Full Judgment Text
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 1 of 19
CASE NO.:
Appeal (civil) 4921 of 2000
PETITIONER:
WEST BENGAL STATE ELECTRICITY BOARD
Vs.
RESPONDENT:
PATEL ENGINEERING CO. LTD. & ORS.
DATE OF JUDGMENT: 15/01/2001
BENCH:
S.S.M.Quadri, S.N.Phukan
JUDGMENT:
L.....I.........T.......T.......T.......T.......T.......T..J
J U D G M E N T
Syed Shah Mohammed Quadri, J.
This appeal by the West Bengal State Electricity Board
is from the common judgment of a Division Bench of the High
Court at Calcutta in M.A.T. No.398 of 2000, C.A.N. No.1089
of 2000 and M.A.T. No.523 of 2000 with cross objections
(C.O.T. No.522 of 2000) dated April 4, 2000 dismissing the
appeals and cross objections and confirming the order of the
learned Single Judge in W.P.No.22458(W) of 1999 dated
February 3, 2000. To appreciate the controversy in this
case narration of the following relevant facts will be
necessary. As a pragmatic solution to meet the peak demand
of the energy/power by the West Bengal and also to cater to
the requirements of the entire Eastern Region, the West
Bengal State Electricity Board (for short, the appellant)
formulated Purulia Pumped Storage Project (for short,
the Project), at an estimated cost of about Rs.3,188.9
crores with an installed capacity of 900 M.W. For funding
that project the Central Government entered into a loan
agreement with the Overseas Economic Cooperative Fund now
Japan Bank of International Cooperation (for short, the
J.B.I.C.). The Project is proposed to be completed in six
Lots of which Lot No.4 relates to main civil works. For
carrying out the work of Lot No.4, the appellant, after
complying with the formalities and after satisfying itself
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 2 of 19
of the pre- qualification of the bidders, invited revised
tenders (hereinafter referred to as, the tenders). The
bids were to be submitted on or before April 27, 1998.
Three bidders are now in fray. The first is a consortium of
four companies (respondent Nos.1 to 4), the second is M/s.
Taisei Corporation (respondent No.10) and the third is M/s.
Skanska International (respondent No.11). They submitted
their bids along with the summary sheets thereof. On
September 8, 1999 the bids were opened in the presence of
the representatives of the bidders and they were read out;
the bid of respondent Nos.1 to 4 was Rs.647.90 crores, of
respondent No.11 was Rs.691.22 crores and of respondent
No.10 was 726.50 crores. While the details of the bid were
under scrutiny, by letter dated October 25, 1999, respondent
Nos.1 to 4 informed the appellant that there was a
repetitive systematic computer typographical transmission
failure and requested that it be corrected. On December
17, 1999 they sent another letter stating that they had
reason to believe that the appellant was evaluating their
price bid by an illogical and incorrect application of the
Instructions To Bidders (for short, the ITB) and pointed
out that the mistake indicated in their letter of October
25, 1999 was that Indian Rupee unit rate stated in the first
line Item 0.2 was repeated in the next two succeeding lines,
which is clerical in nature and not an arithmetic error.
They emphasised that their bid was the lowest at Rs.647.90
crores and assured that they would maintain the said bid
price. Under the ITB, the appellant evaluated their bid and
on December 18, 1999 informed them that during checking of
their bid documents a good number of arithmetic errors was
discovered. Copies of duly corrected documents were
communicated to the said respondents for their response to
be sent in writing to the appellant before December 27, 1999
(1700 IST). A caveat was also entered that the said letter
did not provide any confirmation towards acceptance of their
bid and subsequent award of contract by the appellant.
Challenging the validity of the said letter of the appellant
dated December 18, 1999, respondent Nos.1 to 4 filed the
aforementioned writ petition in the High Court at Calcutta.
On December 21, 1999 a learned Single Judge of the High
Court granted an interim direction to the appellant to
consider the representation which would be made to it by the
writ petitioners (respondent Nos.1 to 4). A representation
was accordingly made to the appellant on December 23, 1999,
which was decided by the Evaluation Committee of the
appellant on January 6, 2000. The decision taken by the
appellant pursuant to the order of the High Court dated
December 21, 1999 did not meet with the approval of the High
Court. On February 3, 2000, while disposing of the writ
petition, a learned Single Judge of the High Court directed
the appellant to reconsider the representation of respondent
Nos.1 to 4, after giving hearing to them, and to pass and
communicate a reasoned order within one week from the date
of the order. Against the said order of the learned Single
Judge, the aforementioned appeals and cross-objections were
filed both by the appellant as well as by respondent Nos.1
to 4. A Division Bench of the High Court at Calcutta, by
the impugned common judgment, dismissed the appeals and the
cross-objections upholding the order of the learned Single
Judge, directed the appellant to permit respondent Nos.1 to
4 to correct the errors in the bid documents and then
consider their bid along with the other bids and take a
decision objectively and rationally. Mr. Altaf Ahmed, the
learned Additional Solicitor General, appearing for the
appellant, has submitted that the appellant is bound by the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 3 of 19
ITB and it acted accordingly. The letter dated October 25,
1999 of respondent Nos.1 to 4 did not indicate the errors in
the bid documents and the correction sought by them. Even
their letter of December 17, 1999 did not specify in any
detail the desired corrections, therefore, the appellant
proceeded to evaluate the bid in terms of ITB. The actual
scope of correction sought by respondent Nos.1 to 4 came to
light in their representation dated December 23, 1999, filed
after approaching the High Court. The appellant, submitted
the learned Additional Solicitor General, committed no wrong
in rejecting the representation as the same was not
acceptable in terms of Clause 29 of the ITB because neither
the unit rate can be changed nor the price bid can be
altered at the request of the bidder; the unit rate quoted
is final and the appellant can correct only arithmetic
mistakes in the line total on the basis of the quoted unit
rate. Mr.Ashok H.Desai, the learned senior counsel
appearing for respondent No.11, argued that the resolution
of the appellant rejecting the representation on January 6,
2000 was in accordance with Clause 29.1(b) of the ITB and
that there was no case for interference by the High Court.
The decision of the appellant in evaluating the bid
documents in terms of ITB, submitted the learned counsel,
could not be termed as arbitrary or illegal; in the
example: A x B = C; B being the quantity for which the bid
is offered; A and C being the unit rate and the result of
the multiplication respectively, are unalterable at the
instance of the bidder. If any arithmetic error in arriving
at the line total is noticed by the appellant, that alone
could be corrected by it. But, the correction sought by
respondent Nos.1 to 4, was in effect a change in the unit
rate which was impermissible and, therefore, the decision of
the appellant could not have been interfered with by the
High Court. Mr.Bhaskar P.Gupta, the learned senior counsel
appearing for respondent No.10, submitted that the unit rate
given by respondent Nos.1 to 4 was an essential term which
would be evident from Clauses 14, 27 and 29 of the ITB, so
permitting them to correct the bid would tantamount to
modifying the essential term of the bid and as such the High
Court ought not to have directed the appellant to permit
correction of bid documents and further to consider their
bid along with the other bids. Mr.P.Chidambaram, the
learned senior counsel appearing for respondent Nos.1 to 4,
argued that in Annexures 1 to 9 which comprised of 749 items
there were mistakes in only 37 items due to the fault of the
computer; the nature of mistake was not arithmetic (which
would mean in multiplication or addition) but mechanical,
attributable to the computer and that such mistakes are not
covered by Clause 29 of the ITB; in a case of an unintended
mistake, a court of equity would not be a silent spectator
and the High Court, being both a court of law and equity,
had rightly directed the appellant to permit correction of
the mistakes by respondent Nos.1 to 4. It was submitted
that having regard to the nature of the mistakes, the
appellant itself ought to have sought clarification from the
said respondents under Clause 27 of ITB instead of
evaluating the bid on the basis of an unintended unit rate
to reach an astonishing figure which was wholly
disproportionate to the cost of the Project. His contention
is that once the total bid price is maintained, the unit
rate is a matter of arithmetic exercise which should have
been corrected by the appellant; further the mode of
payment by the appellant for the work done is not on the
basis of each unit but on the basis of bid price. Accepting
that the bid price is unalterable, the unit rate should be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 4 of 19
regarded as adjustable. It was also argued by Mr.
Chidambaram that there was no mistake in giving the unit
rate as such; the mistake was in giving the conversion
equivalent in US Dollars and, therefore, the correction not
being the one falling under Clause 29 of the ITB was rightly
permitted to be corrected by the High Court. Finally, he
contended that their bid being less than the bids of
respondent Nos.11 and 10 by Rs.40 crores and Rs.80 crores
respectively, the High Court rightly directed consideration
of the bid of respondent Nos.1 to 4 after due correction of
the bid documents in public interest which did not warrant
interference by this Court. In the light of the above
contentions, we have to examine as to what is the
permissible course of action under ITB. A reference to the
relevant clauses of the ITB will be apposite here. Clause
14.1 says that unless stated otherwise in the bid documents,
the Contract shall be for the whole Works as described in
sub-clause 1.1 thereof based on the schedule of unit rates
and prices submitted by the bidder. Clause 14.2 enjoins all
the bidders to fill in rates and prices for all items of the
Works described in the Bill of Quantities both in figures
and words and cautions that items against which no rate or
price is entered by the bidder will not be paid for by the
Employer (the appellant herein) on the execution of items of
those works and the same shall be deemed covered by the
other rates and prices in the Bill of Quantities. With
regard to the currencies of the bid, Clause 15.1 directs
that unit rates and prices shall be quoted by the bidder in
Indian Rupee (INR) and either in U.S. Dollar or Japanese
Yen. The bidders are given option to assess the component
of currency requirements as follows: (a) for those inputs
to the Works which the bidder expects to supply from within
the Employers country (the appellants country - India) in
Indian Rupee; and
(b) for those inputs to the Works which the bidder
expects to supply from outside the Employers i.e. outside
India in U.S. Dollar or Japanese Yen.
In regard to modification and withdrawal of bids,
Clause 24.1 provides that the bidder may modify or withdraw
his bid after bid submission but before the deadline for
submission of bids. The mandate of Clause 24.3 of the ITB
is that no bid shall be modified by the bidder after the
deadline for submission of bids. Inasmuch as Clauses 27 and
29 of the ITB deal with clarification of bids and correction
of errors respectively and their true interpretation has a
bearing on the decision in this case, it will be apt to
quote them here : 27. Clarification of Bids 27.1 To
assist in the examination, evaluation and comparison of
bids, the Employers authorised representative may, at his
discretion, ask any or all bidders for clarification of
his/their Bids, including breakdowns of unit rates,
technical information, documents and materials after opening
of the Bid. The request for clarification and the response
shall be in writing or by cable, but no change in the price
or substance of the Bid after opening the Price Bid shall be
sought, offered or permitted except as required to confirm
the correction of arithmetic errors discovered by the
Employers authorised representative in the evaluation of
the bids in accordance with Clause 29 of ITB.
29. Correction of Errors
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 5 of 19
29.1 Bids determined to be substantially responsive
will be checked by the Employers authorised representative
for any arithmetic errors. Errors will be corrected by the
Employers authorised representative as follows:
(a) where there is a discrepancy between the amounts
in figures and in words, the amount in words will govern;
and (b) where there is a discrepancy between the unit rate
and the line item total resulting from multiplying the unit
rate by the quantity, the unit rate as quoted will govern.
(c) Where there is a discrepancy between figures and in
words of an unit rate, the unit rate as quoted in words will
govern. 29.2 The amount stated in the Form of Bid will be
adjusted by the Employers authorised representative in
accordance with the above procedure for the correction of
errors and shall be communicated to the Bidder in writing
for his acceptance in writing within seven (7) days from the
date of issue of such communication. Such corrections
however shall be binding upon the Bidder. If the Bidder
does not accept the corrected amount of bid, his bid will be
rejected, and the bid security shall be forfeited in
accordance with sub-clause 17.6(b) of ITB. It may be seen
that Clause 27.1 enables the appellant or its authorised
representative to ask any or all bidders for clarification
of his/their bids, including breakdowns of unit rates,
technical information, documents and materials after opening
of the bid. The request for such clarification is required
to be made in writing or by cable, so also the response to
such request. It is important to note that the said clause
prohibits seeking, offering or permitting any change in the
price or substance of the bid after opening of the price
bid. The exception provided to that mandate is correction
of arithmetic errors discovered by the appellant’s
authorised representative in the evaluation of the bids in
accordance with Clause 29 thereof. A plain reading of
Clause 29.1 shows it has two limbs; the first limb imposes
a duty on the appellants authorised representative to check
bids determined to be substantially responsive for any
arithmetic errors and the second postulates correction of
such errors by the authorised representative in the manner
laid down in sub-clauses (a) to (c) thereof. Sub-clause (a)
says that in the event of discrepancy between the amounts in
figures and in words, the amount in words will govern;
sub-clause (b), which is germane for our discussion,
provides that in case of a discrepancy between the unit rate
and the line item total resulting from multiplying the unit
rate by the quantity, the unit rate as quoted will govern;
and the import of sub-clause (c) is that in case of a
discrepancy between figures and in words of any unit rate,
the unit rate as quoted in words will govern. Where errors
are corrected in accordance with the above guidelines by the
appellants authorised representative, Clause 29.2 specifies
the procedure to adjust the amount stated in the Form of
Bid. The authorised representative has to communicate the
correction of errors to the bidder in writing for his
written acceptance within seven days from the date of issue
of such communication. It also provides that such
corrections shall be binding upon the bidder and in the
event of the bidder not accepting the corrected amount of
bid, his bid will be rejected and the bid security is liable
to be forfeited in accordance with sub- clause 17.6 (b) of
the ITB. Now adverting to the Annexures, the statement of
B.Upper Dam price bid submitted by respondents 1 to 4
discloses that with reference to each work item the quantity
thereof is mentioned. The bidder is expected to give the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 6 of 19
unit price in Indian Rupee as well as in U.S. Dollar both
in figures as well as in words and enter the line item total
resulting from multiplying the unit rate by the quantity. A
plain reading of sub-clause (b) of Clause 29.1, referred to
above, leaves no room for doubt that once the unit rate and
line item total are filled in by the bidder, both the quoted
unit rate and item total are treated as unalterable at the
instance of the bidder though arithmetic errors in arriving
at line item total by multiplication are permitted to be
corrected by the appellants authorised representative.
This being the intendment of the ITB, we shall now examine :
(i) whether the correction made by the appellant in the bid
documents of respondent Nos.1 to 4 and consequential
evaluation of their bid communicated with letter dated
December 18, 1999 are valid in law; and (ii) whether
respondents 1 to 4 are entitled to seek correction in their
bid documents either under ITB or in equity and the
direction given by the High Court to the appellant to permit
the correction of errors, is sustainable. Before proceeding
to ascertain answers to the above questions, it will be
useful to bear in mind the principles governing the exercise
of power of judicial review by the High Courts. We consider
it unnecessary to refer to cases on the scope of the power
of judicial review of administrative action by the High
Court as a three Judge Bench of this Court has, after
exhaustive consideration of long line of authorities,
succinctly summarised the position and laid down the
following principles in Tata Cellular Vs. Union of India
[1994 (6) SCC 651] : (1) The modern trend points to
judicial restraint in administrative action. (2) The court
does not sit as a court of appeal but merely reviews the
manner in which the decision was made. (3) The court does
not have the expertise to correct the administrative
decision. If a review of the administrative decision is
permitted it will be substituting its own decision, without
the necessary expertise which itself may be fallible. (4)
The terms of the invitation to tender cannot be open to
judicial scrutiny because the invitation to tender is in the
realm of contract. Normally speaking, the decision to
accept the tender or award the contract is reached by
process of negotiations through several tiers. More often
than not, such decisions are made qualitatively by experts.
(5) The Government must have freedom of contract. In other
words, a fair play in the joints is a necessary concomitant
for an administrative body functioning in an administrative
sphere or quasi-administrative sphere. However, the
decision must not only be tested by the application of
Wednesbury principle of reasonableness (including its other
facts pointed out above) but must be free from arbitrariness
not affected by bias or actuated by mala fides. (6)
Quashing decisions may impose heavy administrative burden on
the administration and lead to increased and unbudgeted
expenditure. In the light of these principles, we shall
determine the aforementioned points. Taking up the first
question first, it will be necessary to understand the
nature of errors, correction made by the appellant and the
relief sought by respondent Nos.1 to 4 in respect of 37
items in the bid documents. We shall extract here, as a
sample of errors in 37 items, the price bid submitted by
respondent Nos.1 to 4 relating to B. Upper Dam found on
page No.70 of Vol.IV of the documents (marked A). It
reads thus: Annexure
B. Upper Dam A
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 7 of 19
Price Bid as Submitted
Item
Work Item
Esc.
Coeff.
Remarks
Unit
Quantity Unit Price
Amount
Clause In Specifica- tions
INR
US$
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 8 of 19
Figure Words
1.Care of river
02 Rock Excavation
I
Cum
1000
148.08
One hundred forty-eight point nil eight
148,077.97 7.4
148.08
One hundred forty-eight point nil eight
3,384.64
03 Impervious Core Embankment I
Cum
148.08
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 9 of 19
One hundred forty-eight point nil eight
328,418.53 9.5
1.92
One point ninety-two
7,506.71
According to respondents 1 to 4, the above price bid
should be corrected to read as given in the following
statement (marked B):
B
Item
Work Item
Esc. Coeff.
Remarks
Unit
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 10 of 19
Quantity Unit Price
Amount
Clause In Specifica- tions
INR
US$
Figure Words
1.Care of river
02 Rock Excavation
I
Cum
1000
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 11 of 19
148.08
One hundred forty-eight point nil eight
148,077.97 7.4
3.38
Three point thirty eight
3,384.64
03 Impervious Core Embankment I
Cum
3,900
84..21
Eight four point twenty one
328,418.53 9.5
1.92
One point ninety-two
7,506.71
A perusal of the price bid statement A shows that
the unit price filled in by the bidder in the first line
against Item (02) - Work Item -, Rock Excavation is
repeated in two lines - in the second line of the same item
and in the first line of Item (03) - Work item - Impervious
Core Embankment. In the quantity column, 1000 is noted
by the appellant. The unit rate for Rock Excavation is
given by respondent Nos.1 to 4 in the first line in Indian
Rupee as Rs.148.08 both in figures as well as in words. In
the amount column Rs.148,077.97 is entered which is arrived
at by multiplying quantity, 1000, by unit rate, Rs.148.08.
It contains an arithmetic error; instead of Rs.148,080.00,
it is noted as Rs.148,077.97. It has been noticed above
that under Clause 29.1(b) of the ITB, such an error in the
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 12 of 19
line total in the amount column is amenable for correction
and not the unit rate noted by the bidder in the figure
column. In the second line, the same entry is repeated
though that line should contain unit rate in U.S.Dollar
which is rupee equivalent of the unit rate mentioned in the
first line. Respondent Nos.1 to 4 seek correction of
148.08 in the second line as 3.38 in the figure column
and also in words to conform to 3,384.64 which is noted in
the amount column, to wit as US Dollar equivalent of
148,077.97 Indian Rupee in the first line. This appears to
be the import of their letter of December 17, 1999.
Respondent Nos.1 to 4 seek correction of the entries in the
third line also which is the first line against work item
Impervious Core Embankment. It is plain that against this
Work Item the entries in the first line are quite different.
The quantity column is blank, though 3900 should have been
noted therein. In that line also the entries in the first
line are repeated. There the correction sought is that the
figure column should read as 84.21 both in figure and words.
It is stated that in the second line the unit rate 1.92 both
in figures and words, represents U.S. Dollar equivalent of
84.21 Indian Rupee which is now sought to be inserted. The
errors in other 36 items are said to be similar. Had the
errors been confined to these aspects, it would not have
resulted in material change in the unit rate because the
unit rate in one of the permissible currencies is correctly
given and there will be no discrepancy as envisaged in
sub-clause (b) of Clause 29.1. It would not really be a
case of incorporating a new unit rate but a case of either
recording U.S. Dollar equivalent of the unit rate already
noted in Indian Rupee or vice versa as given in statement
B above. In such a case, perhaps, they would have been
entitled to equitable relief of rectification of mistake.
But here, as would be shown presently, the position is
different. With regards to the mistakes in the bid
documents, for the first time respondent Nos.1 to 4 informed
the appellant in their letter of October 25, 1999 which runs
as follows :
Re : Purulia Pumped Storage Project Lot 4 - Main
Civil Works - Resubmittal Price Bid. Dear Sirs, We regret
that certain repetitive systematic computer typographical
data transmission failure have occurred in items as per
attached annexure in our bid submitted to you on 08.09.99.
In order to dispel any doubts, we hereby unconditionally
declare that we stand by the amounts (both INRs and US $)
against the affected schedules A to I, announced at the
opening of the revised price bid on the 8th of September at
WBSEB and reiterate that there is no change in the price or
substance of our bid. Our unit bid prices should be
computed accordingly for the aforesaid items. This letter
is strictly without prejudice to our rights and
contentions. It may be noticed that in this letter they
informed that certain mistakes had crept in the items
mentioned in the annexure to the letter and declared that no
change in the price or substance of the bid was asked for
and that they stood by the amounts announced at the time of
the bids on September 8, 1999. However, the actual mistakes
are not pointed out. In their letter of December 17, 1999
they attempted to clarify the position. The relevant
excerpt of that letter may be quoted here: West Bengal
State Electricity Board Office of the Project Manager, Mr.
S.K. Roy Choudhury, The Project Manager, Purulia Pumped
Storage Project, Vidyut Bhawan, 5th Floor, Salt Lake City,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 13 of 19
Calcutta - 700 091, India,
Fax No.0091 33 3591854 / 3581533 1999-12-17
Purulia Pumped Storage Project
Dear Sir,
We refer to our telefax dated 25th October 1999. A
copy thereof is again enclosed for your convenience.
We request that the systematic computer
typographical transmission failure pointed out in the said
telefax is merely clerical in nature and not arithmetical
and do not in any way affect the validity of our bid. Its
nature is fully explained below.
I. The computer has unfortunately systematically
copied, in the first page (Serial items 2 & 3) of the BOQ
(Schedule A to I), the INR unit rates stated in line 1
Serial Item 2 to the next two succeeding lines i.e. the
computer has overwritten the unit rates in US$ terms for the
serial item no.2 and the INR unit rates for the immediately
succeeding serial item.
However, the figures appearing the amount column of
the BOQ for the said lines/items in which the above
mentioned errors have occurred are the correct tendered
figures both in US$ terms as well as INR terms.
II. Further the BOQ quantities stated in the quantity
column of serial item no.3 on each and every page has been
erased.
Enclosed is an attachment which would show the
applicable unit rates (in the lower half) and the unit rates
which were overwritten due to computer failure (in the upper
half).
It is an admitted position that at the time of opening
of the tender on 8th September 1999, our bid was the lowest
at Rs.647.90 crores. The bid of Skanska was Rs.691.22
crores and that of Taisei was Rs.726.50. We confirm that we
have all along maintained and still maintain the said bid
price of Rs.647.90 crores.
However, we have reasons to believe that you have
chosen to ignore our said letter and have proceeded to
evaluate our price bid by an illogical and mis-application
of the rules for the evaluation of the bids set down in the
ITB.
We, therefore, once again call upon you to evaluate
our bid after taking into consideration the applicable unit
rates. As already mentioned in our earlier fax there is no
change in the price or substance of our bid as mentioned in
the amount column of the BOQ. (Emphasis supplied)
Here, though the nature of mistakes are pointed out
yet the scope of the correction sought is not indicated.
The appellant could not have ignored these letters. Had the
appellant taken note of these letters and the mistakes
occurring due to repetition of entries in 37 items in the
bid documents, it would not have proceeded with correction
of such mistakes and evaluation of their bid without first
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 14 of 19
seeking clarification from respondents 1 to 4 under Clause
27.1. We have already referred to the gist of that clause.
The only prohibition contained therein is that no change in
the price or substance of the bid after its opening can be
sought, offered or permitted. In that regard they had made
their position clear. The prohibition is, therefore, not
attracted. In these circumstances any reasonable person in
the position of the appellant would have sought
clarification from respondent Nos.1 to 4 under Clause 27.1.
Even assuming that after the letter of December 17, 1999, no
further clarification was required to be sought by the
appellant, we cannot but hold that correction of the errors
taking note of the unit rates which are mere repetition of
the unit rates quoted for a different work item is
mechanical and without application of mind by the appellant.
In our view such a correction is far beyond the scope of
Clause 29. From the description of the mistakes, noted
above, and the correction and evaluation made by the
appellant, it is evident that except the error in the first
line against the work item Rock Excavation and Schedule
N day work, all other mistakes/errors are beyond the scope
of Clause 29.1, so Clause 29.2 will not be attracted. It
follows that the corrections in the bid documents of
respondent Nos.1 to 4 carried out by the appellant,
evaluation of bid under Clause 29.2 and the impugned
communication of the appellant dated December 18, 1999 are
unsustainable and of no consequence. Now, reverting to the
relief of correction of errors, Mr. Chidambaram has argued
that in the two lines against each of the Work Items, the
first line denotes 50 per cent of the quoted unit rate in
Indian Rupee and the second line represents the other 50 per
cent of the unit rate in U.S. Dollar. According to him the
actual rate quoted for quantity 1000 is the sum total of two
lines i.e. 148.08 in Indian Rupee plus 3.38 in U.S.
Dollar. This is not noted either in statement A or in
statement B. Be that as it may, quoting the unit rate 50
per cent in Indian Rupee and 50 per cent in U.S. Dollar is
not provided in the ITB. Nothing is brought to our notice
to justify splitting of unit rate in that ratio. There is
no indication of this fact in the price bid documents
submitted by the said respondents to explain that the unit
rate has been so quoted. This is also not in conformity
with Clause 15 of ITB which, as noted above, requires a
bidder to quote unit rates and prices in Indian Rupee and
either in U.S.Dollar or Japanese Yen. The learned
Additional Solicitor General, in our view, is right in his
submission that till the representation was made by the said
respondents on December 23, 1999, after the interim
direction of the High Court, the appellant was unaware of
the quoted unit rate being in such proportion. A combined
reading of ITB and the annexure, extracted above, makes it
clear that the second line against each work item is meant
for writing U.S. Dollar or Japanese Yen equivalent of the
unit rate and line total in the amount column entered in
the first line and not for writing bifurcated unit price in
different currencies in the ratio of 50 : 50. On these
facts, the errors cannot be termed as mere clerical or
mechanical. Permitting correction of such errors, if they
can be so called, would result in not only re-writing unit
rates in 37 entries in which such errors are said to have
been committed but also appending an explanation thereto
regarding splitting of unit rates in terms of representation
dated 23.12.1999 of respondent Nos.1 to 4. Neither Clauses
27 and 29 nor any other clause in the ITB permits such
corrections. The mistakes/errors in question, it is stated,
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 15 of 19
are unintentional and occurred due to the fault of computer
termed as a repetitive systematic computer typographical
transmission failure. It is difficult to accept this
contention. A mistake may be unilateral or mutual but it is
always unintentional. If it is intentional it ceases to be
a mistake. Here the mistakes may be unintentional but it
was not beyond the control of respondent Nos.1 to 4 to
correct the same before submission of the bid. Had they
been vigil in checking the bid documents before their
submission, the mistakes would have been avoided. Further,
correction of such mistakes after one and a half month of
opening of the bids will also be violative of Clauses 24.1,
24.3 and 29.1 of ITB. The controversy in this case has
arisen at the threshold. It cannot be disputed that this is
an international competitive bidding which postulates keen
competition and high efficiency. The bidders have or should
have assistance of technical experts. The degree of care
required in such a bidding is greater than in ordinary local
bids for small works. It is essential to maintain the
sanctity and integrity of process of tender/bid and also
award of a contract. The appellant, respondent Nos.1 to 4
and respondent Nos.10 & 11 are all bound by the ITB which
should be complied with scrupulously. In a work of this
nature and magnitude where bidders who fulfil pre-
qualification alone are invited to bid, adherence to the
instructions cannot be given a go-bye by branding it as a
pedantic approach otherwise it will encourage and provide
scope for discrimination, arbitrarinessand favouritism which
are totally opposed to the Rule of law and our
Constitutional values. The very purpose of issuing
Rules/instructions is to ensure their enforcement lest the
Rule of law should be a casuality. Relaxation or waiver of
a rule or condition, unless so provided under ITB, by the
State or its agencies (the appellant) in favour of one
bidder would create justifiable doubts in the minds of other
bidders, would impair the rule of transparency and fairness
and provide room for manipulation to suit the whims of the
State agencies in picking and choosing a bidder for awarding
contracts as in the case of distributing bounty or charity.
In our view such approach should always be avoided. Where
power to relax or waive a rule or a condition exists under
the Rules, it has to be done strictly in compliance with the
Rules. We have, therefore, no hesitation in concluding that
adherence to ITB or Rules is the best principle to be
followed, which is also in the best public interest. For
all these reason, in such a highly competitive bid of global
tender, the appellant was justified in not permitting
respondent Nos. 1 to 4 to correct the errors of the nature
and the magnitude which, if permitted, will give a different
complexion to the bid. The High Court erred in directing
the appellant to permit respondent Nos.1 to 4 to correct the
errors in the bid documents. Mr.Chidambram, however,
submitted that in equity respondent Nos.1 to 4 would be
entitled to relief of correction of mistakes. He invited
our attention to para 84 of the American Jurisprudence
(Second Edition, Volume 64, Page No.944). It will be useful
to quote the relevant part of that para here: As a
general rule, equitable relief will be granted to a bidder
for a public contract where he has made a material mistake
of fact in the bid which he submitted, and where, upon the
discovery of that mistake, he acts promptly in informing the
public authorities and requesting withdrawal of his bid or
opportunity to rectify his mistake particularly where he
does so before any formal contract is entered into. The
principle is based on the judgment of the Supreme Court of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 16 of 19
U.S.A. in Moffett, H. & C. Co. Vs. Rochester, 178 U.S.
373; 44 L Ed 1108, 20 S Ct 957. There the plaintiff gave
proposals by way of bid for two works of excavation of
earth, quoting the unit rate 1.5 Dollar instead of 15
Dollars and 50 cents instead of 70 cents per cubic yard.
The City of Rochester which called for tenders, was promptly
informed of the mistake by the plaintiffs agent as soon as
it was discovered but before entering into contract.
However, the proposal of the plaintiff was accepted by the
City of Rochester in regard to one work and the other work
was allotted to another bidder. The plaintiff declined to
enter into a contract with the City of Rochester which took
steps to enforce execution of the contract. The plaintiff
filed the suit for correction of proposals to conform to the
asserted intention in making them and for execution of the
contract on corrected rates or alternatively for the
recission of the proposals. It also sought injunction
against the officers of the City of Rochester declaring it
to be defaulter, its bond forfeited or enforced. It was
found that the price noted was grossly inadequate and far
below what would be the actual cost of the work under the
most favourable circumstances. The trial court decreed the
suit holding that the proposals of the bidder be rescinded,
cancelled and declared null, void, and of no effect and
granting the injunction prayed for. But on appeal the
decree was reversed by the circuit court of appeals. On
further appeal to the Supreme Court of U.S.A., it was
observed that both the courts below found that there was a
mistake and while the trial court opined it was clear,
explicit and undisputed, the court of appeal was of the view
that it was not a mistake in any legal sense but was a
negligent omission arising from an inadequate calculation of
the cost of the work and held that the mistake was not
sufficient to preclude a claim for relief if the mistake
justified it. The Supreme Court relied on the following
observation in an earlier judgment of that Court in Hearne
Vs. Marine Ins. Co. 22 L ed. 305, A mistake on one
side may be a ground for rescinding, but not for reforming,
a contract. Where the minds of the parties have not met
there is no contract, and hence none to be rectified. And
it was concluded that the last two propositions might be
claimed to be pertinent to that case even though the
transactions between the parties be considered as a
completed contract and held that the action of the City of
Rochester in awarding one contract to another bidder and
forcing the plaintiff to enter into the second contract
after it had declared there was a mistake in its proposal
was inequitable. Exceptions to the above general principle
of seeking relief in equity on the ground of mistake, as can
be culled out from the same para, are : (1) where the
mistake might have been avoided by the exercise of ordinary
care and diligence on the part of the bidder; but where the
offeree of the bid has or is deemed to have knowledge of the
mistake, he cannot be permitted to take advantage of such a
mistake. (2) where the bidder on discovery of the mistake
fails to act promptly in informing to the concerned
authority and request for rectification, withdrawal or
cancellation of bid on the ground of clerical mistake is not
made before opening of all the bids, (3) where the bidder
fails to follow the rules and regulations set forth in the
advertisement for bids as to the time when bidders may
withdraw their offer; however where the mistake is
discovered after opening of bids, the bidder may be
permitted to withdraw the bid. In the instant case, we have
also noted that the mistakes in the bid documents of
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 17 of 19
respondent Nos.1 to 4 even though caused on account of
faulty functioning of computer, could have been discovered
and notified by the said respondents with exercise of
ordinary care and diligence. Here, the mistakes remained in
the documents due to gross negligence in not checking the
same before the submission of bid. Further Clauses 24 and
27 of ITB permit modification or withdrawal of bids after
bid submission but before the dead line for submissions of
the bids and not thereafter. And equity follows the
law. Having submitted the bid they did not promptly act
in discovering the errors and informing the same to the
appellant. Though letters were written on October 25, 1999,
and December 17, 1999, yet the real nature of
errors/mistakes and corrections sought were not pointed out
till December 23, 1999 when representation was made after
interim direction of the High Court was given on December
21, 1999. Indeed it appears to us that they improved their
claim in the representation. In our view the said
respondents are not entitled to rectification of
mistakes/error for being considered along with the other
bidders. Mr. Chidambaram relied upon a decision of the
Superior Court of New Jersey in Spina Asphalt Paving
Excavating Contractors, Inc., Vs. Borough of Fairview [304
N.J. Super 425] to justify the claim for rectification of
mistakes. In that case, the Borough of Fairview invited
tenders. Spina and one Tomaro participated in the bid. The
bid was on a unit price basis and the proposals were
submitted on Forms supplied by the Borough. The bid
specifications provided, inter alia : in the event there
is a discrepancy between the unit price and the extended
total, the unit price shall prevail. The Borough reserved
the right to waive any informality if deemed in the best
interests of the owner. On the evening when the bids were
opened, Spina discovered that its secretary had erroneously
indicated the unit price for one of the items as 400 dollars
per square yard though it should have been 4 dollars per
square yard as reflected in the total bid for that work.
Spina faxed the Borough indicating that the intended unit
price was 4 dollars per square yard. On the basis of 400
dollars per square yard Spinas bid was calculated which
obviously worked out far higher than the intended bid
amount. Taking note of that amount the Borough awarded the
contract to Tomaro. Spina instituted action claiming that
the Borough arbitrarily failed to recognise that its bid was
lower than that of Tomaro. The Law Division held that the
error in the bid was non-material and subject to waiver.
The Superior Court while agreeing with the Law Division
observed that they did not hold that generally an error in
the statement of a price could be treated as immaterial and
it was only when as in that case the error was patent and
the true intent of the bidder obvious that such an error
might be disregarded. The Superior Court held that when as
in that case the failure to waive the deviation would thwart
the aims of the public bidding laws, the municipality was
obliged to grant the waiver. (Emphasis supplied) Though
Clause 29 in this case appears to be similarly worded as in
the bid documents in Spinas case (supra), a close reading
of these clauses shows that no power of waiver is reserved
in the case on hand. That apart, the nature of the error in
these two cases is entirely different. There, the error was
apparent $ 400 for $ 4, non-material and waiveable by the
Corporation; in the present case the errors pointed out
above are not simply arithmetic and clerical mistake but a
deliberate mode of splitting the bid which would amount to
re-writing the entries in the bid document and cannot be
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 18 of 19
treated as non-material. Therefore, the judgment in Spinas
case (supra) does not help respondent Nos.1 to 4. The
submission that remains to be considered is that as the
price bid of respondent Nos.1 to 4 is lesser by 40 crores
and 80 crores than that of respondent Nos.11 and 10
respectively, public interest demands that the bid of
respondent Nos.1 to 4 should be considered. The project
undertaken by the appellant is undoubtedly for the benefit
of public. The mode of execution of the work of the project
should also ensure that the public interest is best served.
Tenders are invited on the basis of competitive bidding for
execution of the work of the project as it serves dual
purposes. On the one hand it offers a fair opportunity to
all those who are interested in competing for the contract
relating to execution of the work and on the other hand it
affords the appellant a choice to select the best of the
competitors on competitive price without prejudice to the
quality of the work. Above all it eliminates favouritism
and discrimination in awarding public works to contractors.
The contract is, therefore, awarded normally to the lowest
tenderer which is in public interest. The principle of
awarding contract to the lowest tenderer applies when all
things are equal. It is equally in public interest to
adhere to the rules and conditions subject to which bids are
invited. Merely because a bid is the lowest the
requirements of compliance of rules and conditions cannot be
ignored. It is obvious that the bid of respondent Nos.1 to
4 is the lowest of bids offered. As the bid documents of
respondent Nos.1 to 4 stands without correction there will
be inherent inconsistency between the particulars given in
the annexure and the total bid amount, it cannot be directed
to be considered along with other bid on the sole ground of
being the lowest. We find no force in the submission that
as under Clause 14.2 items against which no rate or price is
entered by the bidder will not be paid by the employer when
executed and shall be deemed covered by the other rates and
prices in the bill of quantities, the unit price in items
containing errors be ignored and the bid be considered on
the basis of total price bid which is the lowest. In our
view, there is a basic distinction between a case where
against some items no rates or prices are quoted and a case
where some rate is quoted. Whereas in the former case the
bidder will not be entitled to claim any specific amount for
the work done by him in the absence of any rate for that
work, because in the aforementioned clause it is clarified
that the bidders will not be paid by the employer and that
the execution of the work shall be deemed covered by other
rates and prices in the bill of quantities but in the latter
case the bidder will be entitled to claim for the work
executed on the basis of quoted price/rate. We may,
however, clarify that the appellant is not obliged to award
contract to any of the bidders at their quoted price bid.
It is always open to the appellant to negotiate with the
next lowest bidder for awarding the contract on economically
viable price bid. For the reasons abovementioned, though
the impugned order of the High Court insofar as it relates
to quashing of letter of the appellant dated December 18,
1999, falls within the purview of judicial review, yet the
direction to the appellant to permit correction of errors by
respondents 1 to 4 in their bid documents and consider their
bid along with other bid, goes far beyond the scope of
judicial review, as elucidated by this Court in Tata
Cellular (supra). In the result, we uphold the impugned
order of the Division Bench insofar as it relates to
quashing of communication and letter dated December 18, 1999
http://JUDIS.NIC.IN SUPREME COURT OF INDIA Page 19 of 19
and set aside that part of the impugned order giving
direction to the appellant to permit respondent Nos.1 to 4
to correct bid documents and to consider their bid after
correction along with other bids. The appeal is thus
allowed in part. On the facts and in the circumstances of
this case we leave the parties to bear their own costs.