Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 5
PETITIONER:
UNION OF INDIA
Vs.
RESPONDENT:
SURJIT SINGH ATWAL
DATE OF JUDGMENT18/01/1979
BENCH:
REDDY, O. CHINNAPPA (J)
BENCH:
REDDY, O. CHINNAPPA (J)
SARKARIA, RANJIT SINGH
CITATION:
1979 AIR 1701 1979 SCR (2)1002
1979 SCC (1) 520
CITATOR INFO :
D 1987 SC1577 (12)
ACT:
Fleas-Plea of non-compliance with the provisions of
Section 175(3) of the Govt. of India Act, 1935 is a mixed
plea of fact and law-A plea not having been so pleaded in
the written statement and any issue not having been so
raised with regard to it, cannot be allowed later.
HEADNOTE:
Pleadings-Denial of a contract-Civil Procedure Code,
1908 (Act V of 1908), Order VI Rule 8 and Order VIII Rule 2
scope of.
The respondent-plaintiff undertook the construction of
a hard Runway, taxi tracks and dispersal roads at
Dalbhumghar Aerodrome, pursuant to a formal written
agreement with appellant. The respondent completed the work.
At a subsequent conference, it was agreed that the total
amount of the final bill prepared in accordance with the
agreed rates less a sum of Rs. 50,000/- should be paid
forthwith and the balance of Rs. 50,000/- should be paid two
weeks thereafter. On the appellant’s failure to make the
payment of Rs. 50,000/-, the respondent filed a suit on the
original side of the High Court of Calcutta to recover the
said sum together with interest. The suit was dismissed by a
single judge but on appeal, the Division Bench of the High
Court allowed the appeal and decreed the suit.
Dismissing the appeal by certificate, the Court,
^
HELD : 1. A plea of non-compliance with the provisions
of Section 175(3) of the Goverrnment of India Act, 1935 is a
mixed plea of fact and law. [1006 B]
2. The plea of illegality of an agreement, not having
been so pleaded in the written statement and no issue having
been raised with regard to it cannot be allowed later. To
permit such a plea to be raised several years after the
institution of the suit would greatly prejudice the
plaintiff. If such a plea had been raised, in the instant
case, at the appropriate stage, the respondent-plaintiff
might have come out with a suitable answer. He might have
had his own pleadings amended either by seeking to rest his
case on the original agreement or under Section 65 or 70 of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 5
the Contract Act. [1005 G-H, 1006 A]
3. The illegality of a contract must be specifically
pleaded as much as the denial of a contract. Under Order VI,
Rule 8 of C.P.C., where a contract is alleged in any
pleading, a bare denial of the same by the opposite party
shall be construed only as a denial in fact of the express
contract alleged or of the matters of fact from which the
same may be implied, and not as a denial of the legality or
sufficiency in law of such contract. And, under Order VIII,
Rule 2 C.P.C., the defendant must raise by the pleading all
matters which show the suit not to be maintainable or that
the transaction is either void or voidable in point of law.
[1006 B-D]
Kalyanpur Lime Works Ltd. v. State of Bihar and Anr.
[1954] S.C.R. 958 referred to.
1003
JUDGMENT:
CIVIL APPELLATE JURISDICTION : Civil Appeal No. 2053 of
1969.
From the Judgment and Decree dated 16-7-68 of the
Calcutta High Court in Appeal No. 199-A of 1964.
R. B. Bhatt, E. C. Agarwala and Girish Chandra for the
Appellant.
H. B. Datar and Ashok Grover for the Respondent.
The Judgment of the Court was delivered by
CHINNAPPA REDDY, J.-Not content with raising a false
plea, the appellant, Union of India has preferred this
appeal on a technical ground. The respondent-plaintiff
undertook the construction of a hard Runway, Taxi tracks and
dispersal roads at Dalbhumghar Aerodrome. There was a formal
written agreement between the parties (Agreement No : A-
VII/96 of 1944-45). The respondent completed the work in
1945. The agreement provided for the work to be done "with
stone at site". As no stone was available at the site, stone
had to be obtained by blasting a rock in a hillock. The
rates stipulated in the agreement were on the basis that
stone was available at site and not on the basis that stone
had to be obtained by blasting rock. Some of the rates,
therefore, required revision. There was a conference between
the parties in November, 1947. On the side of the Government
the Superintending Engineer, the Executive Engineer and the
Deputy Accountant General were present. In respect of
fourteen items of work the old rates were not altered. In
respect of ten items of work only the rates were altered.
Out of these ten items, rates were substantially increased
for nine items but slightly decreased for one item. The
rates agreed between the parties at the conference were the
very rates which had been previously fixed by a Government
Engineer named Ramani Roy and suggested to the plaintiff by
the Superintending Engineer for his acceptance. The
plaintiff initially objected to the rates but withdrew his
objections at the conference. It was agreed that the total
amount of the final bill prepared in accordance with the
agreed rates, less a sum of Rs. 50,000/-, should be paid
forthwith and the balance of Rs. 50,000/ should be paid two
weeks thereafter. As agreed the amount of the final bill,
less Rs. 50,000/-, was paid but not the sum of Rs. 50,000/-.
The sum of Rs. 50,000/- was not paid despite repeated
demands by the plaintiff. The plaintiff therefore, filed
suit No. 531 of 1951 on the original side of the High Court
of Calcutta on 24th January, 1951 to recover the sum of Rs.
50,000/- together with interest.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 5
In the plaint, as filed originally, the plaintiff
stated that it was agreed that the work should be done by
the plaintiff on the terms and conditions
1004
mentioned in certain letters that passed between the
parties. No reference to the written agreement was initially
made in the plaint but by a later amendment reference was
also made to the agreent No. A-VII/96. The plaintiff further
stated in the plaint that after the completion of the work
there was a conference in November, 1947 at Calcutta and an
agreement was arrived at between the parties regarding the
rates at which the plaintiff was to be paid for the work
executed by him. He claimed that in accordance with the
terms of the agreement arrived at in November, 1947, he had
yet to be paid a sum of Rs. 50,000/-.
As we said earlier, the suit was filed on 24th January,
1951. The defendant, Union of India, filed a written
statement on 1st February, 1956, five years after the filing
of the suit. The contract for the execution of the work was
admitted. The completion of the work was admitted. The
conference alleged by the plaintiff to have been held in
November 1947 was denied. The agreement said to have been
arrived at the conference was also denied. These denials
have been found to be false by the Courts below and the
learned Counsel for the appellant had to admit before us
that the denial was ‘unfortunate’. It is a matter not merely
of surprise but of shock to us that such a blatant false
plea should have been raised by a Government in solemn
proceedings before Court of law. Far from setting an example
as an ideal litigant, we notice that such false and
untenable pleas are often raised on behalf of the
Government. This is a matter which needs looking into by the
authorities that are concerned with it and we earnestly hope
that some suitable remedial action will be taken to avoid
such pleas. To continue the story, no plea was taken in the
written statement that the contract between the parties was
hit by any failure to comply with the provisions of Section
175(3) of the Government of India Act, 1935.
More than a dozen years after the institution of the
suit and eight years after the filing of the written
statement, an application for amendment of the written
statement was filed on 25th April, 1964, to enable the
defendant to raise the plea that the contract was hit by the
failure to comply with the provisions of Section 175(3) of
the Govt. of India Act, 1935. The application was dismissed
on 1st May, 1964, but it was observed that the defendant was
entitled to raise the plea sought to be raised by the
amendment even without an amendment. Thereafter the suit
proceeded to trial. Mr. Justice Mallick who tried the case
decided in favour of the plaintiff on the several questions
of fact which were raised. A question regarding compliance
with the provisions of Section 80 Civil Procedure Code was
also decided in favour of the plaintiff. He, however, held
that the suit was based not on Agreement
1005
No. A-VII/96 of 1944-45 but on the agreement arrived at
between the parties in November, 1947, that this agreement
was bad for non compliance with the requirements of Section
175(3) of the Govt. of India Act 1935, and that the suit
had, therefore, to be dismissed. On the basis of the finding
that the 1947 agreement was bad for non compliance with the
requirements of Section 175(3) of the Govt. of India Act,
1935, the learned Judge also held that the Court had no
jurisdiction to entertain the suit. The suit was accordingly
dismissed. On appeal, a Division Bench of the Calcutta High
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 5
Court consisting of A. N. Ray and S. K. Mukherjee. JJ., held
that the defendant not having pleaded in the written
statement that the contract contravened the provisions of
Section 175(3) of the Goverment of India Act there being no
issue with regard to Section 175(3), the learned Single
Judge was wrong in entertaining such a plea, at that belated
stage. It was observed that the request for amendment of the
written statement was made thirteen years after the
institution of the suit and that the plaintiff was greatly
prejudiced by such a plea being entertained. It was also
held by the Division Bench that there was no new agreement
in November 1947. All that was done in November 1947 was to
settle the rates for "additional or substituted work" as
provided in clauses 12 and 12-A of the original agreement.
In view of their concusion that the plea regarding the
invalidity of the agreement should not have been entertained
by the learned single Judge, the Division Bench held that
the Calcutta High Court had jurisdiction to entertain the
suit. The appeal was allowed and a decree was granted for
Rs. 50,000/- with interest from the date of judgment. The
Union of India has preferred this appeal pursuant to a
certificate granted under Article 133(1)(a) of the
Constitution of India (as it stood prior to the 30th
amendment).
Shri Bhatt, learned Counsel for the appellant submitted
that the suit was based on the agreement of November, 1947
and that this agreement was void as the provisions of
Section 175(3) of the Govt. of India Act, 1935, were not
complied with. We do not prima facie agree that the suit was
based on any agreement arrived at in November 1947. We do
not, however, desire to go into the question as we are
satisfied that the Appellate Court was right in holding that
the defendant was not entitled to raise the plea of
illegality of the agreement, not having so pleaded in the
written statement and not having raised any issue with
regard to it. We agree with the learned Judges of the
Calcutta High Court that to permit such a plea to be raised
several years after the institution of the suit would
greatly prejudice the plaintiff. It such a plea had been
raised at the appropriate stage, the plaintiff might have
1006
come out with a suitable answer. He might have had his own
pleadings amended either by seeking to rest his case on the
original agreement or under Section 65 or Section 70 of the
Indian Contract Act. We do not wish to speculate on the
possible alternate cases which the plaintiff might have put
forward had the plea been raised. We only wish to observe
that the plea that the provisions of Section 175(3) of the
Govt. of India Act had not been complied with is a mixed
plea of fact and law. We further agree with the view
expressed by the learned Judges of the Calcutta High Court
that the illegality of a contract must be specifically
pleaded as much as the denial of a contract. Order VI, Rule
8 provides that where a contract is alleged in any pleading,
a bare denial of the same by the opposite party shall be
construed only as a denial in fact of the express contract
alleged or of the matters of fact from which the same may be
implied, and not as a denial of the legality or sufficiency
in law of such contract. Order VIII, Rule 2 Civil Procedure
Code prescribes that the defendant must raise by his
pleading all matters which show the suit not to be
maintainable, or that the transaction is either void or
voidable in point of law. In Kalyanpur Lime Works Ltd. v.
State of Bihar and Anr.,(1) the Supreme Court reversed the
judgment of the High Court on the ground that the High Court
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 5
was not justified in allowing to be raised at the time of
argument the question whether there was a contravention of
Section 30 of the Govt. of India Act 1915. Reliance was
placed upon Order VI, Rule 8 and Order VIII, Rule 2 of the
Civil Procedure Code 1908. We are, therefore, of the view
that the Division Bench of the High Court was right in
holding that the learned single Judge was not justified in
permitting the defendant to take up the plea that the
contract was hit by the failure to comply with the
requirements of Section 175(3) of the Govt. of India Act. In
the result the appeal is dismissed with costs.
S.R. Appeal dismissed
1007