Full Judgment Text
1
REPORTABLE
2023 INSC 996
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 9106 OF 2012
M/S. RAJASTHAN ART EMPORIUM …. APPELLANT
VERSUS
KUWAIT AIRWAYS & ANR. ...RESPONDENTS
WITH
CIVIL APPEAL NO. 9194 OF 2012
J U D G M E N T
PRASHANT KUMAR MISHRA, J.
These two appeals are cross appeals preferred against the
order passed by the National Consumer Disputes Redressal
1
Commission dated 01.10.2012 in Original Petition No. 229 of
1997 whereby the complaint filed by the appellant/complainant
Signature Not Verified
Digitally signed by
SWETA BALODI
Date: 2023.11.09
16:22:05 IST
Reason:
was disposed of while directing respondent no. 1 to pay the
1 (for short ‘the NCDRC’)
2
appellant/complainant US$ 500750/- or Rs. 20 lakhs is less
along with 9% per annum compensation with effect from
31.07.1996 till its realization.
2. The case of the appellant/complainant is that it is an
exporter of all kinds of handicrafts goods to several countries
including USA. The appellant/complainant had received an
order from M/s. Williams Sonoma Inc. USA for supply of
handicraft goods. Accordingly, the appellant/complainant had to
send three shipments of 1538 packages weighing 26,859.5 kg.
to the consignee on an urgent basis, which was specifically
informed to the respondents. On 22.07.1996, the goods were
tendered to respondent no. 1 through respondent no. 2 after
getting an assurance that the shipments will reach destination
at Memphis within 7 days and delivery schedule was handed
over to the appellant/complainant. As per the schedule, the
entire consignment was supposed to reach at Memphis by
31.07.1996.
3. The consignments did not reach the destination at
Memphis (USA) as per the delivery schedule. On enquiry,
respondent no. 1 expressed its inability to deliver the
consignments as per the delivery schedule provided to the
3
appellant and a revised delivery schedule was given on
05.08.1996, which mentioned the date of delivery on
06.08.1996. However, the consignment did not reach at the
destination even as per the revised delivery schedule.
4. On non-receiving the goods, the consignee expressed its
anguish by sending a letter dated 23.08.1996 and informed the
complainant that the goods are not received in toto, and
respondent no. 1 was unable to tell where the remaining
cartons are.
5. It is also on record that 69 cartons were lying with
Lufthansa. The respondent no. 1, by its letter dated 30.08.1996
addressed to respondent no. 2, accepted the short delivery. On
07.09.1996, the appellant/complainant made a modest claim
against the respondents for refund of full freight. In response to
the said claim, respondent no. 2 confirmed having short
delivered 104 cartons out of 288 cartons but did not state
whether the other cartons had arrived at the destination. The
appellant served the legal notice dated 04.08.1997 on the
respondents, which evoked no response.
6. Ultimately, the appellant/complainant lodged a complaint
before the NCDRC with the prayer that respondent no. 1 be
4
directed to refund a sum of Rs. 24,48,345/- being the fair
charges for the consignments; pay a sum of Rs. 20 lakhs as
compensation for loss of business and reputation; pay US$
7042.00 being the value of the goods short delivered; pay
interest @ 18% as well as cost of litigation, which was disposed
of as abovesaid. Hence these appeals.
7. Learned counsel for the appellant would submit that
admittedly, the shipments booked by the appellant on
24.07.1996, which were to be delivered by 31.07.1996, were
delivered to the handling agent of the Consignee only in the
month of September, 1996 from 03.09.1996 to 12.09.1996 with
delay of more than 40 days.
8. Learned counsel submitted that the goods were tendered
to respondent no. 1 on a specific representation that the same
will be delivered within seven days, therefore, time is the
essence of the contract between the parties. It is next argued
that in the case in hand, it is clear from the material on record
that respondent no. 1 has been highly negligent in rendering its
services to the appellant.
9. Learned counsel further submits that once the NCDRC
arrives at the conclusion that there is delay in delivery of
5
consignment due to negligence of respondent no. 1, fair, just
and reasonable compensation must be awarded in accordance
with conditions of the contract and statutory provisions of the
Carriage by Air Act, 1972.
10. Per contra , learned counsel for respondent no. 1 submitted
that there was no deficiency in service rendered by respondent
no. 1. All reasonable care in performing its duties under the
contract of carriage were discharged diligently. He would
submit that no specific instructions were given by the appellant
with regard to the time by which the consignments had to reach
its destination, therefore, time was not the essence of contract
entered into between the parties.
11. Learned counsel next submits that respondent no. 1
should not be held liable for delay in service, as in spite of
being aware of the fact, the appellant sent the consignment
through Kuwait Airways, which has various stops over at Kuwait,
Chicago and Memphis, which would consume a lot of time
period to deliver the consignment.
12. Learned counsel lastly submits that the compensation
awarded by the NCDRC is excessive, unjust and unfair and is
based on the conjectures and surmises.
6
13. We have heard learned counsel for the appellant as well as
the respondents at length and perused the material placed on
record meticulously.
14. Initially, the NCDRC passed a final order on 21.05.2003
holding that there has been a short delivery of 104 pieces equal
to 1822 Kgs. Therefore, in view of Rule 22 of Carriage by Air
Act, multiplying this weight by US $ 20 per Kg., the amount
payable work out to US $ 36440 which becomes payable by the
respondent to the complainant for the loss of goods. This
amount was directed to be paid by the respondent along with
interest @ 9% from 01.10.1996. In so far as the issue
concerning delay in delivering the consignment, the NCDRC
found that in the absence of any communication emanating
from the respondent No.1-Kuwait Airways promising to deliver
the goods by any particular date, the plea raised by the
complainant regarding delay in delivering the goods is not
sustainable.
15. Challenging the above order dated 21.05.2003 of the
NCDRC, the complainant preferred Civil Appeal bearing C.A.No.
8211 of 2003 which was allowed by this Court on 15.03.2011.
7
This Court observed that the issue concerning delay in delivery
of goods has been decided by NCDRC without appreciating the
material and evidence available on record. Resultantly, the
matter was remitted back to NCDRC for fresh consideration of
the complainant case vis-à-vis delay in delivering the
consignment.
16. After the remand, the present impugned order has been
passed holding that there was delay in delivering the
consignment on time for which the complainant is entitled to
compensation of 25037.5 Kg. multiplied by US $ 20 Kg. each
which comes to US $ 500750 which exceed the sum of Rs. 20
lakhs claimed by the complainant therefore the complainant
was only entitled to have compensation of Rs. 20 lakhs along
with interest @ 9% w.e.f. 31.07.1996 till its realization as also
the litigation charges and compensation for harassment and
mental agony in the sum of Rs. 5 lakhs.
17. Basing on the material available on record, the NCDRC has
held that the fax message sent by respondent No.2-agent
through whom the consignment was booked to be shipped by
the respondent No.1 goes to show that the goods shall be
8
delivered at Chicago Memphis on 29.07.1996, 31.07.1996 and
31.07.1996. However, when the consignment did not reach the
destination, appellant - M/s Rajasthan Art Emporium informed
the respondents whereafter, the respondent no. 2 provided a
revised schedule, however, the shipments did not reach the
destination even as per the revised schedule, according to
which the goods were to reach the destination on 06.08.1996.
18. The evidence on record shows that the parts of the
shipments were received at Memphis on 30.08.1996 as
admitted by the respondent No.1 in its letter dated 24.09.1996.
Referring to the documents showing business relation between
complainant and his buyer, the NCDRC would observe that the
buyer was the largest customer of the complainant. Thus, the
complainant has suffered huge loss due to transaction and the
goods were received in the first week of September, 1996.
19. We have perused and examined the material available on
record and we are satisfied that the NCDRC has not committed
any illegality or perversity in recording the finding that there
was delay in delivery of consignment. As a matter of fact, it is
an admitted position that the consignment which was booked
9
on 24.07.1996, was delivered after one and a half month i.e.
from 03.09.1996 to 12.09.1996.
20. In its reply before the NCDRC, the agent-respondent No.2
(Dagga Air Agents) admitted that at the time of booking, the
complainant was informed about the tentative date of arrival of
goods at Memphis by 31.07.1996 and thereafter a revised
schedule was also given to the complainant. Once the agent
has issued a time schedule for delivery of consignment, it
cannot be said that there is no material indicating that there
was no agreement for delivery of the consignment in time.
respondent no.1 – Kuwait Airways has never taken the stand in
any of the communication arising from its office that the
respondent No.2 is not its agents or that there was no
agreement or promise by its agent that the consignment will be
delivered in 07 days. The NCDRC has rightly noted that the
appellant has paid air freight which is ten times more than the
sea freight only to ensure that the consignment reaches its
destination within a week because sea cargo would have taken
25 to 30 days for delivery and the appellant has paid such huge
freight charges for ensuring early delivery, hence, the delay in
delivery of consignment has necessarily inflicted damage to the
10
appellant which is liable to be satisfied by the respondent No.1
as provided under Section 19 and 13(3) of the Carriage by Air
Act 1972.
21. The provisions contained in Section 19 and 13 (3) of the
Carriage by Air Act 1972 read as follows:
“19. The carrier is liable for damage occasioned
by delay in the carriage by air of passengers,
luggage or goods.”
“13 (3). If the carrier admits the loss of the
goods, or if the goods have not arrived at the
expiration of seven days after the date on
which they ought to have arrived, the
consignee is entitled to put into force against
the carrier the rights which flow from the
contract of carriage.”
By virtue of the above provisions, the consignee is entitled
to seek damages for delay in delivering the consignment. It is
not the case of the respondent No.1 that the respondent No.2
had acted beyond the terms of agency. Neither it is averred
that the respondent no.2 was not the agent of respondent No.1.
22. Section 186 of the Contract Act, 1872 provides that
authority of an agent may be expressed or implied. Similarly,
Section 188 of the Contract Act, 1872 prescribes that an agent,
11
having an authority to do an act, has authority to do every
lawful thing which is necessary in order to do such act. In
2
Dilawari Exporters v. Alitalia Cargo & Ors. this Court has
observed in Paragraph 17 to 20 as follows: -
| “17. Section 186 of the Contract Act, 1872 (for<br>short “the Contract Act”) lays down that the<br>authority of an agent may be expressed or<br>implied. As per Section 187 of the Contract Act,<br>an authority is said to be express when it is<br>given by words spoken or written, and an<br>authority is said to be implied when it is to be<br>inferred from the circumstances of the case;<br>and things spoken or written, or the ordinary<br>course of dealing, which may be accounted<br>circumstances of the case. | |||
|---|---|---|---|
| 18. Section 188 of the Contract Act prescribes<br>that: | |||
| “188. Extent of agent's authority.—An<br>agent, having an authority to do an act,<br>has authority to do every lawful thing<br>which is necessary in order to do such<br>act.” | |||
| 19. Section 237 of the Contract Act provides<br>that: | |||
| “237. Liability of principal inducing<br>belief that agent's unauthorised acts<br>were authorised.—When an agent has,<br>without authority, done acts or incurred<br>obligations to third persons on behalf of<br>his principal, the principal is bound by<br>such acts or obligations if he has by his<br>words or conduct induced such third<br>persons to believe that such acts and |
(2010) 5 SCC 754
2
12
| obligations were within the scope of the<br>agent's authority.” | ||
|---|---|---|
| 20. There is no gainsaying that onus to show<br>that the act done by an agent was within the<br>scope of his authority or ostensible authority<br>held or exercised by him is on the person<br>claiming against the principal. This, of course,<br>can be shown by practice as well as by a<br>written instrument. Thus, the question for<br>consideration is whether on the evidence<br>obtaining in the instant case, can it be said that<br>Respondent 3 had an express or implied<br>authority to act on behalf of Respondent 1 as<br>their agent? If Respondent 3 had such an<br>authority, then obviously Respondent 1 was<br>bound by the commitment Respondent 3 had<br>made to the appellant.” |
23. In the case at hand, in the absence of a plea by the
respondent No.1, that the respondent no. 2 was not its agent or
that he had no authority to give schedule of delivery of
consignment, the onus has not been discharged. Therefore, the
respondent No.1 is bound by the promise held by its agent -
respondent No.2, that the goods shall be delivered within one
week and when the time schedule expired and the goods were,
in fact, delivered after one and a half month, there was
negligent delay in delivery of consignment.
13
24. The grievance of the appellant in this appeal is mainly on
account of the NCDRC not allowing the entire claim for
compensation by calculating the total weight of the subject
consignment at 2507.5 Kg. multiplied by US $ 20 per Kg.
According to the appellant, in view of Rule 22 (2) of Schedule-III
of the Carriage by Air Act, 1972 (as amended by the Hague
Protocol) the amount thus calculated would exceed the sum of
Rs. 20 lakhs. The appellant would thus claim the entire amount
equivalent to US $ 50070 without limiting it to Rs. 20 lakhs.
However, on this point also, we approve and sustain the order
passed by the NCDRC for the reason that in its complaint under
Section 21(a)(i) of the Consumer Protection Act, 1986, the
complainant/appellant has sought damages for Rs. 20 lakhs
only as compensation for loss of business and reputation. It is a
trite law that a party is not entitled to seek relief which he has
not prayed for. For this proposition we may profitably refer to
this Court’s judgments in Merrrs. Trojan & Co. Vs. RM.N.N.
3
Nagappa Chettiar , Krishna Priya Ganguly etc. etc. Vs.
4
University of Lucknow & Ors ., Om Prakash & Ors. Vs.
5
Ram Kumar & Ors . , Bharat Amratlal Kothari Vs.
3 AIR 1953 SC 235
4 AIR 1984 SC 186,
5 AIR 1991 SC 409
14
6
Dosukhan Samadkhan Sindhi & Ors ., Manohar Lal
7
(Dead) by Lrs. Vs. Ugrasen (Dead) by Lrs. & Ors .
25. In view of the forgoing reasons, we are not inclined to
interfere with the Order passed by the NCDRC and resultantly
both the Civil Appeals deserve to be and are hereby dismissed.
The parties shall bear their own costs.
Pending application(s), if any, shall stand disposed of
………………………………………J.
(A.S. BOPANNA)
………………………………………J.
(PRASHANT KUMAR MISHRA)
NOVEMBER 09, 2023.
NEW DELHI.
6 AIR 2010 SC 475
7 2010 (11) SCC 557