Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
PETITIONER:
V.G. GEORGE
Vs.
RESPONDENT:
INDIAN RARE EARTHS LTD. SI ANR.
DATE OF JUDGMENT: 08/04/1999
BENCH:
S. Rajendra Babu., S. N. Phukan.
JUDGMENT:
S.N. PHUKAN, J
This appeal is directed against the common judgment
and order dated 25.05.1987 passed in M.F.A. No. 161 of
1986 and 781 of 1986 by the High Court of Kerala.
For the purpose of appreciating the points urged in
this appeal we may briefly state the facts.
The appellant herein, who is a mining contractor
entered into an agreement with respondent No. I namely
Indian Rare Earths Ltd. for mining, collection and supply
of raw-sand during the period from 1.6.1979 to 31.5.1980.
It was agreed between the parties that appellant would
supply 2,02,000 tonnes of raw-sand at the average rate of
920 tonnes per day. The appellant failed to supply entire
quantity and supplied only 1,72,489.24 tonnes. The disputes
between the parties were referred to the arbitrator, who has
been made a party in the present appeal namely respondent
No. 2.
Before the arbitrator the appellant claimed Rs.
24,02,272/under 10 heads along with interest. A counter
claim was also filed by respondent No. I for Rs.
3,29,648.99 paise alongwith interest . The arbitrator
framed as many as 51 issues and after recording his findings
a sum of Rs. 5,40,191.10 paise with interest @ 15% per
annum from 11.11.82 upto the date of decree was awarded in
favour of the appellant. The award was made a rule of the
Court on a petition filed by the appellant under Section 17
of the Arbitration Act, 1940 (for short the Act). The
respondent No. I also filed a petition under Section 30 of
the Act which was dismissed.
Two appeals were filed before the High Court and the
High Court by the common impugned judgment and order held
that there was legal misconduct on the part of the
arbitrator and accordingly set aside the award except the
finding that the present appellant was entitled to refund of
the earnest money deposited. Hence the present appeal.
We have heard Mr. T.L. Vishwanatha Iyer, Sr.
learned counsel for the appellant and Mr. G.B. Pai, Sr.
learned counsel for the respondents.
Before we enter into the contentions raised in the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
case in hand, we may refer to the decisions of this Court.
The case in hand it has to be stated that we are concerned
with Clause(a) of Section 30 of the Arbitration Act which
empowers the Court to set aside an award on the ground that
an arbitrator or umpire has misconducted himself or the
proceedings.
In State of Orissa and others Vs. M/s. Lall
Brothers 1988 (4) SCC 153 this Court inter alia held that an
award may be set aside on the ground of error on the face of
the it but an award is not invalid merely because by a
process of inference and argument it may be demonstrated
that the arbitrator has committed some mistake in arriving
at his conclusion and it is also not open to the Court to
speculate, where no reasons are given by the arbitrator, as
to what impelled him to arrive at his conclusions.
In State of Andhra Pradesh and others Vs. R.V.
Rayanim and others 1990(1) SCC 433 it was held that in
matter of challenging the award there are often two distinct
and different grounds - one is an error apparent on the face
of the record and the other is that the arbitrator has
exceeded his jurisdiction. In the latter case the Court can
look into the arbitration agreement but under the former it
cannot.
In Associated Engineering Co. Vs. Government of
Andhra Pradesh and Another 1991(4) SCC 93 it was held that
the arbitrator cannot act arbitrarily, irrationally,
capriciously or independently of the contract and his sole
function is to arbitrate in terms of the contract as his
authority is derived from the contract. It was also held
that if he has remained inside the parameters of the
contract and has construed the provisions of the contract,
his award cannot be interfered with unless he has given
reasons for the award disclosing an error apparent on the
face of it.
Thus, law is well settled that if the award is
non-speaking, the Court can look into the question as to
whether arbitrator has travelled beyond the scope of the
contract as he derives his jurisdiction from the contract
and if the arbitrator exceeds his jurisdiction the award can
be set aside. An award can also be set aside in case of
misconduct apparent on the face of the award. It can also
be interfered with if the arbitrator has given reasons for
the award disclosing an error apparent on the face of it.
Coming to the present appeal we find that in the
impugned award the arbitrator has stated the case of the
parties, issues framed by him, his findings on each issue
and the amount awarded. We may also state here that in the
counter affidavit dated 23rd May, 1983 filed by the present
appellant before the learned sub-Judge it had been clearly
stated that the contract is evidenced by three integrated
documents namely: (i) Tender dated 3.5.79 (ii) Work order
dated 15.5.79 and (iii) Agreement dated 24.3.79.
Out of claims under 10 heads the arbitrator awarded
amount under claims nos. 3 & 9 of the appellant. Out of 51
issues framed by the arbitrator, issues nos. 15 to 18 were
in respect of claim no. 3 and issues nos. 31 to 37 were in
respect of claim no. 9. We quote below issues nos. 15 to
18 in respect of claim no. 3:
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
"15 - Whether six acres alone out of the mining area covered
by the tender from were available for mining on account of
obstruction of kudikidappukars, ex-workers of Associated
Minerals Co. Ltd. and local public as alleged by claimant
in paragraph 14 of State of of claim?
16 - Whether it was respondent’s duty to see that the entire
extent of mining area detailed in the tender form was
available for mining and that the mining could be carried
out without hindrance and respondent failed to discharge its
duty?
Or
Whether it was claimant’s responsibility to settle all
problems and objections which arose in the course of mining
work?
17 - Whether claimant suffered loss as mentioned in
paragraph 14 of the State of Claim?
18 - Whether respondent is liable to make good the loss
mentioned in issue No. 17 and if so, to what extent?"
In respect of the above issues the arbitrator has
given his findings which are as follows:-
"15- The allegation that six acres of land alone out of the
mining area covered by the tender form was available for
mining is not correct. In 243 acres of land covered by the
tender form out of which 92 acres belonged to respondent,
more than necessary area sufficient to mine and supply the
contract quantity of 2,00,000 to 2,20,000 MT of raw sand was
actually available for mining, but, on some days in April
and except on one day, during the whole month of May 1980,
mining of raw sand even in the available area and supply of
raw sand from there were not possible, on some days
partially and on other days wholly, on account of
obstruction by kudikidappukars and local public.
16 - Claimant’s right under the contract was purely
personal, it did not amount to an interest in the 243 acres
of land covered by the contract and he could not sue
trangers in his own name in respect of that land, it was his
responsibility to settle all problems and objections which
arose in the course of the mining work between him and his
mining workers, but not with strangers like kudikidappukars
and local public who claimed either rights in the land or
rights and privileges against the respondent, and it was
respondent’s duty to see that the entire extent of mining
area detailed in the tender form was available for mining
and mining operations could be carried on there quety and
without hindrance, and whenever complaint regarding
obstruction was received respondent tried to discharge that
duty by appealing to public authorities for help, but
without success.
17-18 - Claimant sufferred loss to the extent of Rs.
2,81,461.26 and respondent is liable to make good that
loss."
The learned counsel for the respondent has brought
to our notice Clause (c) of the tender notice which forms
part of the contract between the parties. Clause(c) of the
tender notice is stated as follows:
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
"(c) - The beach and inland deposits mentioned in Block Nos.
2,4 and 6 may or may not be situated in Company’s lands and
hence it shall be the responsibility of the Contractor to
obtain the consent of the owners in whose registered
holdings the beach or inland deposits appear, before the
Contractor begins to collect the sea washings or inland
deposits as the case may be. As Indian Rare Earths Limited
will not be responsible for the payment of any compensation
to any individual on account of any claims resulting from
such scrapping of sea washings or removal of inland
deposits, it shall again be the responsibility of the
Contractor to enter into agreements with the owners of
registered holdings whose lands the Contractor may be
required to utilise for the purpose of his successful
execution of this contract, and the Company will not in any
manner be responsible or liable for all or any of the claims
for compensation by the said land owners."
It has been urged on behalf of the appellant that as
the award is non-speaking one the High Court erred in law in
going into the facts of the case. On the other hand it has
been urged on behalf of the respondents that the present
award cannot be said to be a non-speaking one as the
findings of the arbitrator on each issue form part of the
award.
As stated above the award contains not only the sum
awarded but also the case of the parties, issues framed,
findings on each issue, therefore, we hold that the findings
of the arbitrator on the issues are the part of the award
and the court can look into the findings.
The arbitrator has come to the findings that the
entire mining area covered with tender was made available to
the appellant but according to the arbitrator mining was not
possible in some days in the month of April ,1980 and whole
month of May, 1980 on account of obstructions by
kudikidappukars And local public. The above finding of the
arbitrator is in respect of the issue No. 15 which forms
part of the award. While awarding the amount the arbitrator
did not take note of the above Clause (c) of the tender
notice which is a part of the agreement and under which the
respondent would not be liable for such obstruction.
Therefore, we hold that the amount awarded under Claim No.
3 is beyond the scope of the agreement entered into between
the parties and, therefore, the awarded amount in respect of
Claim No. 3 cannot be sustained.
Claim No. 9 is in respect of escalation. It is not
disputed at bar that in the agreement entered into between
the parties there was no escalation clause. The arbitrator
has come to the clear finding that the present appellant was
not pressurised by respondent No. I to agree 10% hike in
the wages of the mining workers as recorded in the findings
in respect of issue No. 34. In issue No .35 the arbitrator
has recorded that the present appellant acceded to for raise
in the wages of mining workers.
The amount awarded under Claim No. 9 is not only
beyond the scope of the agreement but also contrary to the
findings recorded by the arbitrator.
Therefore, we hold that the arbitrator has
misconducted himself in the proceedings and, therefore, the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
award is liable to be set aside on the ground of legal
misconduct on the part of the arbitrator under Section 30 of
the Act. The above being the position the present appeal
has no merits and accordingly dismissed. Considering the
facts and circumstances of the case parties to bear their
own costs.