Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 14
CASE NO.:
Appeal (civil) 4079 of 2007
PETITIONER:
Numaligarh Refinery Ltd
RESPONDENT:
Daelim Industrial Company Ltd
DATE OF JUDGMENT: 06/09/2007
BENCH:
A.K.MATHUR & MARKANDEY KATJU
JUDGMENT:
J U D G M E N T
CIVIL APPEAL NO. 4079 OF 2007
[Arising out of S.L.P.(c) No.20989 of 2006]
With :
Civil Appeal No. 4080 of 2007
[ Arising out of S.L.P.(c) No. 4409 of 2007]
A.K. MATHUR, J.
1. Leave granted.
2. Both these appeals arise out of the order dated 24.8.2006
passed by the Division Bench of the High Court of Gauhati at
Guwahati in Arbitration Appeal No.1 of 2002. Therefore they are
taken up together and disposed of by this common order.
3. Brief facts which are necessary for disposal of these
appeals are that the respondent, Daelim Industrial Company
(hereinafter to be referred to as ’DIC’ ) is a company incorporated in
Seoul, Korea having its registered office there. During the pendency
of the arbitration proceedings, Daelim Engineering Company Limited
(DEC) got merged with Daelim Industrial Company Limited (DIC), and
therefore DEC ceased to exist. For our convenience we will take up
DIC for all practical purpose. The appellant, Numaligarh Refinery
Limited (hereinafter to be referred to as ’NRL’) is a Government of
India undertaking incorporated under the Companies Act, 1956,
having its registered office at Guwahati, in the State of Assam. NRL
through its consultant Engineers India Limited (hereinafter to be
referred to as ’EIL’), also a Government of India undertaking, on
22.11.1993 invited global quotations for building of a Cogeneration
Captive Power Plant for its Petroleum Refinery at Numaligarh in
Assam. DIC with its consortium partner, Turbotecnica SPA of Italy,
contested the global bid and after negotiation with NRL, the contract
was awarded to DIC by its fax of intent dated 31.1.1995. Three
contract agreements were signed between NRL and DIC and
Turbotecnica. The total contract price embodied in the above
contract agreements dated 11.4.1995 was on a Turnkey basis and
the time schedule for completion of the works as per the consolidated
contract was as follows :
" (i) First train of Gas Turbine Generator (GTG),
Heat Recovery Steam Generator (HRSG) and Utility
Boiler (UB) within 21 months of the issue of Fax
Intent i.e. by 31.10.1996 and (ii) balance plant within
24 months of issue of the Fax Intent i.e. by
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 14
30.01.1997."
In course of the execution of the project disputes arose between the
parties and therefore, in terms of Clause 9(b) of the Consolidated
Agreement, DIC referred the matter on 7.8.1997 before the
International Chamber of Commerce; International Court of
Arbitration, Paris for resolution thereof and claimed Rs.37.9 crore
under different heads. NRL disputed the claim and submitted its
written reply on 20.9.1997 and a rejoinder was filed by the DIC on
4.11.1997. In terms of the International Chamber of Commerce’s
Arbitration Rules, 1988, (hereinafter to be referred to as the ’Rules’)
the DIC and NRL nominated their Arbitrator. The International Court
of Arbitration confirmed the appointment of Arbitrators and
nominated a third Arbitrator-cum-Chairman to constitute the Arbitral
Tribunal. Meanwhile, DIC updated its claim to be at Rs.55.8 crore to
which NRL submitted its written reply. DIC in response thereto,
submitted its rejoinder. However, no counter claim was made by
NRL. The Tribunal framed necessary issues. The majority award of
the Arbitrators by the order dated 23.9.2000 held that the respondent
was entitled to Rs.29.76 crore and further an amount of US $
170,000 being 50% of the cost of arbitration paid by it, in addition to
its share of the total cost of US$ 340,000. The appellant having
refused to pay its portion thereof interest at the rate of 12% per
annum pendente lite on Rs.29.76 crore from 7.8.1997 till the date of
the award was also sanctioned. In addition, the appellant, NRL was
saddled with the liability of post award interest at the rate of 18% per
annum on the above awarded amounts in case of its failure to make
the payments within 60 days of the receipt the award. However,
Justice M.M.Dutt, Member of the Arbitral Tribunal gave a dissenting
award. He awarded DIC an amount of Rs.13,74,55,272/- with
interest at the rate of 10% till realization, in case of failure on the part
of NRL to disburse the sum. DIC was also further awarded an
amount of Rs.1.65 crore to be recovered from the Customs
authorities exacted on goods not chargeable to duty. Being aggrieved
with the majority award dated 23.9.2000, NRL filed application under
Section 34 of the Arbitration and Conciliation Act, 1996 ( hereinafter
to be referred to as the’ Act’) in the Court of the District Judge at
Golaghat which was registered as Misc. Arbitration Case No.1 of
2001. Notice was issued and in pursuance of such notice the
respondent appeared. The learned District Judge after hearing the
parties and on consideration of the materials on record, set aside the
award. Aggreived against that order of the District Judge an appeal
was preferred by the DIC before the High Court. DIC itemized their
claims as under :
" A. Transfer of US$ 6 million : Rs.9.6 crores
B. Turbotecnica’s Contract price : Included in Item C
C. Countervailing Duty : Rs.13.0 crores
D. Excess Custsoms Duty due to
Fluctuation of exchange rate : Included in Item C
E. Liquidated damages for delay
In approval of Design and
Engineering : Rs.8.9 crores
F. Excess expenses due to lack
of infrastructure : Rs.4.6 crores
G. Additional expenses cost by
Schedule delay : Rs.12.0 crores
H. Interest for borrowed funds,
Delayed opening of LC for
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 14
Design : Rs.0.5 crore
I. Escalation : Rs.4.1 crores
J. Change Order : No dispute
K. Extra tax burden as per AGSI
With effect from 1st May 1997 : Rs.3.1 crores
L. Indian statutory taxes included in
Item No.C.
(Total Claim of DEC) [Rs.55.8 crores ]"
No counter claim was filed by NRL. With regard to transfer of US
$6 million equivalent to Rs.9.6 crore, the issue framed was to the
following effect.
" Is the claimant entitled to a sum of Rs.9.6 crores
as claimed under heading Transfer of US $ 6 million "
Under this heading it was pleaded by the DIC that the overseas
contract required supply by it of various imported items priced at US
$8,750,000. However, after ascertaining the indigenous sourcing of a
good number of such items to be satisfactory, DIC vide its letter dated
13.9.1995, requiring the bidder to bid on the basis of indigenization
scope to the maximum extent possible. The request was based on
clause 14.3 of the ITB, which prescribed that items quoted in the bid
to be imported could be subsequently transferred to indigenous
supply for which NRL was to pay at actuals maximum whereof to be
limited to the computed value on site delivery basis on the pricings
quoted originally for that of the imported origin. Clause 14.3 of the
Instructions to Bidders reads as under:
" In case any item, quoted as imported in
the bid, but is subsequently transferred to the Indian
category, the total cost on project-site-delivery basis
for such item will be payable by Owner at actuals but
maximum limited to the computed value on site
delivery basis based on the pricings quoted originally
for that of imported origin."
Though this was agreed by NRL but it delayed the formal decision
and DIC arranged procurement of the substituted indigenous
materials by undertaking market survey, selecting Indian
manufactures, supplying of design and drawing to the manufacture,
ensuring product with quality control and supplies of finished project
within a stipulated time frame for which it incurred cost and expenses
to the tune of Rs. 25.3 crore which included the cost borne by DIC
towards procurement , service charges, inspection and expediting
charges, overhead expenses and profit. NRL duly approved the
indigenous manufacturers from whom the substituted items were
procured and permitted them to be incorporated in due execution of
the contract. NRL extended its formal approval for the substitution
eventually by its letter dated 13.3.1997. Though the DIC had claimed
Rs.25.3 crore incurred as the total cost, but it limited its claim to
Rs.21.7 crores being the procurement cost of indigenous materials by
applying the conversion rate of Rs. 36.28 per US $ as on 26.2.1996.
Rs.12 crores was paid by NRL and therefore DIC registered its
claim under the above head to the extent of Rs.9.6 crores. For
computing the actual cost of Rs. 25.3 crores, the DIC took into
consideration various factors; like bare cost, Excise duty, Central
Sales tax, freight and insurance, procurement service charges,
inspection and expediting charges, overhead expenses, profit and tax
deduction at source. The majority of the arbitrators after considering
all the materials placed before them came to the conclusion that
since EIL was the prime consultant of NRL for the execution of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 14
project, assessed the value of Rs.17.68 crores by applying its mind to
the submission of DIC, the majority of the Arbitrators accepted the
value expressed by EIL by its communication dated 4.11.1996 and
the majority of the Arbitrators as per clause 14.3 accepted, the advice
of EIL. Though NRL tried to withhold this letter, however same was
brought on record and the majority of the Arbitrators accepted it and
they added 15% profit margin and that worked out to Rs.2.65 crores
on the basis of the decision of this Court in M/s.Brij Paul & Ors. Vs.
State of Gujarat [ AIR 1984 SC 1703]. The majority of the Arbitrators
accepted the claim of the DIC to the extent of Rs.20.33 crores
(Rs.17.65 crores + Rs.2.65 crores ). An amount of Rs.12.19 crores
under this head was already received by the DIC therefore, rest of the
claim amount was accepted and awarded in favour of DIC i.e.
Rs.8.14 crores with US $ exchange rate at $1 = Rs.36.28 as
equivalent on 26.2.1996. As against this, the minority Arbitrator,
Justice M.M.Dutt held that the original documents and vouchers were
not produced by DIC as it was their duty to have produced the whole
vouchers to justify the purchases made in India for the substituted
materials. The minority arbitrator took the view that since the claim
of the DIC was to the tune of Rs.21.77 crores, Rs.12.19 crores
having been paid, there remains only Rs.9.58 crores. But according
to the minority award, as per the cost given by NRL their liability
comes to Rs.14.19 crores and therefore, DIC is not entitled to
beyond this amount. NRL also contested the expenses on account of
procurement service, inspection and expediting for Rs.97 lakhs and
overhead for Rs.3.47 crores as well as the claim of profit for Rs.3.14
crores and tax deduction at source for Rs.1.32 crores was not
payable. After discussion, Justice M.M.Dutt took the view that the
claimant was entitled to Rs.141,920,735.00 plus Rs.1,32,13,395.00
as tax deduction at source aggregating to Rs.15,51,34,130.00 only
out of which the claimant has received Rs.10,69,83,850.00.
Therefore, the claimant was entitled to receive the balance amount
of Rs.4,81,50,272.00 only and not Rs.9.6 crores as claimed. The
District Court disapproved the approach of the arbitrators and
emphasized that the word ’actual’ occurring in Clause 14.3 means
that the party should have produced the necessary evidence to
substantiate it. The High Court however did not approve the same
and took into consideration the letter dated 4.11.1996 of the EIL as
the basis and observed that the Tribunal has rightly accepted the
letter and set aside the order of the District Court. The High Court
further held that while construing the ’actuals’ under Clause 14.3. the
DIC in addition to the charges is also entitled to reasonable margin of
profit amounting to 15 per cent of the cost amount of Rs.17.68 crores
which does not appear to be illogical or arbitrary and confirmed the
finding of the majority award of the Arbitrators.
4. After considering the findings given by the majority and
minority Arbitrators and the view taken by the High Court on the
interpretation of Clause 14.3, in normal course the parties should
have led evidence to substantiate their claims with reference to
vouchers and other documents in evidence in order to justify their
claim, but in the present case we find that when NRL through the
communication dated 4.11.1996 have accepted the total value to the
extent of Rs.14.19 crores, then there is no reason why this should not
have been accepted as they have examined all the items in their
letter. Be that as it may, the fact remains that the DIC has
purchased the indigenous materials and substituted that as
permissible under Clause 14.3, then there is no reason to deny them
the cost for the same especially when intrinsic evidence is available
i.e. an independent body \026 NRL which is a Government of India
undertaking and conceded the amount to the extent of Rs.14.19
crores as the actual cost. Therefore, taking that Rs.14.19 crores as
the actual and Rs.12.19 crores having been paid, we think under this
head, the DIC is legitimately entitled to a sum of Rs.2 crores against
their claim of Rs.9.6 crores. However, the view taken by the minority
Arbitrator with regard to procurement service, inspection and
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 14
expediting, overhead and claim of profit appears to be correct and
that has been rightly disallowed by the minority Arbitrator and we
uphold that view. M/s. Brij Paul’s case (supra) related to breach of
contract under section 73 of the Contract Act and while allowing the
petition, 15% was assessed as loss of fright. This case was decided
on peculiar facts, it cannot provide any assistance to the contractor.
Hence, so far as the claim under Item No.1 for the substituted
material the respondent \026 DIC is entitled to a sum of Rs.2 crores.
[ Rs.2 crores allowed under item No.1]
5. Now, coming to another head \026 Turbo technical price,
under this head Turbocechnica SPA of Italy, a consortium partner of
DIC in the contract agreement with NRL, had to supply various
imported items for a consideration of US $4150000 and DM
22990000 as specified in the Price Schedule of the Overseas
Contract. The said consideration under Item No.2.1.1 was a
consolidated figure including payment on account of service like third
party inspection charges, ocean fright and marine insurance. Note 1
of the above Price Schedule permitted DIC / Turbotechnica to furnish
list of goods with CIF (cost insurance and freight) value of NRL for
availing concession in payment of customs duty payable in respect of
import from overseas. Note 2 reiterated that third party inspection
charges were included in the above price. DIC vide letter dated
13.9.1995 requested NRL to bifurcate the total consideration of the
import items into CIF cost and service cost and to amend the contract
agreement for that purpose but no amendment was made. It was
pointed out that if no amendment was made for the relevant portion,
Turnotechnica shall have to declare the entire contract value as CIF
cost to the customs authority and since payment of customs duty was
DIC’s responsibility, DIC will have to pay customs duty on service
portion also. DIC vide letter dated 25.11.1995 pointed out to NRL
that contract price consisted of CIF value, cost of design and
engineering and supervision and other incidental costs and requested
for break-up of costs, so that DIC may not pay customs duty on the
total contract price when such duty was payable on CIF value by the
owner. Therefore, the amendment not being carried out by the NRL,
DIC could not avail necessary concession in customs duty.
Therefore, they claimed under this head a sum of Rs.1.65 crores and
the same was accepted by the majority of the Arbitrators. The
majority took the view that DIC had to unnecessarily pay the customs
duty on service portion of the price consideration and as such allowed
the claim. As against this, Justice M.M.Dutt in minority took a contrary
view and held that NRL was not responsible for framing of such
agreement and it was held that it was the fault of DIC and as such
the claim was turned down. However, it was observed that DIC
could justify and claim the said amount from the Customs department
but NRL could not be held responsible for the extra duty paid by the
DIC. The District Judge agreed with the minority award. However,
the Division Bench of the High Court reversed the finding and
approved the view taken by the majority of the Arbitrators. We have
heard learned counsel for the parties and find that it depends upon
the framing of the terms of the agreement, if the DIC would have
been vigilant then they could have excluded the service charges; like
design engineering etc. It was their duty to have excluded the
services charges but they have not properly framed the contract and
they cannot insist on amendment of the contract. If all the services
were subjected to duty which they could have segregated the same
but since they did not do this, therefore they could claim the benefit.
No direction could be given to the contracting party to amend their
agreement. It is a mutual affair of the contracting party. The view
taken by the High Court does not appear to be correct. Secondly, it
was not possible for the NRL to amend the agreement as the same
has already been registered with the Customs authorities and the
Reserve Bank of India/ Hence, the DIC is not entitled to the aforesaid
amount of Rs.1.65 crores under this head.
{ Claim of Rs.1.65 crores under this head not allowed]
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 14
6. Next issue is with regard to countervailing duty. DIC claimed a
sum of Rs.8.78 crores which was paid on account of excise duty.
The claim of the DIC was that in fact at the time when the agreement
was executed between the parties, countervailing duty was not there
and it was introduced with effect from 1.1.1995 by Customs Tariff
(Amendment) Ordinance, 1994. New Sections 9, 9A and 9B were
introduced. This Ordinance was subsequently replaced by Customs
Tariff (Amendment) Act, 1995 which was deemed to have come into
force with effect from 1.1.1995. DIC submitted its initial bid on
16.3.1994 and final bid on 23.11.1994 by taking into consideration
customs duty on imported materials at 25% as operative then. DIC
could not have imagined the levy of countervailing duty at 12.5 %
brought into force with effect from 1.1.1995. Bid settlement was
made on 24.1.1995 and NRL finally awarded the contract to DIC by
fax of intent dated 31.1.1995. Therefore, the submission of DIC was
that at the relevant time there was no countervailing duty and it came
into force subsequent to the contract, therefore as per Section 64-A
of the Sale of Goods Act, 1930, the DIC is entitled to get this claim
reimbursed. NRL contended that as per Clause 14.1 in the statement
of claim pertaining to the contract clear instructions were given to the
bidders under clauses 15, 15.1, 15.2, 15.3 that entire customs
duties or levies including the stamp duty and import licence fee
levied on the equipments by Government of India or any State
Government will have to be borne by DIC. The payment of
countervailing duty was allowed by both the Arbitrators i.e. the
Majority and Minority. But the Division Bench of the High Court
reversed the finding. Aggrieved against this part of the order, appeal
has been filed by DIC which has been registered as Civil Appeal
arising out of S.L.P.(c) No.4409 of 2007.
7. In order to appreciate the submission of rival parties it will be
appropriate to refer to necessary clauses of the agreement; Clause 6
of the Consolidated Agreement read with Clauses 1.8, 13.2, 15.3.
The crucial clause is Clause 6 which reads as under :
" It is specifically understood and agreed
between the parties hereto that if there is any liability
towards taxes/ duties (including custom duty on
foreign component of supply portion) as may be
assessed/ claimed/ demanded by the concerned
Indian or Foreign authorities, it shall be the sole
responsibility/ liability of the contractor to pay all such
taxes/ duties and that the owner shall not be
responsible at all the payment of such taxes/ duties. "
Mr.Ganguli, learned senior counsel for the appellant in this case
submitted that the view taken by the High Court is not correct and as
per Section 64-A of the Sale of Goods Act, 1930, if there is no
contract to the contrary, then the parties are entitled to include the
amount of duties to the contract the equivalent amount paid. It was
submitted that both the majority and minority view of the Arbitrators
has upheld the claim and in that connection learned counsel has
placed reliance on a decision of this Court in Pure Helium India (P)
Ltd. v. Oil & Natural Gas Commission [ (2003) 8 SCC 593]. As
against this, learned counsel for the respondent herein has
supported the view taken by the High Court. The Division Bench of
the High Court after considering all the relevant provisions came to
the conclusion that as per various clauses of the contract since it was
the duty of the DIC to pay all taxes and customs duty and levies, they
cannot escape their liability to bear the countervailing duty imposed
by the Government. Mr. Ganguli, learned senior counsel for the
appellant in this appeal argued that in fact this was a new levy and at
the time when the negotiation was entered into it was not in
contemplation and in that connection learned senior counsel invited
our attention to a decision of this Court in The State of Madras v.
Gannon Dunkerley & Co., (Madras) Ltd. ( [1959] SCR 379).
Mr.Ganguli, learned senior counsel for the appellant submitted that so
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 14
far as interpretation of contract is concerned, the arbitrator is the best
judge because he has the jurisdiction to interpret the contract having
regard to the terms and conditions of the contract, the circumstances
of the case, the pleadings of the parties, the High Court should not
substitute its interpretation. In this connection, learned senior
counsel has invited our attention to the following decisions of this
Court.
(i) (1992) 4 SCC 440
Thermax Private Limited. V. Collector of Customs
(Bombay) New Customs House.
(ii) (1968) 3 SCR 387
Kollipara Sriramulu v. T.Aswathanarayana & Ors.
(iii) (1989) 2 SCC 38
M/s. Sudarsan Trading Co. v. Government of Kerala
& Anr.
(iv) (1999) 4 SCC 214
H.P.State Electricity Board v. R.J.Shah & Company
Learned senior counsel for the appellant also invited our attention to
Section 64-A of the Sale of Goods Act, 1930 and Section 69 of the
Contract Act, 1872 and submitted that the contract party is entitled to
reimbursement of tax liability. As against this, learned counsel for
the respondent submitted that Clause 2 (b) & Clause 6 of the
Consolidated Agreement read with Clause 2.1 (g) of the Instructions
to Bidders and Clause 13(f) of the Bid Document, leave no manner
of doubt that it is the duty of the contracting party to pay all taxes,
duties and levies. Relevant provisions are reproduced below :
" "Clause 2(b) all taxes and duties in
respect of job mentioned in the aforesaid contracts
shall be the entire responsibility of the contractor\005 "
" Clause 6. It is specifically understood
and agreed between the parties hereto that if there is
any liability towards taxes/ duties (including custom
duty on foreign component of supply portion) as may
be assessed/ claimed/ demanded by the concerned
Indian or foreign authorities, it shall be the sole
responsibility/ liability of the contractor to pay all such
taxes/ duties and that the owner shall not be
responsible at all for the payment of such taxes/
duties\005"
" Clause 2.1 (g). The scope of this proposal \005
will include the following (g) payment of customs
duty, port clearance charges etc. and customs
clearance at Indian port of entry\005"
" Clause 13(f) , Bid Documents:
\005.. Prices for the entire scope of work on
divisible contract basis and indicate the following
break-up: (f) lump sum charges on accounts of
customs duty, port charges etc. for imported
equipment and materials\005""
Reading of these documents leave s no manner of doubt that all the
taxes and levies shall be borne by the contracting party i.e. DIC.
8. We have considered the rival submissions of the parties. So far
as the legal proposition as enunciated by this Court in various
decisions mentioned above, it is correct that Courts shall not
ordinarily substitute its interpretation for that of the arbitrator. It is
also true that if the parties with their eyes wide open have consented
to refer the matter to the arbitration, then normally the finding of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 14
arbitrator should be accepted without demur. There is no quarrel with
this legal proposition. But in a case where it is found that the
Arbitrator has acted without jurisdiction and has put an interpretation
of the clause of the agreement which is wholly contrary to law then in
that case, there is no prohibition for the Courts to set things right. In
the present case, the aforesaid clauses reproduced above, clearly
lays down that all taxes, duties and levies have to be borne by the
contracting party. Countervailing duty which came into force with
effect from 1.1.1995 by way of ordinance (subsequently converted
into an Act) is a duty enforced by the Statute and hence in face of
Clause 2(b) and Clause 6 of the Consolidated Agreement read with
Clause 2.1 (g) of the Instructions to Bidders and Clause 13 (f) of the
Bid Document. There is leaves no manner of doubt that DIC has to
pay the same. Therefore, this levy has to be borne by the DIC and
they cannot escape from this situation. In this connection, learned
counsel has invited our attention to Section 64-A of the Sale of Goods
Act, 1930 which reads as under:
" 64-A. In contracts of sale, amount of
increased or decreased taxes to be added or
deducted.- (1) Unless a different intention appears
from the terms of the contract, in the event of any
tax of the nature described in sub-section (2) being
imposed, increased, decreased or remitted in respect
of any goods after the making of any contract for the
sale or purchase of such goods without stipulation as
to the payment of tax where tax was not chargeable
at the time of the making of the contract, or for the
sale or purchase of such goods tax-paid where tax
was chargeable at that time,-
(a) if such imposition or increase so takes effect
that the tax or increased tax, as the case may be, or
any part of such tax is paid or is payable, the seller
may add so much to the contract price as will be
equivalent to the amount paid or payable in respect
of such tax or increase of tax, and he shall be entitled
to be paid and to sue for and recover such addition;
and
(b) if such decrease or remission so takes effect
that the decreased tax only, or no tax, as the case
may be, is paid or is payable, the buyer may deduct
so much from the contract price as will be equivalent
to the decrease of tax or remitted tax, and he shall
not be liable to pay, or be sued for, or in respect of,
such deduction.
(2) The provisions of sub-section (1) apply to the
following taxes, namely;-
(a) any duty of customs or excise on goods;
(b) any tax on the sale or purchase of goods."
This section also clearly says that unless a different intention appears
from the terms of the contract, in case of the imposition or increase
in the tax after the making of a contract, the party shall be entitled
to be paid such tax or such increase. In this connection, the intention
of the parties is to be ascertained, as per the clauses mentioned
above. A perusal of the contract makes it clear that DIC is under
obligation to pay the taxes, duties and levies. Therefore, the
intention is very clear that taxes and duties will be the obligation of
the DIC. Section 69 of the Indian Contract Act, 1872 deals with
reimbursement of a person paying money due by another, in
payment of which he is interested. Section 69 has no role to pay in
the present case in view of the clear terms of the agreement that the
taxes, levies have to be paid by the DIC. Therefore, nothing turns on
Section 69 of the Contract Act. In view of the above discussion, we
are of opinion that so far as the payment of countervailing duty is
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 14
concerned, it was the obligation of the DIC and the view taken by the
Division Bench of the Act appears to be correct and there is no
ground to interfere with this part of the order. Consequently, we
uphold the judgment of the High Court and dismiss the appeal arising
out of S.L.P.(c) No.4409 of 2007 filed by the DIC.
9. The next question is with regard to payment of extra customs
duty due to fluctuation of the exchange rate. In this connection, the
majority of the Arbitrators took the view that the DIC was entitled to
Rs.2.09 crores on account of excess payment of customs duty on
account of fluctuation of the exchange rate. As against this, the
minority view taken by Justice MM Duty was to the contrary. He has
observed that the NRL had entered into a turnkey firm-price contract
with the sole object of avoiding any future additional burden till the
completion of the contract. He has also observed that the price
quoted in the bid documents is fixed and cannot be varied according
the variation of the fluctuation of the exchange rate of US dollar. He
has also observed that this also holds good both for upward and
downward variations. Therefore, he found that the claim of DIC
cannot be acceded to and accordingly rejected the claim of DIC. The
Division Bench of the High Court has affirmed the majority view.
10. We have heard learned counsel for the parties and
perused both the views expressed by majority as well as minority. In
this connection, it is relevant to mention Clause 12.2 of the
Instructions to the Bidders which clearly stipulates that it must be
understood and agreed that such factors have properly been
investigated and considered while submitting the bids. It also clearly
stipulates that no financial adjustments arising thereof shall be
permitted by the owner. Clause 12.2. of the Instructions to Bidders is
reproduced as under :
" 12.2. It must be understood and
agreed that such factors have properly been
investigated and considered while submitting the
bids. No claim for financial adjustment to the contract
awarded under these specifications and documents
will be entertained by the owner. Neither any change
in the time schedule of the contract nor any financial
adjustments arising thereof shall be permitted by the
owner, which are based on the lack of such clear
information of its effect on the cost of the works to
the bids."
Similarly, clause 13 which deals with price scope and basis clearly
stipulates that price for the entire scope of work on divisible contract
basis, break up has been given in the schedule. In this connection,
clause 13 which is most relevant reads as under :
" 13.0. Price Scope & Basis:
The Bidders shall quote in their proposals,
Prices for the entire scope of work on divisible
contract basis and indicate the following break-up
schedule:
a) Dosing and Engineering charges for the
complete works.
b) Lump sum Price on F.O.B.port of Shipment
basis for all Imported equipment and
materials.
c) Lump sum ocean fright and Insurance for
the above imported goods.
d) Lump sum Price on FOR/FOT dispatch
point basis for5 all indigenous equipment/
material, cement and steel, inclusive of
taxes, duties, levies, licence feee etc.
e) Lump sum service charges towards
documentations, handling, forwarding,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 14
payment of customs duty, inland
transportations, transit insurance of all the
imported goods.
f) Lump sum charges on account of customs
duty, port charges etc. for Imported
equipment and materials.
g) Lump sum charges, forwards,
transportations through waterways for over
Dimensional consignment inclusive or en
route Indian/ Bangladesh Custom clearance
to Project site.
h) Lump sum charges toward clearance,
handling, transportation ( other than ODCS)
storage, preservation and conservation of
all equipment at project site.
i) Lump sum cost of all civil works.
j) Lump sum charges toward pre-assembly, if
any, erection, testing and commissioning of
the complete system.
k) LIST OF RECOMMENDED SPARES for
two years normal operation indicating Parts
name, cagalogues No., quantity and Unit
Prices.
l) List o components with itemized unit rate for
all individual equipment and materials, to
enable Price Adjustment, if required during
detailed engineering and execution of the
work.
m) Fees/ Charges payable, if Owner/
Consultant opts for inspection by Lloyds
Register or third party inspection for
IMPORTED equipment.
n) Agency commission if any, included for
Indian Agents."
Clause 14 deals with pricing and currency changes. Clause 14.1.
reads as under :
" The prices quoted for the entire scope of work
shall remain firm and fixed till complete execution of
the work."
In these parameters of the terms and conditions, that the price quoted
for the entire work shall remain firm and fixed till the complete
execution of the work, the heading pricing and currency changes
leaves no manner of doubt that there is no scope for giving any
benefit of fluctuation on the exchange rates. Once the price is fixed
there is no provision for giving any benefit for fluctuation in terms of
the contract then in that case, the claimant \026DIC cannot raise this
claim of excess payment made towards customs duty on account of
fluctuation on exchange rate. The minority view expressed by Justice
M.M.Dutt appears to be correct. Had there been downward trend in
the exchange rate, then the DIC would not have slashed the
exchange rate. If the downward trend cannot benefit either party then
equally the up-ward trend cannot benefit the DIC for claiming the
payment of the higher customs duty on account of fluctuation in
exchange rate. Therefore, the expression, ’firm and fixed’ is clear
answer to the question if during the course of contract certain
fluctuation has taken place in the market then on that count the
claimant cannot raise extra demand on account of upward trend in
the exchange rate. In this connection, reliance was placed on a
decision of this Court in Pure Helium India (P) Ltd. v. Oil & Natural
Gas Commission [(2003) 8 SCC 593]. In this case this Court granted
the contractor’s claim for being compensated for foreign exchange
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 14
fluctuation and not for any escalation in the price. This Court held
that the claimant does not violate any terms of contract. In the
present case, in view of the fact that the price is firmly fixed and DIC
has clearly understood and agreed the terms of the contract, and it
was clearly stipulated in Clause 12.2. that no financial adjustment
arising there from shall be permitted by the owner. In these
circumstances, the minority view taken by the Arbitrator, Justice
M.M.Dutt appears to be well founded. Pure Helium India (P) Ltd.
(supra) was decided on peculiar facts. As such, it cannot provide us
any assistance.
11. Similarly, our attention was invited to a decision of this
Court in Tarapore and Company v. Cochin Shipyard Ltd., Cochin &
Anr. [ (1984) 2 SCC 680]. In this case, their Lordships held that if a
question of law is specifically referred by the parties to the arbitrator
for decision, award of the arbitrator would be binding on the parties
and court will have no jurisdiction to interfere with the award even on
ground of error of law apparent on the face of award. We have no
quarrel with this proposition. So far as other decisions of this Court
mentioned above, that the Court should accept the interpretation of
the terms of the agreement made by the arbitrator, and should not
interfere, there is no two opinion on that question but in the present
case, we are faced with a peculiar situation that the three Arbitrators
out of whom two has taken one view of the matter and the third has
taken another view of the matter. The District Judge has also set
aside the award on some issues and the High Court has also
accepted some items of the majority award of the Arbitrators and
some items of the minority award of the Arbitrator. Therefore, in the
peculiar state of affairs in the present case when there is variation of
views ; the majority award takes one view and the minority award
takes another view, the District Judge takes the third view and the
High Court takes the fourth view, in the state of these conflicting
views on the subject, we have to enter into the merit to put an end to
the controversy by adjudicating the conflicting views of various
Forum. However, general consensus of the view emerging from
various judgments of this Court is there is no two opinion that the
Court should not sit in appeal and normally should not interfere with
the views of the Arbitrator in interpretation of the terms of
agreements interpreted by the Arbitrator when the Arbitrator is
appointed with consent of parties. However, in peculiar facts and
circumstances of the case, the view taken by the High Court in
accepting the majority view of the arbitrators cannot be accepted. We
overrule the view taken by the High Court in accepting the majority
view and accept the minority view taken by Justice M.M.Dutt and
decline the claim of DIC in the sum of Rs.2.9 crores on account of
fluctuation in the exchange rate.
[Claim of Rs.2.9 crores on account of fluctuation on
exchange rate declined]
12. The next item is with regard to liquidity damages for delay of
929 days. So far as this liquidity damages is concerned, it was
decided purely on the question of fact. The majority of the Arbitrators
after review of the factual aspect held that whole contract was time
bound delay occurred at various level, like delay in approval of
drawing and designs submitted by DIC, delay in opening of letter of
credit. After review of all these factual aspects, the Tribunal
concluded that on account of delay for about 929 days, the contractor
had suffered loss on account of fluctuation in the prices as well as
fluctuation in the exchange rates and therefore, the claimant claimed
liquidity damages to the extent of Rs.8.9 crores under this head. The
question is whether the case of DIC for such liquidity damages was
covered under Clause 18 or Clause 22 of the General terms and
conditions of the contract. Clause 18 stipulates the price reduction
schedule for delay in co-operation. In case the contractor fails to
complete successfully the system within the time fixed under the
contract, the contract price shall be reduced at the rate of 1% of the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 14
contract value per week of delay or part thereof subject to the
maximum of 15% of the contract value. Clause 18 of the General
conditions of the contract reads as under :
" 18.0 Price Reduction Schedule for
delay in Co-operation: If the Contractor fails to
successfully commission the complete system within
the time fixed under the Contract, the Contract Price
shall be reduced at the rate of 1% of the Contract
value per week of delay or part thereof subject to the
maximum of 15% of the Contract value. "
But this clause was amended subsequently and one percent was
reduced to = percent and 15 percent was reduced to 5 per cent as
per the consolidated agreement. The said amendment reads as
under:
" II) PRICE REDUCTION SCHEDULE IN
THE ENVENT OF DELAYS:
If the contractor fails to comply any of the
time schedule mentioned hereinabove, the Contract
price shall be reduced @ =% of the total contract
value per week of delay or part thereof subject to a
maximum of 5% of the total contract value i.e. total
aggregate contract value of Contract Nos.3244-00-
LZ-PO-7012/10091 and 3244-00-LZ-PO-7013/10092
mentioned hereinabove. Price reduction as set forth
in this clause shall be the sole remedy available to
owner and the sole liability of the contractor for delay.
In the event of delay of over 10 weeks, owner may
exercise their rights to invoke any or all provisions
under this agreement."
This was for the contractor’s failure to complete the contract.
13. However in this connection, our attention was invited to
clause 22. This relates to delay on the part of the owner or its various
agents. Clause 22 reads as under :
" 22.0 Delay by Owner or his Authorised
Agents :
22.1. In case the Contractor’s performance is
delayed due to any act of omission on the part of the
Owner or his authorized agents, then the Contractor
shall be given due extension of time for the
completion of the works, to the extent such omission
on the part of the owner has caused delay in the
Contractor’s performance of his work.
22.2. In addition, the Contractor shall be entitled
to claim demonstrable and reasonable compensation
if such delays have resulted in any increase in the
cost. The owner shall examine the justification for
such a request for claim, and if satisfied, the extent of
compensation shall be mutually agreed depending
upon the circumstances at the time of such an
occurrence."
In terms of this clause if delay has been caused to the contractor on
account of the omission or commission on the part of the owner or its
authorized agent then the contractor is entitled to claim demonstrable
and reasonable compensation if such delay has resulted in any
increase in the cost. In that case, the owner shall examine the
justification for such claim and if satisfied then compensation shall be
mutually agreed depending upon the circumstances at the time of
such an occurrence. Since DIC’s claim for compensation was on
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 14
account of delay on the part of the owner, therefore, it was the
obligation on the part of DIC to demonstrate as to how delay has
escalated the loss to it. Then and then alone the claimant will be
entitled to the compensation for this delay. The minority Arbitrator
has taken the view that since the claimant has nothing to
demonstrate therefore, it is not entitled to any compensation
whatsoever. However, the majority has taken the factum of delay
by reviewing all evidence on record and has come to the conclusion
that there was a delay of 929 days and on the basis of factual
assessment has granted damages to the extent of 5 % of the total
contract value. An argument was raised that in fact 5 % damages
could be granted under clause 18 to the owner for the delays on
account of the contractor and the contractor has to demonstrate
reasonably how loss has occurred to him. However, the majority of
the Arbitrators has taken into consideration the parameter that in
case the delay was occasioned on the part of the contractor, then
the owner would have been entitled to the damages to the extent of
5%. This has been taken as the yardstick and the compensation has
been worked out at 5% of the contract value and damages to the tune
of Rs.8.9 crores has been awarded to the claimant. We are of
opinion that this issue is purely dependent on the factual controversy
of the matter and the majority of the arbitrators has assessed the loss
on account of the delays on the part of the owner and awarded 5% of
the contract value as a measure to award compensation to the owner
on account of the delay on the part of the owner in completing the
work and no exception can be taken to this approach. The amount
cannot be said to be a wrong assessment of the situation. We cannot
sit over the finding of fact arrived at by the majority of Arbitrators and
affirmed by the High Court. Therefore, we accept the view taken by
the Division Bench of the High Court in accepting the view the
majority of the Arbitrators in granting damages to the tune of Rs.8.9
crores in favour of the claimant- DIC.
[ Rs.8.9 crores granted as damages for delay of 929 days ]
13. Next item relates to interest on borrowing of the funds.
Under this head, the DIC has claimed Rs.6.5 crores. The majority of
the Arbitrators has granted Rs.0.2 crores. However, the minority
award has denied the claim. The High Court has affirmed the
majority view of the Tribunal. Since in view of our finding on the issue
of delay in liquidity damages we are of opinion that the view taken by
the majority of the arbitrators is correct as there was delay on the part
of the owner \026 NRL and therefore, DIC had to pay interested on the
delayed sum. Therefore, the view taken by the majority of the
arbitrators cannot be said to be wrong as it is a pure question of fact
and therefore, we are of opinion that the grant of Rs.0.2 crore
towards interest on delayed amount has been rightly held by the
majority of the arbitrators and affirmed by the High Court.
[ Rs.0.2 crores granted as interest paid on delayed funds]
14. The next claim is with regard to interest. The majority of
the arbitrators have granted interest on the amount at the rate of 12
per cent pendente lite and post pendente lite at rate of 18 per cent
but the minority arbitrator, Justice M.M.Dutt has granted 10 per cent
interest uniformally. The grant of interest is discretionary and the
majority of the arbitrators has rightly granted interest at the rate of 12
per cent pendente lite and at the rate of 18 per cent post pendent
lite. Therefore, no exception can be taken to grant of such interest.
Consequently, we affirm this finding of the majority of the Arbitrators
and of the High Court.
[Interest at the rate of 12% P.I. & at the rate of 12% post P.I.]
15. Hence, as a result of our above discussion, we are of
opinion that the claimant \026DIC is entitled to Rs.2 crores for
substituted material, Rs.8.9 crores for liquidity damages, Rs.0.2 crore
as interest paid on the delayed funds i.e. Rs.11.1 crore ( Rs.2 crore +
Rs.8.9 crore + Rs.02 crore) and finally interest at the rate of 12 per
cent pendente lite from the date of the claim petition till realization.
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 14
The payment should be made within a period of six months from
today failing which it will carry interest at the rate of 15 per cent per
annum. The appeal arising out of S.L.P.(c) No.20989 of 2006 is
partly allowed. The order passed by the High Court is modified as
indicated above. The claim of the DIC is decreed to the extent
indicated above. However, the appeal arising out of S.L.P.(c)
No.4409 of 2007 filed by the DIC is dismissed. No order as to costs.