Full Judgment Text
REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 2523 OF 2008
Anand Singh & Anr. …Appellants
Versus
State of Uttar Pradesh & Ors. …Respondents
WITH
CIVIL APPEAL NO. 2517 OF 2008
CIVIL APPEAL NO. 2518 OF 2008
CIVIL APPEAL NO. 2519 OF 2008
CIVIL APPEAL NO. 2524 OF 2008
CIVIL APPEAL NO. 2525 OF 2008
CIVIL APPEAL NO. 2561 OF 2008
CIVIL APPEAL NO. 2731 OF 2008
CIVIL APPEAL NO. 2724 OF 2008
AND
CIVIL APPEAL NO. 2703 OF 2008
JUDGEMENT
R.M. Lodha, J.
Of this group of ten appeals, 7 arise from the
common judgment and order dated May 6, 2005 passed by the
High Court of Judicature at Allahabad. The remaining 3 appeals
arise from separate judgments (dated January 18, 2007, March
22, 2007 and April 25, 2007) and in one of them, the common
judgment and order dated May 6, 2005 was followed. As
identical questions are involved, these appeals were heard
together and are being disposed of by this common judgment.
2. The appellants in these appeals have small
holdings of land in Manbela, Hamidpur and Jangal Sikri etc.,
Pargana Haveli, District Gorakhpur in the State of Uttar
Pradesh. About 209.515 hectares of land including the land of
the appellants was sought to be acquired for the public
purpose, namely, for residential colony by the Gorakhpur
Development Authority (GDA), Gorakhpur. Vide public notices
issued under sub-section (1) of Section 4 of the Land
Acquisition Act, 1894 (for short, ‘the Act’) on November 22,
2003 and February 20, 2004 notifying for general information
that the land mentioned in the schedule appended thereto was
needed for the said public purpose. The provisions of sub-
section (1) of Section 17 of the Act were also invoked as in the
opinion of the Governor, the land proposed to be acquired was
urgently required. By use of power under Section 17(4) of the
Act, it was stated in the notification that Section 5A of the Act
shall not apply. These public notices are said to have been
published in the Official Gazette as well as other modes as
prescribed in Section 4.
3. On December 28, 2004, a declaration was made
under Section 6 of the Act that the land mentioned in the
schedule including the subject land was needed for public
purpose, namely, for the construction of residential colony
under a planned development scheme. By the said notification,
the Collector, Gorakhpur was also directed that on expiration of
15 days from the publication of the notice under Section 9(1),
the possession of the land mentioned in the schedule may be
taken, although no award under Section 11 has been made.
4. The present appellants and the other tenure holders
whose land was sought to be acquired pursuant to the
aforesaid notifications, approached the High Court by filing writ
petitions wherein, inter alia, a plea was raised that there was no
justification to invoke urgency clause and there was no material
before the Government for dispensing with the enquiry under
Section 5A of the Act. They averred that structures and
buildings were existing on their respective holdings and even
otherwise they are entitled to release of their land from
acquisition.
5. The State Government as well as the GDA opposed
the writ petitions and justified invocation of urgency clause and
the dispensation of summary enquiry under Section 5A as the
land was required for providing residential and housing colony
for the lower income group, middle income group and higher
income group by the GDA.
6. The High Court by its common judgment and order
dated May 6, 2005 held that none of the grounds raised by the
petitioners in the writ petitions was sustainable and
consequently upheld the notifications under challenge. While
dealing with the aspect of existence of buildings on the subject
land and petitioners’ prayer for direction to the State
Government to consider deacquisition by exercising its power
under Section 48 of the Act, the Court observed that the
petitioners may approach the State Government for the
redressal of their grievance in accordance with law. As noticed
above, in one of the subsequent orders, the High Court has
followed the common judgment and order dated May 6, 2005.
7. Be it noticed here that prior to the issuance of the
notifications dated November 22, 2003/February 20, 2004
under Section 4(1) read with Sections 17(1) and 17(4) of the
Act, somewhere in the month of February, 2000, a Land
Selection Committee was constituted to identify the availability
of land for a housing colony in or around Gorakhpur. The
Committee so constituted made spot inspection in April, 2001
and proposed acquisition of land in nine villages including
Manbela, Jungle Sikri @ Khorabar, Khorabar @ Subba Bazar,
Salempur @ Mugalpur, Hamidpur etc. However, nothing further
was done as the tenure holders opposed the acquisition of their
land and the Commissioner, Gorakhpur by his order dated May
2, 2001 stayed proposal submitted by the Land Selection
Committee in public interest.
8. Mr. K.B. Sinha, learned senior counsel for the
appellants principally raised two-fold submission before us.
Firstly, learned senior counsel submitted that invocation of
urgency clause under Section 17(1) and dispensation of
summary enquiry for the public purpose, namely, ‘development
of residential colony’ were wholly unjustified. He contended
that such an act of the State was in colourable exercise of
power. He would submit that the development of residential
colony takes sufficiently long time and does not necessitate
dispensation with the enquiry and no exceptional circumstances
have been brought on record by the Government that may
justify exercise of such extraordinary power. Secondly, learned
senior counsel submitted that in view of the fact that the
appellants have constructed their residential houses much
before the issuance of impugned notifications, the State must
exercise its power under Section 48 and release their land from
acquisition. He would submit that the State Government has
adopted a policy of pick and choose inasmuch as some land
has been released from acquisition while the appellants’ land
has not been considered for being released.
9. Learned counsel for the other appellants adopted
the arguments of Mr. K.B. Sinha. Insofar as Civil Appeal No.
2703 of 2008 is concerned, learned counsel submitted that in
respect of the land under consideration in this appeal, a Degree
College is in existence and this aspect has been overlooked by
the Government while issuing impugned notifications.
10. Mr. Dinesh Dwivedi, learned senior counsel for the
State of Uttar Pradesh as well as Mr. Irshad Ahmad, learned
counsel for the GDA justified the impugned notifications and
submitted that the State Government has acted within its
competence and power in invoking urgency clause and
dispensation of enquiry under Section 5A for the public purpose
viz., development of residential colony since in Gorakhpur
housing was urgently required for various groups of the society.
They submitted that there is no impediment for the State
Government in invoking urgency clause for the public purpose
of housing. On behalf of the GDA, it was contended that many
steps have been taken in developing the land acquired under
the impugned notifications inasmuch as water line, electric line,
sewerage line, drainage etc. have been laid and roads
constructed. In the written arguments submitted by the GDA, it
has been stated that the total cost of development of the
acquired land is Rs. 8,85,14,000/- and out of which
5,28,00,000/- have already been spent and about 60% work
has already been completed. It has also been submitted by
the GDA that after the award was made, compensation amount
has been deposited and barring appellants and 6-7 other
persons, all land owners have accepted compensation. As
regards appellants’ land, it is stated that structures have been
put up subsequent to the issuance of impugned notifications.
11. Learned senior counsel and counsel for the parties
cited some decisions of this Court in support of their respective
submissions. We shall refer to them appropriately a little later.
12. In the light of the contentions of the parties, the
question for our consideration is as to whether the impugned
notifications dated November 22, 2003/February 20, 2004
invoking urgency clause and dispensation of enquiry under
Section 5A for the public purpose viz., ‘development of
residential colony’ are legal and valid and if the answer is in
negative, whether on the facts and in the circumstances, the
appellants are entitled to any relief.
13. Before we advert to the aforesaid question, it is
appropriate that we briefly notice the relevant provisions
contained in the Act. The Act was enacted for the acquisition of
land needed for public purposes and for companies and for
determining the amount of compensation to be made on such
acquisition. Section 4 makes a provision for publication of
preliminary notification notifying that land mentioned therein is
needed for a public purpose. It provides for the mode of
publication of such notification and empowers the authorized
officers to make survey and set out the boundaries of the land
proposed to be taken amongst other acts as provided in the
said Section. Section 5A confers a right on the person
interested in any land which has been notified under Section
4(1) as being needed for a public purpose or likely to be
needed for public purpose to object to the acquisition of the
land. It provides that the objector shall be provided an
opportunity of hearing and after hearing all such objections and
after making such further enquiry, the Collector may submit his
report to the appropriate government along with his
recommendations on the objections and the record of
proceedings. Section 6 provides for declaration of intended
acquisition in the mode prescribed thereunder. The declaration
made under Section 6 is conclusive evidence that the land is
needed for a public purpose and after making such declaration,
the appropriate government may acquire the land in the manner
provided in subsequent provisions. Section 6 also prescribes
time limit in making such declaration. Section 9 provides a
public notice to be given by the Collector stating that the
government intends to take possession of the land and that
claims to compensation for all interests in such land may be
made to him. As per Section 11, the Collector is required to
enquire into the objections that may be received from the
persons interested pursuant to the notice issued under Section
9 and determine the award of compensation, inter alia by
enquiring into the value of the land and the respective interests
of the persons claiming compensation. Section 11-A prescribes
the limitation for making an award under Section 11. Section 16
provides for taking possession of the land after the Collector
has made an award under Section 11. The special powers in
cases of urgency and unforeseen emergency are conferred
upon the government under Section 17. Sub-section (1) thereof
provides that in case of urgency the appropriate government
may direct the Collector to take possession of any land needed
for public purpose on expiration of fifteen days from the
publication of the notice mentioned in Section 9, although no
award has been made. Sub-section (2) confers power on the
appropriate government to acquire the immediate possession of
the land for the purposes specified thereunder in the cases of
unforeseen emergency. Sub-section (3A), however mandates
that before taking possession of any land under sub-section (1)
or sub-section (2), the Collector shall tender payment of 80% of
the compensation as estimated by him to the persons entitled
thereto and pay the said compensation to them unless
prevented by the contingencies under Section 31(2). Sub-
section (4) empowers the government to direct that the
provisions of Section 5A shall not apply, on its satisfaction that
the provisions contained in sub-section (1) or sub-section (2)
are applicable and a declaration may be made under Section 6
after the publication of the notification under Section 4(1).
Insofar as Uttar Pradesh is concerned, sub-section (1A) has
been inserted after sub-section (1) of Section 17 which provides
that the power to take possession under sub-section (1) may
also be exercised, inter alia, if the land is required for ‘planned
development’. Section 48 gives liberty to the government to
withdraw from acquisition of any land.
14. The matters involving invocation of urgency clause
and dispensation of the enquiry under Section 5A have come
up for consideration before this Court from time to time. In Raja
1
Anand Brahma Shah v. State of Uttar Pradesh and Ors. , this
Court observed that the opinion of the government formed
under Section 17(4) of the Act can be challenged as ultra vires
1
(1967) 1 SCR 373
in a court of law, if it could be shown that the government never
applied its mind to the matter or that the action of the
government is mala fide.
15. In case of Jage Ram and Ors. v. State of Haryana
2
and Ors. while considering the urgency provision contained in
Section 17, this Court held that merely because there was
some laxity at an earlier stage, it cannot be inferred that on the
date the notification was issued there was no urgency. It was
held that the conclusion of the government in a given case that
there was urgency is entitled to weight, if not conclusive.
16. A three-Judge Bench of this Court in Narayan
3
Govind Gavate and Ors. v. State of Maharashtra and Ors.
extensively considered Section 17 of the Act vis-à-vis extent of
judicial review. That was a case wherein the public purpose
recited in the notification was ‘development and utilization of
said land as a residential and industrial area’. This Court stated
the legal position as follows :
“ 37. We think that Section 17(4) cannot be read in
isolation from Section 4(1) and 5-A of the Act. The
immediate purpose of a notification under Section
4(1) of the Act is to enable those who may have any
objections to make to lodge them for purposes of an
enquiry under Section 5-A of the Act. It is true that,
2
(1971) 1 SCC 671
3
(1977) 1 SCC 133
although only 30 days from the notification under
Section 4(1) are given for the filing of these
objections under Section 5-A of the Act, yet,
sometimes the proceedings under Section 5-A are
unduly prolonged. But, considering the nature of the
objections which are capable of being successfully
taken under Section 5-A, it is difficult to see why the
summary enquiry should not be concluded quite
expeditiously. In view of the authorities of this Court,
the existence of what are prima facie public
purposes, such as the one present in the cases
before us, cannot be successfully challenged at all
by objectors. It is rare to find a case in which
objections to the validity of a public purpose of an
acquisition can even be stated in a form in which the
challenge could succeed. Indeed, questions relating
to validity of the notification on the ground of mala
fides do not seem to us to be ordinarily open in a
summary enquiry under Section 5-A of the Act.
Hence, there seems to us to be little difficulty in
completing enquiries contemplated by Section 5-A of
the Act very expeditiously.
38. Now, the purpose of Section 17(4) of the Act is,
obviously, not merely to confine action under it to
waste and arable land but also to situations in which
an inquiry under Section 5-A will serve no useful
purpose, or, for some overriding reason, it should be
dispensed with. The mind of the officer or authority
concerned has to be applied to the question whether
there is an urgency of such a nature that even the
summary proceedings under Section 5-A of the Act
should be eliminated. It is not just the existence of an
urgency but the need to dispense with an inquiry
under Section 5-A which has to be considered.
39. Section 17(2) deals with a case in which an
enquiry under Section 5-A of the Act could not
possibly serve any useful purpose. Sudden change
of the course of a river would leave no option if
essential communications have to be maintained. It
results in more or less indicating, by an operation of
natural physical forces beyond human control, what
land should be urgently taken possession of. Hence,
it offers no difficulty in applying Section 17(4) in
public interest. And, the particulars of what is
obviously to be done in public interest need not be
concealed when its validity is questioned in a Court
of justice. Other cases may raise questions involving
consideration of facts which are especially within the
knowledge of the authorities concerned. And, if they
do not discharge their special burden, imposed by
Section 106, Evidence Act, without even disclosing a
sufficient reason for their abstention from disclosure,
they have to take the consequences which flow from
the non-production of the best evidence which could
be produced on behalf of the State if its stand was
correct.
40. In the case before us, the public purpose
indicated is the development of an area for industrial
and residential purposes. This, in itself, on the face
of it, does not call for any such action, barring
exceptional circumstances, as to make immediate
possession, without holding even a summary enquiry
under Section 5-A of the Act, imperative. On the
other hand, such schemes generally take sufficient
period of time to enable at least summary inquiries
under Section 5-A of the Act to be completed without
any impediment whatsoever to the execution of the
scheme. Therefore, the very statement of the public
purpose for which the land was to be acquired
indicated the absence of such urgency, on the
apparent facts of the case, as to require the
elimination of an enquiry under Section 5-A of the
Act.
41. Again, the uniform and set recital of a formula,
like a ritual or mantra, apparently applied
mechanically to every case, itself indicated that the
mind of the Commissioner concerned was only
applied to the question whether the land was waste
or arable and whether its acquisition is urgently
needed. Nothing beyond that seems to have been
considered. The recital itself shows that the mind of
the Commissioner was not applied at all to the
question whether the urgency is of such a nature as
to require elimination of the enquiry under Section 5-
A of the Act. If it was, at least the notifications gave
no inkling of it at all. On the other hand, its literal
meaning was that nothing beyond matters stated
there were considered.
42. All schemes relating to development of industrial
and residential areas must be urgent in the context
of the country’s need for increased production and
more residential accommodation. Yet, the very
nature of such schemes of development does not
appear to demand such emergent action as to
eliminate summary enquiries under Section 5-A of
the Act. There is no indication whatsoever in the
affidavit filed on behalf of the State that the mind of
the Commissioner was applied at all to the question
whether it was a case necessitating the elimination
of the enquiry under Section 5-A of the Act. The
recitals in the notifications, on the other hand,
indicate that elimination of the enquiry under Section
5-A of the Act was treated as an automatic
consequence of the opinion formed on other matters.
The recital does not say at all that any opinion was
formed on the need to dispense with the enquiry
under Section 5-A of the Act. It is certainly a case in
which the recital was at least defective. The burden,
therefore, rested upon the State to remove the
defect, if possible, by evidence to show that some
exceptional circumstances which necessitated the
elimination of an enquiry under Section 5-A of the
Act and that the mind of the Commissioner was
applied to this essential question. It seems to us that
the High Court correctly applied the provisions of
Section 106 of the Evidence Act to place the burden
upon the State to prove those special circumstances,
although it also appears to us that the High Court
was not quite correct in stating its view in such a
manner as to make it appear that some part of the
initial burden of the petitioners under Sections 101
and 102 of the Evidence Act had been displaced by
the failure of the State to discharge its duty under
Section 106 of the Act. The correct way of putting it
would have been to say that the failure of the State
to produce the evidence of facts especially within the
knowledge of its officials, which rested upon it under
Section 106 of the Evidence Act, taken together with
the attendant facts and circumstances, including the
contents of recitals, had enabled the petitioners to
discharge their burden under Sections 101 and 102
of the Evidence Act.”
17. In State of Punjab and Anr. v. Gurdial Singh and
4
Ors. while dealing with the invocation of Section 17 of the Act
for the public purpose, namely, grain market, this Court stated
that compulsory taking of a man’s property is a serious matter
and the smaller the man the more serious the matter. This
Court observed that hearing the owner before depriving him is
both reasonable and pre-emptive of arbitrariness and denial of
this administrative fairness is constitutional anathema except
for good reasons. It was further observed that save in real
urgency where public interest does not brook even the
minimum time needed to give a hearing land acquisition
authorities should not, having regard to Articles 14 (and 19),
burke an enquiry under Section 17 of the Act.
18. In the case of Deepak Pahwa and Ors. v. Lt.
5
Governor of Delhi and Ors. , a three-Judge Bench of this Court
was concerned with the challenge to the notification issued
under Sections 4 and 17 of the Act for the public purpose viz.;
‘construction of a New Transmitting Station for the Delhi
4
(1980) 2 SCC 471
5
(1984) 4 SCC 308
2
Airport’. While noticing the decision of this Court in Jage Ram ,
the Court observed that very often the delay makes the problem
more and more acute and increases the urgency of the
necessity for acquisition. It was further observed that pre-
notification delay would not render the invocation of the urgency
provisions void.
19. In the case of State of U.P. v. Smt. Pista Devi and
6
Ors. , this Court was concerned with the question of urgency in
acquisition of large tract of land by the Meerut Development
Authority for its housing scheme with the object of providing
housing accommodation to the residents of Meerut city. The
notification under Section 4 read with Section 17(1) and (4) was
published in the U.P. Gazette on July 12, 1980 and the
declaration under Section 6 of the Act was issued on May 1,
1981. The possession of the land was taken and handed over
to the Meerut Development Authority in July 1982. Thereafter,
about 17 persons who owned in all about 40 acres of land out
of the total of about 412 acres acquired, filed writ petitions in
the High Court challenging the aforesaid notifications on the
ground that the action of the government in invoking Section
6
(1986) 4 SCC 251
17(1) of the Act and dispensing with the enquiry under Section
5A of the Act was not called for in the circumstances of the
case. The High Court after hearing the parties held that the
dispensation with the enquiry under Section 5A was invalid one
and, accordingly, quashed the notifications. Aggrieved by the
judgment of the High Court, the State of U.P. as well as Meerut
Development Authority preferred appeal before this Court by
special leave. This Court set aside the judgment of the High
Court. While doing so, this Court held thus :
“ 6. What was said by the learned Judge in the context
of provision of housing accommodation to Harijans is
equally true about the problem of providing housing
accommodation to all persons in the country today
having regard to the enormous growth of population in
the country. The observation made in the above
decision of the High Court of Andhra Pradesh is
quoted with approval by this Court in Deepak Pahwa
v. Lt. Governor of Delhi, (1984) 4 SCC 308, even
though in the above decision the Court found that it
was not necessary to say anything about the post-
notification delay. We are of the view that in the facts
and circumstances of this case the post-notification
delay of nearly one year is not by itself sufficient to
hold that the decision taken by the State Government
under Section 17(1) and (4) of the Act at the time of
the issue of the notification under Section 4(1) of the
Act was either improper or illegal.
7. It was next contended that in the large extent of
land acquired which was about 412 acres there were
some buildings here and there and so the acquisition
of those parts of the land on which buildings were
situated was unjustified since those portions were not
either waste or arable lands which could be dealt with
under Section 17(1) of the Act. This contention has
not been considered by the High Court. We do not,
however, find any substance in it. The government
was not acquiring any property which was
substantially covered by buildings. It acquired about
412 acres of land on the outskirts of Meerut city which
was described as arable land by the Collector. It may
be true that here and there were a few super-
structures. In a case of this nature where a large
extent of land is being acquired for planned
development of the urban area it would not be proper
to leave the small portions over which some super-
structures have been constructed out of the
development scheme. In such a situation where there
is real urgency it would be difficult to apply Section 5-
A of the Act in the case of few bits of land on which
some structures are standing and to exempt the rest
of the property from its application. Whether the land
in question is waste or arable land has to be judged
by looking at the general nature and condition of the
land. It is not necessary in this case to consider any
further the legality or the propriety of the application of
Section 17(1) of the Act to such portions of land
proposed to be acquired, on which super-structures
were standing because of the special provision which
is inserted as sub-section (1-A) of Section 17 of the
Act by the Land Acquisition (U.P. Amendment) Act
(22 of 1954) which reads thus:
“(1-A) The power to take possession under sub-
section (1) may also be exercised in the case of land
other than waste or arable land, where the land is
acquired for or in connection with sanitary
improvements of any kind or planned development.”
8. It is no doubt true that in the notification issued
under Section 4 of the Act while exempting the
application of Section 5-A of the Act to the
proceedings, the State Government had stated that
the land in question was arable land and it had not
specifically referred to sub-section (1-A) of Section 17
of the Act under which it could take possession of
land other than waste and arable land by applying the
urgency clause. The mere omission to refer expressly
Section 17(1-A) of the Act in the notification cannot be
considered to be fatal in this case as long as the
government had the power in that sub-section to take
lands other than waste and arable lands also by
invoking the urgency clause. Whenever power under
Section 17(1) is invoked the government
automatically becomes entitled to take possession of
land other than waste and arable lands by virtue of
sub-section (1-A) of Section 17 without further
declaration where the acquisition is for sanitary
improvement or planned development. In the present
case the acquisition is for planned development. We
do not, therefore find any substance in the above
contention.”
20. In Rajasthan Housing Board and Ors. v. Shri
7
Kishan and Ors. , a large extent of land was acquired for the
benefit of Rajasthan Housing Board. While dealing with the
provisions contained in Sections 17(4) and (1), 4 and 6 of
Rajasthan Land Acquisition Act, 1953 (the provisions being pari
materia to the provisions of the Act), this Court held that the
satisfaction under Section 17(4) is a subjective one and that so
long as there is material upon which the Government could
have formed the said satisfaction fairly, the Court would not
interfere nor would it examine the material as an appellate
authority. This Court noticed that in view of the time bound
programme stipulated by the lender (HUDCO) and a large
number of engineers and other subordinate staff for carrying
7
(1993) 2 SCC 84
out the said work having already been appointed, the
satisfaction of the State Government that holding an enquiry
under Section 5A would result in uncalled for delay
endangering the entire scheme and time schedule of the
Housing Board could not be faulted.
21. In Chameli Singh and Ors. v. State of U.P. and
8
Anr.. , a three-Judge Bench of this Court was seized with a
matter wherein acquisition of the land was for the public
purpose, namely, for providing ‘houses to Scheduled Castes’.
Dealing with a challenge to the opinion of urgency formed by
the appropriate government and its satisfaction to eliminate the
enquiry under Section 5A, this Court observed that the opinion
of the government is entitled to great weight unless it is vitiated
by mala fides or colourable exercise of power. Noticing the
6
earlier judgments of this Court, particularly, Pista Devi , Deepak
5 2 3
Pahwa , Jage Ram , Narayan Govind Gavate and Rajasthan
8
Housing Board , this Court said:
“ 14. What was said by Chinnappa Reddy, J. in the
context of provisions of housing accommodation to
Harijans is equally applied to the problem of providing
housing accommodation to all persons in the country
in State of U.P. v. Pista Devi , (1986) 4 SCC 251,
holding that today having regard to the enormous
growth of population, urgency clause for planned
8
(1996) 2 SCC 549
development in urban areas was upheld by a two-
Judge Bench. The ratio of Kasireddy Papaiah case,
AIR 1975 AP 269, was quoted with approval by a
three-Judge Bench in Deepak Pahwa v. Lt. Governor
of Delhi, (1984) 4 SCC 308 . The delay by the officials
was held to be not a ground to set at naught the
power to exercise urgency clause in both the above
decisions. It would thus be clear that housing
accommodation to the Dalits and Tribes is in acute
shortage and the State has undertaken as its
economic policy under planned expenditure to provide
shelter to them on a war footing, in compliance with
the constitutional obligation undertaken as a member
of the UNO to the resolutions referred to hereinbefore.
15. The question, therefore, is whether invocation of
urgency clause under Section 17(4) dispensing with
inquiry under Section 5-A is arbitrary or is
unwarranted for providing housing construction for the
poor. In Aflatoon v. Lt. Governor of Delhi, (1975) 4
SCC 285, a Constitution Bench of this Court had
upheld the exercise of the power by the State under
Section 17(4) dispensing with the inquiry under
Section 5-A for the planned development of Delhi. In
Pista Devi case this Court while considering the
legality of the exercise of the power under Section
17(4) exercised by the State Government dispensing
with the inquiry under Section 5-A for acquiring
housing accommodation for planned development of
Meerut, had held that providing housing
accommodation is national urgency of which court
should take judicial notice. The pre-notification and
post-notification delay caused by the officer
concerned does not create a cause to hold that there
is no urgency. Housing conditions of Dalits all over
the country continue to be miserable even till date and
is a fact of which courts are bound to take judicial
notice. The ratio of Deepak Pahwa case was
followed. In that case a three-Judge Bench of this
Court had upheld the notification issued under
Section 17(4), even though lapse of time of 8 years
had occurred due to inter-departmental discussions
before receiving the notification. That itself was
considered to be a ground to invoke urgency clause.
It was further held that delay on the part of the
lethargic officials to take further action in the matter of
acquisition was not sufficient to nullify the urgency
which existed at the time of the issuance of the
notification and to hold that there was never any
urgency. In Jage Ram v. State of Haryana, (1971) 1
SCC 671 , this Court upheld the exercise of the power
of urgency under Section 17(4) and had held that the
lethargy on the part of the officers at an early stage
was not relevant to decide whether on the day of the
notification there was urgency or not. Conclusion of
the Government that there was urgency, though not
conclusive, is entitled to create weight. In Deepak
Pahwa case this Court had held that very often
persons interested in the land proposed to be
acquired may make representations to the authorities
concerned against the proposed writ petition that is
bound to result in multiplicity of enquiries,
communications and discussions leading invariably to
delay in the execution of even urgent projects. Very
often delay makes the problem more and more acute
and increases urgency of the necessity for
acquisition. In Rajasthan Housing Board v. Shri
Kishan , (1993) 2 SCC 84, this Court had held that it
must be remembered that the satisfaction under
Section 17(4) is a subjective one and that so long as
there is material upon which Government could have
formed the said satisfaction fairly, the Court would not
interfere nor would it examine the material as an
appellate authority. In State of U.P. v. Keshav Prasad
Singh , (1995) 5 SCC 587, this Court had held that
the Government was entitled to exercise the power
under Section 17(4) invoking urgency clause and to
dispense with inquiry under Section 5-A when the
urgency was noticed on the facts available on record.
In Narayan Govind Gavate case a three-Judge Bench
of this Court had held that Section 17(4) cannot be
read in isolation from Section 4(1) and Section 5-A of
the Act. Although 30 days from the notification under
Section 4(1) are given for filing objections under
Section 5-A, inquiry thereunder unduly gets
prolonged. It is difficult to see why the summary
inquiry could not be completed quite expeditiously.
Nonetheless, this Court held the existence of prima
facie public purpose such as the one present in those
cases before the Court could not be successfully
challenged at all by the objectors. It further held that it
was open to the authority to take summary inquiry
under Section 5-A and to complete inquiry very
expeditiously. It was emphasised that:
“... The mind of the officer or authority concerned
has to be applied to the question whether there is
an urgency of such a nature that even the
summary proceedings under Section 5-A of the
Act should be eliminated. It is not just the
existence of an urgency but the need to dispense
with an inquiry under Section 5-A which has to be
considered.”
16. It would thus be seen that this Court emphasised
the holding of an inquiry on the facts peculiar to that
case. Very often the officials, due to apathy in
implementation of the policy and programmes of the
Government, themselves adopt dilatory tactics to
create cause for the owner of the land to challenge
the validity or legality of the exercise of the power to
defeat the urgency existing on the date of taking
decision under Section 17(4) to dispense with Section
5-A inquiry.
17. It is true that there was pre-notification and post-
notification delay on the part of the officers to finalise
and publish the notification. But those facts were
present before the Government when it invoked
urgency clause and dispensed with inquiry under
Section 5-A. As held by this Court, the delay by itself
accelerates the urgency: Larger the delay, greater be
the urgency. So long as the unhygienic conditions and
deplorable housing needs of Dalits, Tribes and the
poor are not solved or fulfilled, the urgency continues
to subsist. When the Government on the basis of the
material, constitutional and international obligation,
formed its opinion of urgency, the court, not being an
appellate forum, would not disturb the finding unless
the court conclusively finds the exercise of the power
mala fide. Providing house sites to the Dalits, Tribes
and the poor itself is a national problem and a
constitutional obligation. So long as the problem is not
solved and the need is not fulfilled, the urgency
continues to subsist. The State is expending money to
relieve the deplorable housing condition in which they
live by providing decent housing accommodation with
better sanitary conditions. The lethargy on the part of
the officers for pre and post-notification delay would
not render the exercise of the power to invoke
urgency clause invalid on that account.”
22. A three-Judge Bench of this Court in Meerut
9
Development Authority & Ors. v. Satbir Singh and Ors. held
that the acquisition for housing development is an urgent
purpose and exercise of power under Section 17(4) dispensing
with the enquiry under Section 5A is not invalid.
10
23. In Om Prakash and Anr. v. State of U.P. and Ors. ,
the question presented before this Court for consideration was,
inter alia, whether the State Government was justified in
invoking urgency clause under Section 17(1) and dispensing
with the enquiry under Section 5A for acquisition of the land for
residential and industrial purpose for the purposes of New
Okhla Industrial Development Authority (NOIDA). The argument
on behalf of the appellants therein was that there was no
relevant material with the appropriate government to enable it
to arrive at its subjective satisfaction about dispensing with the
enquiry under Section 5A in connection with the subject
9
(1996) 11 SCC 462
10
(1998) 6 SCC 1
acquisition and there was delay of more than one year in
issuance of declaration under Section 6 after issuance and
publication of notification under Section 4 read with Section 17
of the Act. This Court observed :
“ ……. Even that apart, if that was the urgency
suggested by NOIDA on 14-12-1989, we fail to
appreciate as to how the State authorities did not
respond to that proposal equally urgently and why
they issued notification under Section 4 read with
Section 17(4) after one year in January 1991. On this
aspect, no explanation whatsoever was furnished by
the respondent-State authorities before the High
Court. It is also interesting to note that even after
dispensing with inquiry under Section 5-A pursuant to
the exercise of powers under Section 17(4) on 5-1-
1991, Section 6 notification saw the light of day only
on 7-1-1992. If the urgency was of such a nature that
it could not brook the delay on account of Section 5-A
proceedings, it is difficult to appreciate as to why
Section 6 notification in the present case could be
issued only after one year from the issuance of
Section 4 notification. No explanation for this delay is
forthcoming on record. This also shows that according
to the State authorities, there was no real urgency
underlying dispensing with Section 5-A inquiry despite
NOIDA suggesting at the top of its voice about the
need for urgently acquiring the lands for the
development of Sector 43 and other sectors.”
Noticing the conflict in the decisions of this Court in Narayan
3 6
Govind Gavate and Pista Devi , the Bench said :
“20. It is no doubt true that the aforesaid decision of
the three-Judge Bench of this Court was explained by
a latter two-Judge Bench decision of this Court in
State of U.P. v. Pista Devi, (1986) 4 SCC 251, as
being confined to the fact situation in those days
when it was rendered. However, it is trite to note that
the latter Bench of two learned Judges of this Court
could not have laid down any legal proposition by way
of a ratio which was contrary to the earlier decision of
the three-Judge Bench in Narayan Govind Gavate . In
fact, both these decisions referred to the fact
situations in the light of which they were rendered.”
24. In the case of Union of India and Ors. v. Mukesh
11
Hans , a three-Judge Bench of this Court while dealing with the
interpretation of Section 17(4) of the Act and the procedure to
be followed by the appropriate government while dispensing
with the enquiry contemplated under Section 5A of the Act said:
31. Section 17(4) as noticed above, provides that in
cases where the appropriate Government has come
to the conclusion that there exists an urgency or
unforeseen emergency as required under sub-section
(1) or (2) of Section 17, it may direct that the
provisions of Section 5-A shall not apply and if such
direction is given then Section 5-A inquiry can be
dispensed with and a declaration may be made under
Section 6 on publication of Section 4(1) notification
and possession can be made.
32. A careful perusal of this provision which is an
exception to the normal mode of acquisition
contemplated under the Act shows that mere
existence of urgency or unforeseen emergency
though is a condition precedent for invoking Section
17(4), that by itself is not sufficient to direct the
dispensation of the Section 5-A inquiry. It requires an
opinion to be formed by the Government concerned
that along with the existence of such urgency or
unforeseen emergency there is also a need for
11
(2004) 8 SCC 14
dispensing with Section 5-A inquiry which indicates
that the legislature intended the appropriate
Government to apply its mind before dispensing with
Section 5-A inquiry. It also indicates that mere
existence of an urgency under Section 17(1) or
unforeseen emergency under Section 17(2) would not
by itself be sufficient for dispensing with Section 5-A
inquiry. If that was not the intention of the legislature
then the latter part of sub-section (4) of Section 17
would not have been necessary and the legislature in
Sections 17(1) and (2) itself could have incorporated
that in such situation of existence of urgency or
unforeseen emergency automatically Section 5-A
inquiry will be dispensed with. But then that is not the
language of the section which in our opinion requires
the appropriate Government to further consider the
need for dispensing with Section 5-A inquiry in spite
of the existence of unforeseen emergency. This
understanding of ours as to the requirement of an
application of mind by the appropriate Government
while dispensing with Section 5-A inquiry does not
mean that in each and every case when there is an
urgency contemplated under Section 17(1) and
unforeseen emergency contemplated under Section
17(2) exists that by itself would not contain the need
for dispensing with Section 5-A inquiry. It is possible
in a given case the urgency noticed by the
appropriate Government under Section 17(1) or the
unforeseen emergency under Section 17(2) itself may
be of such degree that it could require the appropriate
Government on that very basis to dispense with the
inquiry under Section 5-A but then there is a need for
application of mind by the appropriate Government
that such an urgency for dispensation of the Section
5-A inquiry is inherent in the two types of urgencies
contemplated under Sections 17(1) and (2) of the Act.
33. An argument was sought to be advanced on
behalf of the appellants that once the appropriate
Government comes to the conclusion that there is an
urgency or unforeseen emergency under Sections
17(1) and (2), the dispensation with inquiry under
Section 5-A becomes automatic and the same can be
done by a composite order meaning thereby that
there is no need for the appropriate Government to
separately apply its mind for any further emergency
for dispensation with an inquiry under Section 5-A.
We are unable to agree with the above argument
because sub-section (4) of Section 17 itself indicates
that the “Government may direct that the provisions of
Section 5-A shall not apply” (emphasis supplied)
which makes it clear that not in every case where the
appropriate Government has come to the conclusion
that there is urgency and under sub-section (1) or
unforeseen emergency under sub-section (2) of
Section 17, the Government will ipso facto have to
direct the dispensation of the inquiry. For this we do
find support from a judgment of this Court in the case
of Nandeshwar Prasad v. State of U.P. , (1964) 3 SCR
425, wherein considering the language of Section 17
of the Act which was then referable to waste or arable
land and the U.P. Amendment to the said section, this
Court held thus:
“It will be seen that Section 17(1) gives power to
the Government to direct the Collector, though no
award has been made under Section 11, to take
possession of any waste or arable land needed for
public purpose and such land thereupon vests
absolutely in the Government free from all
encumbrances. If action is taken under Section
17(1), taking possession and vesting which are
provided in Section 16 after the award under
Section 11 are accelerated and can take place
fifteen days after the publication of the notice
under Section 9 . Then comes Section 17(4) which
provides that in case of any land to which the
provisions of sub-section (1) are applicable, the
Government may direct that the provisions of
Section 5-A shall not apply and if it does so direct,
a declaration may be made under Section 6 in
respect of the land at any time after the publication
of the notification under Section 4(1). It will be
seen that it is not necessary even where the
Government makes a direction under Section
17(1) that it should also make a direction under
Section 17(4) . If the Government makes a
direction only under Section 17(1) the procedure
under Section 5-A would still have to be followed
before a notification under Section 6 is issued,
though after that procedure has been followed and
a notification under Section 6 is issued the
Collector gets the power to take possession of the
land after the notice under Section 9 without
waiting for the award and on such taking
possession the land shall vest absolutely in
Government free from all encumbrances. It is only
when the Government also makes a declaration
under Section 17(4) that it becomes unnecessary
to take action under Section 5-A and make a
report thereunder. It may be that generally where
an order is made under Section 17(1), an order
under Section 17(4) is also passed; but in law it is
not necessary that this should be so. It will also be
seen that under the Land Acquisition Act an order
under Section 17(1) or Section 17(4) can only be
passed with respect to waste or arable land and it
cannot be passed with respect to land which is not
waste or arable and on which buildings stand.”
(emphasis
supplied)
34. A careful reading of the above judgment shows
that this Court in the said Nandeshwar Prasad case
has also held that there should be an application of
mind to the facts of the case with special reference
to this concession of Section 5-A inquiry under the
Act.
35. At this stage, it is relevant to notice that the
limited right given to an owner/person interested
under Section 5-A of the Act to object to the
acquisition proceedings is not an empty formality and
is a substantive right, which can be taken away for
good and valid reason and within the limitations
prescribed under Section 17(4) of the Act. The object
and importance of Section 5-A inquiry was noticed
by this Court in the case of Munshi Singh v. Union of
India , (1973) 2 SCC 337, wherein this Court held
thus:
“ 7 . Section 5-A embodies a very just and
wholesome principle that a person whose
property is being or is intended to be acquired
should have a proper and reasonable
opportunity of persuading the authorities
concerned that acquisition of the property
belonging to that person should not be made.
... The legislature has, therefore, made
complete provisions for the persons interested
to file objections against the proposed
acquisition and for the disposal of their
objections. It is only in cases of urgency that
special powers have been conferred on the
appropriate Government to dispense with the
provisions of Section 5-A:”
36. It is clear from the above observation of this
Court that right of representation and hearing
contemplated under Section 5-A of the Act is a very
valuable right of a person whose property is sought
to be acquired and he should have appropriate and
reasonable opportunity of persuading the authorities
concerned that the acquisition of the property
belonging to that person should not be made.
Therefore, in our opinion, if the appropriate
Government decides to take away this minimal right
then its decision to do so must be based on
materials on record to support the same and bearing
in mind the object of Section 5-A.”
25. In Union of India and Ors. v. Krishan Lal Arneja and
12
Ors. , the issue under consideration before this Court related to
the validity of notification for the acquisition of the land for a
public purpose, inter alia, ‘housing of the government offices’
and ‘residential use of government servants’ invoking Section
17(1) and (4). This Court emphasized that failure to take timely
action for acquisition by the authorities cannot be a ground to
12
(2004) 8 SCC 453
invoke the urgency clause to the serious detriment to the right
of the land owner to raise objections to the acquisition under
4
Section 5A. It was observed that Gurdial Singh is not an
authority for the proposition that in the absence of material to
justify urgency clause, long delay in issuing the notification
could be ignored or condoned to uphold the validity of such
notification.
26. In Hindustan Petroleum Corporation Ltd. v. Darius
13
Shapur Chenai and Ors. , this Court observed that Section 5A
of the Act confers a valuable right in favour of a person whose
lands are sought to be acquired. It was further observed that
the Act is an expropriatory legislation and, therefore, its
provisions should be strictly construed as it deprives a person
of his land without consent.
27. This Court in the case of Mahadevappa Lachappa
14
Kinagi and Ors. v. State of Karnataka and Ors. posited that
Section 17 of the Act confers extraordinary powers on the
authorities under which it can dispense with the normal
procedure laid down under Section 5A of the Act in cases of
exceptional urgency and that such powers cannot be lightly
13
(2005) 7 SCC 627
14
(2008) 12 SCC 418
resorted to except in case of real urgency enabling the
government to take immediate possession of the land proposed
to be acquired for public purpose. That case related to the
acquisition of land for the rehabilitation of 145 families uprooted
because of commissioning of barrage of Bhima River. It was
held that the case indicated an exceptional case where
exceptional power under Section 17 could be invoked.
28. Now, two recent decisions of this Court need to be
15
noticed. In Babu Ram and Anr. v. State of Haryana and Anr. ,
this Court was concerned with the legality of the notification for
acquisition of land for construction of sewage treatment plant.
The appropriate government invoked its power under Section
17(2)(c) and by invoking its power under Section 17(4)
excluded the application of Section 5A of the Act. After referring
4
to few decisions of this Court, particularly, Gurdial Singh and
10
Om Prakash , it was observed that these decisions assign a
great deal of importance to the right of a citizen to file
objections under Section 5A of the Act and the fact that such
right was elevated to the status of a fundamental right is in itself
sufficient to indicate that great care had to be taken by the
15
(2009) 10 SCC 115
authorities before resorting to Section 17(4) of the Act and they
have to satisfy themselves that there was an urgency of such
nature which could brook no delay whatsoever. In another
case, viz.; Tika Ram and Ors. v. State of Uttar Pradesh and
16
Ors. , constitutional validity of the provisions of Sections 17(1),
17(1A), 17(3A), 17(4) and the proviso to Section 17(4) as
amended by U.P. Act 5 of 1991 was under challenge besides
the various other provisions of the Act. This Court overruled
the challenge to the constitutionality of the aforenoticed
provisions. As regards invocation of power under Section 17 of
the Act and doing away with Section 5A enquiry, it was held :
“ 115. While considering as to whether the
Government was justified in doing away with the
inquiry under Section 5-A, it must be noted that there
are no allegations of mala fides against the authority.
No evidence has been brought before the judgment
and the High Court has also commented on this. The
housing development and the planned developments
have been held to be the matters of great urgency by
the Court in Pista Devi case . In the present case we
have seen the judgment of the High Court which has
gone into the records and has recorded categorical
finding that there was sufficient material before the
State Government and the State Government has
objectively considered the issue of urgency. Even
before this Court, there were no allegations of mala
fides. A notice can be taken of the fact that all the
lands which were acquired ultimately came to be
utilised for the Scheme. We, therefore, reject the
16
(2009) 10 SCC 689
argument that there was no urgency to justify
dispensation of Section 5-A inquiry by applying the
urgency clause”.
29. `Eminent domain’ is right or power of a sovereign
State to appropriate the private property within the territorial
sovereignty to public uses or purposes. It is exercise of
strong arm of government to take property for public uses
without owner’s consent. It requires no constitutional
recognition; it is an attribute of sovereignty and essential to the
sovereign government. ( Words and Phrases, Permanent
Edition, Volume 14, 1952 (West Publishing Co .,).
30. The power of eminent domain, being inherent in the
government, is exercisable in the public interest, general
welfare and for public purpose. Acquisition of private property
by the State in the public interest or for public purpose is
nothing but an enforcement of the right of eminent domain. In
India, the Act provides directly for acquisition of particular
property for public purpose. Though right to property is no
longer fundamental right but Article 300A of the Constitution
mandates that no person shall be deprived of his property save
by authority of law. That Section 5A of the Act confers a
valuable right to an individual is beyond any doubt. As a matter
of fact, this Court has time and again reiterated that Section 5A
confers an important right in favour of a person whose land is
sought to be acquired. When the government proceeds for
compulsory acquisition of particular property for public purpose,
the only right that the owner or the person interested in the
property has, is to submit his objections within the prescribed
time under Section 5A of the Act and persuade the State
authorities to drop the acquisition of that particular land by
setting forth the reasons such as the unsuitability of the land for
the stated public purpose; the grave hardship that may be
caused to him by such expropriation, availability of alternative
land for achieving public purpose etc. Moreover, right
conferred on the owner or person interested to file objections to
the proposed acquisition is not only an important and valuable
right but also makes the provision for compulsory acquisition
just and in conformity with the fundamental principles of natural
justice. The exceptional and extraordinary power of doing away
with an enquiry under Section 5A in a case where possession
of the land is required urgently or in unforeseen emergency is
provided in Section 17 of the Act. Such power is not a routine
power and save circumstances warranting immediate
possession it should not be lightly invoked. The guideline is
inbuilt in Section 17 itself for exercise of the exceptional power
in dispensing with enquiry under Section 5A. Exceptional the
power, the more circumspect the government must be in its
exercise. The government obviously, therefore, has to apply its
mind before it dispenses with enquiry under Section 5A on the
aspect whether the urgency is of such a nature that justifies
elimination of summary enquiry under Section 5A. A repetition
of statutory phrase in the notification that the state government
is satisfied that the land specified in the notification is urgently
needed and provision contained in Section 5A shall not apply,
though may initially raise a presumption in favour of the
government that pre-requisite conditions for exercise of such
power have been satisfied, but such presumption may be
displaced by the circumstances themselves having no
reasonable nexus with the purpose for which power has been
exercised. Upon challenge being made to the use of power
under Section 17, the government must produce appropriate
material before the court that the opinion for dispensing with the
enquiry under Section 5A has been formed by the government
after due application of mind on the material placed before it. It
is true that power conferred upon the government under
Section 17 is administrative and its opinion is entitled to due
weight, but in a case where the opinion is formed regarding the
urgency based on considerations not germane to the purpose,
the judicial review of such administrative decision may become
necessary. As to in what circumstances the power of
emergency can be invoked are specified in Section 17(2) but
circumstances necessitating invocation of urgency under
Section 17(1) are not stated in the provision itself. Generally
speaking, the development of an area (for residential purposes)
or a planned development of city, takes many years if not
decades and, therefore, there is no reason why summary
enquiry as contemplated under Section 5A may not be held and
objections of land owners/persons interested may not be
considered. In many cases on general assumption, likely
delay in completion of enquiry under Section 5A is set up as a
reason for invocation of extraordinary power in dispensing with
the enquiry little realizing that an important and valuable right of
the person interested in the land is being taken away and with
some effort enquiry could always be completed expeditiously.
The special provision has been made in Section 17 to eliminate
enquiry under Section 5A in deserving and cases of real
urgency. The government has to apply its mind on the aspect
that urgency is of such nature that necessitates dispensation of
enquiry under Section 5A. We have already noticed few
decisions of this Court. There is conflict of view in the two
3
decisions of this Court viz.; Narayan Govind Gavate and
6 10
Pista Devi . In Om Prakash this Court held that decision in
6
Pista Devi must be confined to the fact situation in those days
when it was rendered and the two-Judge Bench could not have
laid down a proposition contrary to the decision in Narayan
3
Govind Gavate . We agree. As regards the issue whether pre-
notification and post-notification delay would render the
invocation of urgency power void, again the case law is not
consistent. The view of this Court has differed on this aspect
due to different fact-situation prevailing in those cases. In our
opinion such delay will have material bearing on the question of
invocation of urgency power, particularly in a situation where no
material has been placed by the appropriate government before
the court justifying that urgency was of such nature that
necessitated elimination of enquiry under Section 5A.
31. In a country as big as ours, the roof over head is a
distant dream for large number of people. The urban
development continues to be haphazard. There is no doubt
that planned development and housing are matters of priority in
developing nation. The question is as to whether in all cases of
‘planned development of the city’ or ‘for the development of
residential area’, the power of urgency may be invoked by the
government and even where such power is invoked, should the
enquiry contemplated under Section 5A be dispensed with
invariably. We do not think so. Whether `planned development
of city’ or `development of residential area’ cannot brook delay
of few months to complete the enquiry under Section 5A? In
our opinion, ordinarily it can. The government must, therefore,
do a balancing act and resort to the special power of urgency
under Section 17 in the matters of acquisition of land for the
public purpose viz.; ‘planned development of city’ or ‘for
development of residential area’ in exceptional situation. Use
of the power by the government under Section 17 for `planned
development of the city’ or `the development of residential area’
or for `housing’ must not be as a rule but by way of an
exception. Such exceptional situation may be for the public
purpose viz., rehabilitation of natural calamity affected persons;
rehabilitation of persons uprooted due to commissioning of dam
or housing for lower strata of the society urgently; rehabilitation
of persons affected by time bound projects, etc. The list is only
illustrative and not exhaustive. In any case, sans real urgency
and need for immediate possession of the land for carrying out
the stated purpose, heavy onus lies on the government to
justify exercise of such power. It must, therefore, be held that
the use of the power of urgency and dispensation of enquiry
under Section 5A by the government in a routine manner for the
‘planned development of city’ or ‘development of residential
area’ and thereby depriving the owner or person interested a
very valuable right under Section 5A may not meet the statutory
test nor could be readily sustained.
32. Adverting now to the facts of the present case, it
would be seen that somewhere in February, 2000, a Land
Selection Committee was constituted to identify the availability
of land for a housing colony by the GDA. In April, 2001, the
Committee so constituted inspected the site and proposed
acquisition of land in Village Manbela and few other villages but
nothing further was done as the tenure holders opposed the
acquisition of their land and the Commissioner, Gorakhpur in
public interest stayed proposal for acquisition. Abruptly the
notifications for the proposed acquisition were issued on
November 22, 2003/February 20, 2004 under Section 4 of the
Act. In these notifications urgency clause was invoked and the
enquiry under Section 5A was dispensed with. Then, for more
than one year nothing was done. It was only on December 28,
2004 that a declaration under Section 6 was made. If the
matter could hang on from April, 2001 to November 22,
2003/February 20, 2004 before the notifications under Section
4 were issued and for about a year thereafter in issuance of
declaration under Section 6, acquisition proceedings could
have been arranged in a manner so as to enable the land
owners and/or the interested persons to file their objections
under Section 5A within the prescribed time and complete the
enquiry expeditiously. It is true that insofar as Uttar Pradesh is
concerned, there is amendment in Section 17. Sub-section
(1A) enables the Government to take possession under sub-
section (1) of Section 17 if the land is required for public
purpose viz.; ‘planned development’. Yet for forming an opinion
that provisions of Section 5A shall not apply, the state
government must apply its mind that urgency is of such nature
warranting elimination of enquiry under Section 5A. Although
some correspondence between the authorities and the
government was placed before the High Court by the GDA, but
no material has been placed on record by the State
Government either before the High Court or before this Court
indicating the application of mind that the urgency was of such
nature which warranted elimination of the enquiry under Section
5A of the Act. It is interesting to note that GDA wanted the
subject land to be acquired because their land bank had no
land and they wanted land to keep the Authority running. If
profit-making and the sustenance of the Development Authority
was the motive, surely urgency was not of such nature that it
could brook no delay whatsoever. In the facts and
circumstances of the present case, therefore, the Government
has completely failed to justify the dispensation of an enquiry
under Section 5A by invoking Section 17(4). For this reason,
the impugned notifications to the extent they state that Section
5A shall not apply suffer from legal infirmity. The question,
then, arises whether at this distance of time, the acquisition
proceedings must be declared invalid and illegal. In the written
submissions of the GDA, it is stated that subsequent to the
declaration made under Section 6 of the Act in the month of
December, 2004, award has been made and out of the 400
land owners more than 370 have already received
compensation. It is also stated that out of the total cost of Rs.
8,85,14,000/- for development of the acquired land, an amount
of Rs. 5,28,00,000/- has already been spent by the GDA and
more than 60% of work has been completed. It, thus, seems
that barring the appellants and few others all other tenure
holders/land owners have accepted the `takings’ of their land.
It is too late in the day to undo what has already been done.
We are of the opinion, therefore, that in the peculiar facts and
circumstances of the case, the appellants are not entitled to any
relief although dispensation of enquiry under Section 5A was
not justified.
33. On behalf of the appellants, it was vehemently
argued that the government may be directed to release their
land from proposed acquisition. It was submitted by the
appellants that houses/structures and buildings (including
educational building) are existing on the subject land and as per
the policy framed by the State Government, the land deserves
to be exempted from acquisition. The submission of the
appellants has been countered by the respondents and in the
written submissions filed by the GDA, it is stated that the
houses/structures and buildings which are claimed to exist,
have been raised by the appellants subsequent to the
notification under Section 4(1) of the Act and, therefore, they
are not entitled to release of their land from acquisition. In our
view, since the existence of houses/structures and buildings as
on November 22, 2003/February 20, 2004 over the appellants’
land has been seriously disputed, it may not be appropriate to
issue any direction to the State Government, as prayed for by
the appellants, for release of their land from acquisition.
However, as the possession has not been taken, the interest of
justice would be subserved if the appellants are given liberty to
make representation to the State authorities under Section
48(1) of the Act for release of their land. We, accordingly, grant
liberty to the appellants to make appropriate representation to
the State Government and observe that if such representation
is made by the appellants within two months from today, the
State Government shall consider such representation in
accordance with law and in conformity with the State policy for
release of land under Section 48(1) without any discrimination
within three months from receipt of such representation.
34. In the result, these appeals fail and are dismissed,
subject to the liberty reserved to the appellants for making
representations under Section 48 (1) of the Act.
35. I.A. for impleadment is rejected and I.A. for
discharge of Advocate – Mr. S.C. Birla is allowed.
36. No order as to costs.
……………………J
(R.V. Raveendran)
…….……………..J
(R. M. Lodha)
New Delhi
July 28, 2010