Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 7
CASE NO.:
Appeal (civil) 2846 of 2006
PETITIONER:
Maharashtra Electricity Regulatory Commission
RESPONDENT:
Reliance Energy Ltd. & Ors.
DATE OF JUDGMENT: 14/08/2007
BENCH:
A.K.MATHUR & MARKANDEY KATJU
JUDGMENT:
J U D G M E N T
1. This appeal under Section 125 of the of the Electricity Act, 2003 (hereinafter
for short "the Act") is directed against the judgment and order dated 29th March,
2006 passed by the Appellate Tribunal for Electricity whereby the Appellate Tribunal
has allowed the appeals filed by the distribution companies and set aside the orders
passed by the Maharashtra Electricity Regulatory Commission (hereinafter for short
"The Commission") dated 23.2.2005. The Commission on 3.8.2004 addressed a notice
to all its licensees/distribution companies in Maharashtra and made an inquiry from
them with regard to raising of the bills by the said licensees/distribution companies on
the basis other than the actual meter reading for the relevant period, when large
variations in consumption were noticed, or for other reasons. The notice dated
3.8.2004 sent by the Commission to all its licensees/distribution companies reads as
under :-
"Several instances have come to the Commission’s notice of so-
called "amendment", "supplementary" or other such bills being
raised by some licensees to consumers, often several years later,
on a basis other than the actual meter reading for the relevant
period, when large variations in consumption are noticed, or for
other reasons. Computerised systems have sometimes been put
in place which generate such bills automatically.
Wide variations observed in recorded consumption
and other such apparent anomalies may be useful for
monitoring, checking/testing of meters and for taking corrective
action. However, billing on a basis other than recorded
consumption, and raising amended bills accordingly (often after
several years later, and without giving reasons), is not mandated
by law.
The electricity statutes (in the past, and at present)
provide inter alia that, in case of metered consumers, energy
consumption charges have to be billed on the basis of meter
readings. Moreover, the licensee, and not the consumer, is
responsible for maintaining, rectifying, or having such meters
replaced where necessary. Thus, no "amendment" bills of the
kind referred to above can be raised, and any additional billing
has to follow due process and the provision of law.
In the context of such "amendment" bills, I am
directed to ask that the billing practices followed be immediately
reviewed and brought into conformity with the statutory
provisions. An affidavit stating the corrective action taken
(including withdrawal of all such pending bills, and refund,
though adjustment in energy bills or otherwise, of amounts
received from consumers on or after 10.6.2003) may be
furnished by 3rd September, 2004."
2. In response to the said notice all the licensees/distribution companies in
Maharashtra made their respective submissions before the Commission explaining
under what circumstances the supplementary/amended bills were sent to the
consumers. They tried to justify raising of such bills and stated that the these bills
were rightly sent as they found that some time the meters were not registering proper
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 7
consumption and on that basis they tried to justify their action.
3. The Commission examined the matter in detail and vide its order dated
23.2.2005 in para 46 directed as under:-
"46. After considering all these factors and the
submissions made, the Commission directs that the
supplementary/amendment bills issued in the circumstances set
out at para 42 and 43 above from 10th June, 2003 (the date of
coming into force of EA, 2003) and upto notification of the
Supply Code.
a. should be withdrawn, if due meter testing has not been
done with the results intimated to the consumer.
b. any amounts collected should be refunded to the
concerned consumers (without interest considering the
earlier lack of clarity on this meter on the part of the
licensees);
c. where meters have been found to be defective upon
subsequent due testing (and the results intimated to the
consumer), the bills may be adjusted for upto 3 months
prior to the date of testing or meter replacement,
whichever is earlier, and any amounts recovered in
excess refunded without interest (in the case of ’stopped’
meters, the analogy of the Supply Code provisions should
be applied for assessment);
d. the above action should be completed by 30th May, 2005,
so as to give the licensees more than 3 months’ time in
view of the work likely to be involved;
e. compliance should be submitted on affidavit by 15th
June, 2005, with a list of consumers involved, and
certifying that no further action remains to be done in
terms of this Order."
By another order dated 23.8.2005 in the case of M/s. Prayas (Energy Group) Pune, the
Commission in para 45 directed as under :-
"45. Considering the foregoing, the Commission disposes
of Prayas’ petition with the following directions, which would
apply for the period from 1st June, 2004 (i.e. around 3 months
after the detailed Tariff Order dated 10th March, 2004, uptil
19th January, 2005 (following which the Supply code
Regulations were notified):
(a) no billing using past consumption or some related
’average’ basis should be resorted to for more than a
period of 3 months. (where average billing has been
continuing for more than that period just prior to 1st
June, 2004, then it cannot be continued from that date.
In case average billing has been resorted to for, say, 2
months prior to that, it can be continued only for upto
one month more). During that period 3 months, the
meter should have been tested/replaced, with the results
intimated to the consumer, and appropriate bill
adjustments carried out thereafter (where such average
billing is being done on the basis of presumed faulty
meter, and where defectiveness of the meter has
accordingly been established). If due and timely
diligence has not been exercised by the licensee, he
cannot claim the right to continue billing on a
presumptive, average basis. The same principle will
apply to all other situations in which such ’average’
billing has been resorted to, except in cases where the
meter is not accessible. (However, the Commission notes
that, in the case of locked/inaccesible meters, the
licensees have recourse to the remedies provided under
Section 163 of EA, 2003, and it would be expected that
MSEB would exercise it sooner rather than later).
(b) In all cases where bills have been raised and/or
recoveries made which are not in accordance with (a)
above, the bills should be withdrawn and/or amounts
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 7
refunded to the consumers, through energy bills or other
means, as may be relevant, by 30th November, 2005,
with interest at the same rate as payable by consumers to
MSEB for delayed payments."
4. Aggrieved against both these orders, the matter was taken up in appeal before
the Appellate Authority. The Appellate Authority by the impugned order dated 29th
March, 2006 set aside the orders passed by the Commission and directed that each
consumer should approach the forum created under Section 42(5) of the Act for the
individual grievances. 5. Aggrieved against the order dated 29.3.2006 passed
by the Appellate Authority, the present appeal has been filed under Section 125 of the
Act.
6. We have heard learned counsel for the parties and perused the record.
7. Learned counsel for the appellant-Commission has submitted before us that
the Commission has the power to give a general direction to its licensees/distribution
companies and he also submitted that in exercise of the power under the Act, the
Commission was competent to issue the aforesaid direction. As against this, the
learned counsel appearing for the respondent-licensees/distribution companies
submitted that the Commission has no power to issue a direction like the one issued in
the present case and entertain individual complaints and direct refund of the whole
amount by a blanket order.
8. The question before us is : what is the power of the Commission and to what
extent the Commission can issue directions. Suffice it to say that the Regulatory
Commission was constituted under the Electricity Act, 2003. The Act was a new
enactment which was promulgated by superseding the Indian Electricity Act, 1910 and
the Electricity Supply Act, 1948. The Statement of Objects and Reasons of the Act
which have been summarized in the Preamble, reads as under:-
"An Act to consolidate the laws relating to generation,
transmission, distribution, trading and use of electricity and
generally for taking measures conducive to development of
electricity industry, promoting competition therein, protecting
interest of consumers and supply of electricity to all areas,
rationalisation of electricity tariff, ensuring transparent policies
regarding subsidies, promotion of efficient and environmentally
benign policies, constitution of Central Electricity Authority,
Regulatory Commissions and establishment of Appellate
Tribunal and for matters connected therewith or incidental
thereto."
"Appropriate Commission" as defined in Section 2(4) of the Act means the
"Central Regulatory Commission referred to in sub-section (1) of Section 76 or the
State Regulatory Commission referred to in Section 82 or the Joint Commission
referred to in Section 83, as the case may be". In exercise of its power under Section
82 of the Act, the State of Maharashtra constituted the Maharashtra Electricity
Regulatory Commission. The Commission exercises all the powers which are
enumerated in the Act. Though various provisions were pointed out to us by learned
counsel for the parties, but Section 82 which is relevant for our purposes reads as
under :-
"82. Constitution of State Commission-(1) Every State
Government shall, within six months from the appointed date,
by notification, constitute for the purposes of this Act, a
Commission for the State to be known as the (name of the State)
Electricity Regulatory Commission :
Provided that the State Electricity Regulatory
Commission, established by a State Government under Section
17 of the Electricity Regulatory Commissions Act, 1998 (14 of
1998) and the enactments specified in the Schedule, and
functioning as such immediately before the appointed date shall
be the State Commission for the purposes of this Act and the
Chairperson, Members, Secretary, and officers and other
employees thereof shall continue to hold office on the same
terms and conditions on which they were appointed under those
Acts :
Provided further that the Chairperson and other
Members of the State Commission, appointed, before the
commencement of this Act, under the Electricity Regulatory
Commissions Act, 1998 (14 of 1998) or under the enactments
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 7
specified in the Schedule, may, on the recommendations of the
Selection Committee constituted under sub-section (1) of
Section 85, be allowed to opt for the terms and conditions under
this Act by the concerned State Government.
(2) The State Commission shall be a body corporate by
the name aforesaid, having perpetual succession and a common
seal, with power to acquire, hold and dispose of property, both
movable and immovable, and to contract and shall, by the said
name, sue or be sued.
(3) The head office of the State Commission shall be at
such place as the State Government may, by notification,
specify.
(4) The State Commission shall consist of not more than
three Members, including the Chairperson.
(5) The Chairperson and Members of the State
Commission shall be appointed by the State Government on the
recommendation of a Selection Committee referred to in
Section 85."
9. We are not concerned with the provisions of appointment of Members of the
Commission as they are dealt with by Sections 84 and 85 of the Act. Section 86 deals
with the functions of the Commission and is relevant for our purposes. For ready
reference, the same is reproduced hereunder.
"86. Functions of State Commission:- (1) The State Commission
shall discharge the following functions, namely :-
(a) determine the tariff for generation, supply, transmission
and wheeling of electricity, wholesale, bulk or retail, as
the case may be, withing the State:
Provided that where open access has been permitted to a
category of consumers under section 42, the State
Commission shall determine only the wheeling charges
and surcharge thereon, if any, for the said category of
consumers;
(b) regulate electricity purchase and procurement process of
distribution of licensees including the price at which
electricity shall be procured from the generating
companies or licensees or from other sources through
agreements for purchase of power for distribution and
supply within the State;
(c) facilitate intra-State transmission and wheeling of
electricity;
(d) issue licences to persons seeking to act as transmission
licensees, distribution licensees and electricity traders
with respect to their operations within the State;
(e) promote congeneration and generation of electricity
from renewable sources of energy by providing suitable
measures for connectivity with the grid and sale of
electricity to any person, and also specify, for purchase of
electricity from such sources, a percentage of the total
consumption of electricity in the area of a distribution
licensee;
(f) adjudicate upon the disputes between the licensees and
generating companies and to refer any dispute for
arbitration;
(g) levy fee for the purposes of the Act;
(h) specify State Grid Code consistent with the Grid Code
specified under clause (h) of sub-section (1) of Section 79;
(i) specify or enforce standards with respect to quality,
continuity and reliability of service by licensees;
(j) fix the trading margin in the intra-State trading of
electricity, if considered, necessary;
(k) discharge such other functions as may be assigned to it
under this Act.
(2) The State Commission shall advise the State Government
on all or any of the following matters, namely :-
(i) promotion of competition, efficiency and economy in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 7
activities of the electricity industry;
(ii) promotion of investment in electricity industry;
(iii)reorganisation and restructuring of electricity industry in
the State;
(iv) matters concerning generation, transmission,
distribution and trading of electricity or any other
matter referred to the State Commission by that
Government;
(3) The State Commission shall ensure transparency while
exercising its powers and discharging its functions.
(4) In discharge of its functions, the State Commission shall
be guided by the National Electricity Policy, National
Electricity Plan and Tariff Policy published under section
3.
10. Thus, from the above provision it is clear that the primary purpose of the
Commission is to determine tariff for generation, supply, transmission of electricity
etc. and to regulate the electricity purchase and procurement process of distribution
licensees, to facilitate intra-State transmission, to promote congeneration and
generation of electricity from renewable sources of energy, to adjudicate upon the
disputes between the licensees and generation companies and to refer any dispute for
arbitration, to levy fee for the purposes of this Act, specify State Grade Code
consistent with the Grid Code specified under clause (h) of sub-section (1) of Section
79. Sub-Section (2) of Section 86 also empowers the State Commission to advise the
State Government on any of the matters including promotion of competition,
efficiency, matters concerning generation, transmission, distribution and trading of
electricity etc. Sub-Section (3) provides that the Commission shall ensure
transparency while exercising its powers and discharging its functions. Sub-section (4)
provides that in discharge of its functions the Commission shall be guided by the
National Electricity Policy, National Electricity Plan and Tariff Policy published under
Section 3.
11. We are not going into other questions as to how licenses were granted to all
these utilities, i.e., various distribution companies. It is not necessary for us to go int
o
these questions as in the present case, we are primarily concerned to decide the powers
of the Commission and to what extent it can issue directions and whether the direction
given by the Commission in the present case is sustainable or not.
12. It may be noted from a perusal of Section 86(1)(f) of the Act that the State
Government has only power to adjudicate upon disputes between licensees and
generating companies. It follows that the Commission cannot adjudicate disputes
relating to grievances of individual consumers. The adjudicatory function of the
Commission is thus limited to the matter prescribed in Section 86(1)(f).
13. Section 14 of the Act provides for grant of licence; Section 16 provides for
conditions of licence; Section 61 lays down the tariff regulations and Section 62
provides for determination of tariff. The Commission under Section 94 has civil
powers also and under Section 96 it has power of entry and seizure. Under Section 126
the Commission has the power to investigate and make assessment. Section 127
provides for an appeal to the appellate authority. Under Section 128 the Commission
can make investigation of certain matters where it is satisfied that the licensee has
failed to comply with any of the conditions of licence or failed to comply with any of the
provisions of the Act or the rules and regulations made thereunder. Sub-Section (6) of
Section 128 empowers the Commission to take any action against the
licensee/generating company. Sub-section (6) reads as under :-
(6) On receipt of any report under sub-section (1) or
sub-section (5), the Appropriate Commission may, after giving
such opportunity to the licensee or generating company, as the
case may be, to make a representation in connection with the
report as in the opinion of the Appropriate Commission seems
reasonable, by order in writing :-
(a) require the licensee or the generating company to
take such action in respect of any matter arising
out of the report as the Appropriate Commission
may think fit; or
(b) cancel the licence; or
(c) direct the generating company to cease to carry
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 7
on the business of generation of electricity.
Section 142 of the Act provides for punishment for non-compliance of directions
issued by the Commission and Section 143 empowers the Commission to adjudicate
after holding an inquiry in such manner as may be prescribed by the Government.
Section 181 empowers the Commission to make regulations.
14. A comprehensive reading of all these provisions leaves no manner of doubt
that the Commission is empowered with all powers right from granting licence and
laying down the conditions of licence and to frame regulations and to see that the same
are properly enforced and also power to enforce the conditions of licence under sub-
section (6) of Section 128.
15. Thus, insofar as the first contention of the learned counsel for the respondents
that the Commission has no power is concerned, we are of the view that the same is
wrong. In this behalf the provisions of The Electricity Act, 2003 are quite clear and
categoric and Section 128(6) empowers the Commission to get the conditions of licence
enforced. But the question is whether the said power under Section 128(6) has been
rightly exercised by the Commission or not. After clearing the first hurdle, that the
Commission has power to issue directions, we shall now examine whether the direction
given by the Commission in the present case is correct or not.
16. When the Commission received a spate of complaints from consumers against
its licensees/distribution companies that they are arbitrarily issuing
supplementary/amended bills and charging excess amounts for supply of electricity, it
felt persuaded to invoke its general power to supervise the licensees/distribution
companies and in that connection issued notice dated 3.8.2004. There can be no
manner of doubt that the Commission has full power to pull up any of its licensee or
distribution company to see that the rules and regulations laid down by the
Commission are properly complied with. After all, it is the duty of the Commission
under Sections 45(5), 55(2), 57, 62, 86, 128, 129, 181 and other provisions of the Act to
ensure that the public is not harassed.
17. In exercise of this general power notice dated 3.8.2004 was issued when mass
scale supplementary/amended bills were issued to the consumers. When these
consumers approached the Commission, the Commission directed its licensees to
immediately review their billing policies and bring the same in conformity with the
statutory provisions of the Act. The Commission did not get an investigation made
under Section 128(1) which it could have done, and without that, and without getting a
report under Section 128(5) it passed an order directing refund of the amounts
collected by the licensees/distribution companies, which in our opinion was not
permissible, since such a direction could, if at all, be given after getting a report of the
investigation agency. The Commission could have made an investigation and got a
report from the investigation agency and on that basis directions could have been
given. However, that was not done. In these circumstances, in our opinion, the view
taken by the Appellate Authority in the impugned order to that extent is correct that
the individual consumers should have approached the appropriate forum under
Section 42(5) of the Act.
18. Thus while we hold that the Commission has power to issue a general direction
to licencees that they should abide by conditions of the licence issued by them and
charge only as per the tariff fixed under the Act so that the public at large should not
be harassed, we are of the opinion that so far as the blanket direction given by the
Commission for refunding the entire amount without making a proper investigation
whether the issue of supplementary/amended bills was really warranted in every case
or not is unsustainable. Here the Commission has gone beyond its jurisdiction. After
all the distribution/ generating companies have to incur expenses for
generation/distribution of power, and we cannot at the same time give license to the
consumers to commit theft of electricity or to be benefited by improper functioning of
the meter to the disadvantage of the distribution/generating company. Thus, keeping
in view the equity of both the parties, we think it will be proper for us to direct that all
the licensees/distribution companies in the State of Maharashtra issue a general public
notice in two daily newspapers having wide circulation in the State, one English
newspaper and one in vernacular language. The notice shall state that whoever feels
aggrieved by the supplementary/amended bill, he/she can approach the
licensee/distribution company for redressal of their grievance within a period of three
months from the date of publication of the notice. In our view, that would meet the
ends of justice instead of passing a blanket order as given by the Commission for
refunding the money charged by the licensees/distribution companies by issuing
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 7
supplementary/amended bills. The individual consumers may make a grievance
before the licensee/distribution company that they have not consumed the electricity
for which they are charged or that the meter reading was not proper or that they have
been excessively charged for the power which they have not actually consumed.
Therefore, we direct that all the licensees/distribution companies shall issue a public
notice in two daily newspapers having wide circulation in the State of Maharashtra,
one in English language and the other in vernacular language requiring their
respective consumers to make their representations for redressal of their grievances in
respect of the supplementary/amended bills. The licensees/distribution companies shall
decide the individual cases received by them after giving a fair opportunity of hearing
to the consumers. The consumers who still feel not satisfied with the order passed by
the licensees/distribution companies can approach the appropriate forum constituted
under Section 42(5) of the Act and, if still not satisfied, with the order passed by the
appropriate forum to approach the Ombudsman under Section 42(6) of the Act.
Accordingly, we hold that while the Commission had a power to issue general
directions to prevent harassment to the public at large by its licensees/distribution
companies, but a blanket direction to refund the amounts collected by the
licensees/distribution companies which has been given by the Commission was not
warranted.
19. Although, the Appellate Authority has set aside the order passed by the
Commission and issued a direction that the individual consumers may approach the
appropriate orders under Sections 42(5) and (6) we are not interfering with that
direction, but we direct that before that the licensees/distribution companies shall hear
the parties as directed hereinabove and decide whether the supplementary/amended
bills issued by them are proper or not.
20. In view of the above discussion, this appeal stands disposed of with no order as
to costs.