Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 8
PETITIONER:
U.P. RAJKIYA NIRMAN NIGAM LTD.
Vs.
RESPONDENT:
INDURE PVT. LTD. & ORS.
DATE OF JUDGMENT: 09/02/1996
BENCH:
RAMASWAMY, K.
BENCH:
RAMASWAMY, K.
AHMAD SAGHIR S. (J)
G.B. PATTANAIK (J)
CITATION:
1996 AIR 1373 1996 SCC (2) 667
JT 1996 (2) 322 1996 SCALE (2)247
ACT:
HEADNOTE:
JUDGMENT:
J U D G M E N T
K. Ramaswamy, J.
Leave granted.
This appeal by special leave arises from the judgment
and order passed on April 10, 1992 by the Delhi High Court
in O.M.P. No.62 of 1992.
The appellant filed an application under Section 33 of
the Arbitration Act, 1940 [for short, "the Act"] for
declaration that there exist no agreement between the
appellant and the first respondent-Indure Pvt. Ltd. on the
basis of which a dispute for a claim of Rs.1,68,73,628/-
could be referred for arbitration as the agreement set up by
the respondent was non est and alternatively the dispute
was not arbitrable under the agreement. Accordingly it
sought declaration to set aside the said agreement. The
learned single Judge of the High Court in the impugned
order held that the draft agreement dated June 22, 1984
contains provision for arbitration under clause [14] and the
appellant is bound thereby; consequently, the arbitrators
are entitled to arbiter the dispute.
The dispute arose in the backdrop of the facts that the
U.P. State Electricity Board had floated tenders for
construction, supply and erection of mechanical equipment
and construction work including consultancy services. Last
date for submission of the tender was June 30, 1984. The
appellant-Nigam, an Undertaking of State of U.P. had
purchased tender documents-from the Board on February 6,
1984. The respondent approached the appellant for their
joint participation to submit the tenders to the Board. In
furtherance thereof, negotiations were set on foot and they
decided to enter into an agreement in that behalf and
ultimately draft agreement dated. June 22, 1984 was sent to
the respondent for signature. The appellant did not sign the
draft agreement. On June 27, 1984, the respondent sent a
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 8
counter-proposal deleting clause [10] of the agreement
suggested by the appellant and materially altering clause
[12] therein after signing the same. The tenders were
submitted on June 30, 1984, i.e., the last date for
submission of tenders; but before negotiating with the Board
on February 23, 1985 the appellant had withdrawn the
tenders. On February 25, 1985, the respondent had offered in
its letter to the Board agreeing to undertake the entire
contract by itself and offered to complete the formalities
with the Board. Simultaneously, on March 3, 1985, the
respondent sent a notice through its counsel claiming
damages stating therein that there was no arbitration
agreement between the parties. On January 21, 1986, the
respondent had further sent a notice nominating an
arbitrator an arbitrator on its part and called upon the
Appellant to nominate its arbitrator. The respondent
purported to have exercised that right under clause [14] of
the draft agreement proposed by the appellant on June 22,
1984 alleging that they had accepted the same by letter
dated June 27, 1984. The appellant by letter dated February
28, 1986 disputed the existence of the arbitration agreement
and also asserted that no concluded contract existed between
the parties. It was further stated therein that deletion of
material clause [10] of the draft agreement and material
alteration of clause [12] constituted substantial
modification of the draft agreement and consequently it did
not accept the counter-proposal of the respondent and that,
therefore, no valid agreement came into existence which was
admitted by the respondent in their letter dated March 5,
1985. The question of appointing an arbitrator on their
behalf did not arise. However, without prejudice to their
right to claim that no valid agreement, much less
arbitration agreement, was in existence, they nominated an
arbitrator on their behalf to arbiter on the question
"whether there existed ant valid or subsisting agreement
between the parties and whether there existed any valid and
binding arbitration clause between the parties?" Since the
arbitrator nominated by them expired, the respondent was
called upon the appellant to nominate another arbitrator. At
that stage the appellant filed above petition under Section
33 of the Act.
The High Court found that the respondent returned the
agreement duly signed but after deleting clause [10] and
materially altering clause [12] thereof. There was no
communication by the appellant refusing or negativing the
alternations made in the draft agreement. Tenders were
submitted on June 30, 1984 after receipt of the modified
agreement. Till March 1, 1986, the respondent had not
received any communication disowning the contract between it
and the appellant. Clause [14] of the agreement contained an
arbitration clause for adjudication of the disputes. The
withdrawal of the tenders by the appellant caused damages as
claimed by the appellant in the notice. Therefore, the
respondent called upon appellant to nominate their
arbitrator to adjudicate the dispute intimating in their
letter appointment of the arbitrator on their part. From
this there emerged a concluded contract containing clause
[14] providing for arbitration for adjudication of the
disputes.
As stated earlier, the High Court came to the
conclusion that from the correspondence between the parties
there emerged a concluded contract. After due discussion
between the parties the draft agreement duly signed with
official seal of the respondent affixed thereon, was
communicated to the appellant on June 27, 1984 which
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 8
contained clause [14] which formed an integral part of the
contract. The modifications suggested by the respondent were
acted upon by the appellant. At no point of time it was
suggested by any communication that the modifications were
not accepted. On the other hand, tenders were submitted on
June 30, 1984 for the joint participation of the appellant
and the respondent. The respondent had sent a bank Draft for
a sum of Rs.2 lakhs on October 29, 1984. "(I)t is clear that
the petitioner had accepted the agreement and in such an
eventuality, the petitioner cannot deny the existence of
arbitration clause". "Therefore, from the conduct of the
petitioner the inference can be drawn that the agreement had
come into force the moment it was signed by the respondent
and sent the same to the petitioner and the petitioner
though did not sign it but acted upon it which amounts to
indirect acceptance".
Section 3 of the Indian Contract Act, 1872 envisages
communication of proposal, acceptance of proposal and the
revocation of the proposal and acceptance. Communication of
proposal is complete under Section 4 when it comes to the
knowledge of the person to whom it is made. Communication of
an acceptance is complete - as against the proposer, when it
is put in the course of transmission to him, so as to be out
of the power of the acceptor; as against the acceptor, when
it comes to the knowledge of the proposer. Under Section 7,
"in order to convert a proposal into a promise, the
acceptance must [1] be absolute and unqualified; [2] be
expressed in some usual and reasonable manner, unless the
proposal prescribes the manner in which it is to be
accepted...". Under Section 10, "all agreements are
contracts if they are made by the free consent of parties
competent to contract, for a lawful consideration and with a
lawful object, and are not expressly declared to be void".
Section 31 defines "Contingent contract" to mean to contract
to do or not to do something, if some event, collateral to
such contract, does or does not happen". A contingent
contract to do or not to do anything, if an unforeseen
future event happens, cannot be enforced by law, under
Section 32, unless and until that event has happened. If the
event becomes impossible, such contract becomes void.
Section 2 [a] of the Act defines "arbitration agreement" to
mean "a written agreement to submit, present or future
differences, to arbitration, whether an arbitrator is named
therein or not". To constitute an arbitration agreement,
there must be an agreement between the parties, viz., the
parties must be ad idem. The parties are not ad unless they
agree to the terms and conditions mentioned in the
agreement. As seen, under the Contract Act unless there is
an agreement, i.e., there is an acceptance of the proposal,
the contract is not complete. It is seen that the draft
agreement dated June 22, 1984 was sent to the respondent for
acceptance, Admittedly, clause [10] was deleted and clause
[12] was materially altered unilaterally to convert joint
liability to individual liability of the appellant. It
would, therefore, be a counter-proposal signed by the
respondent and communicated to the appellant. At this
juncture, it is relevant to notice the Articles of
Association of the appellant-Company, a State Government
Undertaking. Article 125 of the Articles of Association
gives power to the Board of Directors of the appellant-
Company and Article 126, clause [xii] confers power on the
Board of Directors "to refer claims or demands, by or
against the Company to arbitration". Under Article 125, the
Company has the control and the competent authority has
power to sign the contract on behalf of the Company. After
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 8
the counter-proposal was signed by the respondent, the
appellant had not signed any contract to bind the parties.
From this factual matrix, the question arises: whether
there emerged any concluded contract pursuant to which the
parties are bound by the terms and conditions of the tenders
submitted to the Board and for further performance? It is
seen that the tenders were not jointly signed by the
appellant and the respondent but were unilaterally submitted
to the Board by the appellant and were later on withdrawn.
There did not exist any concluded contract between the Board
and the appellant for the performance of the work as per
terms and conditions of the tenders floated by the Board.
Under Section 32 it was a contingent contract until it was
accepted by the Board. In this background,the question
emerges: whether there is an arbitration agreement between
the parties? It is see; that clause [141 of the agreement
[subject to the dispute whether it is arbitrable under
clause [14] which is yet another issue with which were are
not concerned] independently does not come into existence
unless there is a concluded contract pursuant to the
proposal made by the appellant on June 22, 1984 or a
counter-proposal by the respondent dated June 26, 1984. It
is not the case of the respondent that there exist any such
independent arbitration agreement.
Shri R.F. Nariman, the learned counsel for the
respondent, therefore, contended that the counter-offer made
by the respondent amounts to acceptance by conduct of the
appellant and he placed reliance on paragraphs 53
[Acceptance by conduct] and 99 [Agreement in principle only]
of the i on Contract. Paragraph 53 provides ’ that "an offer
may be accepted by conduct. For example, an offer to buy
goods can be accepted by supplying them; and an offer to
sell goods, made by sending them to the offeree, can be
accepted by using them". The substance of paragraph 99 is
that parties may reach agreement in principle but the
details may be worked out at a later date. There is no
dispute to the proposition of law but two factors have to be
kept in mind, viz., when the counter offer was made by the
respondent and whether the unilateral offer amounts to
acceptance by submitting the tenders by the appellant to the
Board. We find that it does not amount to acceptance of
counter proposal. It is seen that admittedly, clause [10]
which thrusts responsibility on the first respondent was
deleted in the counter- proposal. In clause 12, for joint
responsibility unilateral liability was incorporated. In
other words the respondent disowned its material
responsibilities. Unless there is acceptance by the
appellant to those conditions no concluded contract can be
said to have emerged. It is seen that the appellant is a
Government Undertaking and unless contract is duly executed
in accordance with the Articles of Association, the
appellant is not bound by any such contract. Shri Nariman
sought to rely on the passage from Palmer on Companies Law
containing that it is an indoor management between the
appellant and its officers. When the negotiations were
undertaken on behalf of the appellant, the respondent was
led to believe that the officer was competent to enter into
the contract on behalf of the appellant. When the counter-
proposal was sent, The appellant had not Returned the
proposal. Therefore it amounts to acceptance and thus
concluded contract came into existence. We fail to
appreciate the contention. As seen, the material
alterations in the contract make world of difference to
draw an inference of concluded contract, The joint
liability of the parties was vade unilateral liability of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 8
The appellant. Thereby, the respondent sought to absolve
itself From the liability of further performance of the
contract with the Board. Similarly, clause [10] which
contains material part of the terms for the performance of
the contract with the Board was deleted Thereby, there is
no consensus A on the material terms of the contact which
contains several clauses. In the absence of consensus ad
idem on the material terms of the contract to be entered
into between the parties, there emerged no concluded
contract. Apart from the draft agreement and the counter-
proposal, there is no independent contract for reference to
arbitration. Clauses [14] which is an integral part of the
draft agreement proposed by the appellant and the counter-
proposal is the foundation for reference to the arbitration.
Section 31 [2] of the Act provides that notwithstanding
anything contained in any other law for the time being in
force and save as otherwise provided in the Act, all
questions regarding the validity, effect or existence of an
award or an arbitration agreement between the parties to the
agreement or persons claiming under them shall be decided by
the Court in which the award under the agreement has been or
may be, filed, and by no other Court. Section 33 envisages
that any party to an arbitration agreement or any person
claiming under him desiring to challenge the existence or
validity of an arbitration agreement or an award or to have
the effect of either determined shall apply to the Court and
the Court shall decide the question on affidavits. Under the
proviso, if the Court deems it just and expedient, it may
set down the application for hearing on other evidence also
and may pass such orders for discovery and particulars as it
may do in a suit.
In "Law of Arbitration" by Justice Bachawat [2nd Edn.]
at page 19 of Chapter II it is stated that "to constitute an
arbitration agreement, there must be an agreement, that is
to say, the parties must be ad-idem. The parties are not ad
-idem if there is an arbitration clause in the bought note
while there is none in the sold note. To be enforceable, the
agreement must be made by the free consent of the parties".
We find no force in the contention of Shri Nariman that
the appellant had submitted to the jurisdiction of the
arbitrators and having nominated the arbitrator, they are
estopped to go back upon it Acquiescence does not confer
jurisdiction,
The arbitrability of a claim depends on the
construction of the clause in the contract. The finding of
the arbitrator/arbitrators on arbitrability of the claim is
not conclusive as under Section 33, ultimately it is the
Court that decides the controversy. It being a
jurisdictional issue, the arbitrator/arbitrators cannot
cloth themselves with jurisdiction to conclusively decide
the issue. In "Russel on Arbitration" [19th Edn.] at page 99
it is stated thus:
"It can hardly be within the
arbitrator’s jurisdiction to decide
whether or not a condition
precedent to his jurisdiction has
been fulfilled. It has indeed
several times been said bluntly
that an arbitrator has no power to
decide his own jurisdiction and in
one case where rules of an
institution prepared to conduct
arbitrations gave the arbitrator
such power, the court will ignore
this when asked to enforce the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 8
award, and decide the question
itself. However, an arbitrator is
always entitled to inquire whether
or not he has jurisdiction. An
umpire faced with a dispute whether
or not there was a contract from
which alone his jurisdiction, if
any, can arise can adopt one of a
number of courses. He can refuse
to deal with the matter at all and
leave the parties to go to court,
or he can consider the matter and
if he forms the view that the
contract upon which the claimant is
relying and from which, if
established, alone his jurisdiction
can arise is in truth the contract,
he can proceed accordingly."
In "Law of Arbitration" by Justice Bachawat [2nd Edn.]
at page 155 it is stated that "the question whether matters
referred to were within the ambit of clause for reference of
any difference or dispute which may arise between the
parties, it is for the Court to decide". The arbitrator by a
wrong decision cannot enlarge the scope of the submission.
It is for the Court to decide finally the ambit of the
clause in dispute or any clause or a matter or a thing
contained therein or the construction thereof. We,
therefore, hold that the arbitrators cannot cloth themselves
with jurisdiction to decide conclusively the arbitrability
of the dispute. It is for the Court under Section 33 or on
appeal thereon to decide it finally. The appellant,
therefore, is not estopped to challenge the action and to
seek a declaration under section 33.
The clear settled law thus is that the existence or
validity of an arbitration agreement shall be decided by the
Court alone. Arbitrators, therefore, have no power or
jurisdiction to decide or adjudicate conclusively by
themselves the question since it is the very foundation on
which the arbitrators proceed to adjudicate the disputes.
Therefore, it is rightly pointed out by Shri Adarsh Kumar
Goel, learned counsel for the appellant that they had by
mistake agreed for reference and that arbitrators could not
decide the existence of the arbitration agreement or
arbitrability of the disputes without prejudice to their
stand that no valid agreement existed. Shri Nariman
contended that having agreed to refer the dispute, the
appellant had acquiesced to the jurisdiction of the
arbitrators and, therefore, they cannot exercise the right
under Section 33 of the Act. We find no force in the
contention. As seen, the appellant is claiming adjudication
under Section 33 which the Court alone has jurisdiction and
power to decide whether any valid agreement is existing
between the parties. Mere acceptance or acquiescing to the
jurisdiction of the arbitrators for adjudication of the
disputes as to the existence of the arbitration agreement or
arbitrability of the dispute does not disentitle the
appellant to have the remedy under section 33 through the
Court. In our considered view the remedy under Section 33 is
the only right royal way for deciding the controversy.
Since the tenders - the source of the contract between
the parties - had not transformed into a contract, even if
the proposal and counter proposal are assumed to be
constituting an agreement, it is a contingent contract and
by operation of Section 32 of the Contract Act, the counter
proposal of the respondent cannot be enforced since the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 8
event of entering into the contract with the Board had not
taken place.
In Ramji Dayawala & sons [P] Ltd. v. Invest Import [AIR
1981 SC 2085], a two-Judge Bench of this Court considered
the existence of the contract and arbitration clause
thereunder. This Court had held that in the facts of a given
case acceptance of a suggestion may be sub silentio
reinforced by the subsequent conduct. Where there is a
mistake as to terms of a document, amendment to the draft
was suggested and a counter-offer was made, the signatory to
the original contract is not estopped by his signature from
denying that he intended to make an offer in the terms set
out in the document. Where the contract is in a number of
parts it is essential to the validity of the contract that
the contracting party should either have assented to or
taken to have assented to the same thing in the same sense
or as it is sometimes put, there should be consensus ad
idem. In that case a sub-contract was signed and executed by
the Managing Director of the appellant-Company but part of
the contract was altered subsequently since counter-proposal
was given by the respondent. This Court had held that one
such case is where a part of the offer was disputed at the
negotiation stage and the original offeree communicated that
fact to the offeror saying that he understood the offer in a
particular sense; this communication probably amounts to a
counter-offer in which case it may be that mere silence of
the original offeror will constitute his acceptance. Where
there is a mistake as to the terms of the documents as in
that case, amendment to the draft was suggested and a
counter-offer was made, the signatory to the original
contract is not estopped by his signature from denying that
he intended to make an offer in the terms set out in the
document; to wit, the letter and the cable. It can,
therefore, be stated that where the contract is in a number
of parts it is essential to the validity of the contract
that the contracting party should either have assented to or
taken to have assented to the same thing in the same senseor
as it is sometimes put, there should be consensus ad idem.
It was held that there was no consensus ad idem to the
original contract. It was open to the party contending
novatio to prove that he had not accepted a part of the
original agreement though it had signed the agreement
containing that part.
As found earlier, there is no signed agreement by a
duly competent officer on behalf of the appellant. The
doctrine of "indoor management" cannot be extended to
formation of the contract or essential terms of the contract
unless the contract with other parties is duly approved and
signed on behalf of a public undertaking or the Government
with its seal by an authorised or competent officer.
Otherwise, it would be hazardous for public undertakings or
Government or its instrumentalities to deal on contractual
relations with third parties.
In view of the fact that Section 2 [a] of the Act
envisages a written agreement for arbitration and that
written agreement to submit the existing or future
differences to arbitration is a pre-condition and further in
view of the fact that the original contract itself was not a
concluded contract, there existed no arbitration agreement
for reference to the arbitrators. The High Court, therefore,
committed a gross error of law in concluding that an
agreement had emerged between the parties, from the
correspondence and from submission of the tenders to the
Board. Accordingly it is declared that there existed no
arbitration agreement and that the reference to the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 8
arbitration, therefore, is clearly illegal. Consequently
arbitrators cannot proceed further to arbiter the dispute,
if any. The conclusion of the High Court is set aside.
The appeal is accordingly allowed with costs quantified
at Rs.15,000/-.