licensee under
the 1910 Act. This section thus provides no shield to the
Board insofar as its present dispute with the respondents is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
concerned.
23. For the reasons aforesaid, we are constrained to dismiss
the appeals, much though we would have liked to lend our
support to the Board in its effort in effectively deal with
theft of electricity caused by manipulation of meters, which
is a known evil. Despite the laudable object which the Board
sought to achieve by issuing the notification, we are of the
view that the same has not been done in accordance with law.
24. The appeals are, therefore, dismissed, leaving the
parties to bear their own costs throughout.