Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 11
PETITIONER:
BADRI PRASAD
Vs.
RESPONDENT:
STATE OF MADHYA PRADESH AND ANOTHER
DATE OF JUDGMENT:
16/03/1965
BENCH:
DAYAL, RAGHUBAR
BENCH:
DAYAL, RAGHUBAR
GAJENDRAGADKAR, P.B. (CJ)
RAMASWAMI, V.
CITATION:
1966 AIR 58 1965 SCR (3) 381
ACT:
Sale of Goods Act (3 of 1930), s. 20-Auction of cut timber
of forest-Delivery-Destruction by fire before removal-Formal
contract signed by competent authority later-If property in
timber passed.
HEADNOTE:
The 2nd respondent purchased on 24th December 1956, at a
public auction sale held by the Divisional Forest Officer,
the cut timber of a coupe and paid the first installment of
the purchase price immediately. The appellant stood surety
for the payment of the remaining three instalments. The
coupe was divided into 4 sections according to the rules
which were deemed to be part of the contract and the
boundary certificates was furnished to the 2nd respondent on
5th February 1957. He began operations in the 1st section
on the last week of February, but defaulted in the payment
of the 2nd instalment which was due on 1st March 1957, and
so, on 25th April the appellant and 2nd respondent were
informed by the forest authorities, that no further removal
of the timber would be allowed, as the value of timber
already removed exceeded the amount paid. On 28th April a
fire broke cut and the timber sold to the 2nd respondent
ceased to exist. On 3rd May 1957, the formal deed of con-
tract, which was signed by the 2nd respondent and the
Divisional Forest Officer on 24th December, was signed by
the Chief Conservator of Forests, as required by the rules.
Since the 2nd respondent had not paid the later instalments
proceedings were commenced by the 1st respondent against the
appellant, whereupon he filed a suit for restraining the 1st
respondent from continuing the proceedings. The suit was
decreed by the trial court, but dismissed on appeal, by the
High Court.
In his appeal to this Court, the appellant contended that
the 2nd respondent had not been put in possession of the
timber sold, except the portion in the 1st section of the
coupe, that there was no transfer of property in the timber
and therefore he was not liable to pay the amounts due on
the other 3 instalments, the transfer of property in the
timber being a condition precedent to his liability.
HELD: There was an unconditional contract for the sale
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 11
of specific goods in a deliverable state, the property in
the timber passed to the 2nd respondent when the contract
was made on 24th December 1956 under s 20 of the Sale of
Goods Act, 1930, and possession was also given on 5th
February 1957. Therefore, the appellant’s suit was rightly
dismissed by the High Court [391 H]
The timber was sufficiently identifiable and was therefore
specified goods and there was nothing in the contract
postponing possession till the other instalments have been
paid. The fact that the contract was signed by the Chief
Conservator, after fire had broken out has no effect on the
validity of the contract, or on the question of delivery of
possession or on the passing of property in the timber. The
instructions in the Forest Manual about execution of
contracts plainly take into consideration the lapse of time
between the execu-
382
tion by the lessee and by the competent forest authority,
and therefore, the date on which the Chief Conservator
signed had not any real effect on the actual date on which
the sale of the timber took place. It was also within the
realm of possibility that the timber might be lost on
account of fire or other risk, before the contract was
formally signed. The sale of the timber to the 2nd
respondent was therefore final on 24th December, the date of
sale, subject to the acceptance of his bid by the competent
authority. [387 E-H; 388 F; 393 A-B]
Williams v. North China Insurance Co., L.R. (1876)1 C.P.D.
757, applied.
Rule 8 of the Forest Contract Rules empowers the Divisional
Forest Officer to stop the removal of the timber on his
finding that the value of the timber already removed
exceeded the amount of instalments paid. But, that would
not amount to reserving a right of disposal in the State,
because, the rules provide that though Ordinarily the timber
should be sold for cash payment in full, payment in
instalments could be considered as payment in full, if a
right in accordance with r. 8 is reserved. When a
contractor is deemed to have paid in full the price, there
could be no occasion for the Government to reserve a right
of disposal. The provision in r. 8 is only in pursuance of
the statutory provision in s. 83 of the Forest Act. 1927,
which provides that when any money is payable for or in
respect of any forest produce, the amount thereof shall be a
first charge on such produce, and that such produce may be
taken possession of by a Forest Officer, until such amount
has been paid. [390 H-391 D]
JUDGMENT:
CIVIL APPELLATE JURISDICTION: Civil Appeal No. 672 of 1964.
Appeal by special leave from the judgement and decree dated
October 1962 of the Madhya Pradesh High Court in First
Appeal No. 8 of 1960.
C. B. Agarwala, W. S. Barlingay and A. G. Ratnaparkhi, for
the appellant.
M. Adhikari, Advocate General for the State of Madhya
Pradesh, B. sen, M. S. K. Sastri, M. N. Shroff, R. P. Kapur
for 1. N. Shroff, for the respondent No. 1.
The judgment of the Court was delivered by
Raghubar Dayal, J. This appeal, by special leave, arises out
of a suit instituted by the appellant for a declaration that
he was not liable to pay a certain amount originally due
from defendant-respondent No. 2 and for the issue of a
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 11
permanent injunction restraining the State Government,
Madhya Pradesh, defendant respondent No. 1 from continuing
the proceedings for the recovery of the amount or for
starting any fresh proceedings. The suit was decreed by the
Trial Court but, on appeal, the High Court reversed the
decree and dismissed the appellant’s suit.
The admitted facts of the case are that on December 24,
1956, respondent No. 2 purchased at the public auction sale
held by the Divisional Forest Officer, Harda, the cut timber
and arkat trees of coupe No. 9 Eastern, East Kalibhit Range,
in Harda Forest
383
Division, for Rs. 70,200. The appellant stood surety for
the purchaser, viz., respondent No. 2. The purchase price
was to be paid in four instalments, according to para 4 of
the deed of contract. Rs. 17,600 were to be paid at once
and were so paid. The other instalments were due on March
1, May 15 and December 15, 1957. These instalments were not
paid by respondent No. 2 and hence respondent No. 1 took
proceedings against the appellant for the recovery of the
amount.
According to the terms of the contract, the contractor, res-
pondent No. 2, was to commence his work of collecting and
removing the cut timber within 1 month after furnishing a
copy of the boundary certificate. This certificate, Exhibit
D-1, was furnished on February 5, 1957 and stated that the
respondent No. 2 had clearly understood the boundaries of
the areas covered by the lease and that he had taken
possession of the standing/felled/ collected material in the
aforesaid coupe as announced at the auction and described in
the said lease and that he was satisfied that the quantity
delivered to him agreed substantially with that announced at
the auction.
The appellant Badri Prasad signed this certificate as a
witness. The work could continue upto June 30, 1958.
Interest was to be charged at 6-1/4 per cent per annum in
respect of the instalments not paid on the due dates. The
removal of the forest produce purchased from the contract
areas was to be according to specified routes and, after
they had been examined at the depots specified in clause 5
of the contract deal. Clauses 5A and 5B of the contract
made it incumbent on the forest contractor respondent No. 2
to set apart certain timber for certain purposes to the
agriculturists and the residents of the villages till three
months before the expiry of the contract. The Forest
Contract Rules were deemed to be part of the contract
entered into between respondent No. 2 and the State, by
clause 6 of the contract.
The formal deed of contract was signed by the Chief Conser-
vator of Forests on May 3, 1957 and the preamble of the deed
gives the date of the making of the contract to be May 3,
1957.
The First Schedule to the Contract states:
"The forest produce sold and purchased consists of: All
standing trees bearing hammer mark of marginally shown
device at base and breast height. All felled trees marked
at the butt end and stumps with the device shown in the
margin".
This is signed by the contractor, respondent No. 2 and by
the Divisional Forest Officer, Harda Division, dated
December 24, 1956. The trace of the coupe sold was signed
by respondent No. 2 and the Divisional Forest Officer on
November 29, 1956, prior to the actual auction sale. The
Third Schedule relating to the out.
384
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 11
turn register was also signed by respondent No. 2 and, by
the appellant who stood surety and the Divisional Forest
Officer, on December 24, 1956.
The security bond was signed by the appellant on December
29, 1956 and by the Divisional Forest Officer on March 30,
1957 and was countersigned by the Chief Conservator on May
3, 1957.
The entire coupe whose cut timber was sold to the respondent
was divided into four sections A, B, C and D. This was done
in accordance with r. 18 of the Forest Contract Rules. This
rule provides that the operations carried out in the
contract area under a forest contract for the sale of
standing trees are divided into two stages (a) cutting and
(b) carting. Cutting operations include felling and all
processes of conversion etc. without removing it further
from the place where it was felled than may be necessary to
carry out such processes. Carting operations include all
operations for the removal of a felled tree, or its
converted products from the place where the tree was felled,
whether such removal be to a depot or to a saw mill or other
destination. Sub-r. (2) of r. 18 authorizes the Divisional
Forest Officer to divide the contract area, shortly termed a
coupe, into such number of sections, not exceeding,, eight,
as he may think fit. The Divisional Forest Officer can
regulate and confine the operations of the forest contract
in accordance with the provisions mentioned in clauses (a)
to (c) of that sub-rule. Clause (b) provides that a forest
contractor can be allowed to carry out cutting operations
first in sections 1 and 2 of the coupe only and as soon as
he begins cutting operations in section 3 he shall be deemed
to have surrendered all his rights to the standing trees in
section 1 and similar would be the result on his beginning
cutting operations in section 4 and so on, till all the
sections of the coupe are completed. Clause (c) authorises
the forest contractor to begin carting operations from the
sections whose trees he has begun to cut and provides that
his rights to the forest produce in section 1 cease when he
starts cutting operations in section 4, and so on.
The provisions of r. 20 apply to contracts where the trees
have been felled by the Forest Department and the felled
trees only were sold to the forest contractor. Sub-r. (3)
makes rules 18 and 19 applicable to such contracts in so far
as they be applicable. Sub-r. (2) of r. 20 provides that a
forest contractor who has purchased felled trees shall
remove all the trees purchased by him under his contract.
Respondent No. 2, the contractor, began his operations in
section A of the coupe in the last week of February, 1957.
He defaulted in the payment of the second instalment which
was due on March 1, 1957 and did not pay that amount till
April 25, 1957,
385
though it was demanded several times from him. On March 23,
1957 a notice. Exhibit P4, was issued to him. It stated:
"You are being informed through this notice
that the removal of goods from the coupe by
you is already in excess of the amount
deposited by you in the treasury. So please
send the challan of the second instalment as
soon as possible by the return load carrier,
otherwise your removal of goods would be
stopped and a report would be made to the
higher authority within two days".
This was duly served on respondent No. 2.
On April 25, 1957 the appellant was told by the forest
authorities that no further removal of the forest produce
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 11
would be allowed in view of the default of payment of the
second instalment. The licence book and the transit pass
were taken back by the Government Forester, Madanlal Pagare.
Fire broke out in the forest and the cut timber sold to res-
pondent No. 2 was burnt. The report about the loss from
fire is Exhibit D2 dated April 29, 1957 and is signed by the
contractor and Sheoprasad Parashar. the Forest Guard. As a
result of the fire the goods purchased by respondent No. 2
and not removed by then, ceased to exist. He did not pay
the amounts due for the 2nd, 3rd and 4th instalments.
The appellant sought to avoid his liability as surety for
the non-payment of the amount inter-alia on the -round that
the contractor respondent No. 2 had not been put in
possession ’of the cut timber sold to him except of such
timber which had been in section A of coupe No. 9, that
therefore there had been no transfer of property in the
timber sold to him and that he was therefore not liable for
paying the amounts due on the 2nd, 3rd and 4th instalments.
It was averred by the appellant in paragraph 5(A) of the
plaint:
"Thus it was clearly understood on both sides
and also explained by the Forest Department
officials of defendant No. 1 and which has
been all along implicit in the contract as per
usual practices of the forest department that
the possession of the goods of each respective
section will be delivered to the Contractor on
payment of each instalment as stated above.
It was only on due payment of each instalment
that the contractor was to become entitled to
remove the goods in pursuance of the licence
book supplied to him by the forest department
of defendant No. 1.
In paragraph 5(B) it was stated:
"That the contractor or his licensee had no
right to remove the goods until the same was
duly hammer marked by the representative of
the said forest department
386
and until the licence and the transit pass
were duly checked and signed by the Coupe
Guard or such other representative as may be
present on the spot".
Para 5(C) mentioned:
"That the contractor or his men were further
liable to carry the forest produce for check
and examination of forest Depot-officers of
Ziri, Rahetgaon and Timarni established for
that purpose and after the cut wood was
checked by the Depot Officers, the same used
to be marked with a special hammer mark, and
unless that was done it was not lawful for any
person to remove timber brought to the depot".
Respondent No. 1 admitted what was stated in paras 5(B) &
(C) of the plaint. It denied the understanding as averred
in para 5(A) and what was alleged in para 5(D) to the effect
that it was after the processes mentioned earlier that
delivery of the goods was deemed to be given to the forest
contractor and was to be at his disposal.
The main question urged before us is that the property in
the cut timber sold and existing in sections B, C and D ’of
the coupe had not passed to the contractor before the fire
broke out in the last week of April 1957 and this contention
is based on the facts that the goods sold were not specific
goods as they had not been hammer-marked, that the goods in
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 11
sections B, C and D could not be delivered till the 2nd, 3rd
and 4th instalments had been paid and that the deed of
contract was signed after the fire had taken place.
We may now consider the points urged in support of the
contention that the property in the timber of sections B, C
and D had not passed to respondent No. 2.
The first schedule to the contract describes the property,
forest produce sold and purchased, thus:
" All standing trees bearing hammer mark of
marginally shown device at base and breast
height. All felled trees marked at the butt
end and stumps with the device shown in the
margin".
It is the case of the plaintiff-appellant that cut trees
timber or cut trees were sold. Para 2(A) of the plaint
describes the property purchased as ’the cut timber and
arkat trees of coupe No. 9’. Clause (1) of para 2 ’of the
statement of the case filed on behalf of the appellant makes
this further clear as it is stated therein that the contract
was for the purchase of ’the cut-timber and cutarkat trees’.
It appears therefore that the expression about ’all standing
trees bearing hammer mark’ in the description of forest
produce sold was inadvertently omitted to be struck out from
the deed of contract though there was no sale of standing
trees to respondent No. 2.
387
Chapter XX of Part IV of Vol. 1 of the Central Provinces &
Berar Forest Manual (hereinafter shortly termed Forest
Manual) gives the rules for the disposal of forest produce.
Rule 5 states that before forest produce is disposed of it
shall be properly marked. The standing trees are marked
with hammer at two places, at the butt end and at the lower
part, a little above the stem. ’the trees are to be felled
so as to leave the lower hammer mark in the un-cut portion.
The felled tree sold is subject to further processes of
cutting etc. The portions so cut have to be hammer marked,
as only one such portion will have the hammer mark which was
first put at the butt end of the tree. A second special
hammer mark is placed on these cut portions at the time of
checking at the depot. The two hammer marks necessary to be
put on the cut portions of the felled tree before they could
be actually taken away from the forest area were not made on
the cut timber existing in sections B, C and D and sold to
respondent No. 2, as the felled trees in those areas had not
been cut further by the contractor. The omission to put
such marks does not make the goods sold unascertained. The
felled trees sold to the respondent No. 2 had a butt mark at
the butt end. A similar hammer mark existed on the stem
near which the felled tree must have lain, it being presumed
that the rules for the felling of trees were properly
complied with by the forest authorities, mentioned above.
The goods sold therefore were specified goods.
There is nothing in the contract that possession would not
be delivered over the cut timber in sections B, C and D till
the 2nd, 3rd and 4th instalments have been paid. The
relevant provisions of r. 18 of the Forest Contract Rules,
extracted earlier, do not contain any such restriction. It
only provides that the operations necessary to be conducted
by the contractor had to start with section A or the first
section and that the rights of the contractor to the
material purchased would be deemed to be surrendered in
certain circumstances. This has nothing to do with the
payment of the instalments by the contractor. He can
proceed to operate on the entire property purchased,
according to his inclination in accordance with the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 11
procedure, as regulated by the rules. There is therefore no
force in the submission that there could have been no
delivery of possession over the produce sold and existing in
section B, C and D till the various instalments had been
paid.
The fact that the contract was signed by the Chief Conser-
vator of Forests on May 3, 1957, after fire had broken out
has no effect on the question of delivery of possession of
the produce sold and consequently on the passing of property
in the goods to the contractor respondent No. 2. The Chief
Conservator who was the proper authority for entering into
the contract of sale of property worth over Rs. 70,000/- had
necessarily to sign the deed of contract subsequent to the
actual auction sale and in view of the L/B(N)3SCI-12
388
exigencies of the procedure to be followed may have to sign
after a substantial period of time.
The bid of respondent No. 2 at the auction sale had been
provisionally accepted by the Divisional Forest Officer who
is authorized under the rules to conduct the auction sale.
The Divisional Forest Officer and respondent No. 2
thereafter signed the deed of contract on December 24, 1956
the date on which the auction sale took place. The
appellant, as surety, also signed the third schedule on
December 24, and the security bond on December 24.
Practically all the formalities necessary for the execution
of the deed except for the signatures of the Chief
Conservator, authorised to enter into a contract of this
magnitude, had been completed. His formal signature on the
deed of contract relates back the contract to the date of
auction when the bid of respondent No. 2 was provisionally
accepted and he and the Divisional Forest Officer signed the
contract.
In this connection, reference may be made to certain rules
and the instructions issued by Government to the various
officers for complying with those rules. Executive
instructions on the preparation of forest contract
agreements are printed at p. 125 of Vol. 11 of the Forest
Manual. Instruction No. 9 provides that if the parties have
signed the deed on the same date, that date should be
entered in the preamble, but if they had signed on two
different dates, then the later of those two dates should be
entered in the preamble. It was in accordance with this
instruction that May 3, 1957, the date on which the Chief
Conservator signed the contract was mentioned in the
preamble of the contract deed. That date therefore had not
any real effect on the actual date on which the sale of the
forest produce took place in favour of respondent No. 2.
Instruction 10 directs that the dates in clause 2 of the
prescribed deed of contract should be very carefully entered
as they have an important bearing on the deed and show the
period during which the contract will remain in force. Such
a period in the deed of contract Exhibit D is the period
’from the date the forest contractor furnishes the necessary
coupe boundary certificate after inspection of the contract
area to the 30th day of June 1958, both days inclusive’.
The coupe boundary certificate was furnished on February 5,
1957. It follows that the period for the operation of the
contract was from February 5, 1957 to June 30, 1958. This
is a clear indication that the date in the preamble has no
real effect and that the contract, after its being duly
signed by the competent authority, relates back to the date
of sale.
Instruction 16 deals with the execution of the deed of
contract. Clause (i) provides for the drawing up of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 11
contract in triplicate. Clause (iii) requires the
Divisional Forest Officer to initial the
389
contract after checking it before the lessee is asked to
sign it. Clause (iv) provides that where the Divisional
Forest Officer himself is empowered to execute the agreement
he and the lessee should execute it together and clause (v)
provides that where the Divisional Forest Officer is not
empowered to execute the agreement, it should be executed by
the lessee and his signature should be attested and that the
agreement should then be sent as soon as possible to the
Forest Officer empowered to execute it, for his signature
and attestation.
These instructions about the execution of the deed of
contract plainly take into consideration the lapse of time
between the execution by the lessee and by the competent
forest authority.
Instructions Nos. 38 to 48 are with regard to the auction of
forest contracts. It is the Divisional Forest Officer who
is directed to take certain steps. Instruction No. 45
provides that Divisional Forest Officers should ordinarily
allow themselves more than one day for the conduct of the
auction sales. Instruction No. 47 provides that where the
agreements are to be signed by the Conservator or higher
authority, the first instalments must still be paid and the
duplicate agreements signed by the contractor and his
surety, if any, and sent to the Conservator immediately.
The Conservators should sign the duplicate agreements in
token of acceptance and return them to the Divisional Forest
Officers as soon as possible. The reason for this is that
it is obviously only fair to a forest contractor that he
should be in possession of his signed agreement before he
starts work on his contract, i.e., before July 1. In case
the Conservators are not competent to sign the contract
deeds such deeds will have to be sent by them to the Chief
Conservator who is competent in view of r. 102A of Vol. 1
of the Forest Manual (under Chapter XIX) and the relevant
-orders of the Government to execute contracts for the sale
of forest produce upto an amount of Rs. 1,00,000 when
payment is received in full at the time of delivery and upto
Rs. 10,000 or upto Rs. 50,000 with the previous sanction of
the Provincial Government when payment is not received in
full at the time of delivery.
The exercise of this power by the Chief Conservator and
other officers is subject to the rules given in the
Government Notification and rule 1(a) of these rules
relating to contracts for forest produce reads:
"No timber or other forest produce may be
ordinarily sold except on cash payment in full
at the time of delivery. Payment in
instalments may, however, be considered as
payment in full at the time of delivery
provided that there is a clause in the
agreement to the effect that when Divisional
Forest Officer considers that the value of any
forest produce removed by the purchaser equals
or exceeds the amount of purchase money paid
by him upto
390
that time, the Divisional Forest Officer may
stop further removal until the purchaser has
paid such further sum, as in the opinion of
the Forest Officer, may be sufficient to cover
the excess value of the forest produce removed
or to be removed".
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 11
In view of this rule it would be deemed that the payment of
the purchase price had been made in full at the time of
delivery, though the actual payment was to be made in four
instalments.
We are therefore of opinion that the sale of the forest pro-
duce to respondent No. 2 was finalised on the date of sale
subject of course to the acceptance of his bid by the
competent authority, the Chief Conservator of Forests and
that the fact that the Chief Conservator signed the deed on
May 3, 1957, does not make the sale effective from the date
of his signature. His signatures do not ratify any action
of the Divisional Forest Officer which he took beyond his
competence, but simply completes the execution of the deed
of contract and relate back its execution to the date on
which the sale took place and the contractor and the Forest
Officer had signed the document.
We may now refer to the approach of the High Court to this
question of the deed of contract operating from the date of
its execution by respondent No. 2. It was of opinion that
respondent No. 2, and the Divisional Forest Officer, had
made the contract in December 1956 long before April 28,
1957 and even if the Divisional Forest Officer was not
competent to enter into the contract, his act had been
subsequently ratified by the competent authority and that
therefore the ratification related back to the date of the
contract and had the same effect as if the Divisional Forest
Officer had performed the act by the authority of the Chief
Conservator of Forests. With respect, we do not consider
this approach to be correct. The Divisional Forest Officer
had authority under the statutory rules for holding the
auction and for provisionally accepting the bid. All that
he did was within his authority. He did not actually enter
into the contract with respondent No. 2. He simply signed
the standard form of the contract for the satisfaction of
the competent authority to the effect that its accepting the
bid and entering into the contract would be correct as is
the usual official procedure where subordinates have to put
up or forward papers to the superior officers for approval,
sanction or orders. The right view of the entire procedure
adopted in the case has been already stated by us above.
The other point urged by Mr. Agarwala, for the appellant, is
that in view of r. 8 of the Forest Contract Rules which
empowered the Divisional Forest Officer to stop the removal
of forest produce sold on his finding that the value of the
forest produce already removed by the contractor exceeded
the amount of the instalments already paid by him, the
seller in this case had reserved the right
391
of disposal of the forest produce until certain conditions
were fulfilled and that therefore s. 25(1) of the Indian
Sale of Goods Act, 1930 (Act III of 1930 applies to the
facts of the case and that therefore, notwithstanding,
delivery of the forest produce to respondent No. 2 in
February 1957, the property in it did not pass to respondent
No. 2 until the conditions imposed by the seller were
fulfilled. There is nothing in the deed of contract ’or in
the Forest Contract Rules which reserved such a right of
disposal in the State. Right given to the Government under
r. 8 is the right to stop the removal of forest produce when
the value of the forest produce already removed exceeded the
amount of the instalments paid. This is to regulate the
compliance with the conditions of the auction one of which
was that ordinary forest produce was to be sold on payment
in full at the time of delivery. The contractor had
therefore to pay full price he had bid at the date of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 11
sale or any day prior to the delivery of the goods to him in
February 1957. The provision for allowing payment by
instalments is a concession for the convenience of the
contractor and it is provided in the rule that payment in
instalments may however be considered as payment in full at
the time of delivery provided there be a clause in the
agreement in accordance with the provisions of r. 8 of the
Forest Contract Rules.
Reference may here be made to the provisions of s. 83 of the
Indian Forest Act, 1927 (Act XVI of 1927). Subsection (1)
provides that when any money is payable for or in respect of
any forest produce, the amount thereof shall be deemed to be
a first charge on such produce, and such produce may be
taken possession of by a Forest Officer until such amount
has been paid. Rule 8 of the Forest Contract Rules is
therefore in pursuance of the statutory provisions of s. 83
of the Forest Act which creates a lien on forest produce for
the money payable to Government. Action which the
Divisional Forest Officer can take for stopping the removal
of the forest produce sold is in pursuance of the statutory
authority conferred on him and not in pursuance of any terms
of the contract between respondent No. 2 and the Government.
When a contractor is deemed to have paid in full the price
there could be no occasion for the Government to reserve a
right of disposal of the property even when its delivery had
been made to the purchaser. As already stated, it is s. 20
of the Sale ’of Goods Act which will apply to this case.
This section provides that where there is an unconditional
contract for the sale of specific goods in a deliverable
state, the property in the goods passes to the buyer when
the contract is made and it is immaterial whether the time
of payment ’of price or the time of delivery of the goods or
both is postponed. The contract was unconditional, the
goods sold were specific. They were in a deliverable state
and therefore the property in the goods did pass at the time
when the contract was made. This section would have applied
even if the time of payment
392
of price hand been postponed. In the present case, as
already stated, the payment allowed by instalments is to be
deemed payment in full at the time of the delivery of the
goods sold.
The last contention raised for the appellant is that as the
contract was signed by the Chief Conservator about a week
after the goods lying in sections B, C and D had been burnt
by fire, the contract must be deemed to have been not made
at all by the Chief Conservator who could not have
contracted to sell goods which did not exist. The
contention really is that there could be no ratification of
the act of the Divisional Forest Officer, who had no
authority to enter into the contract, after the goods had
ceased to exist and reliance is placed in support of this
contention on what is stated at para 415 at p. 177 ’of
Halsbury’s Laws of England, Vol. 1, III Edn. It is stated
there:
"As to the time within which ratification may
take place, the rule is that it must be either
within a period fixed by the nature of the
particular case, or within a reasonable time,
after which an act cannot be ratified to the
prejudice of a third person".
This is the general proposition and will not
be applicable to this case as no third person
is being prejudiced on account of the signing
of the contract by the Chief Conservator on
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 11
May 3, 1957, a week after the fire had
destroyed certain goods purchased. Further,
it is stated in the same paragraph:
"But by an anomalous rule limited to marine
insurance a contract of marine insurance made
by an agent on the principal’s property may be
ratified by the principal after notice of
loss".
This proposition is well-settled in England.
In Williams v. North China Insurance Co.(1)
this proposition was sought to be reviewed.
Cockburn C.J. said at p. 764:
"The existing authorities certainly show that
when an insurance is effected without
authority by one person on another’s behalf,
the principal may ratify the insurance even
after the loss is known. Mr. Benjamin asked
us, as a Court of Appeal, to review those
authorities...... Where an agent effected an
insurance subject to ratification, the loss
insured against is very likely to happen
before ratification, and it must be taken that
the insurance so effected involves that
possibility as the basis of the contract. It
seems to me that, both according to authority
and the principles of justice, a ratification
may be made in such a case".
These observations would fully apply to the facts of the
present case, even if we were of the view that the Chief
Conservator ratified the unauthorised act of the Divisional
Forest Officer on May
(1) L.R. [1876] 1 C.P.D. 757.
393
3, 1957, after the fire had taken place. The provisional
acceptance of the bid and the signing of the deed by the
Divisional Forest Officer must. in the circumstances, be
held to be subject to ratification. It was within the realm
of possibility that the forest produce might be lost on
account of fire or any other risk mentioned in r. 32 of the
Forest Contract Rules before the deed of contract was
formally signed by the Chief Conservator. The contract
entered into therefore involved the possibility of the loss
of goods by fire as the basis of the Contracts
Lastly, reference may be made to r. 32 of the Forest
Contract Rules which provides that a forest contractor shall
not be entitled to any compensation whatever for any loss
that may be sustained by reason of fire etc. This is not a
suit for compensation by the contractor respondent No. 2,
but in essence the basis ’of the suit is that the forest
contractor did not get possession of the forest produce in
sections B, C and D, that such produce was lost by fire and
that therefore he was not to pay the second, third and
fourth instalments and cannot be said to be in default in
payment of those instalments. The loss of such goods by
reason of fire therefore does not in any way give support to
the claim of the appellant.
We are therefore of opinion that the appellant’s suit has
been rightly dismissed by the High Court. We accordingly
dismiss the appeal. There will be no order as to costs.
Appeal dismissed.
394